Virtual energy pool regulation and control space depicting method considering electricity-hydrogen-traffic coupling characteristics

By constructing a virtual energy pool regulation space characterization method with electrical-hydrogen-traffic coupling characteristics, the safety problems of the electrical-hydrogen-traffic system under low-carbon operation and carbon emission constraints are solved, and the system's low-carbon regulation and evaluation are realized. Ensure the low-carbon feasibility and safety of the electric-hydrogen-traffic virtual energy pool.

CN119067341APending Publication Date: 2024-12-03CHONGQING UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410952615.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The existing technology is difficult to achieve the analysis and scheduling of the optimal low-carbon operating state in the electric-hydrogen-traffic system. Especially in the case of fluctuations in the source load, it is impossible to ensure the safe operation of the low-carbon system, and there is a lack of effective low-carbon feasible domain. Analysis method.

Method used

A virtual energy pool regulation space characterization method considering the characteristics of electricity-hydrogen-traffic coupling, including building a virtual energy pool operation model, optimizing the operation model, building a fixed carbon emission operation domain and performing geometric evaluation, and optimizing through mathematical models and constraints The low-carbon operation of the electric-hydrogen-transportation system ensures the safe operation of the system under carbon emission constraints.

Benefits of technology

Realize low-carbon regulatory space portrayal and geometric evaluation of the electric-hydrogen-traffic system, provide quantitative assessment of low-carbon safe operation margin and abundant space, help the system optimize operation within the carbon emission limit, and ensure virtual electricity-hydrogen-traffic Low carbon feasibility and safety of energy pools.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119067341A_ABST
    Figure CN119067341A_ABST
Patent Text Reader

Abstract

The invention discloses a virtual energy pool regulation and control space description method considering electricity-hydrogen-traffic coupling characteristics. The method comprises the following steps: 1) constructing a virtual energy pool operation model considering the electricity-hydrogen-traffic coupling characteristics; 2) establishing an electricity-hydrogen-traffic virtual energy pool optimization operation model considering flexible operation characteristics; 3) constructing an electricity-hydrogen-traffic carbon emission determination operation domain; 4) depicting a low-carbon regulation and control space of the electricity-hydrogen-traffic virtual energy pool; and 5) carrying out geometric evaluation on the low-carbon regulation and control space based on the definite carbon emission operation domain. According to the method, an electricity-hydrogen-traffic virtual energy pool carbon emission determination operation domain geometric characteristic index system is established from the angles of low-carbon operation capability and observation variable coupling characteristics, and a carbon emission determination operation domain geometric characteristic evaluation method is provided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of optimized operation of an electricity-hydrogen-transportation coupling system, and specifically to a method for characterizing a virtual energy pool control space taking into account characteristics of electricity-hydrogen-transportation coupling. Background Art

[0002] With the continuous maturity of hydrogen production and use technologies such as water electrolysis and hydrogen fuel cell vehicles, the hydrogen energy system, power system, and transportation system show a distributed deep coupling development trend, forming an electricity-hydrogen-transportation virtual energy pool. In order to give full play to the green and low-carbon energy attributes of hydrogen energy and promote the deep decarbonization of the power system and transportation system, it is necessary to deeply explore the flexible emission reduction potential of the virtual energy pool under the coupling characteristics of electricity-hydrogen-transportation. However, existing related research is mostly limited to the role of hydrogen energy storage systems (electrolyzers + hydrogen storage tanks + fuel cells) in improving the low-carbon operation capabilities of power systems or integrated energy systems, and less consideration is given to the impact of flexible scheduling of resources and coordination in the entire process of hydrogen energy "production-storage-transportation-use" on low-carbon operation capabilities, which cannot give full play to the important supporting role of hydrogen energy systems in green and low-carbon transformation.

[0003] In addition, the low-carbon operation "point" analysis method of the electric-hydrogen-transportation system that seeks the optimal low-carbon operating state is difficult to cope with the optimal operating point deviation under source-load fluctuations, and cannot guarantee the reasonable low-carbon and safe operating space of the electric-hydrogen-transportation virtual energy pool. At present, there is still a blank in the research on the low-carbon feasible domain analysis method of the electric-hydrogen-transportation system, and the following problems need to be solved urgently: On a theoretical basis, whether the feasible domain that takes into account the carbon emission constraints of the full-time section coupling and the complex operation constraints of the electric-hydrogen coupling equipment has a theoretical basis for projectable observation needs to be explored; in terms of solution methods, the operation constraints of the electric-hydrogen coupling equipment in the full-time section within the scheduling cycle lead to a sharp increase in the difficulty of construction, and it is urgent to propose a feasible domain construction method that takes into account engineering practicality. Summary of the invention

[0004] The purpose of the present invention is to provide a method for characterizing a virtual energy pool control space taking into account the characteristics of electricity-hydrogen-traffic coupling, comprising the following steps:

[0005] 1) Construct a virtual energy pool operation model that considers the coupling characteristics of electricity, hydrogen and transportation;

[0006] 2) Establish an optimized operation model of the electric-hydrogen-transportation virtual energy pool taking into account flexible operation characteristics;

[0007] 3) Constructing the electricity-hydrogen-transportation carbon emission operation domain;

[0008] 4) Characterize the low-carbon regulation space of the electricity-hydrogen-transportation virtual energy pool;

[0009] 5) Conduct geometric evaluation of the low-carbon control space based on the fixed carbon emission operation domain.

[0010] Furthermore, the virtual energy pool is a virtual operation architecture composed of a regional hydrogen energy system integrated through a power network and a transportation network, with electric energy and hydrogen energy as core energy carriers;

[0011] The regional hydrogen energy system includes a centralized hydrogen production station, a distributed hydrogen refueling station, a hydrogen long-tube trailer and a hydrogen fuel cell vehicle.

[0012] Furthermore, the steps of constructing a virtual energy pool operation model considering the coupling characteristics of electricity, hydrogen and transportation include:

[0013] 1) Construct a centralized hydrogen production station hydrogen production and storage model, namely:

[0014]

[0015] Where: and They represent the hydrogen production and carbon emissions from natural gas at the mth centralized hydrogen production station during period t respectively; represents the gas consumption of the mth centralized hydrogen production station during period t; η G2H represents the efficiency of hydrogen production from natural gas, ε CE represents the carbon emission coefficient in the process of producing hydrogen from natural gas; q H ,q G They are hydrogen and natural gas lower calorific value; Indicates the upper and lower limits of natural gas hydrogen production;

[0016] 2) Construct a correlation model between the amount of hydrogen produced by water electrolysis and power consumption in a centralized hydrogen production station, namely:

[0017]

[0018]

[0019] Where: U el,t and I el,t represents the operating voltage and current density of the alkaline electrolytic cell at time t; U rev is the reversible voltage, that is, the open circuit voltage of the electrolytic cell when the current density is 0; r1 and r2 are the resistance and thermal resistance parameters of the electrolytic cell, T el is the average operating temperature of the electrolytic cell, R el is the effective reaction area of ​​the electrolytic cell, s1, s2, s3, s4, s5, s6 are the electrode overvoltage fitting coefficients; N el is the number of electrolytic cells; represents the electrolysis power of the mth centralized hydrogen production station electrolyzer at time t; represents the hydrogen production of the electrolyzer of the mth centralized hydrogen production station at time t, λ H is the standard density of hydrogen, η f is the Faraday efficiency, F is the Faraday constant; The upper and lower limits of the electrolytic power of the electrolytic cell;

[0020] 3) Construct a correlation model between the power consumption of the compressor of the centralized hydrogen production station and the amount of hydrogen produced, namely:

[0021]

[0022] Where: represents the power consumption of the compressor of the mth centralized hydrogen production station at time t, C H is the specific heat capacity constant of hydrogen, T com is the average operating temperature of the compressor, η com is the compressor working efficiency, B is the inlet and outlet gas pressure ratio, and ε is the hydrogen isentropic coefficient. is the maximum operating power of the compressor;

[0023] 4) Construct the operation constraints of hydrogen storage tanks in centralized hydrogen production stations, namely:

[0024]

[0025] Where: represents the pressure and hydrogen change of the hydrogen storage tank of the mth centralized hydrogen production station at time t, R H is the molar gas constant, T H is the average temperature in the hydrogen storage tank, is the hydrogen storage tank capacity of the mth centralized hydrogen production station, M H is the molar mass of hydrogen. It represents the hydrogen refueling amount of the kth HT vehicle in the mth centralized hydrogen production station at time t. Indicates the upper and lower limits of the hydrogen storage tank pressure. Indicates the hydrogen storage tank pressure at the start and end of the scheduling cycle. Ω HPS represents a collection of centralized hydrogen production stations; Indicates the gas pressure of the hydrogen storage tank of the mth centralized hydrogen production station at time t-1;

[0026] 5) Construct the operation constraints of the distributed on-site hydrogen production and refueling station, including the electrolyzer operation constraints (2)-(5) and the operation constraint (9); construct the operation constraints of the distributed off-site hydrogen supply and refueling station, including the operation constraint (9);

[0027]

[0028] Where: Indicates the change in hydrogen tank pressure and hydrogen volume at the nth hydrogen refueling station at time t, is the hydrogen storage tank capacity of the nth hydrogen refueling station, and represents the hydrogen consumption power and power generation power of the hydrogen fuel cell vehicle participating in the H2G mode in the nth hydrogen refueling station, ηfc is the power generation efficiency of hydrogen fuel cells. fc , β fc is the empirical fitting coefficient of hydrogen fuel cell power generation efficiency, and the subscript r represents the rated operating condition. It represents the hydrogen production of electrolyzer n in the hydrogen refueling station at time t, Indicates the amount of hydrogen released by the kth HT in hydrogen refueling station n at time t. Ω on and Ω off They represent the collection of hydrogen refueling stations inside the station and hydrogen refueling stations outside the station respectively; It represents the amount of hydrogen refueled by a hydrogen fuel vehicle at the nth hydrogen refueling station at time t. represents the rated power generation of the hydrogen fuel cell vehicle participating in the H2G mode in the nth hydrogen refueling station; η fc,r is the rated power generation efficiency of the hydrogen fuel cell;

[0029] 6) Considering the driving path of the hydrogen long-tube trailer, the relationship constraints between the driving path and the spatial position are established, namely:

[0030]

[0031] Where: r i,j,k A is a 0-1 logical variable. If it is 1, it means the driving path of the kth HT is (i, j). Otherwise, it means the driving path is not (i, j). i,t,k A is a 0-1 logical variable, 1 means the kth HT is located at hydrogen production station / hydrogen refueling station i at time t; i,ts,k , A i,te,k 0-1 logical variables representing the start and end times of the scheduling period respectively;

[0032] 7) Establish constraints on the amount of hydrogen transported by hydrogen long-tube trailers, namely:

[0033]

[0034] Where: Q i,t,k , ΔQ i,t,k represents the hydrogen storage amount and hydrogen change in the kth hydrogen long tube trailer located in station i at time t; α i,t,k , β i,t,k Q is a 0-1 logical variable, indicating the hydrogenation and dehydrogenation status of the hydrogen long-tube trailer. If it is 1, it means that the kth hydrogen long-tube trailer is refueling and dehydrogenating in station i at time t; k,cap represents the upper limit of hydrogen storage of the kth hydrogen tube trailer; λ cap,min Indicates the minimum hydrogen storage coefficient of the hydrogen long tube trailer; Q i,ts,k and Q i,te,k represents the hydrogen storage capacity of the kth hydrogen long tube trailer at the start and end of the scheduling period respectively; Q j,t+1,k , Q j,t,k , Qj,t-1,k They represent the hydrogen storage capacity in the kth hydrogen long tube trailer located in station j at time t+1, time t, and time t-1 respectively;

[0035] 8) Taking the minimum travel time cost as the path selection standard for all users in the transportation network, static mixed user equilibrium is used to describe the state that the transportation network spontaneously reaches, that is:

[0036]

[0037] Where: h p is the traffic flow of path p, The travel time cost required for HFCV and vehicles other than HFCV to choose path p, v ij is the minimum travel time cost of all paths between travel demand pairs (i→j), W hv , W o is the set of travel demand pairs of HFCV and vehicles other than HFCV, is the set of vehicle paths of all HFCVs and other vehicles except HFCVs between travel demand pairs (i→j);

[0038] 9) Based on the BPR function, a road impedance model is established to describe the road congestion effect, as shown below:

[0039]

[0040] Where: τ p1 (h p ) represents the traffic volume h on road p p The relevant transit time function, represents the free travel time of road p, that is, the vehicle travel time when there is no traffic flow on road p, c p represents the traffic capacity of road p; P ij is the set of all paths between travel demand pairs (i→j);

[0041] 10) Based on the improved Davidson function, a hydrogen refueling queue time model is constructed, namely:

[0042]

[0043] Where: τ p2 (h p ) represents the traffic volume h on road p p The relevant transit time function, Indicates the hydrogen refueling time of a single HFCV, represents the limit of vehicles that can be refueled at the same time at a hydrogen refueling station, R is the function shape parameter; P H This is the collection of hydrogenation roads after topology change.

[0044] Furthermore, formulas (12)-(14) constitute a traffic flow model; the traffic flow model uses the "all or nothing allocation" method to allocate the traffic flow of each road section, thereby outputting all h p gather.

[0045] Furthermore, the objective function C of the electricity-hydrogen-transportation virtual energy pool optimization operation model is as follows:

[0046] minC=C P,buy +C HP +C curt +C CE +C HT (16)

[0047] Electricity purchase cost C P,buy 、Hydrogen production cost C HP , Penalty cost for wind and solar power abandonment C curt 、Carbon emission cost C CE and the operating cost of hydrogen tube trailer C HT They are as follows:

[0048]

[0049] Where: c Pbuy,t P represents the price of electricity purchased from the upper power grid at time t; grid,t It represents the active power purchased from the superior power grid at time t; Δt represents the unit time interval.

[0050]

[0051] Where: c G is the gas purchase price, c PSA is the hydrogen purification cost coefficient, Δt is the unit time interval, N p is the number of centralized hydrogen production stations in EHT-VEP. represents the gas consumption of the mth centralized hydrogen production station during period t; represents the hydrogen production of the mth centralized hydrogen production station at time t;

[0052]

[0053] Where: They represent the abandoned wind and solar power of the wind and solar power unit at the node i at time t; c curt N is the penalty cost per unit of wind and solar power abandonment; B Indicates the number of distribution network nodes.

[0054]

[0055] Where: CE represents the unit cost coefficient of carbon emissions; ε g2hRepresents the carbon emission coefficient in the process of hydrogen production from natural gas, η G2H represents the efficiency of hydrogen production from natural gas, q H is the lower calorific value of hydrogen; ε grid Indicates the carbon emission coefficient of electricity purchased by the superior power grid.

[0056]

[0057] Where: c HT represents the unit storage and transportation cost of hydrogen for long-tube trailers, N k The number of EHT-VEP medium and long tube trailers. Represents the amount of hydrogen refueled by the kth HT vehicle at time t.

[0058] Furthermore, the constraints of the electricity-hydrogen-transportation virtual energy pool optimization operation model include distribution network flow constraints, node power balance constraints, safe operation constraints, distributed power supply operation constraints, and traffic flow balance constraints.

[0059] Furthermore, the power flow constraints of the distribution network are as follows:

[0060]

[0061] Where: v(j) and w(j) represent the first node set and the last node set of the branch connected to node j respectively; P ij,t , Q ij,t represents the active power and reactive power of branch ij at time t; r ij and x ij Represents the resistance and reactance of branch ij; P j,t , Q j,t I represents the active and reactive power injected into node j at time t; ij,t represents the branch ij current at time t; U j,t U represents the voltage of node j at time t. i,t P represents the voltage of node i at time t. jk,t , Q jk,t It represents the active power and reactive power of branch jk at time t;

[0062] The node electrical power balance constraints are as follows:

[0063]

[0064] Where: P WG,i,t , Q WG,i,t P represents the actual active power and reactive power generated by wind turbine i at time t; PV,i,t , Q PV,i,t P represents the actual active power and reactive power generated by the photovoltaic unit at node i at time t; load,i,t and Q load,i,trepresents the conventional active load and reactive load of node i at time t; s is the access node of the interconnection line.

[0065] The safe operating constraints are as follows:

[0066]

[0067] Where: They represent the upper and lower limits of the voltage allowed at node i respectively; They represent the upper and lower limits of the current allowed for line ij respectively;

[0068] The distributed generation operation constraints are as follows:

[0069]

[0070]

[0071] Where: and Indicates the predicted active power generated by the wind and solar generator connected to node i; and Indicates the set power factor of the wind and solar generator set. They represent the abandoned wind and solar power of the wind and solar power generator at the node i at time t respectively;

[0072] The traffic flow balance constraints are as follows:

[0073]

[0074] Where: H Indicates the proportion of vehicles that need hydrogen refueling; h p,t represents the traffic flow on road p at time t; Indicates the average amount of hydrogen refueled in a hydrogen fuel cell vehicle.

[0075] Furthermore, the steps to construct the electricity-hydrogen-transportation carbon emission operation domain are as follows:

[0076] 1) Define the operating point Z that represents the operating state of EHT-VEP, that is:

[0077]

[0078] In the formula, Respectively represent the dimension N B ×T、N L ×T real number space;

[0079] 2) Construct the carbon emission operation domain expression of electricity-hydrogen-transportation, namely:

[0080]

[0081] Where: ΩCR is the fixed carbon emission operation domain; U is the node voltage matrix; I is the branch current matrix; P and Q are the node injected active and reactive power matrices respectively; H represents the node hydrogen load demand matrix; f(x,y)=0 represents the electric hydrogen energy balance constraint; Represents the system safe operation constraints, including voltage constraints and thermal stability constraints; represents the node injection power constraint, including the operation constraint of the electric-hydrogen coupling equipment and the operation constraint of the distributed power source; E(y)≤Bmax 3 represents the system carbon emission constraint, as shown in the following formula; B1, B2 and B3 represent the critical value of safe operation, the critical value of injection power and the carbon emission limit respectively; the superscripts max and min represent the upper and lower bounds; N B and N L represents the number of nodes and branches; T is the scheduling period.

[0082] 3) Establish a fixed carbon emission operation domain transformation model under second-order cone relaxation, transform the fixed carbon emission operation domain, and obtain:

[0083]

[0084] Where: A, B, C are coefficient matrices in equality constraints; D, F are coefficient matrices in linear inequalities; H, V are coefficient matrices in SOC constraints. W is the node voltage square matrix; L is the branch current square matrix. D , Q D represents the node active and reactive load matrix; P G , Q G Represents the active and reactive output matrix of the node unit. Ω SCR It is the fixed carbon emission operation domain after conversion.

[0085] Furthermore, the steps to characterize the low-carbon regulation space of the electricity-hydrogen-transportation virtual energy pool are as follows:

[0086] 1) Based on the typical operation state of EHT-VEP, the EHT-VEP power flow distribution is obtained as the initial working point Z0. Based on the initial working point Z0, the carbon emission flow is calculated and the node carbon emission factor is obtained as the basis for selecting the reduced dimension observation variable, namely:

[0087]

[0088] Where: B , L represents the node and branch carbon emission factor matrix respectively; Y represents the distribution network node association matrix; P L represents the branch power flow distribution matrix; ρ G is the unit carbon emission factor matrix;

[0089] 2) Project the high-dimensional fixed carbon emission operation domain to the node load space, and select the n-dimensional node electrical load as the observed variable according to the carbon emission distribution, that is:

[0090]

[0091] Where: K obs represents the set of observation variables to be selected, where k is a 0-1 variable of the observation variable selection state, k i =1 means that the node i load is selected as the observed variable. and N B dimensional and T-dimensional unit row vectors;

[0092] The fixed carbon emission operation domain in the reduced-dimensional observation space is as follows:

[0093]

[0094] Where: f(p,q)=0 represents the equality constraint including the electric hydrogen energy balance; g(p,q)≤0 represents the inequality constraint including the safe operation constraint and carbon emission constraint; Ω SCRL represents the fixed carbon emission operation domain in the reduced-dimensional observation space;

[0095] 3) Based on Ω SCRL Perform CCEOR boundary convex hull fitting and iteratively shrink the convex hull CCEOR according to the second-order cone relaxation gap; the fitting target is as follows:

[0096]

[0097] Where: z(p) represents the objective function set for solving the boundary point, and the subscripts u and d represent the upper boundary and the lower boundary respectively. c represents n-1 dimensional fixed observation variables.

[0098] The fitting constraints are as follows:

[0099]

[0100] Where: L s+1 is the branch current square matrix of the s+1th iteration; is the precise branch current square matrix in the sth iteration. T is a real matrix; gap max is the maximum relaxation gap allowed during the iteration process.

[0101] Furthermore, the steps for geometrically evaluating the low-carbon control space based on the fixed carbon emission operation domain are as follows:

[0102] 1) Construct a low-carbon regulation spatial geometric evaluation index system, including the EHT-VEP low-carbon regulation spatial geometric evaluation index and the EHT-VEP observed variable coupling characteristic geometric evaluation index;

[0103] The EHT-VEP low-carbon regulation space geometric evaluation indicators include low-carbon safe operation margin, low-carbon operation ample space, and dimension reduction cutoff area;

[0104] The low carbon safety operating margin is as follows:

[0105]

[0106] Where p is the selected observed variable; d(p) is the low-carbon safety operation margin; p * is the feasible space of observed variables;

[0107] The ample space for low-carbon operation is as follows:

[0108]

[0109] In the formula, and They are z u (p) and z d (p) takes the optimal value. CR Allow ample room for low-carbon operation;

[0110] The dimensionality reduction cut-off area is as follows:

[0111]

[0112] In the formula, p i is the observed variable of the i-th dimension; Π is the fixed plane; S CR (p i ) is the cut-off area for dimensionality reduction;

[0113] The geometric evaluation indexes of the EHT-VEP observed variable coupling characteristics include observed variable coupling coefficient, average change rate of truncation surface, and multi-dimensional balance;

[0114] The observed variable coupling coefficients are as follows:

[0115]

[0116] Where, the observed variable coupling coefficient CF ranges from (0, +∞); S RT 、max S CCEOR (p i ) is the area of ​​a rectangle of equal length and width and the maximum SA area;

[0117] The average change rate ACR of the truncation surface is as follows:

[0118]

[0119] In the formula, S CR (p i +Δp i ), S CR (p i ) is the observed variable p i +Δp i , observed variable p i The corresponding dimension reduction cut-off area; the multidimensional balance degree ED is as follows:

[0120]

[0121] Where: V n (maxd(p)) represents the volume of the n-dimensional hypersphere with radius maxd(p); V CR Allow ample room for low-carbon operation;

[0122] 2) Conduct a low-carbon regulation spatial geometry assessment, including the following steps:

[0123] 2.1) Given the initial working point make Solve equations (46)-(47) to obtain Initial feasible range Repeatedly fix the 2D observation variables to obtain the feasible space for initializing the observation variables

[0124] 2.2) Set the iteration step size Δp and the maximum relaxation gap gap max , fixed one-dimensional observation variable make Solve equations (46)-(47) to obtain the upper and lower boundary points and And let p 2 Gradually approach with iterative step size growth Get multiple sets of boundary points and add them to p op ;

[0125] 2.3) Order And gradually increase the iterative step size to approach Repeat step 2.2) to obtain multiple sets of boundary points and add them to p op ;

[0126] 2.4) Repeat steps 2.2) and 2.3) until all dimensional observation variables are traversed to obtain the boundary point set p op , based on the fast convex hull algorithm to obtain the current p op Minimal convex hull

[0127] 2.5) Based on the current p op , add cutting plane constraints and iteratively update p op , until all boundary points satisfy gap≤gap max , and iteratively shrink Fitting the shrinking convex hull CCEOR.

[0128] 2.6) Based on the proposed CCEOR geometric evaluation index system, according to step ⑤, we can obtain Corresponding convex hull vertex set Solve equations (50)-(55) and output the CCEOR geometric evaluation index.

[0129] The technical effect of the present invention is unquestionable. The present invention establishes a geometric characteristic index system for the fixed carbon emission operation domain of the electric-hydrogen-transportation virtual energy pool from the perspective of low-carbon operation capability and the coupling characteristics of observed variables, and proposes a geometric characteristic evaluation method for the fixed carbon emission operation domain. BRIEF DESCRIPTION OF THE DRAWINGS

[0130] Figure 1 It is a flow chart of the method for characterizing the virtual energy pool regulation space considering the coupling characteristics of electricity, hydrogen and transportation; Figure 2 It is the basic framework of the electricity-hydrogen-transportation virtual energy pool; Figure 3 It is the EHT-VEP-I topology; Figure 4 It is the EHT-VEP-II topology; Figure 5 (a) is the typical day time series curve in summer to simulate the output characteristics of wind and solar power stations; 5(b) is the time series characteristic curve of electric load and traffic flow demand; Figure 6 It is the three-dimensional carbon emission operation domain and its two-dimensional projection. DETAILED DESCRIPTION

[0131] The present invention is further described below in conjunction with the embodiments, but it should not be understood that the above subject matter of the present invention is limited to the following embodiments. Without departing from the above technical ideas of the present invention, various substitutions and changes are made according to the common technical knowledge and customary means in the art, which should all be included in the protection scope of the present invention.

[0132] Embodiment 1:

[0133] See also Figures 1 to 6 , a virtual energy pool control space characterization method considering the electricity-hydrogen-transportation coupling characteristics, comprising the following steps:

[0134] 1) Construct a virtual energy pool operation model that considers the coupling characteristics of electricity, hydrogen and transportation;

[0135] 2) Establish an optimized operation model of the electric-hydrogen-transportation virtual energy pool taking into account flexible operation characteristics;

[0136] 3) Constructing the electricity-hydrogen-transportation carbon emission operation domain;

[0137] 4) Characterize the low-carbon regulation space of the electricity-hydrogen-transportation virtual energy pool;

[0138] 5) Conduct geometric evaluation of the low-carbon control space based on the fixed carbon emission operation domain.

[0139] Embodiment 2:

[0140] A method for characterizing a virtual energy pool control space considering the characteristics of electricity-hydrogen-transportation coupling, the technical content of which is the same as that of Example 1, and further, the virtual energy pool is a virtual operation architecture composed of a regional hydrogen energy system integrated with a power network and a transportation network, with electricity and hydrogen as core energy carriers;

[0141] The regional hydrogen energy system includes a centralized hydrogen production station, a distributed hydrogen refueling station, a hydrogen long-tube trailer and a hydrogen fuel cell vehicle.

[0142] Embodiment 3:

[0143] A method for characterizing a virtual energy pool control space considering the electric-hydrogen-transportation coupling characteristics, the technical content of which is the same as any one of Embodiments 1-2, and further, the steps of constructing a virtual energy pool operation model considering the electric-hydrogen-transportation coupling characteristics include:

[0144] 1) Construct a centralized hydrogen production station hydrogen production and storage model, namely:

[0145]

[0146] Where: and They represent the hydrogen production and carbon emissions from natural gas at the mth centralized hydrogen production station during period t respectively; represents the gas consumption of the mth centralized hydrogen production station during period t; η G2H represents the efficiency of hydrogen production from natural gas, ε CE represents the carbon emission coefficient in the process of producing hydrogen from natural gas; q H ,q G They are hydrogen and natural gas lower calorific value; Indicates the upper and lower limits of natural gas hydrogen production;

[0147] 2) Construct a correlation model between the amount of hydrogen produced by water electrolysis and power consumption in a centralized hydrogen production station, namely:

[0148]

[0149] Where: U el,t and I el,t represents the operating voltage and current density of the alkaline electrolytic cell at time t; U revis the reversible voltage, that is, the open circuit voltage of the electrolytic cell when the current density is 0; r1 and r2 are the resistance and thermal resistance parameters of the electrolytic cell, T el is the average operating temperature of the electrolytic cell, R el is the effective reaction area of ​​the electrolytic cell, s1, s2, s3, s4, s5, s6 are the electrode overvoltage fitting coefficients; N el is the number of electrolytic cells; represents the electrolysis power of the mth centralized hydrogen production station electrolyzer at time t; represents the hydrogen production of the electrolyzer of the mth centralized hydrogen production station at time t, λ H is the standard density of hydrogen, η f is the Faraday efficiency, F is the Faraday constant; The upper and lower limits of the electrolytic power of the electrolytic cell;

[0150] 3) Construct a correlation model between the power consumption of the compressor of the centralized hydrogen production station and the amount of hydrogen produced, namely:

[0151]

[0152] Where: represents the power consumption of the compressor of the mth centralized hydrogen production station at time t, C H is the specific heat capacity constant of hydrogen, T com is the average operating temperature of the compressor, η com is the compressor working efficiency, B is the inlet and outlet gas pressure ratio, and ε is the hydrogen isentropic coefficient. is the maximum operating power of the compressor;

[0153] 4) Construct the operation constraints of hydrogen storage tanks in centralized hydrogen production stations, namely:

[0154]

[0155] Where: represents the pressure and hydrogen change of the hydrogen storage tank of the mth centralized hydrogen production station at time t, R H is the molar gas constant, T H is the average temperature in the hydrogen storage tank, is the hydrogen storage tank capacity of the mth centralized hydrogen production station, M H is the molar mass of hydrogen. It represents the hydrogen refueling amount of the kth HT vehicle in the mth centralized hydrogen production station at time t. Indicates the upper and lower limits of the hydrogen storage tank pressure. Indicates the hydrogen storage tank pressure at the start and end of the scheduling cycle. Ω HPS represents a collection of centralized hydrogen production stations; Indicates the gas pressure of the hydrogen storage tank of the mth centralized hydrogen production station at time t-1;

[0156] 5) Construct the operation constraints of the distributed on-site hydrogen production and refueling station, including the electrolyzer operation constraints (2)-(5) and the operation constraint (9); construct the operation constraints of the distributed off-site hydrogen supply and refueling station, including the operation constraint (9);

[0157]

[0158] Where: Indicates the change in hydrogen tank pressure and hydrogen volume at the nth hydrogen refueling station at time t, is the hydrogen storage tank capacity of the nth hydrogen refueling station, and represents the hydrogen consumption power and power generation power of the hydrogen fuel cell vehicle participating in the H2G mode in the nth hydrogen refueling station, η fc is the power generation efficiency of hydrogen fuel cells. fc , β fc is the empirical fitting coefficient of hydrogen fuel cell power generation efficiency, and the subscript r represents the rated operating condition. It represents the hydrogen production of electrolyzer n in the hydrogen refueling station at time t, Indicates the amount of hydrogen released by the kth HT in hydrogen refueling station n at time t. Ω on and Ω off They represent the collection of hydrogen refueling stations inside the station and hydrogen refueling stations outside the station respectively; It represents the amount of hydrogen refueled by a hydrogen fuel vehicle at the nth hydrogen refueling station at time t. represents the rated power generation of the hydrogen fuel cell vehicle participating in the H2G mode in the nth hydrogen refueling station; η fc,r is the rated power generation efficiency of the hydrogen fuel cell;

[0159] 6) Considering the driving path of the hydrogen long-tube trailer, the relationship constraints between the driving path and the spatial position are established, namely:

[0160]

[0161] Where: r i,j,k A is a 0-1 logical variable. If it is 1, it means the driving path of the kth HT is (i, j). Otherwise, it means the driving path is not (i, j). i,t,k A is a 0-1 logical variable, 1 means the kth HT is located at hydrogen production station / hydrogen refueling station i at time t; i,ts,k , A i,te,k 0-1 logical variables representing the start and end times of the scheduling period respectively;

[0162] 7) Establish constraints on the amount of hydrogen transported by hydrogen long-tube trailers, namely:

[0163]

[0164] Where: Q i,t,k , ΔQ i,t,krepresents the hydrogen storage amount and hydrogen change in the kth hydrogen long tube trailer located in station i at time t; α i,t,k , β i,t,k Q is a 0-1 logical variable, indicating the hydrogenation and dehydrogenation status of the hydrogen long-tube trailer. If it is 1, it means that the kth hydrogen long-tube trailer is refueling and dehydrogenating in station i at time t; k,cap represents the upper limit of hydrogen storage of the kth hydrogen tube trailer; λ cap,min Indicates the minimum hydrogen storage coefficient of the hydrogen long tube trailer; Q i,ts,k and Q i,te,k represents the hydrogen storage capacity of the kth hydrogen long tube trailer at the start and end of the scheduling period respectively; Q j,t+1,k , Q j,t,k , Q j,t-1,k They represent the hydrogen storage capacity in the kth hydrogen long tube trailer located in station j at time t+1, time t, and time t-1 respectively;

[0165] 8) Taking the minimum travel time cost as the path selection standard for all users in the transportation network, static mixed user equilibrium is used to describe the state that the transportation network spontaneously reaches, that is:

[0166]

[0167] Where: h p is the traffic flow of path p, The travel time cost required for HFCV and vehicles other than HFCV to choose path p, v ij is the minimum travel time cost of all paths between travel demand pairs (i→j), W hv , W o is the set of travel demand pairs of HFCV and vehicles other than HFCV, is the set of vehicle paths of all HFCVs and other vehicles except HFCVs between travel demand pairs (i→j);

[0168] 9) Based on the BPR function, a road impedance model is established to describe the road congestion effect, as shown below:

[0169]

[0170] Where: τ p1 (h p ) represents the traffic volume h on road p p The relevant transit time function, represents the free travel time of road p, that is, the vehicle travel time when there is no traffic flow on road p, c p represents the traffic capacity of road p; P ij is the set of all paths between travel demand pairs (i→j);

[0171] 10) Based on the improved Davidson function, a hydrogen refueling queue time model is constructed, namely:

[0172]

[0173] Where: τ p2 (h p ) represents the traffic volume h on road p p The relevant transit time function, Indicates the hydrogen refueling time of a single HFCV, represents the limit of vehicles that can be refueled at the same time at a hydrogen refueling station, R is the function shape parameter; P H This is the collection of hydrogenation roads after topology change.

[0174] Embodiment 4:

[0175] A virtual energy pool control space characterization method considering the electric-hydrogen-traffic coupling characteristics, the technical content is the same as any one of embodiments 1-3, further, formulas (12)-(14) constitute a traffic flow model; the traffic flow model uses an "all-or-nothing allocation" method to allocate traffic flow to each section, thereby outputting all h p gather.

[0176] Embodiment 5:

[0177] A method for characterizing a virtual energy pool control space considering the electric-hydrogen-transportation coupling characteristics, the technical content of which is the same as any one of Embodiments 1-4, and further, the objective function C of the electric-hydrogen-transportation virtual energy pool optimization operation model is as follows:

[0178] minC=C P,buy +C HP +C curt +C CE +C HT (16)

[0179] Electricity purchase cost C P,buy 、Hydrogen production cost C HP , Penalty cost for wind and solar power abandonment C curt 、Carbon emission cost C CE and the operating cost of hydrogen tube trailer C HT They are as follows:

[0180]

[0181] Where: c Pbuy,t P represents the price of electricity purchased from the upper power grid at time t; grid,t It represents the active power purchased from the superior power grid at time t; Δt represents the unit time interval.

[0182]

[0183] Where: c G is the gas purchase price, c PSA is the hydrogen purification cost coefficient, Δt is the unit time interval, N p is the number of centralized hydrogen production stations in EHT-VEP. represents the gas consumption of the mth centralized hydrogen production station during period t; represents the hydrogen production of the mth centralized hydrogen production station at time t;

[0184]

[0185] Where: They represent the abandoned wind and solar power of the wind and solar power unit at the node i at time t; c curt N is the penalty cost per unit of wind and solar power abandonment; B Indicates the number of distribution network nodes.

[0186]

[0187] Where: CE represents the unit cost coefficient of carbon emissions; ε g2h Represents the carbon emission coefficient in the process of hydrogen production from natural gas, η G2H represents the efficiency of hydrogen production from natural gas, q H is the lower calorific value of hydrogen; ε grid Indicates the carbon emission coefficient of electricity purchased by the superior power grid.

[0188]

[0189] Where: c HT represents the unit storage and transportation cost of hydrogen for long-tube trailers, N k The number of EHT-VEP medium and long tube trailers. Represents the amount of hydrogen refueled by the kth HT vehicle at time t.

[0190] Embodiment 6:

[0191] A method for characterizing the control space of a virtual energy pool taking into account the coupling characteristics of electricity, hydrogen and transportation. The technical content is the same as any one of Examples 1-5. Furthermore, the constraints of the electricity-hydrogen-transportation virtual energy pool optimization operation model include distribution network flow constraints, node power balance constraints, safe operation constraints, distributed power supply operation constraints, and traffic flow balance constraints.

[0192] Embodiment 7:

[0193] A method for characterizing a virtual energy pool control space considering the coupling characteristics of electricity, hydrogen and transportation, the technical content of which is the same as any one of Embodiments 1-6, and further, the power flow constraints of the distribution network are as follows:

[0194]

[0195] Where: v(j) and w(j) represent the first node set and the last node set of the branch connected to node j respectively; P ij,t , Q ij,t represents the active power and reactive power of branch ij at time t; r ij and x ij Represents the resistance and reactance of branch ij; P j,t , Q j,t I represents the active and reactive power injected into node j at time t; ij,t represents the branch ij current at time t; U j,t U represents the voltage of node j at time t. i,t P represents the voltage of node i at time t. jk,t , Q jk,t It represents the active power and reactive power of branch jk at time t;

[0196] The node electrical power balance constraints are as follows:

[0197]

[0198]

[0199] Where: P WG,i,t , Q WG,i,t P represents the actual active power and reactive power generated by wind turbine i at time t; PV,i,t , Q PV,i,t P represents the actual active power and reactive power generated by the photovoltaic unit at node i at time t; load,i,t and Q load,i,t represents the conventional active load and reactive load of node i at time t; s is the access node of the interconnection line.

[0200] The safe operating constraints are as follows:

[0201]

[0202] Where: They represent the upper and lower limits of the voltage allowed at node i respectively; They represent the upper and lower limits of the current allowed for line ij respectively;

[0203] The distributed generation operation constraints are as follows:

[0204]

[0205] Where: and Indicates the predicted active power generated by the wind and solar generator connected to node i; and Indicates the set power factor of the wind and solar generator set. They represent the abandoned wind and solar power of the wind and solar power generator at the node i at time t respectively;

[0206] The traffic flow balance constraints are as follows:

[0207]

[0208] Where: H Indicates the proportion of vehicles that need hydrogen refueling; h p,t represents the traffic flow on road p at time t; Indicates the average amount of hydrogen refueled in a hydrogen fuel cell vehicle.

[0209] Embodiment 8:

[0210] A method for characterizing a virtual energy pool control space considering the coupling characteristics of electricity, hydrogen and transportation, the technical content of which is the same as any one of embodiments 1-7, and further, the steps of constructing an electricity, hydrogen and transportation fixed carbon emission operation domain are as follows:

[0211] 1) Define the operating point Z that represents the operating state of EHT-VEP, that is:

[0212]

[0213] In the formula, Respectively represent the dimension N B ×T、N L ×T real number space;

[0214] 2) Construct the carbon emission operation domain expression of electricity-hydrogen-transportation, namely:

[0215]

[0216] Where: Ω CR is the fixed carbon emission operation domain; U is the node voltage matrix; I is the branch current matrix; P and Q are the node injected active and reactive power matrices respectively; H represents the node hydrogen load demand matrix; f(x,y)=0 represents the electric hydrogen energy balance constraint; Represents the system safe operation constraints, including voltage constraints and thermal stability constraints; represents the node injection power constraint, including the operation constraint of the electric-hydrogen coupling equipment and the operation constraint of the distributed power source; E(y)≤Bmax 3 represents the system carbon emission constraint, as shown in the following formula; B1, B2 and B3 represent the critical value of safe operation, the critical value of injection power and the carbon emission limit respectively; the superscripts max and min represent the upper and lower bounds; N B and N L represents the number of nodes and branches; T is the scheduling period.

[0217] 3) Establish a fixed carbon emission operation domain transformation model under second-order cone relaxation, transform the fixed carbon emission operation domain, and obtain:

[0218]

[0219] Where: A, B, C are coefficient matrices in equality constraints; D, F are coefficient matrices in linear inequalities; H, V are coefficient matrices in SOC constraints. W is the node voltage square matrix; L is the branch current square matrix. D , Q D represents the node active and reactive load matrix; P G , Q G Represents the active and reactive output matrix of the node unit. Ω SCR It is the fixed carbon emission operation domain after conversion.

[0220] Embodiment 9:

[0221] A method for characterizing a virtual energy pool control space considering the coupling characteristics of electricity, hydrogen and transportation, the technical content of which is the same as any one of embodiments 1-8, and further, the steps of characterizing the low-carbon control space of the electricity, hydrogen and transportation virtual energy pool are as follows:

[0222] 1) Based on the typical operation state of EHT-VEP, the EHT-VEP power flow distribution is obtained as the initial working point Z0. Based on the initial working point Z0, the carbon emission flow is calculated and the node carbon emission factor is obtained as the basis for selecting the reduced dimension observation variable, namely:

[0223]

[0224] Where: B , L represents the node and branch carbon emission factor matrix respectively; Y represents the distribution network node association matrix; P L represents the branch power flow distribution matrix; ρ G is the unit carbon emission factor matrix;

[0225] 2) Project the high-dimensional fixed carbon emission operation domain to the node load space, and select the n-dimensional node electrical load as the observed variable according to the carbon emission distribution, that is:

[0226]

[0227] Where: K obs represents the set of observation variables to be selected, where k is a 0-1 variable of the observation variable selection state, k i =1 means that the node i load is selected as the observed variable. and N B dimensional and T-dimensional unit row vectors;

[0228] The fixed carbon emission operation domain in the reduced-dimensional observation space is as follows:

[0229]

[0230] Where: f(p,q)=0 represents the equality constraint including the electric hydrogen energy balance; g(p,q)≤0 represents the inequality constraint including the safe operation constraint and carbon emission constraint; Ω SCRL represents the fixed carbon emission operation domain in the reduced-dimensional observation space;

[0231] 3) Based on Ω SCRL Perform CCEOR boundary convex hull fitting and iteratively shrink the convex hull CCEOR according to the second-order cone relaxation gap; the fitting target is as follows:

[0232]

[0233] Where: z(p) represents the objective function set for solving the boundary point, and the subscripts u and d represent the upper boundary and the lower boundary respectively. c represents n-1 dimensional fixed observation variables.

[0234] The fitting constraints are as follows:

[0235]

[0236] Where: L s+1 is the branch current square matrix of the s+1th iteration; is the precise branch current square matrix in the sth iteration. T is a real matrix; gap max is the maximum relaxation gap allowed during the iteration process.

[0237] Embodiment 10:

[0238] A method for characterizing a virtual energy pool control space considering the coupling characteristics of electricity, hydrogen and transportation, the technical content of which is the same as any one of Examples 1-9, and further, the steps of geometrically evaluating a low-carbon control space based on a fixed carbon emission operation domain are as follows:

[0239] 1) Construct a low-carbon regulation spatial geometric evaluation index system, including the EHT-VEP low-carbon regulation spatial geometric evaluation index and the EHT-VEP observed variable coupling characteristic geometric evaluation index;

[0240] The EHT-VEP low-carbon regulation space geometric evaluation indicators include low-carbon safe operation margin, low-carbon operation ample space, and dimension reduction cutoff area;

[0241] The low carbon safety operating margin is as follows:

[0242]

[0243] Where p is the selected observed variable; d(p) is the low-carbon safety operation margin; p * is the feasible space of observed variables;

[0244] The ample space for low-carbon operation is as follows:

[0245]

[0246] In the formula, and They are z u (p) and z d (p) takes the optimal value. CR Allow ample room for low-carbon operation;

[0247] The dimensionality reduction cut-off area is as follows:

[0248]

[0249] In the formula, p i is the observed variable of the i-th dimension; Π is the fixed plane; S CR (p i ) is the cut-off area for dimensionality reduction;

[0250] The geometric evaluation indexes of the EHT-VEP observed variable coupling characteristics include observed variable coupling coefficient, average change rate of truncation surface, and multi-dimensional balance;

[0251] The observed variable coupling coefficients are as follows:

[0252]

[0253] In the formula, the range of CF is (0, +∞). The larger the CF, the higher the coupling degree between the observed variables, which means that the change of a certain dimension of observed variables has a more significant impact on other observed variables, and the easier it is to approach the system's fixed carbon operation boundary, and there is a risk of excess carbon emissions. RT 、max S CCEOR (p i ) is the area of ​​a rectangle of equal length and width and the maximum SA area;

[0254] The average change rate ACR of the truncation surface is as follows:

[0255]

[0256] In the formula, S CR (p i +Δp i ), S CR (p i ) is the observed variable p i +Δp i, the dimension reduction cutoff area corresponding to the observed variable pi; the multidimensional balance degree ED is as follows:

[0257]

[0258] Where: Vn(maxd(p)) represents the volume of the n-dimensional hypersphere with radius maxd(p); V CR Allow ample room for low-carbon operation;

[0259] 2) Conduct a low-carbon regulation spatial geometry assessment, including the following steps:

[0260] 2.1) Given the initial working point make Solve equations (46)-(47) to obtain Initial feasible range Repeatedly fix the 2D observation variables to obtain the feasible space for initializing the observation variables

[0261] 2.2) Set the iteration step size Δp and the maximum relaxation gap gap max , fixed one-dimensional observation variable make Solve equations (46)-(47) to obtain the upper and lower boundary points and And let p 2 Gradually approach with iterative step size growth Get multiple sets of boundary points and add them to p op ;

[0262] 2.3) Order And gradually increase the iterative step size to approach Repeat step 2.2) to obtain multiple sets of boundary points and add them to p op ;

[0263] 2.4) Repeat steps 2.2) and 2.3) until all dimensional observation variables are traversed to obtain the boundary point set p op , based on the fast convex hull algorithm to obtain the current p op Minimal convex hull

[0264] 2.5) Based on the current p op , add cutting plane constraints and iteratively update p op , until all boundary points satisfy gap≤gap max , and iteratively shrink Fitting the shrinking convex hull CCEOR.

[0265] 2.6) Based on the proposed CCEOR geometric evaluation index system, according to step ⑤, we can obtain Corresponding convex hull vertex set Solve equations (50)-(55) and output the CCEOR geometric evaluation index.

[0266] Embodiment 11:

[0267] A virtual energy pool control space characterization method considering the electricity-hydrogen-transportation coupling characteristics, comprising the following steps:

[0268] 1) Construct a virtual energy pool operation mode that takes into account the coupling characteristics of electricity, hydrogen and transportation.

[0269] 1.1) Analyze the flexible operation characteristics of the electricity-hydrogen-transportation virtual energy pool;

[0270] The electricity-hydrogen-transportation virtual energy pool (EHT-VEP) refers to a virtual operation architecture composed of a regional hydrogen energy system (RHES) that uses electricity and hydrogen as core energy carriers and integrates power networks and transportation networks. It can effectively aggregate distributed hydrogen energy storage resources in RHES as large-capacity backup energy storage on the grid side, and utilize the flexible time and space transfer characteristics of hydrogen energy "production-storage-transmission-use" to achieve electricity conversion, storage and release, and assist in grid-side power support. RHES includes centralized hydrogen production stations, distributed hydrogen refueling stations, hydrogen trucks (HT) and hydrogen fuel cell vehicles (HFCV), such as Figure 2 shown.

[0271] 1.2) Establish a flexible operation model for the electricity-hydrogen-transportation virtual energy pool

[0272] Centralized hydrogen production station (CHPS) mainly produces hydrogen from natural gas. At the same time, the station is equipped with a water electrolysis hydrogen production device to use idle hydrogen energy storage resources to provide equivalent energy storage services for the power system. The CHPS hydrogen production and storage model is as follows:

[0273]

[0274] Where: and They represent the hydrogen production and carbon emissions of the mth CHPS in period t respectively; represents the gas consumption of the mth CHPS in period t; η G2H represents the efficiency of hydrogen production from natural gas, ε CErepresents the carbon emission coefficient in the process of producing hydrogen from natural gas; q H ,q G They are hydrogen and natural gas lower calorific value; Indicates the upper and lower limits of hydrogen production from natural gas.

[0275] CHPS uses water electrolysis to produce hydrogen as an auxiliary hydrogen production method and uses low-cost alkaline electrolyzers as water electrolysis hydrogen production equipment. According to the empirical model, the nonlinear characteristic relationship between the electrolysis voltage, current density and operating temperature of a single electrolytic cell can be established, as shown in formula (2).

[0276]

[0277] Where: U el,t and I el,t represents the operating voltage and current density of the alkaline electrolytic cell at time t; U rev is the reversible voltage, that is, the open circuit voltage of the electrolytic cell when the current density is 0; r1 and r2 are the resistance and thermal resistance parameters of the electrolytic cell, T el is the average operating temperature of the electrolytic cell, R el is the effective reaction area of ​​the electrolytic cell, and s1-s6 are the electrode overvoltage fitting coefficients.

[0278] In order to increase the hydrogen production, the water electrolysis hydrogen production method based on alkaline electrolyzer usually consists of multiple electrolytic cells connected in parallel to form an array. According to the series and parallel relationship between the current and voltage of multiple electrolytic cells, the correlation between the power consumption of hydrogen production and the operating voltage and current can be established as shown in formula (3).

[0279]

[0280] According to Faraday's law, the relationship between the amount of hydrogen produced by water electrolysis and the power consumption is further established as shown in formula (4). In order to ensure the continuity of the hydrogen production process, formula (5) describes the safe operating range of the electrolyzer.

[0281]

[0282] Where: N el is the number of electrolytic cells; represents the electrolysis power of the mth CHPS electrolyzer at time t; represents the hydrogen production of the mth CHPS electrolyzer at time t, λ H is the standard density of hydrogen (taken under standard conditions as 0.09kg / m 3 ), η f is the Faraday efficiency, and F is the Faraday constant (taken as 96485C / mol). The upper and lower limits of the electrolytic power of the electrolytic cell.

[0283] The hydrogen produced by CHPS must be pressurized by a compressor, stored in a high-pressure hydrogen storage tank and transported to various hydrogen refueling stations by a long-tube trailer.

[0284] Formula (6) describes the relationship between the power consumption of the compressor and the amount of hydrogen produced, and formula (7) is the compressor working limit constraint.

[0285]

[0286] Where: represents the power consumption of the mth CHPS compressor at time t, C H is the specific heat capacity constant of hydrogen, T com is the average operating temperature of the compressor, η com is the compressor working efficiency, B is the inlet and outlet gas pressure ratio, and ε is the hydrogen isentropic coefficient.

[0287] is the maximum operating power of the compressor.

[0288] CHPS produces hydrogen with similar purity through two methods and can use hydrogen storage tanks of the same specifications for storage. The operating constraints of the hydrogen storage tanks are shown in formula (8).

[0289]

[0290] Where: represents the pressure and hydrogen change of the mth CHPS hydrogen storage tank at time t, R H is the molar gas constant, T H is the average temperature in the hydrogen storage tank, is the capacity of the mth CHPS hydrogen storage tank, M H is the molar mass of hydrogen. It represents the hydrogen refueling amount of the kth HT in the mth CHPS at time t. Indicates the upper and lower limits of the hydrogen storage tank pressure. Indicates the hydrogen storage tank pressure at the start and end of the scheduling cycle. Ω HPS Represents a collection of centralized hydrogen production stations.

[0291] Distributed hydrogen refueling stations can be divided into two categories according to the different sources of hydrogen supply: on-site hydrogen production and refueling stations (hereinafter referred to as on-site hydrogen refueling stations) and off-site hydrogen supply and refueling stations (hereinafter referred to as off-site hydrogen refueling stations). Off-site hydrogen refueling stations use hydrogen long-tube trailers to transport hydrogen to meet the hydrogen refueling needs of hydrogen fuel vehicles on the station. On-site hydrogen refueling stations are equipped with water electrolysis hydrogen production devices, which can meet the on-site hydrogen refueling needs through two methods: electrolysis and hydrogen long-tube trailers. The operating constraints of the electrolyzer are the same as those of equations (2)-(5), and other operating constraints are the same as those of off-site hydrogen refueling stations, such as equation (9).

[0292]

[0293] Where: Indicates the change in hydrogen tank pressure and hydrogen volume at the nth hydrogen refueling station at time t, is the hydrogen storage tank capacity of the nth hydrogen refueling station, and represents the hydrogen consumption power and power generation power of the hydrogen fuel cell vehicle participating in the H2G mode in the nth hydrogen refueling station, η fc is the power generation efficiency of hydrogen fuel cells. fc , β fc is the empirical fitting coefficient of hydrogen fuel cell power generation efficiency, and the subscript r represents the rated operating condition. It represents the hydrogen production of electrolyzer n in the hydrogen refueling station at time t, Indicates the amount of hydrogen released by the kth HT in hydrogen refueling station n at time t. Ω on and Ω off They represent the collection of on-site hydrogen refueling stations and off-site hydrogen refueling stations respectively.

[0294] Considering the driving path of the hydrogen long tube trailer, the relationship constraint between the driving path and the spatial position is established as shown in formula (10).

[0295]

[0296] Where: r i,j,k A is a 0-1 logical variable. If it is 1, it means the driving path of the kth HT is (i, j). Otherwise, it means the driving path is not (i, j). i,t,k It is a 0-1 logical variable, where 1 indicates that the kth HT is located at hydrogen production station / hydrogen refueling station i at time t.

[0297] Formula (11) describes the hydrogen transport capacity constraint of hydrogen tube trailer.

[0298]

[0299] Where: Q i,t,k , ΔQ i,t,k represents the hydrogen storage amount and hydrogen change in the kth hydrogen long tube trailer located in station i at time t; α i,t,k , β i,t,k Q is a 0-1 logical variable, indicating the hydrogenation and dehydrogenation status of the hydrogen long-tube trailer. If it is 1, it means that the kth hydrogen long-tube trailer is refueling and dehydrogenating in station i at time t; k,cap represents the upper limit of hydrogen storage of the kth hydrogen tube trailer; λ cap,min Indicates the minimum hydrogen storage coefficient of the hydrogen long tube trailer; Q i,ts,k and Q i,te,k They represent the hydrogen storage capacity of the kth hydrogen tube trailer at the start and end of the scheduling period respectively.

[0300] If all users in a traffic network containing HFCVs select routes based on the minimum travel time cost, this paper considers the presence of HFCVs and other vehicles in the traffic network and adopts static mixed user equilibrium (MUE) to describe the state that the traffic network spontaneously reaches. When the network reaches the MUE state, the total travel time cost required for any demand on all used paths is equal and not greater than that of all unused paths, which can be described in mathematical language as shown in Equation (12).

[0301]

[0302] Where: h p is the traffic flow of path p, The travel time cost required for HFCV (other vehicles) to choose path p, v ij is the minimum travel time cost of all paths between travel demand pairs (i→j), W hv (W o ) is the set of HFCV (other vehicles) travel demand pairs, is the set of all HFCV (other vehicles) paths between travel demand pairs (i→j).

[0303] The road congestion effect describes the relationship between road traffic flow and travel time in a real traffic system. It can be compared to the circuit impedance characteristics and regarded as a special road impedance. In existing studies, the road impedance model is usually established using the BPR function to describe the road congestion effect, as shown below:

[0304]

[0305] Where: τ p1 (h p ) represents the traffic volume h on road p p The relevant transit time function, represents the free travel time of road p, that is, the vehicle travel time when there is no traffic flow on road p, c p represents the traffic capacity of road p. It should be noted that c p It is not the road limit of road p, but it means that when h p >c p , the turning point where the road travel time begins to increase significantly. ij is the set of all paths between travel demand pairs (i→j).

[0306] For HFCVs with hydrogen refueling needs, the HFCV travel time includes not only the road driving time, but also the queuing time and hydrogen refueling time at the hydrogen refueling station. For the roads where the hydrogen refueling stations are located, hydrogen refueling sections are introduced to simulate the HFCV queuing behavior for hydrogen refueling, and bypass roads are introduced to ensure the integrity of the traffic network topology when vehicles without hydrogen refueling needs pass through. For HFCVs or other vehicles without hydrogen refueling needs, the vehicles pass quickly through the hydrogen refueling station bypass road. For HFCVs with hydrogen refueling needs, HFCVs pass through the hydrogen refueling channel and spend a certain amount of hydrogen refueling time. The improved Davidson function is used to model the hydrogen refueling queue time:

[0307]

[0308] Where: τ p2 (h p ) represents the traffic volume h on road p p The relevant transit time function, Indicates the hydrogen refueling time of a single HFCV, represents the limit of vehicles that can be refueled at the same time at a hydrogen refueling station, R is the function shape parameter, usually 0.5, P H This is the collection of hydrogenation roads after topology change.

[0309] For bypass roads, their travel time can be ignored and considered to be zero, that is,

[0310]

[0311] Where: P S is the set of bypass paths after the topology change.

[0312] Based on the above traffic flow model, the “all or nothing allocation” method is used to allocate the traffic flow of each road section. When the iteration reaches the convergence accuracy or the maximum number of iterations, all h p gather.

[0313] 2) Establish an optimized operation model of the electricity-hydrogen-transportation virtual energy pool taking into account flexible operation characteristics.

[0314] 2.1) Objective Function

[0315] Considering the dispatching cost of each link of EHT-VEP, the power purchase cost C P,buy 、Hydrogen production cost C HP , Penalty cost for wind and solar power abandonment C curt 、Carbon emission cost C CE and the operating cost of hydrogen tube trailer C HT The total operating cost C of the sum is the lowest as the optimization goal, as shown in the following formula:

[0316] minC=C P,buy +CHP +C curt +C CE +C HT

[0317] The specific cost items are as follows:

[0318] ① Electricity purchase cost C P,buy That is, the cost of electricity purchased by the distribution network from the upper power grid in EHT-VEP is:

[0319]

[0320] Where: c Pbuy,t P represents the price of electricity purchased from the upper power grid at time t; grid,t It represents the active power purchased from the superior power grid at time t; Δt represents the unit time interval.

[0321] ②Hydrogen production cost C HP That is, the hydrogen production cost of the centralized hydrogen production station in EHT-VEP, including the natural gas purchase cost and hydrogen purification cost:

[0322]

[0323] Where: c G is the gas purchase price, c PSA is the hydrogen purification cost coefficient, Δt is the unit time interval, N p is the number of CHPS in EHT-VEP.

[0324] ③ Penalty cost for wind and solar power abandonment C curt EHT-VEP should absorb the internally connected renewable energy to the greatest extent possible and provide equivalent energy storage services for the power system. If it cannot be fully absorbed, penalty costs will be incurred:

[0325]

[0326] Where: They represent the abandoned wind and solar power of the wind and solar power unit at the node i at time t; c curt N is the penalty cost per unit of wind and solar power abandonment; B Indicates the number of distribution network nodes.

[0327] ④Carbon emission cost C CE EHT-VEP carbon emissions come from the natural gas hydrogen production process of the centralized hydrogen production station and the equivalent carbon emissions of purchased electricity. EHT-VEP pays a certain carbon emission cost based on the carbon emissions:

[0328]

[0329] Where: CE represents the unit cost coefficient of carbon emissions; εg2h Represents the carbon emission coefficient in the process of hydrogen production from natural gas, η G2H represents the efficiency of hydrogen production from natural gas, q H is the lower calorific value of hydrogen; ε grid Indicates the carbon emission coefficient of electricity purchased by the superior power grid.

[0330] ⑤Long-tube trailer operating cost C HT That is, the cost of transporting and storing hydrogen by long-tube trailer:

[0331]

[0332] Where: c HT represents the unit storage and transportation cost of hydrogen for long-tube trailers, N k The number of EHT-VEP medium and long tube trailers.

[0333] 2.2) Constraints

[0334] ①Distribution network power flow constraints

[0335] This paper adopts the Distflow branch model widely used in distribution networks to describe the nonlinear power flow constraints of AC distribution networks, as shown in Equation (22).

[0336]

[0337] Where: v(j) and w(j) represent the first node set and the last node set of the branch connected to node j respectively; P ij,t , Q ij,t represents the active power and reactive power of branch ij at time t; r ij and x ij Represents the resistance and reactance of branch ij; P j,t , Q j,t I represents the active and reactive power injected into node j at time t; ij,t represents the branch ij current at time t; U j,t represents the voltage of node j at time t.

[0338] ②Node power balance constraints

[0339] Formulas (23)-(24) represent the active power and reactive power balance constraints of conventional nodes (i.e., nodes not coupled with the hydrogen energy system); Formula (25) represents the active power balance constraints of the access nodes of centralized hydrogen production stations; Formula (26) represents the active power balance constraints of the access nodes of on-site hydrogen refueling stations; Formula (27) represents the active power balance constraints of the access nodes of off-site hydrogen refueling stations; Formulas (28)-(29) represent the active power and reactive power balance constraints of the distribution network connection nodes.

[0340]

[0341] Where: P WG,i,t , Q WG,i,t P represents the actual active power and reactive power generated by wind turbine i at time t; PV,i,t , Q PV,i,t P represents the actual active power and reactive power generated by the photovoltaic unit at node i at time t; load,i,t and Q load,i,t represents the conventional active load and reactive load of node i at time t; s is the access node of the interconnection line.

[0342] ③Safe operation constraints

[0343] Formula (30) is the voltage deviation constraint of the distribution network node; Formula (31) is the thermal stability constraint of the distribution network line.

[0344]

[0345] Where: They represent the upper and lower limits of the voltage allowed at node i respectively; They represent the upper and lower limits of the allowed current for line ij respectively.

[0346] ④Distributed power supply operation constraints

[0347] Formulas (32)-(37) are the operating constraints of the wind and solar generators in the system, where formulas (32)-(33) constrain the actual output active power of the wind and solar generators to be equal to the predicted output active power of the wind and solar generators minus the abandoned wind and solar active power that cannot be absorbed by the system. Formulas (34)-(35) indicate that the actual output active power of the wind and solar generators cannot be greater than the predicted value. Formulas (36)-(37) indicate that the output reactive power of the wind and solar generators is a constant power factor of active power.

[0348]

[0349] Where: and Indicates the predicted active power generated by the wind and solar generator connected to node i; and Indicates the set power factor of the wind and solar generator set.

[0350] ⑤Traffic flow balance constraints

[0351] The traffic flow balance constraint is shown in Equation (12), and Equation (38) represents the hydrogen refueling demand constraint of hydrogen fuel vehicles in the traffic flow.

[0352]

[0353] Where: H Indicates the proportion of vehicles that need hydrogen refueling; h p,t represents the traffic flow on road p at time t; Indicates the average amount of hydrogen refueled in a hydrogen fuel cell vehicle.

[0354] 3) Propose the theory of carbon emission operation domain of electricity-hydrogen-transportation.

[0355] 3.1) Basic concepts of the electricity-hydrogen-transportation carbon emission operation domain

[0356] The fixed carbon emission operation domain of the electricity-hydrogen-transportation virtual energy pool is defined as: a set of operating points that meet the overall carbon emission level of the power grid dispatch cycle and the safe operation conditions at different time sections within the cycle. For EHT-VEP, its CCEOR describes the low-carbon feasible optimization space of EHT-VEP in response to internal uncontrollable variables (such as electricity and hydrogen load demand). For the convenience of explanation, the operating point Z that represents the operating state of EHT-VEP is defined;

[0357]

[0358] Therefore, CCEOR can be expressed as follows:

[0359]

[0360] Where: Ω CR is the fixed carbon emission operation domain; U is the node voltage matrix; I is the branch current matrix; P and Q are the node injected active and reactive power matrices respectively; H represents the node hydrogen load demand matrix; f(x,y)=0 represents the electric hydrogen energy balance constraint; Represents the system safe operation constraints, including voltage constraints and thermal stability constraints; represents the node injection power constraint, including the operation constraint of the electric-hydrogen coupling equipment and the operation constraint of the distributed power source; E(y)≤Bmax 3 represents the system carbon emission constraint, as shown in the following formula; B1, B2 and B3 represent the critical value of safe operation, the critical value of injection power and the carbon emission limit respectively; the superscripts max and min represent the upper and lower bounds; N B and N L represents the number of nodes and branches; T is the scheduling period.

[0361]

[0362] By using CCEOR to analyze the low-carbon regulation capability of EHT-VEP, it is possible to quantitatively evaluate the low-carbon regulation space of EHT-VEP, avoid EHT-VEP operation in a critical or out-of-bounds state, and guide the low-carbon regulation strategy of EHT-VEP, thereby providing effective guidance for the coordination and mutual assistance between EHT-VEP and the upper power grid. On the other hand, the reduced-dimensional CCEOR can be used as a constraint condition for the coordinated dispatch of EHT-VEP and the upper power grid to limit the boundary coupling variables, and reflect the coupling constraint relationship between specific observed variables according to the boundary characteristics. In addition, based on the low-carbon regulation space of EHT-VEP described by CCEOR and combined with the economic operation indicators of EHT-VEP, EHT-VEP can quantitatively evaluate the economy of the low-carbon operation point within CCEOR, and adjust the operation status of EHT-VEP in terms of low carbon, economy, and safety.

[0363] 3.2) Analysis of mathematical characteristics of the electric-hydrogen-transportation fixed carbon emission operation domain

[0364] The ability of EHT-VEP to carry the extreme electricity and hydrogen loads is limited by the system's safe operating parameters and carbon emission limits. In the node load space, as the electricity and hydrogen loads increase, some operating parameters of EHT-VEP approach the low-carbon safe operating limit. At the current operating point, the system operation reaches the constraint g i The parameter limit of (y, x) is called constraint g. i The boundary point under (y, x) is denoted by A certain boundary point may touch multiple sets of constraints. The effective constraints touched by the boundary point can be determined by post-verification during the solution process.

[0365] The set of all boundary points is denoted as y op By fitting the boundary through regression or convex envelope method, the load space of hydrogen that can be carried by EHT-VEP fixed carbon operation can be intuitively characterized. The distance between the boundary and the internal point can measure the low-carbon operation margin of the current operating point. Considering the Ω described by formula (3.2) CR For a non-convex nonlinear model, the CCEOR boundary solution is difficult and time-consuming. In order to achieve fast boundary solution and effective fitting, this section establishes a CCEOR transformation model under second order conic relaxation (SOCR). SCR The compact representation is as follows:

[0366]

[0367] Where: A, B, C are coefficient matrices in equality constraints; D, F are coefficient matrices in linear inequalities; H, V are coefficient matrices in SOC constraints. W is the node voltage square matrix; L is the branch current square matrix. D, Q D Represents the node active and reactive load (including conventional electric load, power consumption of electric-hydrogen coupling equipment) matrix; P G , Q G Represents the active and reactive output matrix of node units (including hydrogen fuel cells and distributed power sources).

[0368] 4) Establish a method for rapid characterization of the low-carbon regulation space of the electricity-hydrogen-transportation virtual energy pool.

[0369] 4.1) Observation space dimensionality reduction method based on carbon emission flow theory

[0370] Ω CR The mathematical essence of is a high-dimensional polyhedron in a given variable space, which is difficult to observe and apply directly. CR Projecting to the partial variable space and describing CCEOR with partial variables can realize the visual dimensionality reduction observation of CCEOR. In order to assist the virtual energy pool control center to quickly monitor the key factors affecting the low-carbon operation of the system, this paper proposes a method for optimizing dimensionality reduction observation variables to identify key influencing factors based on the carbon emission flow theory. In order to calculate the EHT-VEP carbon emission flow and select the key observation variables that affect the carbon emissions of the microgrid, firstly, based on the typical operating state of EHT-VEP, the EHT-VEP power flow distribution is obtained as the initial working point Z0. Based on the initial working point Z0, the carbon emission flow is calculated and the node carbon emission factor is obtained as the basis for selecting the dimensionality reduction observation variable:

[0371]

[0372] Where: B , L represents the node and branch carbon emission factor matrix respectively; Y represents the distribution network node association matrix; P L represents the branch power flow distribution matrix; ρ G is the carbon emission factor matrix of the unit. The carbon emission factor means the equivalent carbon emission value caused by the consumption / production of unit electricity.

[0373] Considering that the energy demand on the load side is the fundamental factor driving the system carbon emissions and guiding the operation results, the high-dimensional CCEOR is projected into the node load space, and according to the carbon emission distribution, the n-dimensional node electric load is selected as the observed variable:

[0374]

[0375] Where: K obs represents the set of observation variables to be selected, where k is a 0-1 variable of the observation variable selection state, k i =1 means that the node i load is selected as the observed variable. and N B -dimensional and T-dimensional unit row vectors.

[0376] The dimension reduction CCEOR describes the set of all observation points in a given n-dimensional observation variable space for which there is at least one feasible solution that satisfies the constraint set in the domain. SCR , let the selected observation variable be p and other state variables be q, then the compact representation of CCEOR in the reduced-dimensional observation space is as follows:

[0377]

[0378] In the formula: f(p,q)=0 represents the equality constraint including the electric-hydrogen energy balance; g(p,q)≤0 represents the inequality constraint including the safe operation constraint and the carbon emission constraint.

[0379] 4.2) Boundary convex hull shrinkage fitting method based on second-order cone relaxation

[0380] Considering the original Ω CR Including the non-convex constraints of the secondary power flow, the actual CCEOR is a polyhedron with concave features surrounded by non-convex constraints, which makes it difficult to achieve efficient and accurate fitting. SCRL It is essentially a convex relaxation of the original CCEOR, which provides a relaxed boundary for the exact CCEOR and enables fast search and solution of boundary points. Therefore, in order to balance the efficiency and fitting accuracy of CCEOR, we can use Ω SCRL Perform CCEOR boundary convex hull fitting and iteratively shrink the convex hull CCEOR according to the second-order cone relaxation gap.

[0381] For a given observation variable p, fix the n-1-dimensional observation variable according to a certain step size, and obtain multiple sets of optimal solutions p by repeatedly solving the following optimization problem: * The set of boundary points p op :

[0382]

[0383] Where: z(p) represents the objective function set for solving the boundary point, and the subscripts u and d represent the upper boundary and the lower boundary respectively. c represents n-1 dimensional fixed observation variables.

[0384] For the above optimization problem of solving boundary points, second-order cone relaxation will expand the original feasible domain of boundary points, and over-relaxation may occur, resulting in infeasible flow. Therefore, the optimal value obtained is the lower bound of the global optimal value of the original solution problem. The convex hull surrounded by over-relaxed boundary points is further expanded on the basis of the original fixed carbon domain, containing a large number of infeasible points. To this end, the present invention introduces the idea of ​​cutting planes, iteratively adds cutting plane constraints (3.20) during the relaxation process of boundary points, and realizes convex hull shrinkage to reduce infeasible points in the convex hull CCEOR.

[0385]

[0386] Where: L s+1 is the branch current square matrix of the s+1th iteration; is the precise branch current square matrix in the sth iteration.

[0387] The maximum relaxation gap allowed during the iteration process is expressed as follows:

[0388]

[0389] 5) Establish a low-carbon regulation spatial geometry assessment method based on a fixed carbon emission operating domain.

[0390] 5.1) Constructing a low-carbon regulation spatial geometry evaluation index system

[0391] ①EHT-VEP low-carbon regulation spatial geometry evaluation index

[0392] The low-carbon operation capability of EHT-VEP is limited by multi-dimensional coupling constraints such as the spatiotemporal distribution of source and load, equipment operation characteristics, and carbon emission targets. Converting EHT-VEP operation limiting factors into CCEOR geometric features can greatly simplify the complexity of evaluating the low-carbon operation capability of EHT-VEP.

[0393] a. Low-carbon safety operation margin

[0394] The minimum Euclidean distance from the working point in the domain to the domain boundary is defined as the low-carbon safe operation margin, which represents the low-carbon operation margin that can be guaranteed by the operating point in the domain. When the operating point approaches the domain boundary, the system issues a margin shortage warning, and the dispatcher can adjust the working point or expand the domain boundary in time according to the margin information.

[0395]

[0396] b. Ample room for low-carbon operation

[0397] The ample space for EHT-VEP low-carbon operation is defined as the size of the high-dimensional geometric space enclosed by the CCEOR boundary, which represents the ample adjustment range of EHT-VEP while meeting the low-carbon controllable requirements.

[0398]

[0399] In the formula, p*u and p*d are z u (p) and z d (p) takes the optimal value.

[0400] c. Dimensionality reduction cut-off area

[0401] For the n-dimensional observation space, the size of the space enclosed by the other n-1-dimensional working points is defined as the CCEOR Sectional Area (SA) when the observation variable of a certain dimension is fixed. SA describes the size of the CCEOR dimensionality reduction space. The smaller the SA, the greater the restriction of the fixed-dimensional observation variable on the fixed-carbon operation space, which means that the observation variable of this dimension has a greater impact on the fixed-carbon operation of the system, and there is a risk of excessive carbon emissions or unsafe operation.

[0402]

[0403] In the formula, p i is the observed variable of the i-th dimension; Π is the fixed plane.

[0404] ②Geometric evaluation index of EHT-VEP observed variable coupling characteristics

[0405] By projecting to the observation space of key variables, CCEOR can intuitively depict the coupling constraint relationship between observed variables in the form of projection, thereby assisting the dispatching side to timely regulate EHT-VEP and ensure its low-carbon and reliable operation.

[0406] a. Observed variable coupling coefficient

[0407] The coupling factor (CF) of the observed variables reflects the degree of coupling between different observed variables. If the observed variables are decoupled from each other, it means that the single-dimensional observed variable is not affected by the observed variables of other dimensions, and CCEOR is a regular (hyper) cube / rectangle. Therefore, taking the two-dimensional observation space as an example, CF is defined as the maximum area SA and the area S of the rectangle with equal length and width. RT The relative size of the observed variables is used to quantify the degree of coupling between them.

[0408]

[0409] In the formula, the CF value range is (0, +∞). The larger the CF, the higher the degree of coupling between the observed variables, which means that the change of a certain dimension of observed variables has a more significant impact on other observed variables, and the easier it is to approach the system's fixed carbon operation boundary, and there is a risk of excess carbon emissions.

[0410] b. Average rate of change of truncation surface

[0411] The average change rate (ACR) of different SAs in the same dimension reflects the impact of changes in fixed-dimensional observed variables on the overall carbon-fixing domain space. Its physical meaning is the system's ability to adjust to fluctuations in observed variables. The smaller the ACR, the more the system can effectively adjust flexible resources to ensure sufficient carbon-fixing operating space in the face of fluctuations in observed variables. If the ACR is too large in a certain dimension, it means that there is a potential operational risk in the change of the observed variables in that dimension, and the existing scheduling resources of the system are difficult to cope with its fluctuations. In this case, it is necessary to limit the change of the observed variables in that dimension or try to expand the carbon-fixing operating space.

[0412]

[0413] c. Multidimensional balance

[0414] The multidimensional equilibrium degree (ED) is defined as the ratio of the volume of CCEOR to the volume of a hypersphere with the maximum operating margin in the domain as the radius. ED reflects the shape characteristics of CCEOR and the degree of equilibrium of observed variables in different dimensions in the domain. The value range of ED is [0,1]. The closer ED is to 1, the more uniform the CCEOR shape is, the closer the number of low-carbon operating points of the system in different directions is, and the more it can support the safe operation of the system with fixed carbon emissions.

[0415]

[0416] Where: V n (r) represents the volume of an n-dimensional hypersphere with radius r.

[0417] 5.2) Establish a method for evaluating the spatial geometry of low-carbon regulation

[0418] In this paper, the EHT-VEP low-carbon regulation space geometric evaluation method is proposed by combining the CCEOR convex hull shrinkage fitting method. First, based on the proposed boundary point solution method, the boundary point set p in the current observation space is obtained. op ; Secondly, the convex hull is obtained according to the boundary point set, and the convex hull is iteratively shrunk according to the convex hull fitting shrinkage method until the set convergence condition is met; finally, the CCEOR geometric evaluation index is solved according to the convex hull vertex set corresponding to the shrunk convex hull. Taking the three-dimensional observation space as an example, the specific EHT-VEP low-carbon regulation space geometric evaluation steps are given as follows:

[0419] ① Given the initial working point make Solve equations (46)-(47) to obtain Initial feasible range Repeatedly fix the 2D observation variables to obtain the feasible space for initializing the observation variables

[0420] ② Set the iteration step size Δp and the maximum relaxation gap gap max , fixed one-dimensional observation variable make Solve equations (46)-(47) to obtain the upper and lower boundary points and And let p 2 Gradually approach with iterative step size growth Get multiple sets of boundary points and add them to p op ;

[0421] ③ Order And gradually increase the iterative step size to approach Repeat step ② to obtain multiple sets of boundary points and add them to p op ;

[0422] ④ Repeat steps ② and ③ until all dimensional observation variables are traversed to obtain the boundary point set p op , based on the fast convex hull algorithm to obtain the current p op Minimal convex hull

[0423] ⑤Based on the current p op , add cutting plane constraints and iteratively update p op , until all boundary points satisfy gap≤gap max , and iteratively shrink Fitting the shrinking convex hull CCEOR.

[0424] ⑥ Based on the proposed CCEOR geometric evaluation index system, according to step ⑤, we can obtain Corresponding convex hull vertex set Solve equations (50)-(55) and output the CCEOR geometric evaluation index.

[0425] Embodiment 12:

[0426] A method for characterizing the virtual energy pool control space considering the coupling characteristics of electricity, hydrogen and transportation is verified. The main steps are as follows:

[0427] 1) Based on the IEEE 14-node medium-voltage distribution network and the improved Ngugen-Dupius 13-node traffic network, the EHT-VEP-I test system was built, and based on the actual 52-node medium-voltage distribution network and 25-node traffic network, the EHT-VEP-II test system was built for simulation analysis. The topological structures of EHT-VEP-I and EHT-VEP-II are as follows: Figure 3 , Figure 4 Among them, the centralized hydrogen production station, distributed on-site hydrogen production and refueling station, and distributed off-site hydrogen supply and refueling station have been connected to the distribution network and transportation network. Figure 3 , Figure 4The configuration scheme of wind and solar power stations is shown in Table 1. Based on the measured output data of actual wind and solar power stations in central my country, the typical summer day time series curve is selected to simulate the output characteristics of wind and solar power stations, such as Figure 5 (a) is shown. The time series characteristic curve of electric load and traffic flow demand is shown in Figure 5 (b) The price of electricity purchased by EHT-VEP from the upper grid is as follows: Figure 5 (b) The cost parameters of the proposed operation model are shown in Table 2. Setting the carbon emission cap of EHT-VEP-I Take it as 100t. The maximum relaxation gap of the second-order cone is max Set to 10 -3 ;

[0428] 2) Construct a virtual energy pool operation mode that takes into account the coupling characteristics of electricity, hydrogen and transportation;

[0429] 3) Propose the theory of the carbon emission operation domain of electricity-hydrogen-transportation;

[0430] 4) Establish a method for rapid characterization of low-carbon regulation space of the electricity-hydrogen-transportation virtual energy pool;

[0431] 5) Establish a low-carbon regulation spatial geometry assessment method based on a fixed carbon emission operation domain;

[0432] 6) In order to quantitatively analyze the low-carbon regulation space of EHT-VEP, this section selects the active load of distribution network nodes as the observed variable. Based on the proposed observation space dimensionality reduction method, the active load of high-carbon emission nodes 3, 5, and 7 are selected. P load 5 and P load 7 is used as an observation variable to characterize the EHT-VEP three-dimensional fixed carbon emission operation domain space. The three-dimensional fixed carbon emission operation domain and its two-dimensional projection are as follows: Figure 6 Based on the CCEOR geometric feature evaluation index, the feasible range of carbon determination and the influence of coupling variables in the CCEOR observation space are quantified, and the geometric evaluation results are shown in Table 3.

[0433] Table 1 Distributed power configuration schemes for two electric-hydrogen transportation virtual energy pools

[0434]

[0435] Table 2 Optimization parameters of low-carbon operation model

[0436]

[0437] Table 3 CCEOR geometric feature evaluation results

[0438]

[0439] Combination Figure 6From the analysis of Table 3, we can see that the total volume of the three-dimensional CCEOR is 0.0231MW 3 Due to the high-dimensional nonlinear coupling relationship between different observed variables, the geometric characteristics of CCEOR in the observed variable space are expressed as irregular convex polyhedrons. It is specifically reflected in two aspects: (1) The operation constraints of hydrogen production stations / hydrogen refueling stations and hydrogen long-tube trailers in EHT-VEP are time-series coupling constraints, and there is a coupling relationship between the power regulation capabilities of EHT-VEP between adjacent time periods; (2) Affected by the EHT-VEP carbon emission limit, there are coupling restrictions on the supply and demand relationship of electric hydrogen loads at different nodes in each time period of EHT-VEP. In order to reflect the coupling relationship between observed variables of different dimensions, the one-dimensional observed variable is fixed and continuously increased along the axial direction to form a two-dimensional cross-section of CCEOR in different dimensions, as shown in the figure: Figure 6 (b)-6(d). The truncation surface is essentially the mapping surface of the three-dimensional carbon domain projected into the two-dimensional space. According to the observed variable projection plane, it is denoted as SA 35 ,SA 37 and SA 57 , and their maximum cross-sectional areas are 0.0602MW 2 、0.1827MW 2 and 0.1207MW 2 Due to the different effects of the spatial distribution of electric hydrogen load on the EHT-VEP energy flow distribution and total carbon emissions, the cross-sectional shapes and change trends show obvious differences. 35 For example, in the active load vector space of nodes 3 and 5, given the carbon emission limit, the maximum feasible space of the system is 0.0602MW 2 , only for SA 37 32.95% of the maximum feasible space, observed variables and The coupling coefficient is 0.5954, indicating that in the current system, the active load of node 3 and the active load of node 5 are strongly coupled, and the load change of a single node will affect the ability of EHT-VEP to carry the load of another node.

Claims

1. A virtual energy pool control space characterization method considering the electricity-hydrogen-transportation coupling characteristics, characterized in that: The following steps are involved: 1) Construct a virtual energy pool operation model that considers the coupling characteristics of electricity, hydrogen and transportation; 2) Establish an optimized operation model of the electric-hydrogen-transportation virtual energy pool taking into account flexible operation characteristics; 3) Constructing the electricity-hydrogen-transportation carbon emission operation domain; 4) Characterize the low-carbon regulation space of the electricity-hydrogen-transportation virtual energy pool; 5) Conduct geometric evaluation of the low-carbon control space based on the fixed carbon emission operation domain.

2. A virtual energy pool control space characterization method considering the electricity-hydrogen-transportation coupling characteristics according to claim 1, characterized in that: The virtual energy pool is a virtual operation architecture composed of a regional hydrogen energy system integrated with power grid and transportation network, with electricity and hydrogen as core energy carriers; The regional hydrogen energy system includes a centralized hydrogen production station, a distributed hydrogen refueling station, a hydrogen long-tube trailer and a hydrogen fuel cell vehicle.

3. A virtual energy pool control space characterization method considering the electricity-hydrogen-transportation coupling characteristics according to claim 1, characterized in that: The steps to construct a virtual energy pool operation model that considers the coupling characteristics of electricity, hydrogen and transportation include: 1) Construct a centralized hydrogen production station hydrogen production and storage model, namely: Where: and They represent the hydrogen production and carbon emissions from natural gas at the mth centralized hydrogen production station during period t respectively; represents the gas consumption of the mth centralized hydrogen production station during period t; η G2H represents the efficiency of hydrogen production from natural gas, ε CE represents the carbon emission coefficient in the process of producing hydrogen from natural gas; q H ,q G They are hydrogen and natural gas lower calorific value; Indicates the upper and lower limits of hydrogen production from natural gas; 2) Construct a correlation model between the amount of hydrogen produced by water electrolysis and power consumption in a centralized hydrogen production station, namely: Where: U el,t and I el,t represents the operating voltage and current density of the alkaline electrolytic cell at time t; U rev is the reversible voltage, that is, the open circuit voltage of the electrolytic cell when the current density is 0; r1 and r2 are the resistance and thermal resistance parameters of the electrolytic cell, T el is the average operating temperature of the electrolytic cell, R el is the effective reaction area of ​​the electrolytic cell, s1, s2, s3, s4, s5, s6 are the electrode overvoltage fitting coefficients; N el is the number of electrolytic cells; represents the electrolysis power of the mth centralized hydrogen production station electrolyzer at time t; represents the hydrogen production of the electrolyzer of the mth centralized hydrogen production station at time t, λ H is the standard density of hydrogen, η f is the Faraday efficiency, F is the Faraday constant; The upper and lower limits of the electrolytic power of the electrolytic cell; 3) Construct a correlation model between the power consumption of the compressor of the centralized hydrogen production station and the amount of hydrogen produced, namely: Where: represents the power consumption of the compressor of the mth centralized hydrogen production station at time t, C H is the specific heat capacity constant of hydrogen, T com is the average operating temperature of the compressor, η com is the compressor working efficiency, B is the inlet and outlet gas pressure ratio, and ε is the hydrogen isentropic coefficient. is the maximum operating power of the compressor; 4) Construct the operation constraints of hydrogen storage tanks in centralized hydrogen production stations, namely: Where: represents the pressure and hydrogen change of the hydrogen storage tank of the mth centralized hydrogen production station at time t, R H is the molar gas constant, T H is the average temperature in the hydrogen storage tank, is the hydrogen storage tank capacity of the mth centralized hydrogen production station, M H is the molar mass of hydrogen. It represents the hydrogen refueling amount of the kth HT vehicle in the mth centralized hydrogen production station at time t. Indicates the upper and lower limits of the hydrogen storage tank pressure. Indicates the hydrogen storage tank pressure at the start and end of the scheduling cycle. Ω HPS represents a collection of centralized hydrogen production stations; Indicates the gas pressure of the hydrogen storage tank of the mth centralized hydrogen production station at time t-1; 5) Construct the operation constraints of the distributed on-site hydrogen production and refueling station, including the electrolyzer operation constraints (2)-(5) and the operation constraint (9); construct the operation constraints of the distributed off-site hydrogen supply and refueling station, including the operation constraint (9); Where: Indicates the change in hydrogen tank pressure and hydrogen volume at the nth hydrogen refueling station at time t, is the hydrogen storage tank capacity of the nth hydrogen refueling station, and represents the hydrogen consumption power and power generation power of the hydrogen fuel cell vehicle participating in the H2G mode in the nth hydrogen refueling station, η fc is the power generation efficiency of hydrogen fuel cells. fc , β fc is the empirical fitting coefficient of hydrogen fuel cell power generation efficiency, and the subscript r represents the rated operating condition. It represents the hydrogen production of electrolyzer n in the hydrogen refueling station at time t, Indicates the amount of hydrogen released by the kth HT in hydrogen refueling station n at time t. Ω on and Ω off They represent the collection of hydrogen refueling stations inside the station and hydrogen refueling stations outside the station respectively; Indicates the gas pressure of the hydrogen storage tank at the nth hydrogen refueling station at time t-1; It represents the amount of hydrogen refueled by a hydrogen fuel vehicle at the nth hydrogen refueling station at time t. represents the rated power generation of the hydrogen fuel cell vehicle participating in the H2G mode in the nth hydrogen refueling station; η fc,r is the rated power generation efficiency of the hydrogen fuel cell; 6) Considering the driving path of the hydrogen long-tube trailer, the relationship constraints between the driving path and the spatial position are established, namely: Where: r i,j,k A is a 0-1 logical variable. If it is 1, it means the driving path of the kth HT is (i, j). Otherwise, it means the driving path is not (i, j). i,t,k A is a 0-1 logical variable, 1 means the kth HT is located at hydrogen production station / hydrogen refueling station i at time t; i,ts,k , A i,te,k 0-1 logical variables representing the start and end times of the scheduling period respectively; 7) Establish constraints on the amount of hydrogen transported by hydrogen long-tube trailers, namely: Where: Q i,t,k , ΔQ i,t,k represents the hydrogen storage amount and hydrogen change in the kth hydrogen long tube trailer located in station i at time t; α i,t,k , β i,t,k Q is a 0-1 logical variable, indicating the hydrogenation and dehydrogenation status of the hydrogen long-tube trailer. If it is 1, it means that the kth hydrogen long-tube trailer is refueling and dehydrogenating in station i at time t; k,cap represents the upper limit of hydrogen storage of the kth hydrogen tube trailer; λ cap,min Indicates the minimum hydrogen storage coefficient of the hydrogen long tube trailer; Q i,ts,k and Q i,te,k represents the hydrogen storage capacity of the kth hydrogen long tube trailer at the start and end of the scheduling period respectively; Q j,t+1,k , Q j,t,k , Q j,t-1,k They represent the hydrogen storage capacity in the kth hydrogen long tube trailer located in station j at time t+1, time t, and time t-1 respectively; 8) Taking the minimum travel time cost as the path selection standard for all users in the transportation network, static mixed user equilibrium is used to describe the state that the transportation network spontaneously reaches, that is: Where: h p is the traffic flow of path p, The travel time cost required for HFCV and vehicles other than HFCV to choose path p, v ij is the minimum travel time cost of all paths between travel demand pairs (i→j), W hv , W o is the set of travel demand pairs of HFCV and vehicles other than HFCV, is the set of vehicle paths of all HFCVs and other vehicles except HFCVs between travel demand pairs (i→j); 9) Based on the BPR function, a road impedance model is established to describe the road congestion effect, as shown below: Where: τ p1 (h p ) represents the traffic volume h on road p p The relevant transit time function, represents the free travel time of road p, that is, the vehicle travel time when there is no traffic flow on road p, c p represents the traffic capacity of road p; P ij is the set of all paths between travel demand pairs (i→j); 10) Based on the improved Davidson function, a hydrogen refueling queue time model is constructed, namely: Where: τ p2 (h p ) represents the traffic volume h on road p p The relevant transit time function, Indicates the hydrogen refueling time of a single HFCV, represents the limit of vehicles that can be refueled at the same time at a hydrogen refueling station, R is the function shape parameter; P H This is the collection of hydrogenation roads after topology change.

4. A virtual energy pool control space characterization method considering the electricity-hydrogen-transportation coupling characteristics according to claim 1, characterized in that: Formulas (12)-(14) constitute a traffic flow model; the traffic flow model uses the "all or nothing allocation" method to allocate the traffic flow of each road section, thereby outputting all h p gather.

5. A virtual energy pool control space characterization method considering the electricity-hydrogen-transportation coupling characteristics according to claim 1, characterized in that: The objective function C of the electricity-hydrogen-transportation virtual energy pool optimization operation model is as follows: min C=C P,buy +C HP +C curt +C CE +C HT (16) Electricity purchase cost C P,buy 、Hydrogen production cost C HP , Penalty cost for wind and solar power abandonment C curt 、Carbon emission cost C CE and the operating cost of hydrogen tube trailer C HT They are as follows: Where: c Pbuy,t P represents the price of electricity purchased from the upper power grid at time t; grid,t It represents the active power purchased from the superior power grid at time t; Δt represents the unit time interval. Where: c G is the gas purchase price, c PSA is the hydrogen purification cost coefficient, Δt is the unit time interval, N p is the number of centralized hydrogen production stations in EHT-VEP. represents the gas consumption of the mth centralized hydrogen production station during period t; represents the hydrogen production of the mth centralized hydrogen production station at time t; Where: They represent the abandoned wind and solar power of the wind and solar power unit at the node i at time t; c curt N is the penalty cost per unit of wind and solar power abandonment; B Indicates the number of distribution network nodes. Where: CE represents the unit cost coefficient of carbon emission; ε g2h Represents the carbon emission coefficient in the process of hydrogen production from natural gas, η G2H represents the efficiency of hydrogen production from natural gas, q H is the lower calorific value of hydrogen; ε grid Indicates the carbon emission coefficient of electricity purchased by the superior power grid. Where: c HT represents the unit storage and transportation cost of hydrogen for long-tube trailers, N k The number of EHT-VEP medium and long tube trailers. Represents the amount of hydrogen refueled by the kth HT vehicle at time t.

6. A virtual energy pool control space characterization method considering the electricity-hydrogen-transportation coupling characteristics according to claim 1, characterized in that: The constraints of the electricity-hydrogen-transportation virtual energy pool optimization operation model include distribution network flow constraints, node power balance constraints, safe operation constraints, distributed power supply operation constraints, and traffic flow balance constraints.

7. A method for describing a virtual energy pool control space considering the electric-hydrogen-transportation coupling characteristics according to claim 6, characterized in that: The power flow constraints of the distribution network are as follows: Where: v(j) and w(j) represent the first node set and the last node set of the branch connected to node j respectively; P ij,t , Q ij,t represents the active power and reactive power of branch ij at time t; r ij and x ij Represents the resistance and reactance of branch ij; P j,t , Q j,t I represents the active and reactive power injected into node j at time t; ij,t represents the branch ij current at time t; U j,t U represents the voltage of node j at time t. i,t P represents the voltage of node i at time t. jk,t , Q jk,t It represents the active power and reactive power of branch jk at time t; The node electrical power balance constraints are as follows: Where: P WG,i,t , Q WG,i,t P represents the actual active power and reactive power generated by wind turbine i at time t; PV,i,t , Q PV,i,t P represents the actual active power and reactive power generated by the photovoltaic unit at node i at time t; load,i,t and Q load,i,t represents the conventional active load and reactive load of node i at time t; s is the access node of the interconnection line. The safe operating constraints are as follows: Where: They represent the upper and lower limits of the voltage allowed at node i respectively; They represent the upper and lower limits of the current allowed for line ij respectively; The distributed generation operation constraints are as follows: Where: and Indicates the predicted active power generated by the wind and solar generator connected to node i; and Indicates the set power factor of the wind and solar generator set. They represent the abandoned wind and solar power of the wind and solar power generator at the node i at time t respectively; The traffic flow balance constraints are as follows: Where: H Indicates the proportion of vehicles that need hydrogen refueling; h p,t represents the traffic flow on road p at time t; It represents the average amount of hydrogen refueled in hydrogen fuel cell vehicles; It represents the amount of hydrogen refueled by a hydrogen fuel vehicle at the nth hydrogen refueling station at time t.

8. The method for depicting virtual energy pool control space considering the coupling characteristics of electricity, hydrogen and transportation according to claim 1 is characterized in that: The steps to construct the electricity-hydrogen-transportation carbon emission operation domain are as follows: 1) Define the operating point Z that represents the operating state of EHT-VEP, that is: In the formula, Respectively represent the dimension N B ×T、N L ×T real number space; 2) Construct the carbon emission operation domain expression of electricity-hydrogen-transportation, namely: Where: Ω CR is the fixed carbon emission operation domain; U is the node voltage matrix; I is the branch current matrix; P and Q are the active and reactive power matrices injected into the node, respectively; H represents the node hydrogen load demand matrix; f(x, y) = 0 represents the electric-hydrogen energy balance constraint; Represents the system safe operation constraints, including voltage constraints and thermal stability constraints; represents the node injection power constraint, including the operation constraint of the electric-hydrogen coupling equipment and the operation constraint of the distributed power source; E(y)≤Bmax 3 represents the system carbon emission constraint, as shown in the following formula; B1, B2 and B3 represent the critical value of safe operation, the critical value of injection power and the carbon emission limit respectively; the superscripts max and min represent the upper and lower bounds; N B and N L represents the number of nodes and branches; T is the scheduling period. 3) Establish a fixed carbon emission operation domain transformation model under second-order cone relaxation, transform the fixed carbon emission operation domain, and obtain: Where: A, B, C are coefficient matrices in equality constraints; D, F are coefficient matrices in linear inequalities; H, V are coefficient matrices in SOC constraints. W is the node voltage square matrix; L is the branch current square matrix. D , Q D represents the node active and reactive load matrix; P G , Q G Represents the active and reactive output matrix of the node unit; Ω SCR It is the fixed carbon emission operation domain after conversion.

9. A virtual energy pool control space characterization method considering the electricity-hydrogen-transportation coupling characteristics according to claim 1, characterized in that: The steps to characterize the low-carbon regulation space of the electricity-hydrogen-transportation virtual energy pool are as follows: 1) Based on the typical operation state of EHT-VEP, the EHT-VEP power flow distribution is obtained as the initial working point Z0. Based on the initial working point Z0, the carbon emission flow is calculated and the node carbon emission factor is obtained as the basis for selecting the reduced dimension observation variable, namely: Where: B , L represents the node and branch carbon emission factor matrix respectively; Y represents the distribution network node association matrix; P L represents the branch power flow distribution matrix; ρ G is the unit carbon emission factor matrix; 2) Project the high-dimensional fixed carbon emission operation domain to the node load space, and select the n-dimensional node electrical load as the observed variable according to the carbon emission distribution, that is: Where: K obs represents the set of observation variables to be selected, where k is a 0-1 variable of the observation variable selection state, k i =1 means that the node i load is selected as the observed variable. and N B dimensional and T-dimensional unit row vectors; The fixed carbon emission operation domain in the reduced-dimensional observation space is as follows: Where: f(p,q)=0 represents the equality constraint including the electric hydrogen energy balance; g(p,q)≤0 represents the inequality constraint including the safe operation constraint and carbon emission constraint; Ω SCRL represents the fixed carbon emission operation domain in the reduced-dimensional observation space; 3) Based on Ω SCRL Perform CCEOR boundary convex hull fitting and iteratively shrink the convex hull CCEOR according to the second-order cone relaxation gap; The fitting target is as follows: Where: z(p) represents the objective function set for solving the boundary point, and the subscripts u and d represent the upper boundary and the lower boundary respectively. c represents n-1 dimensional fixed observation variable. p is the selected observation variable; The fitting constraints are as follows: Where: L s+1 is the branch current square matrix of the s+1th iteration; is the precise branch current square matrix in the sth iteration. T is a real matrix; gap max is the maximum relaxation gap allowed during the iteration process.

10. The method for describing the virtual energy pool control space considering the electricity-hydrogen-transportation coupling characteristics according to claim 1, characterized in that: The steps for geometrically evaluating the low-carbon regulation space based on the fixed carbon emission operation domain are as follows: 1) Construct a low-carbon regulation spatial geometric evaluation index system, including the EHT-VEP low-carbon regulation spatial geometric evaluation index and the EHT-VEP observed variable coupling characteristic geometric evaluation index; The EHT-VEP low-carbon regulation space geometric evaluation indicators include low-carbon safe operation margin, low-carbon operation ample space, and dimension reduction cutoff area; The low carbon safety operating margin is as follows: Where p is the selected observed variable; d(p) is the low-carbon safety operation margin; p * is the feasible space of observed variables; The ample space for low-carbon operation is as follows: In the formula, and They are z u (p) and z d (p) takes the optimal value. CR Allow ample room for low-carbon operation; The dimensionality reduction cut-off area is as follows: In the formula, p i is the observed variable of the i-th dimension; Π is the fixed plane; S CR (p i ) is the cut-off area for dimensionality reduction; The geometric evaluation indexes of the EHT-VEP observed variable coupling characteristics include observed variable coupling coefficient, average change rate of truncation surface, and multi-dimensional balance; The observed variable coupling coefficients are as follows: Where, the observed variable coupling coefficient CF ranges from (0, +∞); S RT 、max S CCEOR (p i ) is the area of ​​a rectangle of equal length and width and the maximum SA area; The average change rate ACR of the truncation surface is as follows: In the formula, S CR (p i +Δp i ), S CR (p i ) is the observed variable p i +Δp i , observed variable p i The corresponding dimension reduction cut-off area; The multidimensional balance degree ED is as follows: Where: V n (max d(p)) represents the volume of the n-dimensional hypersphere with radius max d(p); V CR Allow ample room for low-carbon operation; 2) Conduct a low-carbon regulation spatial geometry assessment, including the following steps: 2.1) Given the initial working point make Solve equations (46)-(47) to obtain Initial feasible range Repeatedly fix the 2D observation variables to obtain the feasible space for initializing the observation variables 2.2) Set the iteration step size Δp and the maximum relaxation gap gap max , fixed one-dimensional observation variable make Solve equations (46)-(47) to obtain the upper and lower boundary points and And let p 2 Gradually approach with iterative step size growth Get multiple sets of boundary points and add them to p op ; 2.3) Order And gradually increase the iterative step size to approach Repeat step 2.2) to obtain multiple sets of boundary points and add them to p op ; 2.4) Repeat steps 2.2) and 2.3) until all dimensional observation variables are traversed to obtain the boundary point set p op , based on the fast convex hull algorithm to obtain the current p op Minimal convex hull 2.5) Based on the current p op , add cutting plane constraints and iteratively update p op , until all boundary points satisfy gap≤gap max , and iteratively shrink Fitting the shrinking convex hull CCEOR. 2.6) Based on the proposed CCEOR geometric evaluation index system, according to step ⑤, we can obtain Corresponding convex hull vertex set Solve equations (50)-(55) and output the CCEOR geometric evaluation index.