Construction method of self-standing inner and outer cylinder type steel chimney

The segmented lifting and assembly method for self-supporting inner and outer tube steel chimneys addresses the inefficiencies of traditional methods by transferring ground assembly to high-altitude operations, enhancing safety and reducing costs through precise alignment and support structures.

CN119083805APending Publication Date: 2024-12-06CHINA CHEM ENG SECOND CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411513055.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-28
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

Traditional chimney installation methods for inner and outer tube structures with large aspect ratios face challenges in ground assembly accuracy, leading to high safety risks, long construction periods, and high costs due to cumbersome preparation and inefficient use of machinery.

Method used

A segmented lifting and assembly method for self-supporting inner and outer tube steel chimneys, involving ground assembly of ladder platforms and temporary operating platforms, followed by high-altitude assembly of chimney sections with precise alignment and support structures to ensure safe and efficient installation.

Benefits of technology

The method reduces safety risks, shortens construction time, and lowers costs by transferring high-altitude operations to the ground, improving efficiency and reducing machinery tonnage, while ensuring accurate assembly and maintaining ease of maintenance access.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083805A_ABST
    Figure CN119083805A_ABST
Patent Text Reader

Abstract

The invention provides a self-standing inner and outer cylinder type steel chimney construction method which is a mounting method for assembling crawling ladder platforms and temporary operation platforms of all sections of a chimney on the ground and assembling all the sections of the chimney in a high-altitude mode and comprises the steps that 1, construction preparation is conducted, specifically, temporary operation platform suspension points are reserved on all the sections of the chimney, and the temporary operation platforms for temporary suspension are manufactured; crawling ladder platforms of all sections of the chimney are assembled; step 2, installation of the crawling ladder platforms: installing the parts, located above the ground, of all sections of the crawling ladder platforms of the chimney on the ground; and 3, high-altitude assembly is conducted, specifically, all the sections of the chimney are hoisted in place in sequence from bottom to top. By means of the mode of combining ground segmented assembly and high-altitude segmented assembly, the effects of improving the efficiency of operators and machines, reducing the risk of high-altitude operation and shortening the construction period are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of chemical industry, and in particular to a construction method of a self-supporting inner-outer-tube steel chimney. Background Art

[0002] Chimneys are widely used in petrochemical, environmental protection, thermal power, biomass power generation, waste incineration and other fields. They are an indispensable device in the exhaust system of boilers, hot and cold water heaters, diesel generator sets, incinerators and other equipment. The finished self-supporting sleeve steel chimney is widely used for its advantages of light weight, corrosion resistance, good insulation function, long service life, beautiful appearance and easy installation.

[0003] Traditional chimney installation technology mostly adopts the construction method of ground assembly and overall hoisting. This method occupies a large area, the preparation work is cumbersome, and the overall hoisting safety risk is high, especially for chimneys with inner and outer tube structures, which have a large aspect ratio and cannot accurately control the assembly accuracy by ground horizontal assembly. The construction period is long, the construction efficiency is low, and the construction cost is high. Summary of the invention

[0004] In order to solve the above technical problems, the present invention adopts segmented lifting and assembly methods for long and small segmented equipment, which effectively solves the problem that it is not conducive to overall lifting after ground assembly, and achieves the purpose of improving the efficiency of operators and machinery, reducing the risk of working at heights, and shortening the construction period. A self-supporting inner and outer tube steel chimney construction method is proposed.

[0005] The technical solution of the present invention is achieved in this way: A method for constructing a self-supporting inner-outer tube steel chimney, the method comprising: assembling a ladder platform and a temporary operating platform for each section of the chimney on the ground; and assembling each section of the chimney in pairs at high altitude, comprising: Step 1: Construction preparation: reserve temporary operating platform hanging points on each section of the chimney, make temporary hanging temporary operating platforms, and assemble ladder platforms on each section of the chimney; Step 2: Ladder platform installation: Install the above-ground part of the ladder platform of each section of the chimney on the ground; Step 3: High-altitude assembly: hoist each section of the chimney into place in order from bottom to top; including: After each section of the chimney is lifted off the ground, the remaining section is installed below the installed ladder platform; Starting from the hoisting of the second section of the chimney, first install a temporary operating platform and a pair of opposite support frames at the outer periphery of the top of the first section of the chimney and at positions of 90° at the corresponding opposite flange surfaces; When the last section of the chimney is hoisted in a vertical state, the damper, aviation warning light and circular platform are assembled.

[0006] Furthermore, in step one, when placing the various sections of the chimney, installation space for the ladder platform is reserved, and the installation connecting plates of the ladder platforms of various sections of the chimney are reserved at appropriate positions.

[0007] Furthermore, in step three, before the chimney sections are hoisted, the base surfaces of the chimney sections are processed and the shim groups are placed as required, and then the top inner tube limit is checked to ensure that the inner tube is not stuck and can rotate freely to a certain angle.

[0008] Furthermore, when the temporary operating platform and the opposite supporting frame are installed, the flange sealing surface is processed, sealant is applied, and packing is installed.

[0009] Furthermore, during the construction preparation in step one, four limiting structures are arranged between the inner tube and the outer tube of each section of the chimney, and the limiting structures are arranged to include a "U"-shaped outer tube limiting frame preset on the inner wall of the outer tube and an inner tube support preset on the outer wall of the inner tube, so that there is a certain relative displacement between the inner tube and the outer tube of each section of the chimney in the four directions of up, down, left and right.

[0010] Furthermore, when the chimney sections are hoisted, the hoisting points are set on the outer tube, and when the chimney sections are in a vertical state, the inner tube support will move downward in the outer tube limit frame, so that the inner tube moves downward and the bottom end is exposed 400mm from the outer tube.

[0011] Furthermore, starting from the hoisting of the second section of the chimney, after the inner tube of the hoisted chimney section contacts the inner tube of the previous chimney section, the main hoist slowly drops the hook, so that the outer tube of the hoisted chimney section is placed on the opposite support frame of the previous chimney section. The opposite support frame is 400mm high, forming a passage for personnel to enter the inner tubes of the upper and lower chimney sections inside the chimney.

[0012] Furthermore, after the inner tubes of the upper and lower chimney sections are assembled, the opposite support frame of the outer tube assembly is removed, the hook is slowly lowered, and then the outer tubes of the upper and lower chimney sections are assembled and bolted.

[0013] The present invention has the following beneficial effects: The construction method of self-supporting inner and outer tube steel chimney arranges the construction reasonably according to the equipment arrival status and the installation characteristics of each section, transfers more high-altitude operations to the ground, and formulates appropriate installation methods by analyzing the installation requirements of each section structure and accessories. It solves the problem that long and thin equipment is not conducive to ground assembly and overall lifting, reduces the use of machinery, reduces the tonnage of lifting equipment, improves work efficiency, and saves costs. In addition, during the high-altitude assembly process, the platform hanging ears and external temporary operating platforms reserved in advance can not only meet the installation and construction, but also meet the needs of later maintenance; in addition, the use of the opposite support frame of the assembly leaves operating space for the inner tube docking before the outer tube docking, which is convenient, safe and reliable. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic flow chart of the construction method of the self-supporting inner and outer tube steel chimney of the present invention; Figure 2 It is a schematic diagram of the process of installing the first section of the chimney of the present invention; Figure 3 It is a schematic diagram of the process of installing the second, third and fourth sections of the chimney of the present invention; Figure 4 It is a schematic diagram of the process of installing the fifth section of the chimney of the present invention; Figure 5 It is a schematic diagram of the outer cylinder limit frame and the inner cylinder support of the present invention.

[0015] Figure 6 It is a schematic diagram of a top view of the outer cylinder limit frame and the inner cylinder support of the present invention.

[0016] 1-outer cylinder, 2-inner cylinder, 3-outer cylinder limit frame, 4-inner cylinder support. DETAILED DESCRIPTION

[0017] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0018] like Figures 1 to 5 As shown, the present invention provides a method for constructing a self-supporting inner and outer tube type 1 steel chimney, which is a method for assembling a ladder platform and a temporary operating platform of each section of the chimney on the ground, and a method for installing each section of the chimney in a high-altitude team, which sequentially includes step one, construction preparation; step two, ladder platform installation and step three, high-altitude teaming.

[0019] Step 1: Construction preparation refers to reserving temporary operating platform hanging points on each section of the chimney, making temporary hanging temporary operating platforms, and assembling ladder platforms on each section of the chimney.

[0020] On this basis, each section of the chimney is prefabricated in the factory and installed on site. During the construction preparation stage in step one, when the chimney sections are unloaded and placed, installation space for the ladder platform is reserved, and the installation connecting plates of the ladder platforms of each section of the chimney are reserved in appropriate positions.

[0021] In this embodiment, the chimney is divided into five sections for prefabrication.

[0022] Step 2: The installation of the ladder platform refers to the installation of the part of the ladder platform of each section of the chimney directly on the ground. On this basis, the remaining part of the ladder platform of each section of the chimney is installed under the installed ladder platform after the chimney sections are hoisted off the ground.

[0023] Step 3: High-altitude assembly refers to the hoisting of each section of the chimney from bottom to top. On this basis, starting from the hoisting of the second section of the chimney, first install temporary operating platforms and assembly opposite support frames at 90° positions on the top periphery of the previous chimney section and the corresponding assembly flange surface. In addition, when the last section of the chimney is hoisted in a vertical state, assemble the damper, aviation warning light and circular platform.

[0024] Preferably, in step three, before hoisting each section of the chimney, the base surface of each section of the chimney is processed and the shim group is placed as required, and then the limit of the top inner tube 2 is checked to ensure that the inner tube 2 is not stuck and can rotate freely to a certain angle.

[0025] Among them, when installing the temporary operating platform and the opposite support frame, the flange sealing surface is processed, sealant is applied, and packing is installed.

[0026] Preferably, during the construction preparation of step one, four limiting structures are arranged between the inner tube 2 and the outer tube 1 of each section of the chimney, and the limiting structures are arranged to include a "U"-shaped outer tube limiting frame 3 preset on the inner wall of the outer tube 1 and an inner tube support 4 preset on the outer wall of the inner tube 2, so that there is a certain relative displacement between the inner tube 2 and the outer tube 1 of each section of the chimney in the four directions of up, down, left and right.

[0027] On this basis, when each section of the chimney is hoisted, the hoisting point is set on the outer tube 1, and when each section is delayed to be in a vertical state, the inner tube support 4 will move downward in the outer tube limit frame 3, so that the inner tube 2 moves downward, and the bottom end of the inner tube 2 is exposed 1400mm from the outer tube.

[0028] Preferably, starting from the hoisting of the second section of the chimney, after the inner tube 2 of the hoisted chimney section contacts the inner tube 2 of the previous chimney section, the main hoist slowly drops the hook so that the outer tube 1 of the hoisted chimney section is placed on the opposite support frame of the previous chimney section. The opposite support frame is 400mm high, forming a passage for personnel to enter the inner tube 2 of the upper and lower chimney sections inside the chimney.

[0029] On this basis, after the inner tube 2 of the upper and lower chimney sections are assembled, the opposite support frame of the outer tube 1 is removed, the hook is slowly lowered, and then the outer tube 1 of the upper and lower chimney sections is assembled and bolted.

[0030] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A self-supporting inner and outer tube steel chimney construction method, characterized in that: This method is a method for assembling the ladder platform and temporary operating platform of each section of the chimney on the ground, and the installation method of the high-altitude assembly of each section of the chimney, including: Step 1: Construction preparation: reserve temporary operating platform hanging points on each section of the chimney, make temporary hanging temporary operating platforms, and assemble ladder platforms on each section of the chimney; Step 2: Ladder platform installation: Install the above-ground part of the ladder platform of each section of the chimney on the ground; Step 3: High-altitude assembly: hoist each section of the chimney into place in order from bottom to top; including: After each section of the chimney is lifted off the ground, the remaining section is installed below the installed ladder platform; Starting from the hoisting of the second section of the chimney, first install a temporary operating platform and a pair of opposite support frames at the outer periphery of the top of the first section of the chimney and at positions of 90° at the corresponding opposite flange surfaces; When the last section of the chimney is hoisted in a vertical state, the damper, aviation warning light and circular platform are assembled.

2. A self-supporting inner-outer tube steel chimney construction method as claimed in claim 1, characterized in that: In the step 1, when placing the various sections of the chimney, a space for installing the ladder platform is reserved, and the installation connecting plates of the ladder platforms of the various sections of the chimney are reserved at appropriate positions.

3. A self-supporting inner and outer tube steel chimney construction method as claimed in claim 1 or 2, characterized in that: In the step three, before the chimney sections are hoisted, the base surfaces of the chimney sections are processed and the shim groups are placed as required, and then the top inner tube limit is checked to ensure that the inner tube is not stuck and can be freely rotated at a certain angle.

4. A self-supporting inner-outer tube steel chimney construction method as claimed in claim 3, characterized in that: When installing the temporary operating platform and the opposite support frame, process the flange sealing surface, apply sealant, and install packing.

5. A self-supporting inner-outer tube steel chimney construction method as claimed in claim 1 or 4, characterized in that: During the construction preparation in step 1, four limiting structures are arranged between the inner cylinder and the outer cylinder of each section of the chimney. The limiting structures are arranged to include a "U"-shaped outer cylinder limiting frame preset on the inner wall of the outer cylinder and an inner cylinder support preset on the outer wall of the inner cylinder, so that there is a certain relative displacement between the inner cylinder and the outer cylinder of each section of the chimney in the four directions of up, down, left and right.

6. A self-supporting inner and outer tube steel chimney construction method as claimed in claim 5, characterized in that: When the chimney sections are hoisted, the hoisting points are set on the outer tube, and when the chimney sections are in a vertical state, the inner tube support will move downward in the outer tube limit frame, so that the inner tube moves downward and the bottom end is exposed 400mm from the outer tube.

7. A self-supporting inner-outer tube steel chimney construction method as claimed in claim 1 or 6, characterized in that: Starting from the hoisting of the second section of the chimney, after the inner tube of the hoisted chimney section contacts the inner tube of the previous chimney section, the main hoist slowly drops the hook, so that the outer tube of the hoisted chimney section is placed on the opposite support frame of the previous chimney section. The opposite support frame is 400mm high, forming a passage for personnel to enter the inner tubes of the upper and lower chimney sections inside the chimney.

8. A self-supporting inner-outer tube steel chimney construction method as claimed in claim 7, characterized in that: After the inner tubes of the upper and lower chimney sections are assembled, the opposite support frame of the outer tube assembly is removed, the hook is slowly lowered, and then the outer tubes of the upper and lower chimney sections are assembled and bolted.