Electromechanical pipeline mounting system suitable for spherical grid structure

By designing the installation system of the spherical mesh frame, the combined structure of the semicircular shell and the combined shell, combined with lifting and assembly components, the stability and safety problems of the spherical mesh frame structure after the load increases are solved, and stable installation and load are achieved Dispersed, avoiding the occurrence of building renovation accidents.

CN119083648AActive Publication Date: 2024-12-06THE SECOND CONSTR OF CHINA CONSTR EIGHTH ENG DIV
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411303233.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-19
Publication Date
2024-12-06
Estimated Expiration
2044-09-19

AI Technical Summary

Technical Problem

After the spherical mesh structure is built with a hydropower wiring pipeline, structural stability and safety problems are caused by increased load, which is prone to building renovation accidents.

Method used

An electromechanical pipe installation system including a spherical mesh frame, a ball shell, a hoisting assembly and a stable assembly were designed. Through a combined structure of a semicircular shell and a combined shell, a suspender rod, a adjusting drum and an adaptive lap block are used. and other components to achieve stable installation and load dispersion, ensuring the stability and safety of the grid structure.

Benefits of technology

Without destroying the original grid structure, the stable installation of spherical nodes and reasonable load dispersion are achieved, the stability and safety of the entire grid structure are improved, and accidents caused by insufficient load capacity of the structure after transformation are avoided. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083648A_ABST
    Figure CN119083648A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of spherical net rack mounting parts, in particular to an electromechanical pipeline mounting system suitable for a spherical net rack structure, which comprises a spherical net rack, a hoisting assembly and an assembly stabilizing assembly, the spherical net rack comprises a plurality of net rack rod pieces and spherical nodes, and the spherical nodes are sleeved with mounting spherical shells; the installation spherical shell comprises a semicircular cover shell and four combined cover shells, the installation spherical shell composed of the semicircular cover shell and the four combined cover shells is designed according to the arrangement structure postures of the net rack rod piece and the spherical joint, and when pipelines at several points need to be set up for the spherical joint net rack structure, the hoisting assembly is arranged at the lower end of the installation spherical shell, so that the pipelines can be set up conveniently. Stable installation can be carried out under the state that an original grid structure is not damaged, meanwhile, under the matching effect of the splicing stabilizing assembly, connection of the installation spherical shell and the spherical joint is stable and reliable, the load of the electromechanical pipeline can be reasonably dispersed, and the stability and safety of the whole grid structure are ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of spherical grid mounting parts, in particular to an electromechanical pipeline mounting system suitable for a spherical grid structure. Background Art

[0002] The grid roof is a spatial mesh structure composed of rods along a certain curvature or plane. The spherical grid roof structure is widely used in modern large-span buildings. After the spherical grid structure is built, it is necessary to set up a bridge or pipeline on the top of the building according to the design requirements;

[0003] When constructing water and electricity wiring pipelines for spherical grid structures, they are usually constructed by hanging parts or destroying existing grid structures. However, due to the increase in the later use load of the spherical grid structure after the transformation, or the destruction of the original grid structure system, the load capacity of the existing grid structure is affected, which leads to frequent renovation accidents of existing grid structure buildings. Summary of the invention

[0004] The object of the present invention is to provide an electromechanical pipeline installation system suitable for a spherical grid structure to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above object, the present invention provides the following technical solution: an electromechanical pipeline installation system suitable for a spherical grid structure, comprising:

[0006] A spherical grid, the spherical grid comprises a plurality of grid rods and spherical nodes, a mounting spherical shell is sleeved on the spherical nodes, and the mounting spherical shell comprises a semicircular cover shell and four combined cover shells;

[0007] A hoisting assembly is arranged at the lower end of the semicircular cover, and the hoisting assembly includes a suspension rod, an adjustment drum and an adaptive overlap block. A combination screw sleeve is arranged at the lower end of the semicircular cover, and the upper end of the suspension rod is threadedly plugged into the lower end of the combination screw sleeve;

[0008] The assembled stabilizing component comprises a restraining block and a stabilizing tube. The upper ends of the four assembled cover shells are provided with a combination key bar, and the combination key bars of the four assembled cover shells are respectively plugged into the lower ends of the restraining blocks.

[0009] Preferably, a plurality of clearance holes are symmetrically provided on the mounting spherical shell, and the connecting sides of a plurality of grid rods and the spherical nodes are respectively penetrated and plugged into the clearance holes.

[0010] Preferably, the combined cover shell is symmetrically provided with two first connecting ears on both sides close to the semicircular cover shell, a second connecting ear is provided on one side of the semicircular cover shell close to the first connecting ear, and a combined bolt is vertically inserted between the first connecting ear and the second connecting ear.

[0011] Preferably, the upper ends of the four combined cover shells are each provided with a combined hole groove, and when the four combined cover shells are fixedly connected to the semicircular cover shell, the four combined hole grooves form a circular structure, and the combination key bar is arranged on one side of the combined cover shell close to the combined hole groove.

[0012] Preferably, when the four combination cover shells are combined and fixedly connected with the semicircular cover shell, the four combination key bars form a cross-staggered structure, a cross key groove is opened at the lower end of the constraint block, and the cross-staggered structure formed by the four combination key bars is inserted into the cross key groove of the constraint block.

[0013] Preferably, a docking hole is opened through the center of the cross key slot of the constraint block, and the stabilizing tube vertically moves through the docking hole and the combined hole slots of the four combined cover shells. The stabilizing tube is placed in the installation spherical shell and a pressure plate is horizontally provided on one side. The upper end of the stabilizing tube passes through the constraint block and is provided with a stabilizing nut through a threaded sleeve, and the lower end of the stabilizing nut abuts against the upper end of the constraint block.

[0014] Preferably, the upper end of the pressing sheet abuts against one side of four combined cover shells, a positioning groove is provided on one side of the combined cover shell close to the pressing sheet, four positioning blocks are symmetrically provided on the upper end of the pressing sheet, and the four positioning blocks are respectively inserted into the four positioning grooves.

[0015] Preferably, an internal thread groove is provided through the center of the stabilizing tube and passes through the pressure plate, a clamping bolt is vertically inserted in the internal thread groove, and the clamping bolt passes through the lower end of the pressure plate and abuts against the upper end of the spherical node.

[0016] Preferably, the adjusting drum is arranged by threadedly sleeved on the lower end of the suspension rod, an anti-slip shaft block is provided at the center of the lower end of the adjusting drum, the anti-slip shaft block of the adjusting drum is movably sleeved on the upper end of the adaptive overlap block, and an overlap bolt hole is horizontally penetrated through one side of the adaptive overlap block.

[0017] Preferably, a support rod is horizontally provided between the adaptive overlapping blocks at the lower ends of two adjacent mounting spherical shells, and both sides of the support rod respectively penetrate the overlapping bolt holes of the two adaptive overlapping blocks and are provided with fixing nuts through threaded sleeves, and an organic electrical bridge is horizontally installed on the upper end of the support rod.

[0018] Compared with the prior art, the present invention has the following beneficial effects:

[0019] According to the setting structural posture of the grid rods and spherical nodes, an installation spherical shell composed of a semicircular cover shell and four combined cover shells is designed. When it is necessary to build several pipelines on the spherical node grid structure, a hoisting component is set at the lower end of the installation spherical shell, which can be stably installed without destroying the original grid structure. At the same time, with the cooperation of the assembled stabilizing components, the connection between the installation spherical shell and the spherical node is stable and reliable, which can reasonably disperse the load of the electromechanical pipeline and ensure the stability and safety of the entire grid structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a schematic diagram of the structure of the present invention;

[0021] Figure 2 It is a schematic side cut diagram of the structure of the present invention;

[0022] Figure 3 For the present invention Figure 2 Schematic diagram of the structure of part A;

[0023] Figure 4 This is a schematic diagram of the spherical shell structure installed in the present invention;

[0024] Figure 5 This is a schematic diagram of the combined structure of the combination key bar of the present invention;

[0025] Figure 6 This is a schematic diagram of the structure of the tableting arrangement of the present invention;

[0026] Figure 7 This is a schematic diagram of the combined cover structure of the present invention;

[0027] Figure 8 This is an exploded view of the connection between the restraining block and the stabilizing tube of the present invention;

[0028] Fig. 9 This is a schematic diagram of the structure when the pipeline is installed.

[0029] In the figure: grid member 1, spherical node 2, mounting spherical shell 3, combined cover shell 4, semicircular cover shell 5, make way hole 6, combined screw sleeve 7, hanger 8, adjusting drum 9, adaptive overlap block 10, support rod 11, electromechanical bridge 12, first connecting ear 13, second connecting ear 131, combined bolt 14, combined key strip 15, stabilizing tube 16, pressure plate 17, positioning block 18, positioning groove 19, restraining block 20, stabilizing nut 21, cross keyway 22, clamping bolt 23, pipe clamp 24, designed pipeline 25. DETAILED DESCRIPTION

[0030] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0031] Please see attached Figure 1-9 , this application provides the following technical solutions.

[0032] Embodiment 1: An electromechanical pipeline installation system suitable for a spherical grid structure, comprising a spherical grid, the spherical grid comprising a plurality of grid rods 1 and a spherical node 2, a mounting spherical shell 3 is sleeved on the spherical node 2, the mounting spherical shell 3 comprises a semicircular cover shell 5 and four combined cover shells 4, a plurality of symmetrically arranged clearance holes 6 are arranged on the mounting spherical shell 3, the connecting sides of the plurality of grid rods 1 and the spherical node 2 are respectively penetrated by the plug-in clearance holes 6, the combined cover shell 4 is symmetrically provided with two first connecting ears 13 on both sides close to the semicircular cover shell 5, the semicircular cover shell 5 is provided with a second connecting ear 131 on one side close to the first connecting ear 13, and the first connecting ear 131 is provided on the first connecting ear 131. A combination bolt 14 is vertically inserted between the connecting ear 13 and the second connecting ear 131. The four combination cover shells 4 and the semicircular cover shell 5 are fixedly assembled by eight first connecting ears 13, eight second connecting ears 131 and eight combination bolts 14 to form a complete spherical shell structure. The setting of the concession hole 6 is convenient for the structural penetration of the grid rod 1 to avoid damaging the connection state of the grid rod 1 and the spherical node 2. At the same time, the setting of the four combination cover shells 4 is convenient for assembly and use in response to the positional relationship of the grid rod 1. The combination cover shell 4 is a 1 / 8 semicircular structure, and the semicircular cover shell 5 is a 1 / 2 semicircular structure.

[0033] An assembly stabilization component is provided to strengthen and stabilize the assembly state of the four combination cover shells 4. The assembly stabilization component includes a constraint block 20 and a stabilization tube 16. The upper ends of the four combination cover shells 4 are provided with a combination key strip 15, and the combination key strips 15 of the four combination cover shells 4 are respectively plugged into the lower ends of the constraint blocks 20. The upper ends of the four combination cover shells 4 are provided with a combination hole groove. When the four combination cover shells 4 are fixedly connected to the semicircular cover shell 5, the four combination hole grooves form a circular structure, and the combination key strip 15 is provided on one side of the combination cover shell 4 close to the combination hole groove. When the four combination cover shells 4 are combined and fixedly connected to the semicircular cover shell 5, the four combination hole grooves form a circular structure, and the combination key strip 15 is provided on one side of the combination cover shell 4 close to the combination hole groove. The combination key bars 15 form a cross-staggered structure, a cross key groove 22 is opened at the lower end of the constraint block 20, and the cross-staggered structure formed by the four combination key bars 15 is inserted into the cross key groove 22 of the constraint block 20. When the four combination cover shells 4 are assembled, the upper ends of the four combination cover shells 4 may be deformed and separated. At this time, by designing the combination key bar 15, a cross key bar structure is formed after the four combination cover shells 4 are combined. At this time, the constraint block 20 covers the combination key bar 15 through the cross key groove 22, which can avoid the deformation and separation of the combination key bars 15 of two adjacent combination cover shells 4, thereby improving stability.

[0034] A docking hole is provided in the center of the cross key slot 22 of the constraint block 20, and the stabilizing tube 16 vertically moves through the docking hole and the combined hole slots of the four combined cover shells 4. The stabilizing tube 16 is placed in the installation ball shell 3 and a pressure piece 17 is provided horizontally on one side. The upper end of the stabilizing tube 16 that passes through the constraint block 20 is provided with a stabilizing nut 21 through a threaded sleeve, and the lower end of the stabilizing nut 21 abuts against the upper end of the constraint block 20, and the upper end of the pressure piece 17 abuts against one side of the four combined cover shells 4. A positioning groove 19 is provided on one side of the combined cover shell 4 close to the pressure piece 17, and four positioning blocks 18 are symmetrically provided on the upper end of the pressure piece 17, and the four positioning blocks 18 are respectively inserted into the The pressure piece 17 is connected to the four positioning grooves 19, and is located inside the mounting ball shell 3, that is, it contacts the inner sides of the four combination cover shells 4, and the constraint block 20 contacts the outer side of the combination cover shell 4. When the constraint block 20 pulls and fixes the stabilizing tube 16, the constraint block 20 and the pressure piece 17 can press and fix the combination cover shell 4 to keep the combination key bar 15 stable in the cross key groove 22. In addition, when the positioning block 18 is inserted into the positioning groove 19, the deformation of the combination cover shell 4 away from the side of the semicircular cover shell 5 can be further avoided, and at the same time, the combination contact positioning of the combination key bar 15 is convenient, and the connection and use of the constraint block 20 and the combination cover shell 4 are convenient.

[0035] An internal thread groove is provided at the center of the stabilizing tube 16 and passes through the pressure piece 17. A clamping bolt 23 is vertically inserted in the internal thread groove, and the clamping bolt 23 passes through the lower end of the pressure piece 17 and abuts against the upper end of the spherical node 2. When the diameter of the spherical node 2 is slightly smaller than the inner diameter of the mounting spherical shell 3, by adding the clamping bolt 23, the shaking of the mounting spherical shell 3 when the spherical node 2 is sleeved can be avoided, thereby improving the stability of the combination of the two.

[0036] Embodiment 2: On the basis of embodiment 1, a hoisting assembly is provided to facilitate the installation of electromechanical pipelines. The hoisting assembly is arranged at the lower end of the semicircular cover shell 5. The hoisting assembly includes a suspension rod 8, an adjusting cylinder 9 and an adaptive overlap block 10. A combination screw sleeve 7 is provided at the lower end of the semicircular cover shell 5, and the upper end of the suspension rod 8 is threadedly inserted into the lower end of the combination screw sleeve 7. The adjusting cylinder 9 is threadedly sleeved with the lower end of the suspension rod 8. An anti-slip shaft block is provided at the center of the lower end of the adjusting cylinder 9. The upper end of the adaptive overlap block 10 movably sleeves the anti-slip shaft block of the adjusting cylinder 9, and a overlap bolt hole is horizontally penetrated on one side of the adaptive overlap block 10. A support rod 11 is horizontally provided between the adaptive overlap blocks 10 at the lower ends of two adjacent mounting spherical shells 3. The two sides of the support rod 11 respectively penetrate the overlap bolt holes of the two adaptive overlap blocks 10 and are threadedly sleeved A fixing nut is connected, and an electromechanical bridge 12 is horizontally installed on the upper end of the support rod 11. When the electromechanical bridge 12 needs to be installed, according to the laying route of the electromechanical bridge 12, the installation spherical shell 3 composed of the upper semicircular cover shell 5 and the four combined cover shells 4 is fixedly installed on two adjacent spherical nodes 2 along the way, and then the suspension rod 8 is inserted into the lower end of the combined nut sleeve 7, the adjusting drum 9 is sleeved on the lower end of the suspension rod 8, and the upper support rod 11 is horizontally fixed between two adjacent adaptive lap blocks 10, and then the electromechanical bridge 12 is fixedly overlapped with the support rod 11 by bolts or metal connecting sheets, and the electromechanical bridge 12 is laid. When the height of the electromechanical bridge 12 needs to be adjusted, the adjusting drum 9 is rotated to adjust the length of the sleeved suspension rod 8 to achieve height control of the electromechanical bridge 12;

[0037] When the pipe fittings need to be hoisted, a pipe fitting clamp 24 is vertically fixed at the lower end of the adaptive overlap block 10 by bolts, and a designed pipeline 25 is horizontally clamped and fixed in the pipe fitting clamp 24 .

[0038] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. An electromechanical pipeline installation system suitable for a spherical grid structure, characterized in that: include: A spherical grid frame, the spherical grid frame comprising a plurality of grid rods (1) and spherical nodes (2), a mounting spherical shell (3) being sleeved on the spherical node (2), the mounting spherical shell (3) comprising a semicircular cover shell (5) and four combined cover shells (4); A lifting assembly, the lifting assembly being arranged at the lower end of the semicircular cover (5), the lifting assembly comprising a lifting rod (8), an adjusting rotating drum (9) and an adaptive overlapping block (10), a combination screw sleeve (7) being arranged at the lower end of the semicircular cover (5), and the upper end of the lifting rod (8) being threadedly plugged into the lower end of the combination screw sleeve (7); An assembled stabilizing component comprises a restraining block (20) and a stabilizing tube (16); the upper ends of four assembled cover shells (4) are each provided with a combination key bar (15); and the combination key bars (15) of the four assembled cover shells (4) are respectively plugged into the lower ends of the restraining blocks (20).

2. The electromechanical pipeline installation system suitable for a spherical grid structure according to claim 1, characterized in that: The mounting spherical shell (3) is symmetrically provided with a plurality of clearance holes (6), and the connecting sides of the plurality of grid rods (1) and the spherical nodes (2) are respectively penetrated and plugged into the clearance holes (6).

3. The electromechanical pipeline installation system suitable for a spherical grid structure according to claim 2 is characterized in that: The combined cover shell (4) is symmetrically provided with two first connecting ears (13) on both sides close to the semicircular cover shell (5), and a second connecting ear (131) is provided on one side of the semicircular cover shell (5) close to the first connecting ear (13), and a combined bolt (14) is vertically inserted between the first connecting ear (13) and the second connecting ear (131).

4. The electromechanical pipeline installation system suitable for a spherical grid structure according to claim 3 is characterized in that: The upper ends of the four combined cover shells (4) are each provided with a combined hole slot. When the four combined cover shells (4) are fixedly connected to the semicircular cover shell (5), the four combined hole slots form a circular structure, and the combined key bar (15) is arranged on one side of the combined cover shell (4) close to the combined hole slot.

5. The electromechanical pipeline installation system suitable for a spherical grid structure according to claim 4, characterized in that: When the four combined cover shells (4) are combined and fixedly connected with the semicircular cover shell (5), the four combined key bars (15) form a cross-staggered structure, a cross key groove (22) is provided at the lower end of the constraint block (20), and the cross-staggered structure formed by the four combined key bars (15) is inserted into the cross key groove (22) of the constraint block (20).

6. The electromechanical pipeline installation system suitable for a spherical grid structure according to claim 5, characterized in that: A docking hole is provided in the center of the cross keyway (22) of the restraining block (20); a stabilizing tube (16) vertically moves through the docking hole and the combined hole slots of the four combined cover shells (4); a pressure plate (17) is horizontally provided on one side of the stabilizing tube (16) placed in the mounting spherical shell (3); a stabilizing nut (21) is provided at the upper end of the stabilizing tube (16) that passes through the restraining block (20) through a threaded sleeve connection, and the lower end of the stabilizing nut (21) is in contact with the upper end of the restraining block (20).

7. The electromechanical pipeline installation system suitable for a spherical grid structure according to claim 6, characterized in that: The upper end of the pressing piece (17) is in contact with one side of the four combined cover shells (4); a positioning groove (19) is provided on one side of the combined cover shell (4) close to the pressing piece (17); four positioning blocks (18) are symmetrically provided on the upper end of the pressing piece (17); and the four positioning blocks (18) are respectively inserted into the four positioning grooves (19).

8. The electromechanical pipeline installation system suitable for a spherical grid structure according to claim 7, characterized in that: The center of the stabilizing tube (16) is provided with an internal thread groove penetrating through the pressure plate (17), a clamping bolt (23) is vertically inserted in the internal thread groove, and the clamping bolt (23) penetrates the lower end of the pressure plate (17) and abuts against the upper end of the spherical node (2).

9. The electromechanical pipeline installation system suitable for a spherical grid structure according to claim 8, characterized in that: The adjusting rotating cylinder (9) is arranged to be threadedly sleeved on the lower end of the suspension rod (8); an anti-slipping shaft block is arranged at the center of the lower end of the adjusting rotating cylinder (9); the upper end of the adaptive overlapping block (10) is movably sleeved on the anti-slipping shaft block of the adjusting rotating cylinder (9); and an overlapping bolt hole is horizontally penetrated through one side of the adaptive overlapping block (10).

10. The electromechanical pipeline installation system suitable for a spherical grid structure according to claim 9, characterized in that: A support rod (11) is horizontally arranged between the adaptive overlap blocks (10) at the lower ends of two adjacent mounting spherical shells (3), and two sides of the support rod (11) respectively penetrate the overlap bolt holes of the two adaptive overlap blocks (10) and are provided with fixing nuts through threaded sleeves, and an organic electrical bridge (12) is horizontally installed at the upper end of the support rod (11).

Citation Information

Patent Citations

  • Fabricated net rack lifting point device

    CN112412061A

  • Firefighting pipeline erecting mechanism applied to single-layer spherical net rack steel structure workshop

    CN113883337A

  • Fire-fighting pipeline bracket mounting structure with net rack structure

    CN211599754U

  • Hanging bracket for quickly mounting pipeline in upper net rack in high and large space

    CN213685598U

  • Electromechanical installation conversion layer of bolted ball type steel net rack

    CN214658188U