Basement bottom plate sump construction method capable of preventing sand gushing and water seepage

By using fast condensation slurry to cure and optimize the construction process during construction, the problems of water seepage and sand pouring on the basement water collection pit bottom plate are solved, and the construction quality and service life are improved.

CN119083472APending Publication Date: 2024-12-06THE SECOND CONSTRUCTION ENGINEERING CO LTD CCSEB
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411472807.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-22
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The prior art is difficult to effectively prevent water seepage and sand surge in the basement water collection pit floor during construction, resulting in poor construction quality and short service life.

Method used

The foundation pit soil is cured by fast condensation slurry, set up elevation control piles and pour cushion concrete, carry out waterproofing and protective layer construction, combine steel bar binding, formwork support and layered concrete pouring, optimize the construction process to reduce leakage and surge sand.

Benefits of technology

Effectively reduce leakage and sand surge during construction, and improve the efficiency and durability of basement floor water collecting pits.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention provides a construction method of a basement bottom plate sump capable of preventing sand gushing and water seepage, which comprises the following steps: S1, earth excavation: excavating a foundation pit with a specified size according to construction requirements; s2, base grouting is conducted, specifically, rapid-hardening grout is adopted for grouting, and the soil body on the periphery of the foundation pit is subjected to curing treatment; s3, cushion layer construction is conducted, specifically, after elevation control piles are arranged, cushion layer concrete is poured on the foundation pit, and after vibration, strickling and press polishing are conducted; s4, waterproof construction is conducted, specifically, waterproof construction is conducted on the cushion layer and comprises the steps of pulping, brushing, inspection and maintenance; s5, construction of a protective layer: constructing the protective layer and an isolating layer on the basis of waterproof construction; s6, reinforcing steel bar binding, wherein supporting reinforcing steel bars are bound on the foundation pit; s7, a formwork is erected, and a pit side formwork is erected; and S8, concrete pouring is conducted, layered pouring is conducted, pouring is conducted while vibrating is conducted, and a final complete sump structure is formed. By means of the method, leakage and sand gushing in the construction process can be reduced, and the use efficiency and durability of the basement bottom plate foundation pit water pit can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a construction method of a basement bottom sump for preventing sand gushing and water seepage. Background Art

[0002] Most modern urban buildings have basements. There are many factors that affect the change of groundwater level, and it is difficult to accurately provide the micro-pressure water level for the basement sump design. Currently, many building basements are under construction. Due to changes in the hydrogeological conditions around the site, or encountering factors such as heavy rainfall, the basement sump is subject to the buoyancy of groundwater exceeding the original design value during the bottom plate construction, resulting in water seepage and even sand gushing damage.

[0003] Due to the shortcomings of the existing technology for dealing with sand gushing and water seepage during the construction of basement sump pit floors, it is urgently necessary to adopt effective, reliable and economically feasible methods to fundamentally solve the problems of water seepage and sand gushing during the construction of basement sump pit floors. Summary of the invention

[0004] In order to overcome the shortcomings of the prior art, the present invention proposes a basement floor sump construction method that is anti-sand and water seepage-proof, which is beneficial to reducing leakage and sand seepage during construction and can improve the use efficiency and durability of the basement floor foundation pit sump.

[0005] To achieve the above object, a method for constructing a basement floor sump for preventing sand inrush and water seepage according to the present invention comprises the following steps:

[0006] S1: Earth excavation, excavating a foundation pit of specified size according to construction requirements;

[0007] S2: Grouting of the base, using quick-setting slurry to solidify the soil around the foundation pit;

[0008] S3: Construction of cushion layer: After setting the elevation control piles, pour cushion layer concrete on the foundation pit, and then scrape and press it flat after vibration;

[0009] S4: Waterproof construction, waterproof construction on the cushion layer, including slurry preparation, painting, inspection and maintenance;

[0010] S5: Protective layer construction, protective layer and isolation layer construction are carried out on the basis of waterproof construction;

[0011] S6: Steel bar binding, tying the supporting steel bars on the foundation pit;

[0012] S7: Formwork support, support the pit side formwork;

[0013] S8: Concrete pouring, pouring in layers, vibrating and pouring at the same time to form the final complete sump structure.

[0014] Furthermore, in step S1, the size of the foundation pit excavation is 3000mm*2000mm*1500mm, and the surface loose soil is cleaned after the foundation pit excavation.

[0015] Furthermore, in step S2, the penetration radius of the quick-setting slurry in the formation is adjusted according to the permeability coefficient of the fine sand and the slurry viscosity parameters, and the initial setting time of the quick-setting slurry is controlled, and double-liquid grouting is adopted.

[0016] Furthermore, in step S3, the strength grade of the cushion layer concrete is C20. During the cushion layer construction phase, a fixed concrete pump is used for concrete delivery. The pump truck is located on the south side of the foundation pit. When pouring the cushion layer, the delivery pump pipe is set up in the pouring sequence. The elevation control piles use Φ12 steel bars. The spacing between the elevation control piles is 1500mm. During the construction of the concrete cushion layer, a flat vibrator is used for vibration and an iron trowel is used for scraping.

[0017] Further, in step S4, when making slurry, a certain amount of water is first added to the mixing barrel, and the cement-based penetrating crystal material is slowly added under stirring, the cement-based penetrating crystal material is stirred evenly without powder and precipitation, and the paint is mixed into a paste, and the specified viscosity is reached under stirring, and the cement-based penetrating crystal material: water = 1.0:0.35~0.4 ratio is measured;

[0018] When brushing, apply force in the positive and negative directions on the surface of the cushion layer to brush back and forth vertically and horizontally to ensure that the thickness of the coating is uniform on the concave and convex parts, platforms, steps and corners to avoid missing coating. When constructing on the flat surface or steps, brush the cement-based penetrating crystalline waterproof coating evenly, and roll it after one coating. The interval between rolling and brushing is 3 to 4 hours;

[0019] During the inspection, first check whether the coating is uniform. If it is uneven, repair and rework it. Keep the base surface of the reworked part moist. If it is dry, spray water before applying the cement-based penetrating crystalline waterproof coating, and avoid the appearance of visible water.

[0020] During maintenance, the cement-based penetrating crystallization waterproof coating is allowed to solidify for 3 to 4 hours or, depending on the humidity on site, spray water every day for maintenance for 2 to 3 consecutive days. During external construction, care should be taken to avoid rain damage to the coating, and the waterproof layer must not be collided during maintenance.

[0021] Furthermore, in step S5, before the construction of the protective layer, a post-rain observation, water sprinkling or water storage test is carried out, and the construction of the protective layer is carried out only after passing the test. During construction, damage to the waterproof layer and the protective layer should be avoided. The slope of the surface of the block material, cement mortar, and fine stone concrete protective layer should meet the design requirements, and no water accumulation should be allowed.

[0022] Furthermore, in step S6, when tying the lap joints, the joint area percentage of beams, slabs and walls is not greater than 25%, and that of concealed columns is not greater than 50%.

[0023] Further, in step S7, the pit side formwork is made of 14mm thick brown formwork on site; when the side length of the sump is ≤2000mm, 40mm×80mm wooden squares are used with a vertical rib spacing of 300mm, 40mm×80mm wooden squares are used for bracing, and the vertical and horizontal horizontal spacing is 500mm; when the side length of the sump is >2000mm, a Ф48×3.6 steel pipe scaffolding is used for support, and U-supports are set at both ends of the steel pipe. After the pit side formwork is supported, anti-floating measures are taken, and a weight is placed in the drum formwork to prevent the concrete from being poured. The template floats; the main keel is welded with 8# channel steel, and the weld is full; the platform plate is made of 3mm thick patterned steel plate, and the processing size of the platform plate is 100mm smaller than the net size of the inner wall of the water collection tunnel to ensure that the shaft can be lifted smoothly upward; 4 φ20 lifting rings are installed on the upper part of the platform plate, and four lifting points are evenly distributed to ensure the balance of lifting force; when the water collection tunnel is a full shear wall, the height of the operating platform is the floor height minus 300mm, and when the shaft is a partial filling wall, the height is adjusted according to the height of the shaft frame beam to ensure that the load-bearing support at the top of the platform triangle support is a structural beam.

[0024] Furthermore, in step S8, concrete pouring is carried out in layers, with each layer being no thicker than 500 mm. The pouring is carried out in sections and layers continuously without leaving construction joints. Each section and layer is connected to each other, with each section being 2 to 3 m long, so that the concrete is poured in a stepped manner layer by layer, and attention is paid to filling the edges and corners of the mold with concrete first, and then pouring the middle part. The slope is formed by the natural flow of pumped concrete, and the slope is controlled at 1:3. The vibration work starts from the bottom layer of the pouring layer and gradually moves upward.

[0025] The method for constructing a basement floor sump pit for preventing sand gushing and water seepage of the present invention further combines the functions of solidification treatment measures for the base soil, cushion construction, waterproofing construction, waterproof protection layer construction, sump steel bar binding, water stop measures installation, sump template installation, sump concrete pouring, etc. Compared with the traditional construction method, it reasonably optimizes the construction process and avoids the quality defects of leakage and sand gushing in the floor sump pit during the construction process, further improves the use function of the sump pit, and effectively improves the use efficiency and durability of the basement floor foundation pit water pit. DETAILED DESCRIPTION

[0026] The technical solution of the present invention is more clearly and completely explained below through the description of the preferred embodiments of the present invention.

[0027] A preferred embodiment of the present invention is a method for constructing a basement floor sump to prevent sand inrush and water seepage, comprising the following steps:

[0028] S1: Excavation of earthwork. Excavate the foundation pit of the specified size according to the construction requirements. The size of the foundation pit excavation is 3000mm*2000mm*1500mm. The position deviation should meet the construction and specification requirements. The standard axis piles, horizontal piles and gray line sizes of the building location must be inspected and the acceptance procedures must be completed. After the foundation pit is excavated, the surface loose soil is cleaned up, and the elevation and surface flatness meet the design requirements and specifications. Perform segmented inspections according to the procedures. For the soil layers that do not meet the design requirements, the foundation treatment is carried out according to the opinions of the design and survey units. After the treatment is completed, please ask the supervision, design, survey and construction units to accept and handle the hidden inspection records. Check whether the location, quantity and plane size of the sump are consistent with the design according to the drawings. According to the working surface provided by the slope support and earthwork excavation, the inspection is carried out in sequence to save construction time. Commercial concrete is used for the construction of the foundation cushion layer. The concrete process parameters are determined according to the construction requirements, and the required construction machinery and tools are implemented. As required, prepare the personnel and equipment for the foundation concrete cushion construction, organize the work teams according to the specific requirements such as the construction flow section division, and complete the technical briefing in advance.

[0029] S2: Base grouting. Due to the gushing of water and sand during the excavation of the foundation pit, there are large gaps in the sand layer and at the boundary between the sand layer and the soil layer. Therefore, quick-setting slurry is used for injection. Because grouting is carried out underwater, in order to block water and reinforce the sand layer, the slurry should have a sufficient penetration radius in the stratum according to parameters such as the permeability coefficient of fine sand and the viscosity of the slurry. The initial setting time of the slurry should be appropriate. Double-liquid grouting is used to solidify the soil around the foundation pit.

[0030] S3: Construction of cushion layer. After setting the elevation control piles, pour the cushion layer concrete on the foundation pit, and then vibrate and level it and calender it. The strength grade of the cushion layer concrete is C20. During the cushion layer construction stage, the concrete is delivered by a fixed concrete pump. The pump truck is located on the south side of the foundation pit. When pouring the cushion layer, the delivery pump pipe is set up according to the pouring sequence. The elevation control piles use Φ12 steel bars, and the spacing between the elevation control piles is 1500mm. During the construction of the concrete cushion layer, a flat vibrator is used for vibration and an iron trowel is used for smoothing. In order to prevent human trampling and damage to the concrete surface, people can only go up after the strength reaches 1.2MPa. When curing concrete, the watering interval should be appropriately adjusted according to the weather and temperature conditions to ensure that the concrete surface is moist. This work is also the responsibility of the concrete calendering personnel. It is forbidden to step on the smoothed concrete surface. During the construction of the concrete cushion layer, the 50mm×100mm wooden blocks used for fixing the formwork must be planed on three sides. The construction of the sloped part must wait until the large surface is demolded, and the upper and lower openings of the slope must be measured to complete the secondary concrete pouring.

[0031] S4: Waterproof construction, waterproof construction is carried out on the cushion layer, including slurry preparation, painting, inspection and maintenance; when slurry preparation, first add a certain amount of water into the mixing bucket, slowly add cement-based penetrating crystal material under stirring, the cement-based penetrating crystal material is stirred evenly, without powder and precipitation, the paint is mixed into a paste, and the specified viscosity is reached under stirring, and the cement-based penetrating crystal material: water = 1.0:0.35~0.4 ratio is measured;

[0032] When brushing, apply force in the positive and negative directions on the surface of the cushion layer to brush back and forth vertically and horizontally to ensure that the thickness of the coating is even on the concave and convex parts, platforms, steps, and corners to avoid missing coating. When constructing on the flat surface or steps, brush the cement-based penetrating crystalline waterproof coating evenly without excessive deposition to prevent cracking in excessively thick areas. Roll brushing should be performed after one application. The interval between rolling brushing and brushing is 3 to 4 hours;

[0033] During the inspection, first check whether the coating is uniform. If it is uneven, repair and rework it. Keep the base surface of the reworked part moist. If it is dry, spray water before applying the cement-based penetrating crystalline waterproof coating, and avoid the appearance of visible water.

[0034] During maintenance, the cement-based penetrating crystallization waterproof coating is allowed to solidify for 3 to 4 hours or, depending on the humidity on site, spray water every day for maintenance for 2 to 3 consecutive days. During external construction, care should be taken to avoid rain damage to the coating, and the waterproof layer must not be collided during maintenance.

[0035] S5: Protective layer construction. The protective layer and isolation layer are constructed on the basis of waterproof construction. Before the construction of the protective layer, conduct post-rain observation, water sprinkling or water storage test. The protective layer construction can be carried out only after passing the test. During construction, damage to the waterproof layer and protective layer should be avoided. The slope of the surface of the block material, cement mortar, and fine stone concrete protective layer should meet the design requirements and no water accumulation should be allowed.

[0036] S6: For steel bar binding, the requirements for longitudinal tensile steel bar joints in the same connection section shall be taken in accordance with page 59 of 16G101-1, and the percentage of joint area shall meet the following requirements: When binding lap joints, beams, slabs, and walls should not be greater than 25%, and concealed columns should not be greater than 50%. The requirements for setting stirrups in the lap area of ​​longitudinal tensile steel bars of beam components shall also meet the requirements of page 62 of 16G101-1; the requirements for setting stirrups within the lap length of longitudinal bars of edge components and concealed columns of shear walls shall also meet the requirements of page 73 of 16G101-1; the spacing of horizontal distribution bars in the lap area of ​​vertical distribution bars of shear wall body shall not be greater than 10d (d is the minimum diameter of lap bars).

[0037] S7: Formwork support, support the pit side formwork; the pit side formwork uses 14mm thick brown formwork, which is made on site; when the side length of the sump is ≤2000mm, use 40mm×80mm wooden squares with a vertical rib spacing of 300mm, 40mm×80mm wooden squares for bracing, and a vertical and horizontal spacing of 500mm; when the side length of the sump is >2000mm, use Ф48×3.6 steel pipe scaffolding for support, and set U-supports at both ends of the steel pipe. After the pit side formwork is supported, take anti-floating measures, and use heavy objects to place weights in the drum formwork to prevent pouring concrete. The template floats when the soil is filled; the main keel is welded with 8# channel steel, and the weld is full; the platform plate is made of 3mm thick patterned steel plate, and the processing size of the platform plate is 100mm smaller than the net size of the inner wall of the water collection tunnel to ensure that the shaft can be lifted upward smoothly; 4 φ20 lifting rings are installed on the upper part of the platform plate, and four lifting points are evenly distributed to ensure the balance of lifting force; when the water collection tunnel is a full shear wall, the height of the operating platform is the floor height minus 300mm, and when the shaft is a partial filling wall, the height is adjusted according to the height of the shaft frame beam to ensure that the load-bearing support at the top of the platform triangle support is a structural beam.

[0038] S8: Concrete pouring, layered pouring, vibrating and pouring to form the final complete sump structure. Concrete pouring is carried out in layers, with each layer thickness not exceeding 500mm. The pouring is carried out in sections and layers continuously without leaving construction joints. Each section and layer is connected to each other. Each section is 2m to 3m long, so that each section and layer is advanced in a step-like manner. Pay attention to filling the corners of the mold with concrete first, and then pour the middle part. The slope is formed by the natural flow of pumped concrete, and the slope is controlled at 1:3. The vibration work starts from the bottom of the pouring layer and gradually moves up. During the vibration process of concrete, the vibrating rod should be slightly twitched up and down to make the upper and lower concrete vibrate evenly. The vibration time for each time is preferably 20s to 30s (no bubbles appear on the surface of the concrete, and mortar overflows). When vibrating, try to avoid collision with steel bars, embedded pipe parts, etc. The insertion points of the vibrating rods are moved in a determinant order, and the distance of each movement does not exceed 1.25 times the effective action radius of the concrete vibrating rod. The action radius of the vibrating rod is generally 300mm to 400mm. The vibrating operation should be "fast insertion and slow withdrawal" to prevent the concrete from being vibrated unrealistically; "vibrate the low places first, then the high places" to prevent the concrete from vibrating "loose top" on high and low slopes. The reinforcement insertion parts of the independent columns of the pedestal are poured symmetrically and avoid collision with the steel bars to ensure the compactness of the concrete. The bottom plate is poured in sequence according to the pouring order, and the method of "segmented and divided points, one slope, thin layer pouring, step by step, and one time to the top" is adopted to ensure that the setting of the upper and lower concrete does not exceed the initial setting time. The bottom plate concrete of the deep pit should be vibrated first. When the concrete of the pit wall is poured, the bottom will not return to the slurry. The vibration operation should be vibrated in layers, and the layer thickness is 6mm. During the concrete pouring process of deep pits, the quality problems of shaft displacement and formwork running are prone to occur. In order to prevent the formwork from shifting, in addition to the fixed formwork supported by external top and internal support, the materials are symmetrically placed around the shaft formwork and vibrated symmetrically. It is forbidden to pour concrete to the top on one side at a time. After the concrete is poured, it is compacted and smoothed with a wooden trowel, and there must be no loose concrete on the surface. The poured concrete should be covered and properly watered within 12 hours. The construction joint at the root of the high external wall on the external wall bottom plate is 300mm away from the bottom plate. There are steel pipes for fixing the formwork, shear wall positioning ladder bars, and steel plate waterstops. The concrete cannot be directly poured into the center of the formwork when it is poured, and the vibration must be slow and meticulous.

[0039] The method for constructing a basement floor sump pit for preventing sand gushing and water seepage of the present invention further combines the functions of solidification treatment measures for the base soil, cushion construction, waterproofing construction, waterproof protection layer construction, sump steel bar binding, water stop measures installation, sump template installation, sump concrete pouring, etc. Compared with the traditional construction method, it reasonably optimizes the construction process and avoids the quality defects of leakage and sand gushing in the floor sump pit during the construction process, further improves the use function of the sump pit, and effectively improves the use efficiency and durability of the basement floor foundation pit water pit.

[0040] The above specific implementations are only descriptions of the preferred implementations of the present invention, and do not limit the protection scope of the present invention. Without departing from the design concept and spirit of the present invention, various modifications, substitutions and improvements made by ordinary technicians in this field to the technical solution of the present invention based on the text description provided by the present invention should all fall within the protection scope of the present invention. The protection scope of the present invention is determined by the claims.

Claims

1. A method for constructing a basement floor sump to prevent sand inrush and water seepage, characterized in that: The following steps are involved: S1: Earth excavation, excavating a foundation pit of specified size according to construction requirements; S2: Grouting of the base, using quick-setting slurry to solidify the soil around the foundation pit; S3: Construction of cushion layer: After setting the elevation control piles, pour cushion layer concrete on the foundation pit, and then level and press it after vibration; S4: Waterproof construction, waterproof construction on the cushion layer, including slurry preparation, painting, inspection and maintenance; S5: Protective layer construction, protective layer and isolation layer construction are carried out on the basis of waterproof construction; S6: Steel bar binding, tying the supporting steel bars on the foundation pit; S7: Formwork support, support the pit side formwork; S8: Concrete pouring, pouring in layers, vibrating and pouring at the same time to form the final complete sump structure.

2. A method for constructing a basement floor sump to prevent sand inrush and water seepage according to claim 1, characterized in that: In step S1, the size of the foundation pit excavation is 3000mm*2000mm*1500mm, and the surface loose soil of the foundation pit is cleaned after excavation.

3. A method for constructing a basement floor sump to prevent sand inrush and water seepage according to claim 1, characterized in that: In step S2, the penetration radius of the quick-setting slurry in the formation is adjusted according to the permeability coefficient of the fine sand and the viscosity parameters of the slurry, and the initial setting time of the quick-setting slurry is controlled, and double-liquid grouting is adopted.

4. A method for constructing a basement floor sump to prevent sand inrush and water seepage according to claim 1, characterized in that: In step S3, the strength grade of the cushion layer concrete is C20. During the cushion layer construction phase, the concrete is pumped using a fixed concrete pump. The pump truck is located on the south side of the foundation pit. When pouring the cushion layer, the pump pipe is set up in the pouring sequence. The elevation control piles use Φ12 steel bars. The spacing between the elevation control piles is 1500mm. During the construction of the concrete cushion layer, a flat vibrator is used for vibration and an iron trowel is used for scraping.

5. The method for constructing a basement floor sump to prevent sand inrush and water seepage according to claim 1, characterized in that: In step S4, when making slurry, a certain amount of water is first added to the mixing barrel, and the cement-based penetrating crystal material is slowly added under stirring. The cement-based penetrating crystal material is stirred evenly without powder or precipitation, and the paint is mixed into a paste. When the specified viscosity is reached under stirring, the cement-based penetrating crystal material: water = 1.0:0.35-0.4 ratio is measured; When brushing, apply force in the positive and negative directions on the surface of the cushion layer to brush back and forth vertically and horizontally to ensure that the thickness of the coating is uniform on the concave and convex parts, platforms, steps and corners to avoid missing coating. When constructing on the flat surface or steps, brush the cement-based penetrating crystalline waterproof coating evenly, and roll it after one coating. The interval between rolling and brushing is 3 to 4 hours; During the inspection, first check whether the coating is uniform. If it is uneven, repair and rework it. Keep the base surface of the reworked part moist. If it is dry, spray water before applying the cement-based penetrating crystalline waterproof coating, and avoid the appearance of visible water. During maintenance, the cement-based penetrating crystallization waterproof coating is allowed to solidify for 3 to 4 hours or, depending on the humidity on site, spray water every day for maintenance for 2 to 3 consecutive days. During external construction, care should be taken to avoid rain damage to the coating, and the waterproof layer must not be collided during maintenance.

6. A method for constructing a basement floor sump to prevent sand inrush and water seepage according to claim 1, characterized in that: In step S5, before the construction of the protective layer, a post-rain observation, water sprinkling or water storage test is carried out. The construction of the protective layer is carried out only after passing the test. During the construction, damage to the waterproof layer and the protective layer should be avoided. The slope of the surface of the block material, cement mortar, and fine stone concrete protective layer should meet the design requirements and no water accumulation should be allowed.

7. A method for constructing a basement floor sump to prevent sand inrush and water seepage according to claim 1, characterized in that: In step S6, when tying the lap joints, the joint area percentage of beams, slabs and walls is not greater than 25%, and that of concealed columns is not greater than 50%.

8. The method for constructing a basement floor sump to prevent sand inrush and water seepage according to claim 1, characterized in that: In step S7, the pit side formwork is made of 14mm thick brown formwork on site; when the side length of the sump is ≤2000mm, 40mm×80mm wooden squares are used with a vertical rib spacing of 300mm, 40mm×80mm wooden squares are used for bracing, and the vertical and horizontal horizontal spacing is 500mm; when the side length of the sump is >2000mm, a Ф48×3.6 steel pipe scaffolding is used for support, and U-supports are set at both ends of the steel pipe. After the pit side formwork is supported, anti-floating measures are taken, and a weight is placed in the drum formwork to prevent the formwork from floating when pouring concrete. Floating; the main keel is welded with 8# channel steel, and the weld is full; the platform plate is made of 3mm thick patterned steel plate, and the processing size of the platform plate is 100mm smaller than the net size of the inner wall of the water collection tunnel to ensure that the shaft can be lifted upward smoothly; 4 φ20 lifting rings are installed on the upper part of the platform plate, and four lifting points are evenly distributed to ensure the balance of lifting force; when the water collection tunnel is a full shear wall, the height of the operating platform is the floor height minus 300mm, and when the shaft is a partial filling wall, the height is adjusted according to the height of the shaft frame beam to ensure that the load-bearing support at the top of the platform triangle support is a structural beam.

9. A method for constructing a basement floor sump to prevent sand inrush and water seepage according to claim 1, characterized in that: In step S8, concrete pouring is carried out in layers, with each layer being no thicker than 500 mm. The pouring is carried out continuously in sections and layers without leaving construction joints. Each section and layer is connected to each other, with each section being 2 to 3 m long. The concrete is poured in a stepped manner layer by layer, with attention paid to filling the edges and corners of the mold with concrete first, and then pouring the middle part. The slope is formed by the natural flow of pumped concrete, and the slope is controlled at 1:

3. The vibration work starts from the bottom layer of the pouring layer and gradually moves upward.