Horizontal jacket SPMT transporting and shipping process

Through the SPMT transportation and ship loading process, the problem of horizontal conduit rack loading is solved due to the bearing capacity and tide of the slide, and construction is realized at any location, reducing infrastructure investment and ship loading time, and improving ship loading efficiency.

CN119079024AActive Publication Date: 2024-12-06ZHONGHAI FULU HEAVY IND CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411264279.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-12-06
Estimated Expiration
2044-09-10

AI Technical Summary

Technical Problem

The ship loading method of the existing horizontal conduit rack is affected by the bearing capacity of the slide, resulting in large initial investment, and the loading time is affected by tides, which affects the loading efficiency.

Method used

Using SPMT transportation and ship loading process, the carpooling scheme and transportation route are determined through computer simulation, and pre-lifting and debugging are used to use hydraulic systems and three-dimensional laser scanning technology to ensure that the horizontal conduit rack is built at any location, not affected by other projects, and reduce infrastructure Invest in and overcome the impact of the tide.

Benefits of technology

It reduces the initial infrastructure investment, shortens the loading time, improves the loading efficiency, is highly adaptable, is suitable for any construction site, and is not affected by tides.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119079024A_ABST
    Figure CN119079024A_ABST
Patent Text Reader

Abstract

The invention discloses a horizontal jacket SPMT transporting and shipping process, and relates to the technical field of ocean engineering. Comprising the following steps: step 1, determining a carpooling scheme of the SPMT; step 2, inspection and debugging of a vehicle entering road surface and investigation of a transportation route; thirdly, according to the SPMT carpooling scheme, the assembled SPMT is transported to the position below the corresponding horizontal jacket, and the horizontal jacket is pre-jacked; fourthly, the horizontal jacket is transported to the front edge position of the wharf through the SPMT; 5, the horizontal jacket is shipped in place, and the SPMT is transported to the designated position of the barge; and sixthly, the horizontal jacket is loaded into a ship, and SPMT vehicle withdrawing is conducted. According to the SPMT transportation shipping process for the horizontal jacket, the jacket can get rid of the limitation of a slide way, the problem that slide way resources need to be occupied is solved, and meanwhile shipping is carried out without being limited by tide water; in addition, the labor cost can be greatly saved, the construction period is shortened, and the construction cost of ocean engineering is saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of marine engineering technology, in particular to a horizontal jacket SPMT transportation and ship loading process. Background Art

[0002] At present, when the length of the jacket exceeds 100 meters and the total weight exceeds 1,000 tons, the horizontal jacket is traditionally loaded onto the ship by skidding and traction during its construction.

[0003] In the prior art, a horizontal jacket is generally constructed with a sliding shoe. After the horizontal jacket is constructed, it is towed onto a barge by a winch and a fixed pulley. However, this loading method is currently affected by the bearing capacity of the slideway. The construction on the slideway must be strictly carried out in accordance with the order of shipment. The slideway requires a large amount of pile foundation investment in the early stage, resulting in a large initial investment and high construction cost. At the same time, the tidal requirements must be considered during the loading process, resulting in the loading time of the horizontal jacket being extended due to the influence of the tide, which affects the loading efficiency of the horizontal jacket.

[0004] In order to solve the above problems, a horizontal jacket SPMT transportation and loading process is proposed. Summary of the invention

[0005] In view of the deficiencies in the prior art, the present invention provides a horizontal jacket SPMT transportation and loading process, which solves the problem that the current loading method of the horizontal jacket is affected by the bearing capacity of the slideway, the initial slideway requires a large amount of pile foundation investment, resulting in a large initial investment, and the tidal requirements for towing and loading during loading are high, which affects the loading efficiency of the horizontal jacket.

[0006] To achieve the above objectives, the present invention is implemented through the following technical solutions: A horizontal jacket SPMT transportation and loading process comprises the following steps:

[0007] Step 1: Determine the SPMT carpooling plan. Through computer simulation of the strength parameters, deformation parameters and force parameters of each lifting point of the horizontal jacket in the SPMT transportation state, and under the premise of the hydraulic system adopting three-point grouping, confirm the total weight of the equipment, the total weight of the vehicle and cargo, the maximum axis, the minimum axle load, the maximum ground pressure ratio and the horizontal jacket carpooling diagram;

[0008] Step 2: Check and debug the access road surface and survey the transportation route to obtain a transportation route map that meets the requirements of SPMT transportation of horizontal jackets;

[0009] Step 3: According to the SPMT carpooling plan obtained in step 1, the assembled SPMT is transported to the bottom of the corresponding horizontal jacket, and the horizontal jacket is pre-lifted and debugged so that the cargo is fully lifted;

[0010] Step 4: transport the horizontal jacket to the front of the wharf by SPMT according to the transportation route map obtained in step 2;

[0011] Step 5: Load the horizontal jacket onto the ship and transport the SPMT to the designated location on the barge;

[0012] Step six, loading the horizontal jacket. After the SPMT is adjusted to the designated position of the barge in step five, lower the height of the vehicle plate, adjust the position of the horizontal jacket so that the gap between the horizontal jacket beam piers is between 5-15mm, and gradually unload it at a step distance of 30-50bar. During the unloading process, pay attention to the status of the vehicle, cargo and piers. When the overall pressure of the vehicle group is reduced to 50bar, make a final confirmation. After confirmation, lower the SPMT vehicle plate to the lowest walkable height, and finally withdraw the SPMT.

[0013] Preferably, in step one, a finite element analysis method is used to simulate and calculate the parameters of the horizontal jacket under the SPMT transportation state, a three-dimensional model of the horizontal jacket is established, the material properties, boundary conditions and load conditions of the horizontal jacket are set, and meshing and solution calculations are performed to obtain the overall strength parameters, deformation parameters and force parameters of each hanging point of the horizontal jacket under the SPMT transportation state.

[0014] Preferably, in step 2, the vehicle entry road surface inspection, commissioning and transportation route survey are specifically as follows:

[0015] Check whether there is enough space on the approach road, whether there are any sharp protrusions on the approach road, whether all construction on the approach road has been completed and stopped, and whether no objects have fallen during the entire operation;

[0016] Adjust the size of the access road space to meet the requirements of the access space, ensure that there are no sharp protrusions on the access road, stop construction, no objects fall, and no hot work after the vehicle enters and when the goods come into contact with the vehicle board;

[0017] Survey the transportation route and eliminate the unfavorable factors that may affect the transportation of SPMT horizontal jackets.

[0018] Preferably, in step 2, the transport route is scanned using three-dimensional laser scanning technology to obtain three-dimensional point cloud data of the transport route, a three-dimensional model of the transport route is constructed based on the point cloud data, the road surface width, slope and turning radius parameters of the transport route are analyzed, and the transport route is optimized.

[0019] Preferably, in step 3, the operation steps of transporting the SPMT to the bottom of the corresponding horizontal jacket for pre-lifting and debugging specifically include the following steps:

[0020] Arrange monitoring points and reference points of horizontal jackets and configure operating tools;

[0021] Confirm the vehicle entry space and the SPMT placement location according to the vehicle allocation diagram;

[0022] Equip SPMT tooling according to vehicle configuration drawing;

[0023] SPMT enters the vehicle and takes position;

[0024] SPMT vehicle parallel debugging;

[0025] Synchronously lift the SPMT until it fits the bottom surface of the horizontal jacket transport beam, check whether the SPMT tooling is stressed, add pads to the unstressed SPMT tooling and lift it again to check whether the SPMT tooling is stressed, repeat this step until all SPMT tooling is stressed;

[0026] Fix the data connection line between the train sets, measure the height of the bottom surface of the horizontal jacket transport beam from the ground and the height of the car plate, and make adjustments;

[0027] Select a certain step value in the range of 30-50bar, lift the SPMT synchronously until one of the hydraulic groups reaches the pressure value, stop lifting, measure the height of the vehicle plate monitoring point, the deformation of the vehicle plate and the state of the cargo, adjust the oil pressure of other hydraulic groups to ensure the state of the vehicle and cargo

[0028] Then select a certain step value in the step interval within the value range of 30-50bar, and repeat the above steps until the cargo is completely lifted up and the lifting operation is completed.

[0029] Preferably, in step three, a total station is used to arrange monitoring points and reference points of the horizontal conductor rack, and the displacement and deformation of the horizontal conductor rack during the jacking process are monitored in real time. The monitoring data is transmitted to the control center through wireless transmission technology, and the jacking height and speed of the SPMT are dynamically adjusted according to the monitoring data.

[0030] Preferably, in step 4, the horizontal jacket is transported to the front position of the wharf by SPMT by: according to the transportation route map, a road survey is conducted on the driving area for transporting the jacket from the construction position to the designated position and the clearing area of ​​the horizontal jacket, and the factors affecting the shipment are marked for processing. After the inspection and processing results are qualified, the SPMT is used to transport the horizontal jacket along the marked path on the transportation route map until it is transported to the front position of the wharf.

[0031] Preferably, in step 4, the transport position of the SPMT is tracked in real time using GPS positioning technology, the positioning data is transmitted to the control center via wireless transmission technology, and the transport path and speed of the SPMT are dynamically adjusted according to the positioning data to ensure that the horizontal jacket is transported to the front position of the wharf according to the predetermined path and speed.

[0032] Preferably, factors affecting shipment in the SPMT driving area and the horizontal jacket sweeping area include but are not limited to obstacles, ground potholes, sharp protrusions and insufficient bearing capacity.

[0033] Preferably, in step five, laser navigation technology is used to accurately locate the transport position of the SPMT, and the position and posture information of the SPMT relative to the barge is obtained in real time by a laser navigation sensor. The transport path and speed of the SPMT are dynamically adjusted according to the position and posture information to ensure that the horizontal conductor rack is accurately transported to the designated position of the barge.

[0034] The present invention discloses a horizontal jacket SPMT transportation and loading process, which has the following beneficial effects:

[0035] The horizontal jacket SPMT transportation and loading process provided by the present invention can be constructed at any location in the site by adopting the SPMT transportation mode, is not affected by other projects, has low requirements on construction conditions, and has high adaptability; SPMT has low requirements on ground bearing capacity due to wheel pressure, does not need to carry out pile foundation work, reduces initial infrastructure investment, and reduces costs; SPMT itself has a hydraulic device, which can overcome the influence of tides, can greatly shorten the loading process, and improve work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0037] Figure 1 The present invention is a plan view of an embodiment of a horizontal jacket SPMT transportation and loading process.

[0038] Figure 2 The present invention is a top view of an embodiment of a horizontal jacket SPMT transportation and loading process.

[0039] Figure 3 This is a plan view of an embodiment of a horizontal jacket SPMT transportation and loading process of the present invention.

[0040] Figure 4 This is a diagram of loading a barge onto a horizontal jacket SPMT according to an embodiment of the present invention.

[0041] Figure 5 The following is a barge diagram of an embodiment of a horizontal jacket SPMT transportation and loading process of the present invention.

[0042] Figure 6 The present invention is a flow chart of a horizontal jacket SPMT transportation and loading process.

[0043] In the figure: 1. Horizontal jacket; 2. SPMT; 3. Barge; 4. Onboard steel plate; 5. Center of gravity. DETAILED DESCRIPTION

[0044] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention are clearly and completely described. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0045] The embodiment of the present application provides a horizontal jacket SPMT transportation and loading process, which solves the problem that the current loading method of the horizontal jacket is affected by the bearing capacity of the slideway, the slideway requires a large amount of pile foundation investment in the early stage, resulting in a large initial investment, and the tidal requirements must be considered during the loading period, which affects the loading efficiency of the horizontal jacket. By adopting the SPMT transportation method, it can be constructed at any location in the site without being affected by other projects, with low requirements for construction conditions and high adaptability; SPMT has low requirements for ground bearing capacity due to wheel pressure, and does not need to carry out pile foundation work, reducing initial infrastructure investment and reducing costs; SPMT itself has a hydraulic device that can overcome the influence of tides, which can greatly shorten the loading process and improve work efficiency.

[0046] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0047] The embodiment of the present invention discloses a horizontal jacket SPMT transportation and ship loading process.

[0048] According to the attached Figure 1 -6, including the following steps:

[0049] Step 1: Determine the carpooling plan for SPMT2. Use computer simulation to determine the parameters of the horizontal jacket 1 in the state of SPMT2 transportation, including overall strength parameters, deformation parameters and force parameters of each lifting point. The hydraulic system is divided into three groups, and each group of hydraulic systems is controlled separately to facilitate subsequent adjustments. Confirm the total weight of the equipment, the total weight of the vehicle and cargo, the maximum axis (including deadweight), the minimum axle load (including deadweight), the maximum ground pressure ratio and the horizontal jacket 1 vehicle distribution diagram. The total weight of the equipment refers to the weight of the horizontal jacket 1 itself, and the total weight of the vehicle and cargo refers to the total weight of SPMT2 and the horizontal jacket 1; the maximum axis refers to the wheelbase of SPMT2, and the minimum axle load It refers to determining the minimum load of SPMT2 on each axle, which needs to be compared with the ground bearing capacity to ensure that SPMT2 will not cause damage to the ground; the maximum ground contact pressure refers to determining the pressure of each wheel of SPMT2 on the ground, which needs to be compared with the ground bearing capacity to ensure that SPMT2 will not cause excessive pressure on the ground to prevent ground settlement or damage. The vehicle matching diagram is to clearly display the connection method, suspension point position, balance matching and other information between SPMT2 and horizontal jacket 1, which can guide the assembly, operation and transportation of SPMT2; the confirmation of the above parameters is an important basis for selecting the appropriate SPMT2 and transportation route;

[0050] Step 2: Check and debug the access road surface and survey the transportation route. Check whether the access road surface has sufficient space, whether there are sharp protrusions on the access road surface, whether the construction on the access road surface has been completed and stopped, and whether there is no object falling from the goods during the entire operation. Debug the size of the access road surface to meet the access space requirements, make sure there are no sharp protrusions on the access road surface, stop construction, no objects falling, and no hot work after the vehicle enters and when the goods come into contact with the vehicle board. Survey the transportation route, use an excavator to remove sharp protrusions on the transportation route, widen the road width of the transportation route, and use a roller to widen and level the transportation route;

[0051] Step 3: According to the SPMT2 carpooling plan, transport the assembled SPMT2 to the bottom of the corresponding horizontal jacket rack 1, pre-lift and debug the horizontal jacket rack 1, arrange the monitoring points and reference points of the horizontal jacket rack 1, configure the operating tools, confirm the entry space and the position of SPMT2 according to the car allocation diagram, configure the SPMT2 tooling according to the car allocation diagram, put SPMT2 in place, debug SPMT2 in parallel, and simultaneously lift SPMT2 until it fits the bottom surface of the horizontal jacket rack 1 transport beam, check whether the SPMT2 tooling is stressed, install pads on the unstressed SPMT2 tooling and lift it again to check whether the SPMT2 tooling is stressed, and repeat this process. The steps are as follows: until all SPMT2 tooling is stressed, fix the data connection line between the train groups, measure the height of the bottom surface of the horizontal jacket 1 transport beam from the ground and the height of the car plate and adjust them, select a certain step value in the step interval of 30-50bar, and synchronously lift the SPMT2 until one of the hydraulic groups reaches the pressure value and stops lifting, measure the height of the car plate monitoring point, the deformation of the car plate and the state of the cargo, adjust the oil pressure of other hydraulic groups to ensure the state of the car and cargo, and then select a certain step value in the step interval of 30-50bar, repeat the above steps until the cargo is completely lifted and the lifting operation is completed;

[0052] Step 4: transport the horizontal jacket 1 to the front of the wharf by SPMT2. According to the transportation route map, conduct a road survey of the driving area for transporting the jacket from the construction location to the designated location and the clearing area of ​​the horizontal jacket 1, mark the factors affecting the shipment for processing, and after the inspection and processing results are qualified, use SPMT2 to transport the horizontal jacket 1 along the marked path on the transportation route map until it is transported to the front of the wharf.

[0053] Step 5: Load the horizontal jacket 1 onto the ship and transport the SPMT 2 to the designated position of the barge 3;

[0054] Step six, the horizontal jacket rack 1 is loaded on board. After the horizontal jacket rack 1 is transported to the designated storage location, the height of the vehicle plate is lowered, and the position of the horizontal jacket rack 1 is adjusted so that the gap between the beam piers of the horizontal jacket rack 1 is between 5 and 15 mm. The cargo is gradually unloaded at a step distance of 30 to 50 bar. During the unloading process, attention is paid to the status of the vehicle, cargo and piers. When the overall pressure of the vehicle group is reduced to 50 bar, a final confirmation is made. After confirmation, the SPMT2 vehicle plate is lowered to the lowest walkable height, and finally the SPMT2 is withdrawn.

[0055] It should be noted that: in the step 1, the computer simulation of the parameters of the horizontal jacket frame 1 in the SPMT2 transportation state is to simulate and calculate the parameters of the horizontal jacket frame 1 in the SPMT2 transportation state by the finite element analysis method, establish a three-dimensional model of the horizontal jacket frame 1, set the material properties, boundary conditions and load conditions of the horizontal jacket frame 1, perform grid division and solution calculation, and obtain the overall strength parameters, deformation parameters and force parameters of each hanging point of the horizontal jacket frame 1 in the SPMT2 transportation state; specifically:

[0056] Establishing the model: First, according to the actual size and structural characteristics of the horizontal jacket 1, establish an accurate geometric model in the computer software. The geometric model should include all the key parts and details of the horizontal jacket 1, as well as the model of the SPMT2 transport equipment (CAD or other drawing software that meets the requirements can be used to establish the model);

[0057] Define material properties: define accurate material properties for each component in the above model, including physical parameters such as elastic modulus, Poisson's ratio, density, strength, etc. These parameters should be set according to the actual practical materials;

[0058] Meshing: Divide the model into a finite number of small units (i.e., finite elements). The meshing should take into account the geometric shape and force characteristics of the model to ensure the accuracy and efficiency of the analysis.

[0059] Loading and boundary conditions: Appropriate loads and boundary conditions are applied to the model according to the actual situation, including gravity loads, external loads that may be encountered during transportation, and transportation conditions of the SPMT2 transportation equipment;

[0060] Solution and analysis: Run finite element analysis software to solve the mechanical response of the model, including overall strength, deformation, and stress conditions of each hanging point;

[0061] Result post-processing: Post-process the analysis results and display them in the form of graphics or data, including the stress distribution and deformation of the overall structure and the forces at each hanging point.

[0062] Furthermore, in step two, the transport route is scanned using three-dimensional laser scanning technology to obtain three-dimensional point cloud data of the transport route, a three-dimensional model of the transport route is constructed based on the point cloud data, parameters such as the road width, slope, and turning radius of the transport route are analyzed, and the transport route is optimized.

[0063] In step 3, the SPMT 2 is transported to the bottom of the corresponding horizontal jacket 1 and pre-lifted, and the specific operation steps include the following steps:

[0064] Arrange the monitoring points and reference points of the horizontal jacket 1, configure the operating tools, and the operators need to be in place in advance before arranging the points. The operating tools include but are not limited to tape measures and walkie-talkies. The walkie-talkies are debugged to the same channel, and communication tests are performed to ensure smooth communication. Operators at various points can communicate and transmit information through walkie-talkies to ensure timely transmission of fault problems and measurement data. The tape measure can assist the operator in measuring the height of the jacket transport beam from the ground;

[0065] Confirm the vehicle entry space and the position of SPMT2 according to the vehicle configuration diagram; configure SPMT2 tooling according to the vehicle configuration diagram; move SPMT2 into position; SPMT2 parallel commissioning; SPMT2 moving into position means accurately moving SPMT2 to the bottom of the horizontal conductor frame 1 to prepare for subsequent lifting and parallel operations. The specific steps are to consider factors such as the wheelbase of SPMT2, ground bearing capacity, and road conditions to select the best route; lay wooden blocks under the conductor frame to ensure that the wheels of SPMT2 are in good contact with the ground and prevent ground settlement or damage; use the SPMT2's built-in drive system to slowly move SPMT2 to the predetermined position; use laser locators, levels and other tools to ensure that SPMT2 is accurately parked under the conductor frame and aligned with the conductor frame lifting point position; the purpose of SPMT2 parallel commissioning is to place multiple The SPMT2s are combined together to form an integrated transport platform, which improves the carrying capacity and operational flexibility; the specific steps of the parallel vehicle debugging are to connect multiple SPMT2s together using a special connecting device to form a whole; by adjusting the drive system of each SPMT2, ensure that all SPMT2s move synchronously to avoid deflection or dislocation; according to the weight of the jacket and the position of the hanging point, adjust the load distribution of each SPMT2 to ensure that all SPMT2s are evenly stressed; test the SPMT2 after parallel vehicle operation to ensure that it can move, turn and stop smoothly and meet the safety operation requirements. Through the SPMT2 car entry and SPMT2 parallel vehicle debugging, the center of gravity 4 on the horizontal jacket 1 can be placed at the center of gravity 4 position, so that the horizontal jacket 1 can remain stable during transportation and not easily shake;

[0066] Synchronously lift SPMT2 until it fits in with the bottom surface of the horizontal jacket frame 1 transport beam, check whether the SPMT2 tooling is under stress, add pads (rubber or suitable wooden boards, etc.) to the unstressed SPMT2 tooling, and then synchronously lift SPMT2 again until it fits in with the ground of the horizontal jacket frame 1 transport beam, check whether the SPMT2 tooling is under stress, if not, repeat this step until all SPMT2 tooling is under stress, so as to ensure that the SPMT2 and the horizontal jacket frame 1 fit tightly and are evenly stressed, which helps to ensure the stability of the transportation process; fix the data connection line between the train sets, measure the height of the bottom surface of the horizontal jacket frame 1 transport beam from the ground and the height of the car plate and adjust them; the operator checks the status of the car and the cargo, and starts the lifting operation when everything is in place, with a value range of 30-50ba In the step interval of r, select a certain step value, and synchronously lift SPMT2 until one of the hydraulic groups (referring to the hydraulic system of the three-point group on SPMT2) reaches the pressure value, then stop lifting, measure the height of the vehicle plate monitoring point, the deformation of the vehicle plate and the status of the cargo, adjust the oil pressure of other hydraulic groups to ensure the status of the vehicle and cargo; then select a certain step value, repeat the above steps until the cargo is completely lifted, adjust the vehicle plate height, check the status of the cargo, and complete the lifting operation; during this process, use a total station to arrange the monitoring points and reference points of the horizontal jacket 1, monitor the displacement and deformation of the horizontal jacket 1 in real time during the lifting process, transmit the monitoring data to the control center through wireless transmission technology, and dynamically adjust the lifting height and speed of SPMT2 according to the monitoring data.

[0067] In step 4, after the lifting work of the horizontal jacket frame 1 is completed, the horizontal jacket frame 1 is transported to the front of the wharf according to the transportation route map, and waits for the right time for roll-on / roll-off. Before transportation, it is necessary to conduct a road survey of the driving area where the jacket frame is transported from the construction position to the designated position and the clearing area of ​​the horizontal jacket frame 1 according to the transportation route map, and mark the factors affecting the shipment for processing. The factors affecting the shipment in the SPMT2 driving area and the clearing area of ​​the horizontal jacket frame 1 include but are not limited to obstacles, potholes on the ground, sharp protrusions and insufficient bearing capacity. After the inspection and processing results are qualified, the SPMT2 transports the horizontal jacket frame 1 along the marked path on the transportation route map until it is transported to the front of the wharf. In this process, the transportation position of the SPMT2 can be tracked in real time using GPS positioning technology, and the positioning data can be transmitted to the control center through wireless transmission technology. The transportation path and speed of the SPMT2 are dynamically adjusted according to the positioning data to ensure that the horizontal jacket frame 1 is transported to the front of the wharf according to the predetermined path and speed.

[0068] In step five, a boarding steel plate 4 is provided at the rear end of the barge 3, and the boarding steel plate 4 is used for connection between the dock and the port of the barge 3, so as to achieve an auxiliary support effect on the loading of the horizontal jacket 1; in addition, the transportation position of the SPMT is accurately positioned using laser navigation technology, and the position and posture information of the SPMT relative to the barge is obtained in real time through the laser navigation sensor, and the transportation path and speed of the SPMT are dynamically adjusted according to the position and posture information, so as to ensure that the horizontal jacket is accurately transported to the designated position of the barge.

[0069] The construction steps of the SPMT2 transportation and loading process of the horizontal jacket 1 provided in this embodiment can solve the problem that the current loading method of the horizontal jacket 1 is affected by the bearing capacity of the slideway, a large amount of pile foundation investment is required for the early slideway, resulting in a large initial investment, and the tidal requirements must be considered during the loading period, which affects the loading efficiency of the horizontal jacket 1. By adopting the SPMT2 transportation method, it can be constructed at any location in the site without being affected by other projects, with low requirements for construction conditions and high adaptability; SPMT2 has low requirements for ground bearing capacity due to wheel pressure, and does not need to carry out pile foundation work, which reduces initial infrastructure investment and reduces costs; SPMT2 itself has a hydraulic device that can overcome the influence of tides, which can greatly shorten the loading process and improve work efficiency.

[0070] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. A horizontal jacket SPMT transportation and loading process, It is characterized in that The following steps are involved: Step 1: Determine the SPMT carpooling plan. Through computer simulation of the strength parameters, deformation parameters and force parameters of each lifting point of the horizontal jacket in the SPMT transportation state, and under the premise of the hydraulic system adopting three-point grouping, confirm the total weight of the equipment, the total weight of the vehicle and cargo, the maximum axis, the minimum axle load, the maximum ground pressure ratio and the horizontal jacket carpooling diagram; Step 2: Check and debug the access road surface and survey the transportation route to obtain a transportation route map that meets the requirements of SPMT transportation of horizontal jackets; Step 3: According to the SPMT carpooling plan obtained in step 1, the assembled SPMT is transported to the bottom of the corresponding horizontal jacket, and the horizontal jacket is pre-lifted and debugged so that the cargo is fully lifted; Step 4: transport the horizontal jacket to the front of the wharf by SPMT according to the transportation route map obtained in step 2; Step 5: Load the horizontal jacket onto the ship and transport the SPMT to the designated location on the barge; Step six, loading the horizontal jacket. After the SPMT is adjusted to the designated position of the barge in step five, lower the height of the vehicle plate, adjust the position of the horizontal jacket so that the gap between the horizontal jacket beam piers is between 5-15mm, and gradually unload it at a step distance of 30-50bar. During the unloading process, pay attention to the status of the vehicle, cargo and piers. When the overall pressure of the vehicle group is reduced to 50bar, make a final confirmation. After confirmation, lower the SPMT vehicle plate to the lowest walkable height, and finally withdraw the SPMT.

2. A horizontal jacket SPMT transportation and loading process according to claim 1, It is characterized in that In the step one, the finite element analysis method is used to simulate and calculate the parameters of the horizontal jacket under the SPMT transportation state, a three-dimensional model of the horizontal jacket is established, the material properties, boundary conditions and load conditions of the horizontal jacket are set, and meshing and solution calculations are performed to obtain the overall strength parameters, deformation parameters and force parameters of each hanging point of the horizontal jacket under the SPMT transportation state.

3. A horizontal jacket SPMT transportation and loading process according to claim 2, It is characterized in that In step 2, the inspection of the road surface for the vehicle, commissioning and survey of the transportation route are specifically as follows: Check whether there is enough space on the approach road, whether there are any sharp protrusions on the approach road, whether all construction on the approach road has been completed and stopped, and whether no objects have fallen during the entire operation; Adjust the size of the access road space to meet the requirements of the access space, ensure that there are no sharp protrusions on the access road, stop construction, no objects fall, and no hot work after the vehicle enters and when the goods come into contact with the vehicle board; Survey the transportation route and eliminate the unfavorable factors that may affect the transportation of SPMT horizontal jackets.

4. A horizontal jacket SPMT transportation and loading process according to claim 3, It is characterized in that In step 2, the transport route is scanned using 3D laser scanning technology to obtain 3D point cloud data of the transport route, a 3D model of the transport route is constructed based on the point cloud data, the road width, slope and turning radius parameters of the transport route are analyzed, and the transport route is optimized.

5. A horizontal jacket SPMT transportation and loading process according to claim 4, It is characterized in that In step 3, the SPMT is transported to the bottom of the corresponding horizontal jacket for pre-lifting and debugging, and the specific operation steps include the following steps: Arrange monitoring points and reference points of horizontal jackets and configure operating tools; Confirm the vehicle entry space and the SPMT placement location according to the vehicle allocation diagram; Equip SPMT tooling according to vehicle configuration drawing; SPMT enters the vehicle and takes position; SPMT vehicle parallel debugging; Synchronously lift the SPMT until it fits the bottom surface of the horizontal jacket transport beam, check whether the SPMT tooling is stressed, add pads to the unstressed SPMT tooling and lift it again to check whether the SPMT tooling is stressed, repeat this step until all SPMT tooling is stressed; Fix the data connection line between the train sets, measure the height of the bottom surface of the horizontal jacket transport beam from the ground and the height of the car plate and make adjustments; Select a certain step value in the range of 30-50bar, lift the SPMT synchronously until one of the hydraulic groups reaches the pressure value, stop lifting, measure the height of the vehicle plate monitoring point, the deformation of the vehicle plate and the status of the cargo, adjust the oil pressure of other hydraulic groups to ensure the status of the vehicle and cargo Then select a certain step value in the step distance range of 30-50bar, and repeat the above steps until the cargo is completely lifted and the lifting operation is completed.

6. A horizontal jacket SPMT transportation and loading process according to claim 5, It is characterized in that In step three, a total station is used to arrange monitoring points and reference points of the horizontal jacket, and the displacement and deformation of the horizontal jacket during the jacking process are monitored in real time. The monitoring data is transmitted to the control center through wireless transmission technology, and the jacking height and speed of the SPMT are dynamically adjusted according to the monitoring data.

7. A horizontal jacket SPMT transportation and loading process according to claim 6, It is characterized in that In the step 4, the horizontal jacket is transported to the front position of the wharf by the SPMT as follows: according to the transportation route map, a road survey is conducted on the driving area for transporting the jacket from the construction position to the designated position and the clearing area of ​​the horizontal jacket, and the factors affecting the shipment are marked for processing. After the inspection and processing results are qualified, the SPMT is used to transport the horizontal jacket along the marked path on the transportation route map until it is transported to the front position of the wharf.

8. A horizontal jacket SPMT transportation and loading process according to claim 7, It is characterized in that In step 4, the transport position of the SPMT is tracked in real time using GPS positioning technology, and the positioning data is transmitted to the control center via wireless transmission technology. The transport path and speed of the SPMT are dynamically adjusted according to the positioning data to ensure that the horizontal jacket is transported to the front position of the wharf according to the predetermined path and speed.

9. A horizontal jacket SPMT transportation and loading process according to claim 8, It is characterized in that Factors that affect shipment in the SPMT driving area and the horizontal jacket sweeping area include but are not limited to obstacles, ground potholes, sharp protrusions, and insufficient bearing capacity.

10. A horizontal jacket SPMT transportation and loading process according to claim 9, It is characterized in that In step five, laser navigation technology is used to accurately locate the transportation position of the SPMT, and the position and posture information of the SPMT relative to the barge is obtained in real time through the laser navigation sensor. The transportation path and speed of the SPMT are dynamically adjusted according to the position and posture information to ensure that the horizontal jacket is accurately transported to the designated position of the barge.

Citation Information

Patent Citations

  • Construction method for split type jacket foundation of deep sea converter station

    CN112726548A

  • Jacket platform installation device, installation method and installation ship

    CN115704208A

  • Jacket design scheme capable of adopting non-slideway construction and SPMT trolley shipment

    CN116446363A

  • Fastening tool for marine transportation of upper module of marine booster station

    CN217436017U

  • Equipment and method for sharing railway cars lower chassis with upper chassis or cabins

    US20200317232A1