Tunnel lining concrete hydration heat cooling system and control method thereof

The tunnel lining concrete hydration heat cooling system addresses high hydration heat issues by using temperature sensors and controlled water supply to outer and inner sides, effectively reducing temperature differences and preventing cracks in mass concrete structures.

CN119080530APending Publication Date: 2024-12-06SINOHYDRO BUREAU 5
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411065814.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

Existing tunnel construction methods fail to effectively control high hydration heat in mass concrete structures, leading to significant temperature differences and potential temperature cracks in secondary lining concrete.

Method used

A tunnel lining concrete hydration heat cooling system comprising outer and inner temperature control devices with water inlet and outlet pipes, branch pipes, and temperature sensors to monitor and regulate temperature differences, using selective water supply to the outer or inner sides based on temperature sensor readings.

Benefits of technology

The system effectively reduces temperature differences within the concrete, inhibiting or reducing temperature cracks by targeted water cooling, enhancing cooling efficiency and reducing energy consumption.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119080530A_ABST
    Figure CN119080530A_ABST
Patent Text Reader

Abstract

The invention provides a tunnel lining concrete hydration heat cooling system and a control method thereof. The tunnel lining concrete hydration heat cooling system comprises an outer side temperature control device, an inner side temperature control device and a temperature sensor set. The outer side temperature control device is arranged on the outer side of the secondary lining formwork and comprises an outer side water inlet pipe and a plurality of outer side branch pipes. The outer side water inlet pipe is arranged along the edge of one opening end of the secondary lining template; one end of each outer side branch pipe is connected to the outer side water inlet pipe, and the other end of each outer side branch pipe is located on the edge of the other opening end of the secondary lining formwork. The inner side temperature control device is arranged on the inner side of the secondary lining formwork and comprises an inner side water inlet pipe and a plurality of inner side branch pipes. The structure is the same as that of the outside temperature control device; and the temperature sensor group comprises a first temperature sensor and a second temperature sensor which are arranged on the outer side and the inner side of the same position on the secondary lining template. According to the technical scheme, water cooling can be carried out through the pipeline system, the temperature difference inside and outside the concrete is reduced, the temperature of high hydration heat is controlled, and temperature cracks are inhibited or reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of tunnel construction, and in particular to a tunnel lining concrete hydration heat cooling system and a control method thereof. Background Art

[0002] As underground railway lines continue to expand, the cross-sectional area of ​​subway stations is gradually increasing to meet construction capacity requirements. Correspondingly, the thickness of the secondary lining of the tunnel also needs to be increased to meet the structural safety requirements. When the thickness of the secondary lining is greater than 1m, it belongs to mass concrete. When a mass concrete structure is poured, the heat generated by the high hydration heat inside the concrete is difficult to dissipate in time, resulting in an increase in the temperature difference between the inside and outside of the concrete, which is easy to generate large tensile stress on the concrete surface, causing temperature cracks in the concrete structure and affecting the quality of the concrete structure.

[0003] In the prior art, there is still a lack of effective devices or methods that can control the high hydration heat of any part of the secondary lining in large-volume tunnel lining concrete, reduce the temperature difference between the inside and outside of the concrete, and inhibit or reduce the generation of temperature cracks. Summary of the invention

[0004] In order to solve the above-mentioned technical problems existing in the prior art, the technical purpose of the present invention is to realize the temperature monitoring and regulation of the high hydration heat of any part of the secondary lining in the large-volume tunnel lining concrete, so as to suppress or reduce the occurrence of temperature cracks by reducing the temperature difference between the inside and outside of the concrete.

[0005] In order to achieve the above technical objectives, in a first aspect, the present invention provides a tunnel lining concrete hydration heat cooling system, which specifically includes an outer temperature control device, an inner temperature control device and a temperature sensor group;

[0006] The outer temperature control device is arranged on the outer side of the secondary lining formwork, and includes an outer water inlet pipe and a plurality of outer branch pipes; the outer water inlet pipe is arranged along the edge of an open end of the secondary lining formwork; one end of each outer branch pipe is connected to the outer water inlet pipe, and the other end is located at the edge of the other open end of the secondary lining formwork;

[0007] The inner temperature control device is arranged inside the secondary lining formwork, and includes an inner water inlet pipe and a plurality of inner branch pipes; its structure is the same as that of the outer temperature control device;

[0008] The temperature sensor group comprises: a first temperature sensor and a second temperature sensor which are arranged on the outside and inside of the same position on the secondary lining formwork.

[0009] Furthermore, there are multiple groups of temperature sensors, which are evenly distributed on the secondary lining formwork.

[0010] Furthermore, a plurality of outer cooling pipes are provided between adjacent outer branch pipes.

[0011] Preferably, the outer cooling tube is an S-shaped tube.

[0012] In a second aspect, the present invention provides a method for controlling the hydration heat cooling state of tunnel lining concrete, specifically comprising collecting a temperature t1 collected by a first temperature sensor and a temperature t2 collected by a second temperature sensor;

[0013] If t1-t2≥Δt, water is supplied to the outer water inlet pipe;

[0014] If t2-t1≥Δt, water is supplied to the inner water inlet pipe;

[0015] Wherein, Δt is the preset temperature difference.

[0016] Furthermore, there are multiple groups of temperature sensors, which are evenly distributed on the secondary lining formwork;

[0017] The control method also includes:

[0018] Acquire the temperature collected by the first temperature sensor and the second temperature sensor in each temperature sensor group;

[0019] For any temperature sensor group,

[0020] If t1-t2≥Δt, water is supplied to the outer water inlet pipe;

[0021] If t2-t1≥Δt, water is supplied to the inner water inlet pipe.

[0022] Furthermore, each of the water inlet and water outlet of the outer branch pipe and the inner branch pipe is provided with a second valve;

[0023] The control method also includes:

[0024] If t1-t2≥Δt, open the second valve on the outer branch pipe at the corresponding position;

[0025] If t2-t1≥Δt, open the second valve on the inner branch pipe at the corresponding position.

[0026] Furthermore, a plurality of outer cooling pipes are provided between adjacent outer branch pipes, and a third valve is provided on each outer cooling pipe;

[0027] If t1-t2≥Δt, open the third valve on the outer cooling pipe at the corresponding position;

[0028] If t2-t1≥Δt, open the third valve on the inner cooling pipe at the corresponding position.

[0029] In a third aspect, the present invention provides another method for controlling the hydration heat temperature of tunnel lining concrete, which specifically includes:

[0030] A second valve is provided at the water inlet and outlet of each outer branch pipe and inner branch pipe;

[0031] A plurality of outer cooling pipes are arranged between adjacent outer branch pipes, and a third valve is arranged on each outer cooling pipe;

[0032] There are multiple groups of temperature sensors, which are evenly distributed on the secondary lining formwork; each temperature sensor group also includes an attachment rod; the attachment rod is vertically penetrated through the secondary lining formwork, and the first temperature sensor and the second temperature sensor are respectively attached to the two ends of the attachment rod; the middle section of the attachment rod is also provided with a third temperature sensor;

[0033] Calculate the average temperature of the inner, middle and outer sides within the preset area of ​​the secondary lining template

[0034]

[0035] Where, t Zi ,t Ni ,t Wi are the temperature values ​​of the inner side, the middle side and the outer side collected by the temperature sensor on the i-th attachment rod in the preset area of ​​the secondary lining formwork, respectively, and m is the number of attachment rods in the preset area;

[0036] Calculate the temperature difference per unit length Δt′ in the thickness direction of the preset area Z And the temperature difference per unit length of the outside Δt′ W ,

[0037]

[0038]

[0039] Where l is the spacing between the three temperature sensors.

[0040] Introduce the fitting proportional coefficient k to obtain the temperature difference change value kρt′ per unit volume in the thickness direction of the preset area Z And the temperature difference per unit volume outside kρt′ W ;

[0041] Calculate the theoretical value of temperature change T1 in the thickness direction of the secondary lining formwork and the theoretical value of temperature T2 in the middle of the secondary lining formwork.

[0042]

[0043] Where, W is the cement consumption per unit volume of the secondary lining formwork, Q is the total hydration heat of cement per unit mass, C is the specific heat capacity of concrete, ρ is the density of concrete, V is the volume of concrete detected by each temperature sensor, u and n are the thickness constant coefficients of concrete, d is the unit thickness of the secondary lining formwork, y is the solidification time of concrete, and D is the thickness of the secondary lining formwork;

[0044] like Then all the second valves and third valves corresponding to the preset area are opened and water is supplied;

[0045] like And kΔt′ Z -T≤T1, kΔt′ W -T>T1, then open the second valve and the third valve on the outer temperature control device corresponding to the preset area and supply water;

[0046] like And kρt′ Z -T>T1, kΔt′ W -T≤T1, then open the second valve and the third valve on the inner temperature control device corresponding to the preset area and supply water;

[0047] like And kΔt′ Z -T>T1,kΔt′ W -T>T1, the second valve and the third valve corresponding to the preset area are opened and water is supplied.

[0048] The technical solution provided by the present invention can monitor the temperature difference between the inside and outside of the secondary lining formwork in real time according to the temperature sensor, and selectively perform water cooling on the side with higher temperature through the pipeline system to reduce the temperature difference between the inside and outside of the concrete, achieve temperature control of high hydration heat, and inhibit or reduce the occurrence of temperature cracks. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] Figure 1 Schematic diagram of the overall structure of a hydration heat cooling device in one embodiment of the present invention.

[0050] Figure 2 It is a schematic structural diagram of the water inlet side of the hydration heat cooling device in one embodiment of the present invention.

[0051] Figure 3 Schematic diagram of the distribution of attachment rods in a secondary lining module in one embodiment of the present invention.

[0052] The symbols in the figure indicate: secondary lining formwork -1, temperature sensor group -2, temperature sensor -3, attachment rod -4, outer branch pipe -5, outer water inlet pipe -6, outer water outlet pipe -7, outer cooling pipe -8, inner water inlet pipe -9, first valve -10, main water inlet pipe -11, main water outlet pipe -12, second valve -13. DETAILED DESCRIPTION

[0053] The technical solution provided by the present invention will be further explained in detail below in combination with embodiments and drawings.

[0054] Example 1

[0055] like Figure 1 , Figure 2 As shown, this embodiment provides a tunnel lining concrete hydration heat cooling system, including an outer temperature control device, an inner temperature control device, a main water inlet pipe 11, a main water outlet pipe 12, a water supply device and multiple temperature sensor groups.

[0056] The outer temperature control device is arranged outside the secondary lining formwork 1, and includes an outer water inlet pipe 6, an outer branch pipe 5 and an outer water outlet pipe 7; the outer water inlet pipe 6 is arranged along the edge of an open end of the secondary lining formwork 1; a plurality of outer branch pipes 5 supply water, one end of each outer branch pipe 5 is connected to the outer water inlet pipe 6, and the other end is connected to the outer water outlet pipe 7; the outer water outlet pipe 7 is arranged along the edge of the other open end of the secondary lining formwork 1. Among them, the water inlet of the outer water inlet pipe 6 and the water outlet of the outer water outlet pipe 7 are both provided with a first valve 10.

[0057] In some simple cases, one or more of the main water inlet pipe, the main water outlet pipe, the external water outlet pipe and the first valve may not be provided.

[0058] The inner temperature control device is arranged inside the secondary lining formwork 1, and includes an inner water inlet pipe 9, an inner branch pipe and an inner water outlet pipe, and its structure is the same as that of the outer temperature control device. It should be noted that in the subsequent optional schemes, all the components or structures of the outer temperature control device are also possessed by the inner temperature control device. In other words, except for the different positions, the structure of the outer temperature control device is exactly the same as that of the inner temperature control device.

[0059] The outer water inlet pipe 6 and the inner water inlet pipe 9 are both connected to the water supply device via the main water inlet pipe 11; the outer water outlet pipe 7 and the inner water outlet pipe are both connected to the water supply device via the main water outlet pipe 12.

[0060] like Figure 3 As shown, a plurality of temperature sensor groups 2 are evenly distributed, and each temperature sensor group 2 includes: at the same position, a first temperature sensor is arranged on the outside of the secondary lining formwork 1 , and a second temperature sensor is arranged on the inside of the secondary lining formwork 1 .

[0061] In some simple cases, the temperature sensor group 2 is set to one, and the staff can set it at the position where the hydration heat effect is most obvious based on experience.

[0062] Furthermore, the water inlet and the water outlet of each outer branch pipe 5 are provided with a second valve 13. As mentioned above, the water inlet and the water outlet of each inner branch pipe are also provided with a second valve 13.

[0063] Further, a plurality of outer cooling pipes 8 are provided between adjacent outer branch pipes 5. Correspondingly, a plurality of inner cooling pipes are provided between adjacent inner branch pipes. Optionally, the plurality of outer cooling pipes 8 are equidistantly distributed, and the plurality of inner cooling pipes are equidistantly distributed.

[0064] Optionally, the outer cooling pipe 8 and the inner cooling pipe are S-shaped pipes to increase the contact area between the cooling pipe and the concrete and slow down the flow rate of the water flow, so that the heat absorbed by the water flow is increased and the cooling effect is improved.

[0065] Further, if Figure 1 As shown, in a preselected area, there are four evenly distributed temperature detection points A, B, C, and D, each of which is provided with a temperature sensor group 2. The temperature sensor group 2 also includes an attachment rod 4 and three temperature sensors 3; the attachment rod 4 is vertically penetrated through the secondary lining formwork 1, and the first temperature sensor (i.e., W) and the second temperature sensor (i.e., N) are respectively attached to the two ends of the attachment rod 4; the middle section of the attachment rod 4 is also provided with a third temperature sensor (i.e., Z).

[0066] In addition, in conjunction with the above cooling device, this embodiment also provides a control method, which specifically includes:

[0067] Acquire the temperature collected by the first temperature sensor and the second temperature sensor in each temperature sensor group 2;

[0068] For any temperature sensor group 2,

[0069] If t1-t2≥Δt, the first valve 10 and the water supply device of the outer water inlet pipe 6 are opened to supply water for cooling;

[0070] If t2-t1≥Δt, the first valve 10 of the inner water inlet pipe 9 and the water supply device are opened to supply water for cooling;

[0071] Wherein, t1 is the temperature collected by the first temperature sensor, t2 is the temperature collected by the second temperature sensor, and Δt is the preset temperature difference.

[0072] Among them, the initial state of closing all first valves 10 and the water supply device is the closed state;

[0073] Under this method, as long as the temperature difference detected by one temperature sensor group reaches the preset range, comprehensive cooling is started, and the high-temperature side (outside or inside) of the secondary lining formwork 1 is cooled as a whole by flowing water.

[0074] In some optional solutions, before the cooling device is turned on, all the second valves 13 are in a closed state. After the cooling device is turned on, the temperature of the inner side and the outer side of the secondary lining formwork 1 is fully monitored.

[0075] For any temperature sensor group 2,

[0076] If t1-t2≥Δt, open the second valve 13 on the outer branch pipe at the corresponding position;

[0077] If t2-t1≥Δt, the second valve 13 on the inner branch pipe at the corresponding position is opened.

[0078] The setting and switch control of the second valve 13 can make the water supply and cooling more targeted. According to the location of the specific temperature sensor group that detects the abnormal temperature, water can be supplied separately to the corresponding outer branch pipe and inner branch pipe to reduce the consumption of invalid power and improve the cooling efficiency.

[0079] Further, in some alternatives,

[0080] If t1-t2≥Δt, open the third valve on the outer cooling pipe 8 at the corresponding position;

[0081] If t2-t1≥Δt, open the third valve on the inner cooling pipe at the corresponding position.

[0082] Among them, the initial states of all third valves are closed states.

[0083] This embodiment also provides a second control method for the cooling device, which specifically includes:

[0084] like Figure 1 As shown, in a preselected area, there are four evenly distributed temperature detection points A, B, C, and D, each of which is provided with a temperature sensor group 2.

[0085] In the preset area of ​​the secondary lining template 1, calculate the average temperature of the inner, middle and outer sides

[0086]

[0087] Where, t Zi ,t Ni ,t Wiare the temperature values ​​of the inside, middle and outside collected by the temperature sensor on the i-th attachment rod 4 in the preset area of ​​the secondary lining formwork 1, that is, the temperatures detected by the three temperature sensors N, Z and W respectively; m is the number of attachment rods 4 in the preset area. Calculate the inner temperature difference Δt in the thickness direction of the preset area Z , outside temperature difference Δt W , the temperature difference change per unit length of the inner side Δt′ Z And the temperature difference per unit length of the outside Δt′ W ,

[0088]

[0089] Where l is the spacing between the three temperature sensors.

[0090] The temperature difference per unit length of the inner side is Δt′ Z And the temperature difference per unit length of the outside Δt′ W Introduce the fitting proportional coefficient k to obtain the temperature difference change value kΔt′ per unit volume in the thickness direction of the preset area Z And the temperature difference per unit volume outside kΔt′ W .

[0091] Calculate the theoretical value of temperature change T1 in the thickness direction of the secondary lining formwork 1 and the theoretical value of temperature T2 in the middle of the secondary lining formwork.

[0092]

[0093] Wherein, W is the cement consumption per unit volume of the secondary lining formwork 1, Q is the total hydration heat of cement per unit mass, C is the specific heat capacity of concrete, ρ is the density of concrete, V is the volume of concrete detected by each temperature sensor, u and n are the thickness constant coefficients of concrete, d is the unit thickness of the secondary lining formwork 1, y is the solidification time of concrete, and D is the thickness of the secondary lining formwork 1.

[0094] Open the first valve 10 on the main water inlet pipe 11 and the main water outlet pipe 12.

[0095] Calculate the temperature difference per unit volume inside kΔt′ Z And the temperature difference per unit volume outside kΔt′ W The difference v from the theoretical value of temperature change T Z and v W ,

[0096] v Z = kΔt′ Z -T

[0097] v W = kΔt′ W -T;

[0098] like Then the second valve 13 and the third valve corresponding to the preset area are opened, and water is supplied through the water supply device for cooling;

[0099] like And kΔt′ Z -T≤T1, kΔt′ W -T>T1, then open the second valve 13 and the third valve on the outer temperature control device corresponding to the preset area, and supply water through the water supply device to cool down;

[0100] like And kΔt′ Z -T>T1,kΔt′ W -T≤T1, then open the second valve and the third valve on the inner temperature control device corresponding to the preset area, and supply water through the water supply device to cool down;

[0101] like And kΔt′ Z -T>T1,kΔt′ W -T>T1, then open the second valve 13 and the third valve corresponding to the preset area, and supply water through the water supply device to cool down

[0102] Among them, the initial states of all the first valves, the second valves and the third valves are closed states.

[0103] Optionally, all the first valves, the second valves and the third valves are electrically controlled valves and are connected to a controller, which is connected to each temperature sensor and is provided with an application program that can implement the above method.

[0104] Optionally, the controller is further connected to a memory, which is used to store historical temperature information detected by each temperature sensor and historical operation information executed by the controller.

[0105] The technical solution provided by the present invention can monitor the temperature difference between the inside and outside of the secondary lining formwork in real time according to the temperature sensor, and selectively perform water cooling on the side with higher temperature through the pipeline system to reduce the temperature difference between the inside and outside of the concrete, achieve temperature control of high hydration heat, and inhibit or reduce the occurrence of temperature cracks.

[0106] Furthermore, on the basis of achieving the above-mentioned beneficial effects, the above preferred scheme also achieves the following beneficial effects: the second valve, the outer cooling pipe, the inner cooling pipe and the third valve are provided to achieve precise cooling of the temperature abnormal area, improve the cooling efficiency, and reduce the cooling energy consumption; the S-shaped cooling pipe can increase the contact area between the cooling pipe and the concrete, slow down the water flow rate, absorb more hydration heat, and improve the cooling effect; the third temperature sensor is provided in the secondary lining formwork through the attachment rod, and the control method of the cooling device is based on calculating the average temperature in the preset area, which are conducive to improving the accuracy of temperature difference detection, and can further inhibit or reduce the occurrence of temperature cracks; the electric control valve and the controller can realize the automatic regulation of the hydration heat of the lining concrete; the memory can provide data support for adjusting and optimizing the control method of the cooling device.

Claims

1. A tunnel lining concrete hydration heat cooling system, characterized in that: It includes an outer temperature control device, an inner temperature control device and a temperature sensor group (2); The outer temperature control device is arranged outside the secondary lining formwork (1), and comprises an outer water inlet pipe (6) and a plurality of outer branch pipes (5); the outer water inlet pipe (6) is arranged along the edge of an open end of the secondary lining formwork (1); one end of each outer branch pipe (5) is connected to the outer water inlet pipe (6), and the other end is located at the edge of the other open end of the secondary lining formwork (1); The inner temperature control device is arranged inside the secondary lining formwork (1), and comprises an inner water inlet pipe (9) and a plurality of inner branch pipes; its structure is the same as that of the outer temperature control device; The temperature sensor group (2) comprises a first temperature sensor and a second temperature sensor which are arranged on the outside and inside of the same position on the secondary lining formwork (1).

2. A tunnel lining concrete hydration heat cooling system as claimed in claim 1, characterized in that: There are multiple groups of temperature sensor groups (2), which are evenly distributed on the secondary lining formwork (1).

3. A tunnel lining concrete hydration heat cooling system as claimed in claim 1, characterized in that: A plurality of outer cooling pipes (8) are arranged between adjacent outer branch pipes (5).

4. A tunnel lining concrete hydration heat cooling system as claimed in claim 3, characterized in that: The outer cooling pipe (8) is an S-shaped pipe.

5. A control method for a cooling system as claimed in claim 1, characterized in that: Collecting the temperature t1 collected by the first temperature sensor and the temperature t2 collected by the second temperature sensor; If t1-t2≥Δt, water is supplied to the outer water inlet pipe; If t2-t1≥Δt, water is supplied to the inner water inlet pipe; Wherein, Δt is the preset temperature difference.

6. The control method of the cooling system according to claim 5, characterized in that: There are multiple groups of temperature sensors (2) which are evenly distributed on the secondary lining formwork (1); The control method further comprises: Acquire the temperature collected by the first temperature sensor and the second temperature sensor in each temperature sensor group; For any temperature sensor group, If t1-t2≥Δt, water is supplied to the outer water inlet pipe; If t2-t1≥Δt, water is supplied to the inner water inlet pipe.

7. The control method according to claim 6, characterized in that: The cooling system further comprises: a second valve (13) is provided at the water inlet and the water outlet of each outer branch pipe (5) and the inner branch pipe; The control method further comprises: If t1-t2≥Δt, open the second valve on the outer branch pipe at the corresponding position; If t2-t1≥Δt, open the second valve on the inner branch pipe at the corresponding position.

8. The control method according to claim 7, characterized in that: The cooling system further comprises: a plurality of outer cooling pipes (8) are arranged between adjacent outer branch pipes (5), and each outer cooling pipe is provided with a third valve; The control method further comprises: If t1-t2≥Δt, open the third valve on the outer cooling pipe at the corresponding position; If t2-t1≥Δt, open the third valve on the inner cooling pipe at the corresponding position.

9. A control method for a cooling system as claimed in claim 1, characterized in that: The cooling system also includes: A second valve (13) is provided at the water inlet and the water outlet of each outer branch pipe (5) and the inner branch pipe; A plurality of outer cooling pipes (8) are provided between adjacent outer branch pipes (5), and each outer cooling pipe (8) is provided with a third valve; There are multiple groups of temperature sensor groups (2) which are evenly distributed on the secondary lining formwork (1); each temperature sensor group (2) also includes an attachment rod (4); the attachment rod (4) is vertically penetrated through the secondary lining formwork (1), and a first temperature sensor and a second temperature sensor are respectively attached to two ends of the attachment rod (4); a third temperature sensor is also provided in the middle section of the attachment rod (4); The control method comprises: Calculate the average temperature of the inner, middle and outer sides within the preset area of ​​the secondary lining template Where, t Zi ,t Ni ,t Wi are the temperature values ​​of the inner side, the middle side and the outer side collected by the temperature sensor on the i-th attachment rod in the preset area of ​​the secondary lining formwork, respectively, and m is the number of attachment rods in the preset area; Calculate the temperature difference per unit length Δt′ in the thickness direction of the preset area Z And the temperature difference per unit length of the outside Δt′ W , Where l is the spacing between the three temperature sensors. Introduce the fitting proportional coefficient k to obtain the temperature difference change value kΔt′ per unit volume in the thickness direction of the preset area Z And the temperature difference per unit volume outside kΔt′ W ; Calculate the theoretical value of temperature change T1 in the thickness direction of the secondary lining formwork and the theoretical value of temperature T2 in the middle of the secondary lining formwork. Where W is the cement mass per unit volume of the secondary lining formwork, Q is the total hydration heat of cement per unit mass, C is the specific heat of concrete, ρ is the density of concrete, V is the volume of concrete detected by each temperature sensor, u and n are the thickness constant coefficients of concrete, d is the unit thickness of the secondary lining formwork, y is the solidification time of concrete, and D is the thickness of the secondary lining formwork; like Then all the second valves and third valves corresponding to the preset area are opened and water is supplied; like And kΔt′ Z -T≤T1, kΔt′ W -T>T1, then open the second valve and the third valve on the outer temperature control device corresponding to the preset area and supply water; like And kΔt′ Z -T>T1,kΔt′ W -T≤T1, then open the second valve and the third valve on the inner temperature control device corresponding to the preset area and supply water; like And kΔt′ Z -T>T1,kΔt′ W -T>T1, the second valve and the third valve corresponding to the preset area are opened and water is supplied.

Citation Information

Patent Citations

  • Tunnel secondary lining early warning cooling device

    CN209277908U

  • Four-season skiing tunnel heat preservation supporting structure

    CN212614772U

  • Curing method for lining concrete for tunnel, molded by using travelling form

    JP2007231518A

  • Lining concrete curing device and lining concrete curing system

    JP2012087481A