Intelligent management system and method for subway train

Through the vehicle-level intelligent Ethernet network and hot backup redundant on-board intelligent host and wireless transmission device, the in-car PIS system backbone network, intelligent network and maintenance network are integrated, and the design of in-car intelligent operation and maintenance equipment of subway trains is solved. The problems of low utilization rate and difficulty in fault location have achieved efficient data transmission and unified management, and improved network maintenance efficiency and security.

CN119078916AInactive Publication Date: 2024-12-06GUANGZHOU YUNDA INTELLIGENT TECH CO LTD
View PDF 15 Cites 0 Cited by

Patent Information

Application Number
CN202411291766.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-14
Publication Date
2024-12-06
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing subway trains have complex designs, low equipment utilization, irregular access to each subsystem, difficult fault location, limited transmission performance, and cannot meet the requirements of big data and real-time data transmission.

Method used

Adopt vehicle-level intelligent Ethernet network, including layer three and layer two intelligent Ethernet switches to form a redundant ring network, integrating the on-board PIS system backbone network, intelligent network and maintenance network, providing hot backup and redundant on-board intelligent hosts and Wireless transmission device supports multi-network bearer, VLAN division, SNMP management protocol and QOS strategy, realizing intelligent networking and data transmission redundancy.

Benefits of technology

It reduces the complexity of train Ethernet networking, improves the utilization rate of switch equipment, realizes unified intelligent management and rapid fault positioning of each subsystem, improves network maintenance efficiency and system operation safety, and is suitable for a variety of train arrangements.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119078916A_ABST
    Figure CN119078916A_ABST
Patent Text Reader

Abstract

The invention discloses a subway train intelligent management system and method, and belongs to the technical field of subway train intelligent management. Two three-layer intelligent Ethernet switches and a plurality of two-layer intelligent Ethernet switches form a whole-vehicle-level intelligent Ethernet network through a redundant ring network, and whole-vehicle Ethernet backbone network networking, whole-vehicle intelligent network networking and whole-vehicle maintenance network networking of a train-mounted PIS system are supported. The two vehicle-mounted intelligent hosts are connected to the whole vehicle level intelligent Ethernet network to realize a whole vehicle level network management function and data acquisition of each monitoring subsystem of the train; and the two vehicle-mounted wireless transmission devices are accessed to the whole vehicle-level intelligent Ethernet network and are used for vehicle-ground wireless transmission of data. The vehicle-mounted PIS system backbone network, the vehicle-mounted intelligent network and the maintenance network are integrated, the train Ethernet networking complexity is reduced, and the utilization rate of switch equipment is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of intelligent management of subway trains, and in particular to an intelligent management system and method for subway trains. Background Art

[0002] With the rapid development of intelligent technology in the urban rail transit industry, the level of intelligence required for vehicle operation and maintenance is getting higher and higher, which puts forward higher intelligent requirements for the monitoring, management, networking and data transmission of various on-board subsystems. At the same time, it is also necessary to take into account economy and improve the utilization rate of on-board equipment.

[0003] Modern subway trains are gradually equipped with on-board equipment specifically for intelligent train operation and maintenance to support the ground intelligent operation and maintenance system. Traditional on-board operation and maintenance equipment uses a self-built vehicle-level Ethernet network to collect basic status, fault and alarm data of each subsystem, including traction system, braking system, LCU (Logic Control Unit, programmable logic control unit) system, battery monitoring system, running monitoring system, door monitoring system, air conditioning monitoring system, train auxiliary unit control system, etc. However, the Ethernet access management method of each monitoring subsystem is single, and it is impossible to achieve standardization and unified management of the access of each subsystem. The utilization rate of the self-built vehicle-level Ethernet network is low, and it occupies additional limited installation space and electrical interface resources on the train.

[0004] Currently, there is another networking method, which is to use the vehicle-level Ethernet network of the on-board PIS (Passenger Information System) system to realize the networking of each subsystem. However, the vehicle-level Ethernet network of the on-board PIS system usually does not have the intelligent network management function of each subsystem, and the access methods of each subsystem are not unified. If a fault occurs later, it is difficult to locate and troubleshoot. In addition, the performance of the vehicle-level Ethernet network of the on-board PIS system is limited, and it cannot guarantee the requirements of big data and real-time data transmission of individual subsystems. Summary of the invention

[0005] The present application proposes an intelligent management system and method for subway trains. The present application integrates the on-board PIS system backbone network, the on-board intelligent network and the maintenance network, reduces the complexity of train Ethernet networking, improves the utilization rate of switch equipment, and solves the problems of the existing subway train on-board intelligent operation and maintenance equipment with complicated design, low equipment utilization rate, irregular access to various subsystems and difficulty in fault location.

[0006] This application is implemented through the following technical solutions:

[0007] An intelligent management system for subway trains, comprising:

[0008] The vehicle-level intelligent Ethernet network includes two three-layer intelligent Ethernet switches deployed in the first and last carriages of each train and several two-layer intelligent Ethernet switches deployed in the middle carriage. The two three-layer intelligent Ethernet switches and several two-layer intelligent Ethernet switches are connected in a redundant ring network to form the vehicle-level intelligent Ethernet network, supporting the vehicle Ethernet backbone network of the train on-board PIS system, the vehicle intelligent network network and the vehicle maintenance network network;

[0009] Two on-board intelligent hosts, which are respectively deployed in the first and last carriages of each train, and serve as hot standby redundancy for each other. The two on-board intelligent hosts are connected to the vehicle-level intelligent Ethernet network to realize the vehicle-level intelligent Ethernet network management function and the data collection of each monitoring subsystem of the train;

[0010] Also, two vehicle-mounted wireless transmission devices are respectively deployed in the first and last carriages of each train, serving as hot standby redundancy for each other. The two vehicle-mounted wireless transmission devices are connected to the vehicle-level intelligent Ethernet network for wireless transmission of data between the vehicle and the ground.

[0011] In some embodiments, the three-layer intelligent Ethernet switch and the two-layer intelligent Ethernet switch have Ethernet data forwarding functions and multi-network carrying capabilities, and can divide the train on-board PIS system vehicle Ethernet backbone network, vehicle intelligent network network and vehicle maintenance network network through different VLANs to ensure isolation between each network and real-time and reliability of data transmission.

[0012] In some embodiments, the three-layer intelligent Ethernet switch and the two-layer intelligent Ethernet switch have network management functions, can achieve ring network redundancy and VLAN division, support SNMP network management protocol for network management at different levels, and support QOS policy to allocate bandwidth, priority and control network access for application flows; wherein, the three-layer intelligent Ethernet switch supports dynamic and static routing configuration and address mapping, which is used to isolate the internal and external networks of the train to ensure that the train-ground network has no impact on the internal network of the train.

[0013] In some embodiments, the three-layer intelligent Ethernet switch supports VRRP virtual routing function, provides a unique vehicle-to-ground transmission gateway for the vehicle-level intelligent Ethernet network, realizes vehicle-mounted data collection and transmission redundancy, and when the main route of one of the three-layer intelligent Ethernet switches is abnormal, switches to another three-layer intelligent Ethernet switch backup route;

[0014] The two three-layer intelligent Ethernet switches are respectively configured with a super maintenance port. After the PC is connected to the super maintenance port and the IP is automatically allocated, the vehicle monitoring subsystem program upgrade, configuration modification and historical data download are realized through the super maintenance port.

[0015] In some embodiments, the on-board intelligent host has big data processing capabilities and big data storage capabilities, can process real-time data and historical data of each monitoring subsystem, and collect, analyze, filter and repackage the data; at the same time, it can save the real-time data and historical data of each monitoring subsystem for a long time.

[0016] In some embodiments, the on-board intelligent host has an intelligent network management function, which can automatically identify the train location of the switch, realize the automatic networking of the vehicle-level intelligent Ethernet network, detect the working status of the switch, the occupancy of the switch interface, and alarm for abnormal working status of the switch; at the same time, it can also determine the legal identity of each monitoring subsystem access, automatically allocate the access monitoring subsystem IP, real-time monitoring of the networking status and offline alarm of the monitoring subsystem.

[0017] In some embodiments, the on-board intelligent host has the subway train TCMS access function, can access the TCMS network through the MVB and TRDP interfaces, and collect key train status, fault and warning data in real time.

[0018] In some embodiments, the vehicle-mounted wireless transmission device supports multiple communication modes and can realize autonomous switching;

[0019] The vehicle-mounted wireless transmission device has a port, IP address and MAC address filtering security protection mechanism, and also supports the SNMP network management protocol, and can send its own connection status, transmission rate, port occupancy status and fault alarm to the vehicle-mounted intelligent host;

[0020] The vehicle-mounted wireless transmission device has multiple networking modes.

[0021] On the other hand, the present application also proposes a subway train intelligent management method, comprising:

[0022] Construct a vehicle-level intelligent Ethernet network, deploy a three-layer intelligent Ethernet switch in the first and last carriages of each train, and deploy several two-layer intelligent Ethernet switches in the middle carriage of each train, and use a redundant ring network to connect the two three-layer intelligent Ethernet switches and several two-layer intelligent Ethernet switches to form the vehicle-level intelligent Ethernet network, supporting the vehicle Ethernet backbone network of the train on-board PIS system, the vehicle intelligent network networking and the vehicle maintenance network networking;

[0023] Two on-board intelligent hosts are provided. The two intelligent hosts are respectively deployed in the first and last carriages of each train, and serve as hot standby redundancy for each other. The two on-board intelligent hosts are connected to the vehicle-level intelligent Ethernet network to realize the vehicle-level intelligent Ethernet network management function and the data collection of the monitoring subsystem of the train;

[0024] Two vehicle-mounted wireless transmission devices are provided, and the two vehicle-mounted wireless transmission devices are respectively deployed in the first and last carriages of each train, serving as hot standby redundancy for each other. The two vehicle-mounted wireless transmission devices are connected to the vehicle-level intelligent Ethernet network for wireless transmission of data between the vehicle and the ground.

[0025] In some embodiments, the three-layer intelligent Ethernet switch and the two-layer intelligent Ethernet switch have Ethernet data forwarding functions and multi-network carrying capabilities, and can divide the train on-board PIS system vehicle Ethernet backbone network, vehicle intelligent network network and vehicle maintenance network network through different VLANs to ensure isolation between each network and real-time and reliability of data transmission.

[0026] The present application proposes an intelligent management system and method for subway trains, which uses an on-board intelligent Ethernet switch to integrate the on-board PIS system backbone network, the on-board intelligent network and the maintenance network, thereby reducing the complexity of train Ethernet networking and improving the utilization rate of switch equipment; in addition, two hot standby redundant on-board intelligent hosts are used, which have their own network management module, can intelligently realize intelligent networking of switches, intelligently allocate IP addresses of access subsystems, realize online real-time monitoring of network status and fault alarm, isolate and alarm illegal access subsystems, and perform Ethernet fast fault location, effectively improving the network maintenance efficiency of the entire vehicle and the safety of system operation;

[0027] The present application proposes an intelligent management system and method for subway trains, which adopts an on-board intelligent host and can adapt to the interface requirements of more on-board monitoring subsystems, such as MVB, TRDP bus and Gigabit Ethernet, etc., providing a more effective and reliable train intelligent operation and maintenance data collection technology;

[0028] The present application proposes an intelligent management system and method for subway trains, with local flexible redundant ring network networking capabilities, which can achieve unified intelligent management of various networking devices through an on-board intelligent host and can be applied to a variety of train formations. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] The drawings described herein are used to provide a further understanding of the embodiments of the present application, constitute a part of the present application, and do not constitute a limitation on the embodiments of the present application. In the drawings:

[0030] Figure 1 This is a schematic diagram of the intelligent management system architecture of an embodiment of the present application;

[0031] Figure 2 This is a schematic diagram of the vehicle-mounted intelligent main machine structure of an embodiment of the present application;

[0032] Figure 3 This is a schematic diagram of the architecture of a vehicle-mounted wireless transmission device according to an embodiment of the present application;

[0033] Figure 4 This is a flow chart of the intelligent management method according to an embodiment of the present application. DETAILED DESCRIPTION

[0034] Hereinafter, the term "include" or "may include" used in various embodiments of the present application indicates the presence of the invented function, operation or element, and does not limit the addition of one or more functions, operations or elements. In addition, as used in various embodiments of the present application, the terms "include", "have" and their cognates are intended only to indicate specific features, numbers, steps, operations, elements, components or a combination of the foregoing items, and should not be understood as first excluding the presence of one or more other features, numbers, steps, operations, elements, components or a combination of the foregoing items or the possibility of adding one or more features, numbers, steps, operations, elements, components or a combination of the foregoing items.

[0035] In various embodiments of the present application, the expression "or" or "at least one of A or / and B" includes any combination or all combinations of the words listed at the same time. For example, the expression "A or B" or "at least one of A or / and B" may include A, may include B, or may include both A and B.

[0036] The expressions (such as "first", "second", etc.) used in the various embodiments of the present application may modify the various constituent elements in the various embodiments, but may not limit the corresponding constituent elements. For example, the above expressions do not limit the order and / or importance of the elements. The above expressions are only used for the purpose of distinguishing one element from other elements. For example, the first user device and the second user device indicate different user devices, although both are user devices. For example, without departing from the scope of the various embodiments of the present application, the first element may be referred to as the second element, and similarly, the second element may also be referred to as the first element.

[0037] It should be noted that if it is described that one component element is “connected” to another component element, the first component element may be directly connected to the second component element, and a third component element may be “connected” between the first component element and the second component element. Conversely, when one component element is “directly connected” to another component element, it can be understood that there is no third component element between the first component element and the second component element.

[0038] The terms used in the various embodiments of the application are only used to describe the purpose of specific embodiments and are not intended to limit the various embodiments of the application. As used herein, the singular form is intended to also include the plural form, unless the context clearly indicates otherwise. Unless otherwise limited, all terms used here (including technical terms and scientific terms) have the same meaning as the meanings commonly understood by ordinary technicians in the field of the various embodiments of the application. The terms (such as the terms defined in the dictionary generally used) will be interpreted as having the same meaning as the contextual meaning in the relevant technical field and will not be interpreted as having an idealized meaning or an overly formal meaning, unless clearly defined in the various embodiments of the application.

[0039] In order to make the objectives, technical solutions and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with examples and drawings. The illustrative implementation scheme of the present application and its description are only used to explain the present application and are not intended to limit the present application.

[0040] Example:

[0041] Existing subway trains mainly use self-built vehicle-level Ethernet or vehicle-level Ethernet of the on-board PIS system to manage various monitoring subsystems, which has problems such as single Ethernet networking management mode, low network utilization, inconsistent access mode or difficult fault location. In view of this, this embodiment proposes an intelligent management system and method for subway trains. The management system proposed in this embodiment adopts an on-board intelligent switch with intelligent network management function, which integrates the on-board PIS system backbone network, on-board intelligent network and maintenance network, reduces the complexity of train Ethernet networking and improves the utilization rate of switch equipment.

[0042] Specific as Figure 1 As shown, the management system proposed in this embodiment includes:

[0043] The vehicle-level intelligent Ethernet network includes two Layer 3 intelligent Ethernet switches (i.e. HUB L3) deployed in the first and last carriages of each train and several Layer 2 intelligent Ethernet switches (i.e. HUB L2) deployed in the middle carriages, wherein one Layer 2 intelligent Ethernet switch is deployed in each middle carriage, and a redundant ring network is used to form a vehicle-level intelligent Ethernet network for all Ethernet switches, supporting the vehicle Ethernet backbone network networking, vehicle intelligent network networking and vehicle maintenance network networking of the train on-board PIS system, wherein the on-board PIS system backbone network is used to realize the cross-carriage networking of the PIS system host in each carriage, the intelligent network is used for the networking of the on-board intelligent host and various monitoring subsystems, and the vehicle maintenance network is used for the networking of the super maintenance port and all on-board subsystems;

[0044] Two on-board intelligent hosts, namely on-board intelligent host 1 and on-board intelligent host 2, are deployed in the first and last carriages of each train, including the driver's cab, and serve as hot standby redundancy for each other. The two on-board intelligent hosts are connected to the vehicle-level intelligent Ethernet network to realize the vehicle-level intelligent Ethernet network management function and data collection of other monitoring subsystems of the train;

[0045] In addition, two on-board wireless transmission devices, namely on-board wireless transmission device 1 and on-board wireless transmission device 2, are respectively deployed in the first and last carriages of each train containing the driver's cab, and serve as hot standby redundancy for each other. The two on-board wireless transmission devices are connected to the vehicle-level intelligent Ethernet network for wireless transmission of data between the train and the ground (i.e., between the train and the ground).

[0046] In an optional implementation, both the Layer 3 intelligent Ethernet switch and the Layer 2 intelligent Ethernet switch comply with the EN50155 standard, use a DC 110V input power supply, have a built-in switch-specific IC, and are separately configured with an embedded processor responsible for receiving relevant network configuration instructions and sending the switch's own status and protection alarm status.

[0047] The three-layer intelligent Ethernet switch and the two-layer intelligent Ethernet switch have powerful Ethernet data forwarding functions, built-in high-performance dedicated ICs, and multi-network carrying capabilities. They can realize the train on-board PIS system vehicle Ethernet backbone network networking, vehicle intelligent network networking and vehicle maintenance network networking through different VLAN divisions. The PIS system backbone network is divided into VLAN1, the intelligent network is divided into VLAN2, and the maintenance network is divided into VLAN3. The three VLANs belong to different network segments and are virtually isolated from each other. The network services do not conflict with each other. The maintenance network VLAN3 obtains access rights to VLAN1 and VLAN2 for the entire vehicle network through the three-layer switch routing function, ensuring isolation between each network and real-time and reliability of data transmission.

[0048] The three-layer intelligent Ethernet switch supports VRRP virtual routing function, providing a unique vehicle-to-ground transmission gateway for the vehicle-level intelligent Ethernet network, realizing redundant transmission of vehicle-mounted data collection. When the main route of one of the three-layer intelligent Ethernet switches is abnormal, it can switch to another three-layer intelligent Ethernet switch as a backup route.

[0049] Two three-layer intelligent Ethernet switches are each equipped with a super maintenance port. When a PC (terminal device for operation and maintenance personnel) is connected to the super maintenance port and the IP is automatically assigned, the port can be used to perform operations such as program upgrades, configuration modifications, and historical data downloads for other monitoring subsystems of the entire vehicle, thereby avoiding the need to replace the maintenance port during the subsequent maintenance of each monitoring subsystem, which would increase additional maintenance time.

[0050] The three-layer intelligent Ethernet switch and the two-layer intelligent Ethernet switch have network management functions, can achieve ring network redundancy, VLAN division, support SNMP network management protocol for network management at different levels, support QOS strategy to allocate bandwidth and priority for application flow and control network access. Among them, the three-layer intelligent Ethernet switch supports dynamic and static routing configuration and address mapping, which is used to isolate the internal and external networks of the train to ensure that the train-ground network (external network) has no impact on the train network (intranet).

[0051] Layer 3 intelligent Ethernet switches and Layer 2 intelligent Ethernet switches provide multiple management functions such as ACL control, port-based and 802.1Q-based VLAN, Web-based network management, MAC address binding, etc., which can improve the security of the entire network and provide multiple functions such as preventing illegal access and suppressing broadcast storms.

[0052] Each port of the Layer 3 intelligent Ethernet switch and Layer 2 intelligent Ethernet switch can be assigned a fixed IP. When a subsystem is connected, a fixed IP can be automatically assigned to the subsystem, eliminating the need for manual IP allocation and improving access efficiency.

[0053] An optional implementation method is that the on-board intelligent host has big data processing and big data storage capabilities, can efficiently process the real-time and historical data of each monitoring subsystem, collect, analyze, filter and repackage the data, and can save the real-time and historical data of each monitoring subsystem for a long time to prevent the loss of original collected data due to unstable train-ground network; the on-board intelligent host has intelligent network management function, can automatically identify the train location of the switch, realize the automatic networking of the whole vehicle-level intelligent Ethernet network, and monitor the working status of the intelligent Ethernet switch, the occupancy of the switch interface and alarm for abnormal working conditions of the switch; it can also determine the legal identity of each monitoring subsystem access, automatically allocate the access subsystem IP, real-time monitoring of the networking status and subsystem offline alarm; the on-board intelligent host has the subway train TCMS access function, and can access the TCMS network through the MVB and TRDP interfaces to collect the train's key status, fault and warning data in real time. The on-board intelligent host adopts a 3U plug-in modular design, and each main function realizes modular design, which is conducive to the subsequent maintenance and replacement of related fault modules and improves maintenance efficiency. Figure 2 As shown, the vehicle-mounted intelligent host of this embodiment includes:

[0054] The power module provides the required working power for the host. It uses the conventional DC110V voltage input of the train. The power module uses an isolated power supply to isolate the train power supply from the working power supply of other internal modules. The input and output isolation voltage is not less than AC2000V. It provides multiple working voltages such as DC+5V, DC+3.3V, and DC+12V based on the working power supply of other modules. It has protection functions such as input over-voltage and under-voltage, output over-current, and lightning protection.

[0055] Control module, which can use ATMEL automotive-grade S12 series microcontroller as the control core, is used to monitor the host operating voltage, operating current and internal temperature of the chassis, and send the collected information to the CPU processing module through the serial port for basic status monitoring and storage records of the host itself;

[0056] TCMS gateway module, which has two interfaces that meet the train standards: MVB and TRDP. Among them, the MVB interface meets the requirements of Class I MVB equipment in IEC 61375-3-2, uses EMD media, and the connector uses a male and female D-SUB9 interface to meet the MVB bus redundant access requirements. The TRDP interface meets the interface requirements in IEC61375-3-4, uses dual M12-D 100M network material interfaces, and meets the TRDP bus redundant access requirements;

[0057] CPU processing module, the CPU processing module can use Intel's onboard X86 architecture Intel I7 high-frequency processor as the data processing core, provide 4 independent Gigabit Ethernet interfaces to meet the physical access requirements of the Ethernet network, and also provide an Ethernet network maintenance port, which can be logged in and maintained through the remote tool of the PC; it also provides 2 USB interfaces for fast program upgrades and historical data downloads; the CPU processing module has 2 Ethernet, 2 serial ports, 4 PCIE, 4 CPCI, 2 SATA and other interfaces, providing rich and flexible expansion interfaces, which can efficiently process the real-time data and historical data of each monitoring subsystem, and perform operations such as data collection, analysis, filtering and repackaging; the CPU processing module is connected to the storage module through the SATA interface, connected to the TCMS gateway module through the CPCI interface, connected to the control module through the RS232 interface, and connected to the intelligent network control module through the Ethernet interface;

[0058] Intelligent network control module, which adopts high-performance Cortex-A55 embedded processor based on ARM architecture, deploys embedded network management operating system, and logs in through remote WEB mode; it can automatically identify the train location of intelligent Ethernet switch and on-board wireless transmission device, and realize automatic networking of the whole vehicle intelligent network; it can monitor the working status of intelligent Ethernet switch, the occupancy of switch interface and alarm the abnormal working status of switch; it can also determine the legal identity of each subsystem access, automatically allocate the access subsystem IP, real-time monitoring of networking status and subsystem offline alarm;

[0059] And, the storage module realizes the storage record of the host's own log records and collected data. It can use an industrial-grade SATA3 solid-state hard drive with high-speed read and write speeds and power-off protection functions. The solid-state hard drive has the advantages of high stability and long life, ensuring the reliability of data storage.

[0060] The on-board intelligent host has hot standby redundancy function. The two hosts work simultaneously in master-slave hot standby redundancy mode. The two hosts distinguish the master and slave through the chassis address. The two hosts monitor each other's working status. When the host working in the master mode fails, it can switch to another host to work, which greatly improves the system operation reliability.

[0061] An optional implementation method, the vehicle-mounted wireless transmission device supports the function of accessing ground WIFI hotspots, supports WIFI 5 and WIFI 6 standards, and has port, IP address and MAC address filtering security protection mechanisms. It also supports the SNMP network management protocol, and can send its own connection status, transmission rate, port occupancy status and fault alarm to the vehicle-mounted intelligent host; the vehicle-mounted wireless transmission device also supports 4G / 5G transmission function, and has various networking methods including dynamic / static IP routing, PPPoE, Modem dial-up, and supports Open VPN, PPTP, IPSEC, VPN reliable network to protect the security of the vehicle-to-ground transmission channel; the vehicle-mounted wireless transmission device supports autonomous switching between WIFI and 4G / 5G networks. When the WIFI signal is weak or there is no signal, it can automatically switch to the 4G / 5G network to ensure the continuity and stability of line communication. The vehicle-mounted wireless transmission device adopts a highly integrated and wall-mounted fixed design, with a large surface area heat sink, internally integrated with a high-performance industrial-grade embedded processor, WIFI module and 5G module, and has 2 sets of WIFI antenna interfaces and 4-way 5G antenna interfaces. Specifically, Figure 3 As shown, the vehicle-mounted wireless transmission device of this embodiment includes:

[0062] Power module, which provides the required working power for the on-board wireless transmission device and uses the train's conventional DC 110V voltage input;

[0063] CPU processing module, which is connected to the intelligent Ethernet switch through the Ethernet interface externally, and is connected to the 5G module and WIFI module internally through the PCIE interface. It supports autonomous switching between WIFI and 4G / 5G networks. When the WIFI signal is weak or there is no signal, it can automatically switch to the 4G / 5G network to ensure the continuity and stability of line communication; it also supports the SNMP network management protocol, and can send its own connection status, transmission rate, port occupancy status and fault alarm to the on-board intelligent host

[0064] 5G module, which supports 4G / 5G transmission functions, has various networking methods including dynamic / static routing, PPPoE, Modem dial-up, supports Open VPN, PPTP, IPSEC, VPN reliable network, and protects the security of vehicle-to-ground transmission channel;

[0065] As well as the WIFI module, this WIFI module supports access to ground WIFI hotspots, supports WIFI 5 and WIFI 6 standards, and has port, IP address and MAC address filtering security protection mechanisms.

[0066] The two vehicle-mounted wireless transmission devices work simultaneously in hot standby redundant mode. The two devices monitor each other's working status. When a device working in the main mode fails, it can switch to another device to work, greatly improving the system operation reliability.

[0067] This embodiment uses an on-board intelligent Ethernet switch to integrate the on-board PIS system backbone network, on-board intelligent network and maintenance network, reducing the complexity of train Ethernet networking and improving the utilization rate of switch equipment. In addition, this embodiment uses two hot standby redundant on-board intelligent hosts with built-in network management modules, which can intelligently realize intelligent networking of switches and intelligently allocate IP addresses of access subsystems, realize online real-time monitoring of network status and fault alarm, isolate and alarm illegal access subsystems, and perform Ethernet fast fault location, effectively improving the network maintenance efficiency of the entire vehicle and the safety of system operation.

[0068] The on-board intelligent host used in this embodiment can adapt to the interface requirements of more on-board monitoring subsystems, such as MVB, TRDP bus and Gigabit Ethernet, providing a more effective and reliable train intelligent operation and maintenance data collection technology.

[0069] The intelligent management system used in this embodiment has flexible redundant ring network networking capabilities. Through the on-board intelligent host, unified intelligent management of various networking devices can be achieved, and it can be applied to a variety of train formations, such as 4, 6 (such as Figure 1 as shown) or 8-car train, etc.

[0070] Based on the same technical concept as above, this embodiment also proposes an intelligent management system and method for subway trains, such as Figure 4 As shown, the management method proposed in this embodiment specifically includes the following steps:

[0071] Build a vehicle-level intelligent Ethernet network, deploy a three-layer intelligent Ethernet switch in the first and last carriages of each train, and deploy several two-layer intelligent Ethernet switches in the middle carriages of each train (i.e., the carriages other than the first and last carriages). Use a redundant ring network to connect two three-layer intelligent Ethernet switches and several two-layer intelligent Ethernet switches to form a vehicle-level intelligent Ethernet network to support the vehicle Ethernet backbone network of the train on-board PIS system, the vehicle intelligent network network, and the vehicle maintenance network network;

[0072] Provide two on-board intelligent hosts, which are deployed in the first and last carriages of each train, including the driver's cab, to provide hot standby redundancy for each other. The two on-board intelligent hosts are connected to the vehicle-level intelligent Ethernet network to realize the vehicle-level intelligent Ethernet network management function and data collection of other monitoring subsystems of the train;

[0073] Two on-board wireless transmission devices are provided. They are respectively deployed in the first and last carriages of each train, which contain the driver's cab. They serve as hot standby redundancy for each other. The two on-board wireless transmission devices are connected to the vehicle-level intelligent Ethernet network for wireless transmission of data between the train and the ground.

[0074] In an optional implementation manner, the configuration and functions of the three-layer intelligent Ethernet switch and the two-layer intelligent Ethernet switch used in the method are as described in the above system, and will not be described in detail here.

[0075] An optional implementation manner, the on-board intelligent host provided by the method has a big data processing function, which can efficiently process the real-time data and historical data of each monitoring subsystem, and perform operations such as data collection, analysis, filtering and repackaging; the on-board intelligent host also has a big data storage function, which can realize long-term storage of real-time data and historical data of each monitoring subsystem, and prevent problems such as loss of original collected data caused by unstable train-ground network; the on-board intelligent host also has an intelligent network management function, which can automatically identify the train position of the switch and realize automatic networking of the entire vehicle intelligent network; it can monitor the working status of the intelligent Ethernet switch, the occupancy of the switch interface and alarm for abnormal working conditions of the switch; it can also determine the legal identity of each monitoring subsystem access, automatically allocate the access subsystem IP, real-time monitoring of the networking status and offline alarm of the monitoring subsystem; the on-board intelligent host also has a subway train TCMS access function, and can access the TCMS network through the MVB and TRDP interfaces to collect key train status, fault and warning data in real time.

[0076] The vehicle-mounted intelligent host has a hot standby redundancy function. The two vehicle-mounted intelligent hosts work simultaneously in hot standby redundancy mode. When the host working in the main mode fails, it can switch to another host to work, which greatly improves the system operation reliability.

[0077] It should be noted that the specific architecture of the vehicle-mounted intelligent host is as follows Figure 2 As shown and described in the above system, no further details will be given here.

[0078] An optional implementation manner, the vehicle-mounted wireless transmission device provided by the method supports the function of accessing ground WIFI hotspots, supports WIFI5 and WIFI6 standards, has port, IP address and MAC address filtering security protection mechanisms, and also supports SNMP network management protocol, which can send its own connection status, transmission rate, port occupancy status and fault alarm to the vehicle-mounted intelligent host. It also supports 4G / 5G transmission function, has various networking methods including dynamic / static IP routing, PPPoE, Modem dial-up, supports Open VPN, PPTP, IPSEC, VPN reliable network, and protects the security of vehicle-to-ground transmission channel. It also supports WIFI and 4G / 5G network autonomous switching strategy. When the WIFI signal is weak or there is no signal, it can automatically switch to the 4G / 5G network to ensure the continuity and stability of line communication.

[0079] In addition, the on-board wireless transmission device has a firewall function, which can effectively prevent illegal intrusions from outside the train, support bandwidth strategies, realize multi-channel bandwidth control, connection number limitation, and connection number monitoring; support ARP protection, which can prevent ARP spoofing and ARP attacks; support a variety of common attack protection, such as DDoS attacks, network scanning, and suspicious packet attacks; support MAC address filtering to block access to illegal hosts; have flexible security strategies, and can set independent security protection configurations for user addresses, services, websites, applications, black and white lists; support HTTP behavior, FTP behavior, email, IM, etc. audit.

[0080] The vehicle-mounted wireless transmission device has a hot standby redundancy function. The two vehicle-mounted wireless transmission devices work simultaneously in hot standby redundancy mode. When a device working in the main mode fails, it can switch to another device to work, greatly improving the system operation reliability.

[0081] It should be noted that the specific architecture of the vehicle-mounted wireless transmission device is as follows: Figure 3 As shown and described in the above-mentioned system, no further details will be given here.

[0082] The specific implementation methods described above further illustrate the purpose, technical solutions and beneficial effects of the present application in detail. It should be understood that the above description is only the specific implementation method of the present application and is not intended to limit the scope of protection of the present application. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application should be included in the scope of protection of the present application.

Claims

1. An intelligent management system for subway trains, characterized in that: include: The vehicle-level intelligent Ethernet network includes two three-layer intelligent Ethernet switches deployed in the first and last carriages of each train and several two-layer intelligent Ethernet switches deployed in the middle carriage. The two three-layer intelligent Ethernet switches and several two-layer intelligent Ethernet switches are connected in a redundant ring network to form the vehicle-level intelligent Ethernet network, supporting the vehicle Ethernet backbone network of the train on-board PIS system, the vehicle intelligent network network and the vehicle maintenance network network; Two on-board intelligent hosts, which are respectively deployed in the first and last carriages of each train, and serve as hot standby redundancy for each other. The two on-board intelligent hosts are connected to the vehicle-level intelligent Ethernet network to realize the vehicle-level intelligent Ethernet network management function and the data collection of each monitoring subsystem of the train; Also, two vehicle-mounted wireless transmission devices are respectively deployed in the first and last carriages of each train, serving as hot standby redundancy for each other. The two vehicle-mounted wireless transmission devices are connected to the vehicle-level intelligent Ethernet network for wireless transmission of data between the vehicle and the ground.

2. The intelligent management system for subway trains according to claim 1, characterized in that: The three-layer intelligent Ethernet switch and the two-layer intelligent Ethernet switch have Ethernet data forwarding functions and multi-network carrying capabilities. They can divide the train on-board PIS system vehicle Ethernet backbone network, vehicle intelligent network network and vehicle maintenance network network through different VLANs to ensure isolation between each network and real-time and reliability of data transmission.

3. The intelligent management system for subway trains according to claim 1 is characterized in that: The three-layer intelligent Ethernet switch and the two-layer intelligent Ethernet switch have network management functions, can realize ring network redundancy and VLAN division, support SNMP network management protocol for network management at different levels, and support QOS strategy to allocate bandwidth and priority for application flows and control network access; among them, the three-layer intelligent Ethernet switch supports dynamic and static routing configuration and address mapping, which is used for isolating the internal and external networks of the train to ensure that the train-ground network has no impact on the internal network of the train.

4. The intelligent management system for subway trains according to claim 1, characterized in that: The three-layer intelligent Ethernet switch supports VRRP virtual routing function, provides a unique vehicle-to-ground transmission gateway for the vehicle-level intelligent Ethernet network, and realizes vehicle-mounted data collection and data transmission redundancy. When the main route of one of the three-layer intelligent Ethernet switches is abnormal, it switches to the backup route of another three-layer intelligent Ethernet switch; The two three-layer intelligent Ethernet switches are respectively configured with a super maintenance port. After the PC is connected to the super maintenance port and the IP is automatically allocated, the vehicle monitoring subsystem program upgrade, configuration modification and historical data download are realized through the super maintenance port.

5. A subway train intelligent management system according to any one of claims 1 to 4, characterized in that: The vehicle-mounted intelligent host has big data processing and big data storage capabilities, can process the real-time data and historical data of each monitoring subsystem, and collect, analyze, filter and repackage the data; at the same time, it can save the real-time data and historical data of each monitoring subsystem for a long time.

6. The intelligent management system for subway trains according to claim 5, characterized in that: The on-board intelligent host has intelligent network management functions, can automatically identify the train location of the switch, realize the automatic networking of the vehicle-level intelligent Ethernet network, detect the working status of the switch, the occupancy of the switch interface, and alarm for abnormal working status of the switch; at the same time, it can also determine the legal identity of each monitoring subsystem access, automatically allocate the access monitoring subsystem IP, real-time monitoring of the networking status and offline alarm of the monitoring subsystem.

7. The intelligent management system for subway trains according to claim 6, characterized in that: The on-board intelligent host has the subway train TCMS access function, can access the TCMS network through the MVB and TRDP interfaces, and collect key train status, fault and warning data in real time.

8. The intelligent management system for subway trains according to claim 5, characterized in that: The vehicle-mounted wireless transmission device supports multiple communication modes and can realize autonomous switching; The vehicle-mounted wireless transmission device has a port, IP address and MAC address filtering security protection mechanism, and also supports the SNMP network management protocol, and can send its own connection status, transmission rate, port occupancy status and fault alarm to the vehicle-mounted intelligent host; The vehicle-mounted wireless transmission device has multiple networking modes.

9. A method for intelligent management of subway trains, characterized in that: include: Construct a vehicle-level intelligent Ethernet network, deploy a three-layer intelligent Ethernet switch in the first and last carriages of each train, and deploy several two-layer intelligent Ethernet switches in the middle carriage of each train, and use a redundant ring network to connect the two three-layer intelligent Ethernet switches and several two-layer intelligent Ethernet switches to form the vehicle-level intelligent Ethernet network, supporting the vehicle Ethernet backbone network of the train on-board PIS system, the vehicle intelligent network networking and the vehicle maintenance network networking; Two on-board intelligent hosts are provided. The two intelligent hosts are respectively deployed in the first and last carriages of each train, and serve as hot standby redundancy for each other. The two on-board intelligent hosts are connected to the vehicle-level intelligent Ethernet network to realize the vehicle-level intelligent Ethernet network management function and the data collection of the monitoring subsystem of the train; Two vehicle-mounted wireless transmission devices are provided, and the two vehicle-mounted wireless transmission devices are respectively deployed in the first and last carriages of each train, serving as hot standby redundancy for each other. The two vehicle-mounted wireless transmission devices are connected to the vehicle-level intelligent Ethernet network for wireless transmission of data between the vehicle and the ground.

10. The intelligent management method for subway trains according to claim 9, characterized in that: The three-layer intelligent Ethernet switch and the two-layer intelligent Ethernet switch have Ethernet data forwarding functions and multi-network carrying capabilities. They can divide the train on-board PIS system vehicle Ethernet backbone network, vehicle intelligent network network and vehicle maintenance network network through different VLANs to ensure isolation between each network and real-time and reliability of data transmission.

Citation Information

Patent Citations

  • Design scheme for inter-station communication network of passenger dedicated railway

    CN102223277A

  • High-speed train intelligent system and communication method thereof

    CN102497393A

  • Data service communication processing method and device

    CN105722118A

  • Military field operation logistics delivery protection box based on internet of things and positioning system thereof

    CN109987318A

  • Data sending and receiving method of cloud game and related equipment

    CN113996056A