Construction personnel management collaborative optimization method and device, terminal equipment and computer readable storage medium

By calculating the average work efficiency of construction personnel and screening construction personnel suitable for the project, the problem of inefficient allocation of construction personnel in the existing technology is solved, and the efficient completion of construction projects is achieved.

CN119067371APending Publication Date: 2024-12-03GUANGDONG POWER GRID CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411105268.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-13
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

In construction projects, the prior art is difficult to achieve optimal personnel allocation, which usually relies on the experience and intuition of managers, resulting in inefficiency in construction.

Method used

By obtaining the historical project workload and efficiency data of construction personnel, calculating their average work efficiency, and screening out construction personnel who are expected to be able to complete high-quality work based on the target amount and time of the project to be allocated, and optimizing the allocation of construction personnel.

Benefits of technology

More accurate personnel matching is achieved, construction efficiency and project success rate are improved, and construction projects are completed on time and in quantity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119067371A_ABST
    Figure CN119067371A_ABST
Patent Text Reader

Abstract

The invention discloses a construction personnel management collaborative optimization method and device, terminal equipment and a computer readable storage medium. The method comprises the steps that the workload, starting time and ending time of each historical construction project of each construction personnel in various construction types are acquired; according to the information, the average working efficiency of all constructors in all kinds of construction work types is obtained through calculation; obtaining a target quantity and target time of a to-be-allocated construction project; according to the target time and the average working efficiency of each constructor in the construction work type corresponding to the construction project to be allocated, calculating to obtain a construction amount expected to be achieved by the corresponding constructor; and comparing the construction amount expected to be achieved by the corresponding constructors with the target amount of the to-be-allocated construction project, and screening the constructors whose construction amount expected to be achieved is greater than the target amount as adaptive constructors of the to-be-allocated construction project. By implementing the method and the system, constructors suitable for completing specific projects can be matched, and optimal personnel matching is realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of building construction management, and in particular to a management collaborative optimization method for construction personnel. Background Art

[0002] At present, there are various separate construction projects in the process of construction projects, such as interior decoration projects undertaken by home improvement companies, wall construction, wall laying, painting, furniture customization, water and electricity, tiling or ceiling projects, and in order to complete the construction projects, various project construction personnel or construction teams corresponding to the construction projects are needed. In order to ensure the smooth progress of the construction projects, it is necessary to select suitable project construction personnel for the construction projects.

[0003] However, the above-mentioned construction personnel allocation process is generally carried out by comparing and analyzing one by one by project management and project managers to select suitable project construction personnel. Such a manual selection process can usually only be based on the experience and intuition of managers, and it is difficult to achieve the best personnel allocation. Summary of the invention

[0004] The embodiments of the present invention provide a method, apparatus, terminal device and computer-readable storage medium for collaborative optimization of construction personnel management, which can more accurately match construction personnel suitable for completing a specific project and achieve optimal personnel matching.

[0005] An embodiment of the present invention provides a construction personnel management collaborative optimization method, including:

[0006] Obtain the workload, start time and end time of each historical construction project of each construction worker in each type of construction work;

[0007] According to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work, the average work efficiency of each construction worker in each type of construction work is calculated;

[0008] Obtaining target quantities of construction projects to be assigned and target times of construction projects to be assigned;

[0009] According to the target time of the construction project to be assigned and the average work efficiency of each construction worker in the construction type corresponding to the construction project to be assigned, the construction volume expected to be achieved by each construction worker in the corresponding construction type is calculated;

[0010] The construction volume that each construction worker in the corresponding construction type is expected to achieve is compared with the target volume of the construction project to be assigned, and the construction workers whose construction volume is expected to be greater than the target volume are screened out as suitable construction workers corresponding to the construction project to be assigned.

[0011] Furthermore, after selecting construction personnel whose construction volume is expected to be greater than the target volume as suitable construction personnel corresponding to the construction project to be assigned, the following steps are also included:

[0012] Extract the end time of the last project construction of the appropriate construction personnel from the end time of the historical construction projects of each construction personnel;

[0013] According to the completion time of the last project construction of each adapted construction personnel, the time interval between the last work of each adapted construction personnel is calculated, and the adapted construction personnel are sorted from largest to smallest according to the time interval;

[0014] According to the number of construction workers required for the construction project to be allocated, a corresponding number of suitable construction workers are selected in order from the sorted suitable construction workers as the final construction workers for the construction project to be allocated.

[0015] Furthermore, the management collaborative optimization method for construction personnel also includes:

[0016] For each construction worker of each construction type, the current average work efficiency of each construction worker is compared with the average work efficiency during the last management collaborative optimization;

[0017] If the current average work efficiency is lower than the average work efficiency during the last management collaborative optimization, and the decreased average work efficiency exceeds the preset efficiency threshold, an efficiency warning signal is issued.

[0018] Furthermore, according to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work, the average work efficiency of each construction worker in each type of construction work is calculated, including:

[0019] According to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work, the work efficiency of each historical construction project of each construction worker in each type of construction work is calculated;

[0020] For each construction worker of each type of construction work, the work efficiencies of several historical construction projects whose end time is closest to the current time are selected from the work efficiencies of each historical construction project of the construction worker to obtain several target work efficiencies;

[0021] Calculate the average of several target work efficiencies to obtain the average work efficiency of each construction worker in each type of construction work.

[0022] Furthermore, according to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work, the work efficiency of each historical construction project of each construction worker in each type of construction work is calculated, including:

[0023] For each historical construction project of each construction worker in each type of construction work, the completion time of the historical construction project is calculated based on the start time and end time of the historical construction project;

[0024] According to the workload of historical construction projects and the completion time of corresponding historical construction projects, the work efficiency of each historical construction project of each construction worker in each type of construction work is calculated.

[0025] Based on the above method embodiment, the present invention provides a corresponding device embodiment, including: a historical construction project information acquisition module, a work efficiency calculation module, a to-be-allocated project information acquisition module, an estimated construction volume calculation module, and an adaptive construction personnel screening module;

[0026] The historical construction project information acquisition module is used to obtain the workload, start time and end time of each historical construction project of each construction worker in each type of construction work;

[0027] The work efficiency calculation module is used to calculate the average work efficiency of each construction worker in each type of construction work according to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work;

[0028] The information acquisition module of the project to be allocated is used to obtain the target quantity and target time of the construction project to be allocated;

[0029] The estimated construction volume calculation module is used to calculate the estimated construction volume to be achieved by each construction worker in the corresponding construction work type according to the target time of the construction project to be allocated and the average work efficiency of each construction worker in the construction work type corresponding to the construction project to be allocated;

[0030] The adaptive construction personnel screening module is used to compare the construction volume that each construction personnel in the corresponding construction type is expected to achieve with the target volume of the construction project to be assigned, and screen out the construction personnel whose estimated construction volume is greater than the target volume as the adaptive construction personnel corresponding to the construction project to be assigned.

[0031] Furthermore, the management collaborative optimization device for construction personnel also includes: a last construction information extraction module, a time interval sorting module, and a final construction personnel determination module;

[0032] The last construction information extraction module is used to extract the end time of the last project construction of the construction personnel from the end time of the historical construction projects of each construction personnel;

[0033] The time interval sorting module is used to calculate the time interval between the last work of each suitable construction personnel according to the end time of the last project construction of each suitable construction personnel, and sort the suitable construction personnel from large to small according to the time interval;

[0034] The final construction personnel determination module is used to select a corresponding number of suitable construction personnel from the sorted suitable construction personnel in order according to the number of construction personnel required by the construction project to be allocated, as the final construction personnel for the construction project to be allocated.

[0035] Furthermore, the management collaborative optimization device for construction personnel also includes: an average work efficiency comparison module and an efficiency early warning module;

[0036] The average work efficiency comparison module is used to compare the current average work efficiency of each construction worker with the average work efficiency of the last management collaborative optimization for each construction worker of each construction type;

[0037] The efficiency warning module is used to issue an efficiency warning signal when the current average work efficiency is lower than the average work efficiency during the last management collaborative optimization, and the decreased average work efficiency exceeds a preset efficiency threshold.

[0038] Based on the above-mentioned method embodiment, the present invention provides a corresponding terminal device embodiment, including: a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor. When the processor executes the computer program, the steps of the construction personnel management collaborative optimization method as described in the present invention are implemented.

[0039] Based on the above-mentioned method embodiment, the present invention provides a corresponding computer-readable storage medium embodiment, including: a stored computer program, which controls the device where the computer-readable storage medium is located to execute the steps of the construction personnel management collaborative optimization method as described in the present invention when the computer program is running.

[0040] Compared with the prior art, the beneficial effects of the embodiment of this solution are:

[0041] The present invention obtains the workload of each historical construction project of each construction personnel in each type of construction work and the corresponding start time; calculates the work efficiency of each construction personnel according to the workload of each historical construction project of each construction personnel in each type of construction work and the corresponding start time, and by calculating the work efficiency of the construction personnel, the ability and performance of the construction personnel can be quantified into specific values; obtains the target amount of the construction project to be allocated and the target time of the construction project to be allocated; calculates the construction volume expected to be achieved by each construction personnel in the corresponding construction work according to the target time of the construction project to be allocated and the work efficiency of each construction personnel in the construction work corresponding to the construction project to be allocated; compares the construction volume expected to be achieved by each construction personnel in the corresponding construction work with the target amount of the construction project to be allocated, respectively, in order to find the best personnel to meet the target amount requirements of the construction project to be allocated, so as to find suitable construction personnel for the construction project; finally, the construction personnel whose expected construction volume is greater than the target volume are screened out to obtain a set of adapted construction personnel, who have demonstrated the ability to complete high-quality work within the specified time, so they can advance the construction process more quickly and improve the overall construction efficiency.

[0042] In summary, the present invention comprehensively considers the historical work performance and target quantity requirements of construction personnel, screens out a set of personnel that meet the requirements, and can more accurately match construction personnel suitable for completing specific projects, thereby achieving optimal personnel matching. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1 It is a flowchart of a collaborative optimization method for management of construction personnel provided by an embodiment of the present invention;

[0044] Figure 2 It is a structural diagram of a construction personnel management collaborative optimization device provided by an embodiment of the present invention;

[0045] Figure 3 It is a structural schematic diagram of another construction personnel management collaborative optimization device provided by one embodiment of the present invention;

[0046] Figure 4 It is a structural schematic diagram of another construction personnel management collaborative optimization device provided by an embodiment of the present invention;

[0047] Figure 5 It is a structural diagram of yet another construction personnel management collaborative optimization device provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0048] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0049] like Figure 1 As shown, an embodiment of the present invention provides a construction personnel management collaborative optimization method, the method comprising at least the following steps:

[0050] Step S1: Obtain the workload, start time and end time of each historical construction project of each construction worker in each type of construction work;

[0051] For step S1, in order to analyze the work efficiency and arrange the work of the construction workers, it is first necessary to obtain detailed information on each historical construction project of each construction worker in each construction trade. These detailed information include the workload, start time and end time of the construction project. These construction trades include plumbing, wall building, painting, welding, furniture customization and tiling, and the corresponding types of construction workers are plumbers, bricklayers, painters, welders, carpenters and bricklayers, etc. Each construction worker can undertake tasks of multiple construction trades.

[0052] In this embodiment, the construction worker is recorded as P, then each construction worker in each type of construction work is Among them, m represents the type of construction work, n m It represents the total number of construction workers in the mth type of construction work;

[0053] The workload of historical construction projects is recorded as SW, then the workload of each construction worker in each type of construction work for each historical construction project is where k m×n Represents the total number of historical construction projects of the nth construction worker in the mth type of construction work;

[0054] The starting time of each historical construction project is End time is

[0055] It should be noted that the workload of a construction project can be determined based on the calculation habits of the type of construction project unit industry, for example, it can be measured by the size of the construction project or other unified methods.

[0056] Step S2: Calculate the average work efficiency of each construction worker in each type of construction work according to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work;

[0057] In a preferred embodiment, the average work efficiency of each construction worker in each type of construction work is calculated based on the workload, start time and end time of each historical construction project of each construction worker in each type of construction work, including:

[0058] According to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work, the work efficiency of each historical construction project of each construction worker in each type of construction work is calculated;

[0059] For each construction worker of each type of construction work, the work efficiencies of several historical construction projects whose end time is closest to the current time are selected from the work efficiencies of each historical construction project of the construction worker to obtain several target work efficiencies;

[0060] Calculate the average of several target work efficiencies to obtain the average work efficiency of each construction worker in each type of construction work.

[0061] In a preferred embodiment, the work efficiency of each historical construction project of each construction worker in each type of construction work is calculated based on the workload, start time and end time of each historical construction project of each construction worker in each type of construction work, including:

[0062] For each historical construction project of each construction worker in each type of construction work, the completion time of the historical construction project is calculated based on the start time and end time of the historical construction project;

[0063] According to the workload of historical construction projects and the completion time of corresponding historical construction projects, the work efficiency of each historical construction project of each construction worker in each type of construction work is calculated.

[0064] For step S2, in order to analyze the work efficiency of each construction worker in each construction type, 6 construction types (water and electricity, wall laying, painting, welding, furniture customization and tiling) are taken as an example, that is, m=6, and each construction type has a different number of construction workers (3 plumbers, 4 bricklayers, 2 painters, 3 welders, 2 carpenters and 5 bricklayers), that is, n1=3, n2=4, n3=2, n4=3, n5=2, n6=5. In this embodiment, the average work efficiency of each construction worker in each construction type is calculated separately based on the construction type.

[0065] First, according to the start time and end time of each historical construction project of each construction worker in each construction type obtained in step S1, taking the first of the three plumbers as an example, the end time of each historical construction project of the plumber is Subtract the start time of each historical construction project Get the completion time of each historical construction project of the construction worker Then, use the workload of each historical construction project Divide by the completion time of each historical construction project Get the work efficiency of each historical construction project of the construction worker Among them, k 1×1 Indicates the number of historical projects worked by the first hydroelectrician in the first category of work (hydroelectricity). If the first hydroelectrician has 7 historical hydroelectric projects, k 1×1 The values ​​are 1, 2, 3, ..., 7 respectively. Then, based on the information of historical water and electricity projects, we can calculate that the work efficiency of these 7 times is E 11_1 、E 11_2 、E 11_3 、E 11_4 、E 11_5 、E 11_6 、E 11_7 .

[0066] Next, calculate the average work efficiency of the first hydroelectrician: subtract the end time of the first hydroelectrician's seven historical hydroelectric projects from the current time to get the project time difference {D 11_1 , D 11_2 , D 11_3 , D 11_4 , D 11_5 , D 11_6 , D 11_7}, and sort the project time differences. The smaller the project time difference, the newer the historical construction project is. Then, select n work efficiency data with the smallest project time difference to obtain the target work efficiency. In this embodiment, n is 3. If the selected 3 smallest project time differences are {D 11_1 , D 11_5 , D 11_7}, then we can get the corresponding E 11_1 、E 11_5 and E 11_7 To target work efficiency;

[0067] Finally, calculate the work efficiency E of these targets 11_1 、E 11_5 and E 11_7 The average value RE, that is, RE = (E 11_1 +E 11_5 +E 11_7 ) / 3, and get the average work efficiency of the first plumber.

[0068] In the same way, the average work efficiency of each construction worker in other plumbers or other construction trades can be calculated.

[0069] It should be noted that in actual work, a construction worker may work in multiple types of jobs, that is, a plumber may also be a carpenter. This embodiment uses construction job types as the classification basis and calculates the average work efficiency of each construction worker in each construction job type.

[0070] Step S3: obtaining the target quantity and target time of the construction project to be allocated;

[0071] For step S3, before allocating the construction project, it is necessary to obtain the target amount and target time of the construction project to be allocated. The target amount refers to the amount of work that needs to be completed for the construction project, and the target time refers to the estimated time required to complete the construction project.

[0072] Step S4: Calculate the construction volume that is expected to be achieved by each construction worker in the corresponding construction type according to the target time of the construction project to be allocated and the average work efficiency of each construction worker in the construction type corresponding to the construction project to be allocated;

[0073] For step S4, if the construction project to be assigned is a hydropower project, it can be calculated based on the target time of the construction project to be assigned and the average work efficiency of each construction worker in the hydropower construction trade. The target time is multiplied by the average work efficiency of each construction worker in the hydropower construction trade to obtain the construction volume Z expected to be completed by each construction worker in the hydropower construction trade within a given time, that is, Z=RE×MT×A, wherein RE represents the average work efficiency of each construction worker in the hydropower construction trade, MT represents the target time of the construction project to be assigned, and A represents a coefficient, and its value range is between 1.2 and 1.5. A is set to facilitate the setting of flexible time to avoid the inability to complete the project task volume due to sudden changes in the efficiency of construction workers.

[0074] Step S5: Compare the construction volume that each construction worker in the corresponding construction type is expected to achieve with the target volume of the construction project to be assigned, and select the construction workers whose construction volume is expected to be greater than the target volume as the suitable construction workers corresponding to the construction project to be assigned.

[0075] For step S5: the construction volume Z that each construction worker in the hydropower construction type is expected to complete within a given time calculated in step S4 is compared with the target volume MZ of the construction project to be assigned. If the construction volume of a construction worker is expected to be greater than the target volume, that is, (Z = RE × MT × A) > MZ, then the construction worker can be considered as a candidate for the construction project to be assigned; next, the construction workers whose expected construction volume is greater than the target volume are screened out and used as the corresponding construction workers for the construction project to be assigned. These construction workers have demonstrated the ability to exceed the target volume within a given time, so they are more likely to complete the project within the specified time and have the ability and experience to complete the project.

[0076] Through the above screening process, we can ensure that the appropriate construction personnel are selected for the construction project to be assigned, so as to improve the success rate and efficiency of the project. By matching the expected construction volume with the target volume, we can find construction personnel who can meet the project requirements, thus providing better guarantee for the smooth progress of the project.

[0077] In a preferred embodiment, after selecting construction personnel whose expected construction volume is greater than the target volume as suitable construction personnel corresponding to the construction project to be assigned, the following steps are further included:

[0078] Extract the end time of the last project construction of the appropriate construction personnel from the end time of the historical construction projects of each construction personnel;

[0079] According to the completion time of the last project construction of each adapted construction personnel, the time interval between the last work of each adapted construction personnel is calculated, and the adapted construction personnel are sorted from largest to smallest according to the time interval;

[0080] According to the number of construction workers required for the construction project to be allocated, a corresponding number of suitable construction workers are selected in order from the sorted suitable construction workers as the final construction workers for the construction project to be allocated.

[0081] In one embodiment of the present invention, after obtaining the adapted construction personnel corresponding to the construction project to be assigned through step S5, the end time of the last construction project of each of these adapted construction personnel is found from the historical construction project information obtained in step S1; then, according to the end time of the last construction project of each adapted construction personnel, their working interval is calculated, and the working interval is obtained by subtracting the current time from the end time of the last project; then, the adapted construction personnel are sorted from large to small according to the working interval, and a longer working interval means that their last work is longer from now, and they may need more job opportunities. By sorting the adapted construction personnel according to the working interval, it can be ensured that people who have not worked for a long time have the opportunity to participate in new projects; finally, according to the number of construction personnel required for the construction project to be assigned, a corresponding number of personnel are selected in order from the sorted adapted construction personnel.

[0082] The entire matching process first screens out suitable construction personnel whose expected construction volume is greater than the target volume, then sorts them according to the working interval of their last construction project, and finally sorts them from the largest to the smallest working interval, and selects the required number of suitable construction personnel from the sorting results as the final team for the construction project to be assigned. This ensures that construction personnel can be reasonably allocated according to their abilities and work experience, while taking into account their working intervals, to avoid people who have not worked for a long time from not having the opportunity to participate in new projects for a long time, which affects the benefits of construction personnel and causes adverse consequences.

[0083] In a preferred embodiment, the construction personnel management collaborative optimization method further includes:

[0084] For each construction worker of each construction type, the current average work efficiency of each construction worker is compared with the average work efficiency during the last management collaborative optimization;

[0085] If the current average work efficiency is lower than the average work efficiency during the last management collaborative optimization, and the decreased average work efficiency exceeds the preset efficiency threshold, an efficiency warning signal is issued.

[0086] In one embodiment of the present invention, the average work efficiency of each construction worker during this management collaborative optimization can be obtained through step S2, and the average work efficiency of each construction worker during this management collaborative optimization is compared with the average work efficiency of each construction worker during the previous management collaborative optimization. If the average work efficiency during this management collaborative optimization is lower than the average work efficiency during the previous management collaborative optimization, and the decreased average work efficiency exceeds a preset efficiency threshold, in this embodiment, the preset efficiency threshold is 30% of the average work efficiency during the previous management collaborative optimization. If the efficiency decreases by 30%, an efficiency warning signal will be issued. This efficiency warning signal specifically highlights the construction workers whose efficiency decreases by 30%. By comparing the average work efficiency, it is helpful for managers to promptly discover the efficiency decrease and take corresponding measures to help construction workers with decreased efficiency improve their average work efficiency, so as to maintain the efficient operation of the construction team.

[0087] It should be noted that each time management collaborative optimization is performed, the average work efficiency of each construction worker is related to the work efficiency of the most recent historical construction projects. Therefore, when the construction workers are constantly working, each time they are matched, the newly entered work efficiency of each construction worker will have an impact on their average work efficiency. In other words, each time a match is made, the average work efficiency of each construction worker will be refreshed. This average work efficiency calculation method can ensure that the average work efficiency of each construction worker is updated as their work experience changes, so as to more accurately reflect their actual work ability.

[0088] like Figure 2 As shown, based on the above method embodiment, a corresponding device embodiment is provided;

[0089] An embodiment of the present invention provides a construction personnel management collaborative optimization device, comprising: a historical construction project information acquisition module, a work efficiency calculation module, a to-be-allocated project information acquisition module, an estimated construction volume calculation module, and an adaptive construction personnel screening module;

[0090] The historical construction project information acquisition module is used to obtain the workload, start time and end time of each historical construction project of each construction worker in each type of construction work;

[0091] The work efficiency calculation module is used to calculate the average work efficiency of each construction worker in each type of construction work according to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work;

[0092] The information acquisition module of the project to be allocated is used to obtain the target quantity and target time of the construction project to be allocated;

[0093] The estimated construction volume calculation module is used to calculate the estimated construction volume to be achieved by each construction worker in the corresponding construction work type according to the target time of the construction project to be allocated and the average work efficiency of each construction worker in the construction work type corresponding to the construction project to be allocated;

[0094] The adaptive construction personnel screening module is used to compare the construction volume that each construction personnel in the corresponding construction type is expected to achieve with the target volume of the construction project to be assigned, and screen out the construction personnel whose estimated construction volume is greater than the target volume as the adaptive construction personnel corresponding to the construction project to be assigned.

[0095] like Figure 3 As shown, an embodiment of the present invention provides another construction personnel management collaborative optimization device;

[0096] In a preferred embodiment, the construction personnel management collaborative optimization device further includes: a last construction information extraction module, a time interval sorting module, and a final construction personnel determination module;

[0097] The last construction information extraction module is used to extract the end time of the last project construction of the construction personnel from the end time of the historical construction projects of each construction personnel;

[0098] The time interval sorting module is used to calculate the time interval between the last work of each suitable construction personnel according to the end time of the last project construction of each suitable construction personnel, and sort the suitable construction personnel from large to small according to the time interval;

[0099] The final construction personnel determination module is used to select a corresponding number of suitable construction personnel from the sorted suitable construction personnel in order according to the number of construction personnel required by the construction project to be allocated, as the final construction personnel for the construction project to be allocated.

[0100] like Figure 4 As shown, an embodiment of the present invention provides another construction personnel management collaborative optimization device;

[0101] In a preferred embodiment, the construction personnel management collaborative optimization device further includes: an average work efficiency comparison module and an efficiency early warning module;

[0102] The average work efficiency comparison module is used to compare the current average work efficiency of each construction worker with the average work efficiency of the last management collaborative optimization for each construction worker of each construction type;

[0103] The efficiency warning module is used to issue an efficiency warning signal when the current average work efficiency is lower than the average work efficiency during the last management collaborative optimization, and the decreased average work efficiency exceeds a preset efficiency threshold.

[0104] like Figure 5 As shown, an embodiment of the present invention provides another construction personnel management collaborative optimization device;

[0105] In a preferred embodiment, the work efficiency calculation module includes: a work efficiency calculation unit, a target work efficiency screening unit, and an average work efficiency calculation unit;

[0106] The work efficiency calculation unit is used to calculate the work efficiency of each historical construction project of each construction worker in each type of construction work according to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work;

[0107] The target work efficiency screening unit is used to select the work efficiencies of several historical construction projects whose end time is closest to the current time from the work efficiencies of each historical construction project of each construction worker of each type of construction work, and obtain several target work efficiencies;

[0108] The average work efficiency calculation unit is used to calculate the average value of the plurality of target work efficiencies to obtain the average work efficiency of each construction worker in each type of construction work.

[0109] In a preferred embodiment, the work efficiency calculation unit includes: a project completion time calculation subunit and a work efficiency calculation subunit;

[0110] The project completion time calculation subunit is used to calculate the completion time of each historical construction project of each construction worker in each type of construction work according to the start time and end time of the historical construction project;

[0111] The work efficiency calculation subunit is used to calculate the work efficiency of each historical construction project of each construction worker in each type of construction work according to the workload of the historical construction projects and the completion time of the corresponding historical construction projects.

[0112] It can be understood that the above-mentioned device item embodiments correspond to the method item embodiments of the present invention, and can implement the construction personnel management collaborative optimization method provided by any of the above-mentioned method item embodiments of the present invention.

[0113] It should be noted that the device embodiments described above are merely illustrative, and some or all of the modules may be selected according to actual needs to achieve the purpose of the present embodiment. In addition, in the accompanying drawings of the device embodiments provided by the present invention, the connection relationship between the modules indicates that there is a communication connection between them, which may be specifically implemented as one or more communication buses or signal lines. Those of ordinary skill in the art may understand and implement the present invention without creative work.

[0114] Based on the above-mentioned embodiment of the collaborative optimization method for management of construction personnel, another embodiment of the present invention provides a terminal device, which includes a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor. When the processor executes the computer program, the collaborative optimization method for management of construction personnel according to any embodiment of the present invention is implemented.

[0115] Exemplarily, in this embodiment, the computer program may be divided into one or more modules, which are stored in the memory and executed by the processor to implement the present invention. The one or more module elements may be a series of computer program instruction segments capable of implementing specific functions, which are used to describe the execution process of the computer program in the terminal device.

[0116] The terminal device may be a computing device such as a desktop computer, a notebook, a PDA, a cloud server, etc. The terminal device may include, but is not limited to, a processor and a memory.

[0117] The processor may be a central processing unit (CPU), other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. The general-purpose processor may be a microprocessor or any conventional processor, etc. The processor is the control center of the terminal device, and uses various interfaces and lines to connect various parts of the entire terminal device.

[0118] Based on the above method embodiment, another embodiment is provided: another embodiment of the present invention provides a computer-readable storage medium, including a stored computer program, wherein when the computer program is running, the device where the computer-readable storage medium is located is controlled to execute the construction personnel management collaborative optimization method described in any one of the above method embodiments of the present invention.

[0119] Wherein, the module / unit integrated in the management collaborative optimization device / terminal equipment of the construction personnel, if implemented in the form of a software functional unit and sold or used as an independent product, can be stored in a computer-readable storage medium. Based on such an understanding, the present invention implements all or part of the processes in the above-mentioned embodiment method, and can also be completed by instructing the relevant hardware through a computer program. The computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. Wherein, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form, etc. The computer-readable medium can include: any entity or device capable of carrying the computer program code, recording medium, U disk, mobile hard disk, magnetic disk, optical disk, computer memory, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), electric carrier signal, telecommunication signal and software distribution medium, etc.

[0120] The above is a preferred embodiment of the present invention. It should be pointed out that a person skilled in the art can make several improvements and modifications without departing from the principle of the present invention. These improvements and modifications are also considered to be within the scope of protection of the present invention.

Claims

1. A collaborative optimization method for management of construction personnel, It is characterized in that include: Obtain the workload, start time and end time of each historical construction project of each construction worker in each type of construction work; The average work efficiency of each construction worker in each type of construction work is calculated based on the workload, start time and end time of each historical construction project of each construction worker in each type of construction work; Obtaining target quantities of construction projects to be assigned and target times of construction projects to be assigned; According to the target time of the construction project to be assigned and the average work efficiency of each construction worker in the construction type corresponding to the construction project to be assigned, the construction volume expected to be achieved by each construction worker in the corresponding construction type is calculated; The construction volume that each construction worker in the corresponding construction type is expected to achieve is compared with the target volume of the construction project to be assigned, and the construction workers whose construction volume is expected to be greater than the target volume are screened out as suitable construction workers corresponding to the construction project to be assigned.

2. The construction personnel management collaborative optimization method according to claim 1, It is characterized in that After selecting the construction personnel whose expected construction volume is greater than the target volume as the appropriate construction personnel for the construction projects to be assigned, it also includes: Extract the end time of the last project construction of the adapted construction personnel from the end time of the historical construction projects of each construction personnel; According to the end time of the last project construction of each suitable construction personnel, calculate the time interval between the last work of each suitable construction personnel, and sort the suitable construction personnel from large to small according to the time interval; According to the number of construction workers required for the construction project to be allocated, a corresponding number of suitable construction workers are selected in order from the sorted suitable construction workers as the final construction workers for the construction project to be allocated.

3. The method for collaborative optimization of construction personnel management according to claim 2, It is characterized in that Also includes: For each construction worker of each construction type, the current average work efficiency of each construction worker is compared with the average work efficiency during the last management collaborative optimization; If the current average work efficiency is lower than the average work efficiency during the last management collaborative optimization, and the decreased average work efficiency exceeds the preset efficiency threshold, an efficiency warning signal is issued.

4. The method for collaborative optimization of construction personnel management according to claim 1, It is characterized in that According to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work, the average work efficiency of each construction worker in each type of construction work is calculated, including: Calculate the work efficiency of each historical construction project of each construction worker in each type of construction work according to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work; For each construction worker of each type of construction work, the work efficiencies of several historical construction projects whose end time is closest to the current time are selected from the work efficiencies of each historical construction project of the construction worker to obtain several target work efficiencies; The average value of the target work efficiencies is calculated to obtain the average work efficiency of each construction worker in each type of construction work.

5. The method for collaborative optimization of construction personnel management according to claim 4, It is characterized in that According to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work, the work efficiency of each historical construction project of each construction worker in each type of construction work is calculated, including: For each historical construction project of each construction worker in each type of construction work, the completion time of the historical construction project is calculated based on the start time and end time of the historical construction project; According to the workload of historical construction projects and the completion time of corresponding historical construction projects, the work efficiency of each historical construction project of each construction worker in each type of construction work is calculated.

6. A construction personnel management collaborative optimization device, It is characterized in that include: Historical construction project information acquisition module, work efficiency calculation module, to-be-assigned project information acquisition module, estimated construction volume calculation module, and suitable construction personnel screening module; The historical construction project information acquisition module is used to obtain the workload, start time and end time of each historical construction project of each construction worker in each type of construction work; The work efficiency calculation module is used to calculate the average work efficiency of each construction worker in each type of construction work according to the workload, start time and end time of each historical construction project of each construction worker in each type of construction work; The to-be-allocated project information acquisition module is used to acquire the target quantity and target time of the to-be-allocated construction project; The estimated construction volume calculation module is used to calculate the estimated construction volume to be achieved by each construction worker in the corresponding construction work type according to the target time of the construction project to be allocated and the average work efficiency of each construction worker in the construction work type corresponding to the construction project to be allocated; The adapted construction personnel screening module is used to compare the construction volume that each construction personnel in the corresponding construction work type is expected to achieve with the target volume of the construction project to be assigned, and screen out the construction personnel whose expected construction volume is greater than the target volume as the adapted construction personnel corresponding to the construction project to be assigned.

7. The construction personnel management collaborative optimization device according to claim 6, It is characterized in that Also includes: The last construction information extraction module, the time interval sorting module, and the final construction personnel determination module; The last construction information extraction module is used to extract the end time of the last project construction of the adapted construction personnel from the end time of the historical construction projects of each construction personnel; The time interval sorting module is used to calculate the time interval between the last work of each suitable construction personnel according to the end time of the last project construction of each suitable construction personnel, and sort the suitable construction personnel from large to small according to the time interval; The final construction personnel determination module is used to select a corresponding number of suitable construction personnel in order from the sorted suitable construction personnel according to the number of construction personnel required for the construction project to be allocated, as the final construction personnel for the construction project to be allocated.

8. The construction personnel management collaborative optimization device according to claim 7, It is characterized in that Also includes: Average work efficiency comparison module and efficiency warning module; The average work efficiency comparison module is used to compare the current average work efficiency of each construction worker with the average work efficiency of the last management collaborative optimization for each construction worker of each construction type; The efficiency warning module is used to send out an efficiency warning signal when the current average work efficiency is lower than the average work efficiency during the last management collaborative optimization and the decreased average work efficiency exceeds a preset efficiency threshold.

9. A terminal device, It is characterized in that The method comprises a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor. When the processor executes the computer program, the method for collaborative optimization of construction personnel management as described in any one of claims 1 to 5 is implemented.

10. A computer-readable storage medium, It is characterized in that include: A stored computer program, wherein when the computer program is running, the device where the computer-readable storage medium is located is controlled to execute the construction personnel management collaborative optimization method as described in any one of claims 1 to 5.