Route test system and method for deep well drilling rig power head

By designing the test system for the power head of the deep well drilling rig, using pressurization and power mechanism combined with locking components, the safety risks and low efficiency in the sealing performance detection of the power head are solved, and efficient and safe sealing performance detection is achieved.

CN119085947APending Publication Date: 2024-12-06ZRIME GEARING TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411459901.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-18
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The lack of targeted detection systems in the prior art leads to safety risks and inefficiency in sealing performance testing of deep well drilling rigs, especially since the height of the power head is close to 2 meters, staff need to frequently adjust the operating height during assembly, which is inconvenient to operate. Potential safety hazards.

Method used

A routine test system for the power head of a deep well drilling rig is designed, including a pressurization mechanism, a power mechanism and a fixing mechanism. High-pressure oil is applied to the hollow spindle through a hydraulic station, and the hollow spindle is driven by a motor to rotate, combining the locking assembly and fixing frame. , realize the flip and fixation of the power head, reduce the assembly height, and improve detection efficiency and safety.

Benefits of technology

It realizes targeted detection of the sealing performance of the power head, reduces safety risks and operation difficulties during the assembly process, improves work efficiency, and ensures the reliability of the sealing performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119085947A_ABST
    Figure CN119085947A_ABST
Patent Text Reader

Abstract

The invention discloses a routine test system and method for a deep well drilling rig power head, and relates to the field of power head sealing performance detection, the power head comprises a hollow main shaft and a gear reduction box used for driving the hollow main shaft to rotate, and the test system comprises a pressurization mechanism, a power mechanism and a fixing mechanism; the pressurizing mechanism comprises a hydraulic station, a plug and a sealing cover plate, an oil injection hole is formed in the sealing cover plate, and the plug comprises a threaded section used for being inserted into the hollow main shaft and a blocking shoulder located outside the hollow main shaft; the fixing mechanism comprises two fixing frames arranged at intervals, each fixing frame is rotatably provided with a connecting assembly, each connecting assembly comprises a flange plate and a rotating shaft fixed to the outer side of the corresponding flange plate, the inner sides of the two flange plates are oppositely arranged to form an installation space used for fixing a power head to be tested, and the rotating shafts are rotatably installed on the fixing frames. A locking assembly capable of limiting rotation of the rotating shaft is arranged between the fixing frame and the flange plate. The device is used for carrying out targeted routine test detection on the drilling machine power head.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of sealing detection of power heads, in particular to a routine test system and method for a power head of a deep well drilling rig. Background Art

[0002] The power head is the core component of the deep well drilling rig. It is driven by a hydraulic motor to drive a first-stage spur gear reduction mechanism, which is output through the hollow main shaft and transmits power to the drill rod, drill bit, etc. to achieve drilling operations. The high-pressure cuttings flow (25MPa) generated by the operation passes through the inner cavity of the hollow main shaft from bottom to top and is discharged through the external connection components. Therefore, the sealing performance of the power head is particularly important in practical applications.

[0003] In order to test the sealing performance of the deep well drilling rig power head, it needs to be pressurized. Since the total height of the power head after assembly is close to 2 meters, the staff needs to frequently adjust the working height during the pressure test, which poses certain safety risks and low work efficiency. At present, there is a lack of test systems for targeted detection of drilling rig power heads. Summary of the invention

[0004] The present invention aims to provide a routine test system and method for a deep well drilling rig power head, so as to carry out targeted routine test and detection on the drilling rig power head.

[0005] In order to achieve the above-mentioned purpose, the specific scheme adopted by the present invention is: a routine test system of a power head of a deep well drilling rig, the power head includes a hollow main shaft and a gear reduction box for driving the hollow main shaft to rotate, the test system includes a pressurizing mechanism for applying high pressure to the inner cavity of the hollow main shaft, a power mechanism for driving the gear reduction box and a fixing mechanism for fixing the power head to be tested;

[0006] The pressurizing mechanism includes a hydraulic station, a plug and a sealing cover plate. The plug and the sealing cover plate are respectively sealed at both ends of the hollow main shaft. The sealing cover plate is provided with an oil filling hole connected with the hydraulic station. The plug includes a threaded section for inserting into the hollow main shaft and a shoulder located outside the hollow main shaft. A sealing groove is provided on a side of the shoulder facing the hollow main shaft.

[0007] The fixing mechanism includes two fixed frames arranged at intervals, each of which is rotatably provided with a connecting assembly, the connecting assembly including a flange and a rotating shaft fixed on the outside of the flange, the inner sides of the two flanges are arranged facing each other to form an installation space for fixing the power head to be tested, the rotating shaft is rotatably installed on the fixed frame, and a locking assembly capable of limiting the rotation of the rotating shaft is arranged between the fixed frame and the flange.

[0008] As a further optimization of the above technical solution: the locking assembly includes a locking bolt, at least one first positioning hole opened on the fixing frame and a plurality of second positioning holes opened on the flange at intervals, and the first positioning hole is located on the rotation trajectory of the second positioning hole around the rotating axis.

[0009] As a further optimization of the above technical solution: the second positioning hole is a strip-shaped hole.

[0010] As a further optimization of the above technical solution: the fixing frame includes a bracket and a mounting plate arranged on the bracket, the mounting plate is provided with an arc groove for installing the rotating shaft, and the first positioning hole is provided on the mounting plate.

[0011] As a further optimization of the above technical solution: the bracket includes legs and a mounting surface, and the mounting plate is arranged on the mounting surface.

[0012] As a further optimization of the above technical solution: an oil filling joint is arranged in the oil filling hole, and the end of the oil outlet pipe of the hydraulic station is connected with the oil inlet end of the oil filling joint.

[0013] As a further optimization of the above technical solution: the power mechanism is a drive motor, and the drive motor and the gear reduction box are connected through a belt drive.

[0014] As a further optimization of the above technical solution: it also includes a control mechanism, and the pressurizing mechanism and the power mechanism are both connected to the control structure.

[0015] A routine test method for a deep well drilling rig power head comprises the following steps:

[0016] S1: Place the power head between two fixing frames, and fix the two sides of the gear reducer to the flanges of the two fixing mechanisms respectively;

[0017] S2: Turn the power head to adjust the inclination angle of the hollow spindle:

[0018] When the lower end of the hollow spindle is adjusted to the target height, the flange and the fixing frame are locked, and the lower end of the hollow spindle is sealed with a plug;

[0019] When the upper end of the hollow spindle is adjusted to the target height, the flange and the fixing frame are locked, the upper end of the hollow spindle is sealed with a sealing cover plate, and the oil filling holes of the hydraulic station and the sealing cover plate are connected;

[0020] S3: Apply high-pressure oil to the hollow spindle through the hydraulic station and start the power mechanism;

[0021] S4: Maintain pressure and observe whether the high-pressure oil in the hollow spindle leaks.

[0022] As a further optimization of the above technical solution: whether the high-pressure oil in the hollow main shaft is leaking is detected by a leakage detector.

[0023] Compared with the prior art, the present invention has the following beneficial effects:

[0024] The present invention provides a routine test system for a deep well drilling rig power head. The power head can be assembled on a fixing mechanism, and hydraulic oil is transported into a hollow main shaft of the power head through a hydraulic station. The hollow main shaft is driven to rotate by a motor to simulate the working state of the hollow main shaft during actual drilling operations, thereby performing targeted testing on the sealing performance of the power head.

[0025] The power head fixing mechanism in the present invention can realize the flipping and fixing of the power head, alleviating the problem of excessive assembly height. Since the total height of the power head is close to 2 meters, during the assembly process, the staff needs to install a plug on its lower end and then install a sealing cover plate on its upper end. Therefore, when installing the sealing cover plate on the upper end, the staff needs to move to a higher position, which is inconvenient to operate and has potential safety risks. The present invention rotatably sets the power head on the fixing mechanism, and during the assembly process, the part to be assembled can be adjusted to a lower position, and then the power head is fixed by the locking assembly, which is convenient for the staff to perform assembly operations. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a connection schematic diagram of the test system of the present invention;

[0027] Figure 2 It is a structural schematic diagram of the fixing mechanism;

[0028] Figure 3 It is a structural schematic diagram of the flange;

[0029] Figure 4 is a schematic diagram of the structure of the connection components;

[0030] Figure 5 is a side cross-sectional schematic diagram of a sealing cover plate;

[0031] Figure 6 It is a structural schematic diagram of the plug;

[0032] Figure 7 is a side cross-sectional schematic diagram of a pulley coupling;

[0033] Reference numerals: 1, hydraulic station, 2, fixing mechanism, 201, fixing frame, 2011, outrigger, 2012, mounting surface, 2013, connecting cross bar, 2014, connecting longitudinal bar, 2015, diagonal brace, 202, locking bolt, 203, fixing bolt, 204, flange, 205, mounting plate, 206, arc groove, 207, rotating shaft, 208, second positioning hole, 209, first positioning hole, 3, plug, 301, threaded section, 302, Shoulder block, 303, sealing groove, 4, motor, 5, first pulley, 6, control mechanism, 7, pulley coupling, 701, second pulley, 703, end cover, 704, bearing, 705, support frame, 706, first sealing ring, 707, second sealing ring, 8, sealing cover plate, 801, cover plate body, 802, oil filling hole, 803, oil filling joint, 9, transmission belt, 10, power head, 101, gear reduction box, 102, hollow main shaft. DETAILED DESCRIPTION

[0034] The technical solution of the present invention is further elaborated in detail below in conjunction with specific embodiments. The parts that are not described and disclosed in detail in the following embodiments of the present invention should be understood as the existing technologies known or should be known to those skilled in the art, such as the way in which the gear reducer drives the hollow main shaft to rotate, the way in which the control mechanism controls the hydraulic station and the motor, etc.

[0035] Example 1

[0036] See also Figure 1 The present invention discloses a routine test system for a deep well drilling rig power head, wherein the power head 10 comprises a hollow main shaft 102 and a gear reduction box 101 for driving the hollow main shaft 102 to rotate. The routine test system of the present invention is mainly used to detect the sealing performance of the hollow main shaft 102 in the power head 10. The test system comprises a pressurizing mechanism for applying high pressure to the inner cavity of the hollow main shaft 102, a power mechanism for driving the gear reduction box 101, a fixing mechanism 2 for fixing the power head 10 to be tested, and a control mechanism 6 for controlling the test process.

[0037] Specifically, the pressurizing mechanism includes a hydraulic station 1, a plug 3 and a sealing cover plate 8, and the plug 3 and the sealing cover plate 8 are respectively sealed at both ends of the hollow main shaft 102. Figure 1 , 5As shown, the sealing cover plate 8 is sealed at the upper end of the hollow main shaft 102, and an oil filling hole 802 connected to the hydraulic station 1 is provided on the cover plate body 801 of the sealing cover plate 8, and an oil filling joint 803 is provided in the oil filling hole 802, and the end of the oil outlet pipe of the hydraulic station 1 is connected to the oil inlet end of the oil filling joint 803. Since the hollow main shaft 102 will rotate due to the drive of the gear reducer 101 during the test, a dynamic sealing joint is provided at the connection between the end of the oil outlet pipe of the hydraulic station 1 and the oil filling joint 803. The specific dynamic sealing joint is a commercially available product, and its structure is a prior art, which will not be described in detail here.

[0038] The plug 3 is sealed at the lower end of the hollow main shaft 102. Figure 6 As shown, the plug 3 includes a cylindrical threaded section 301 and a shoulder 302 arranged at one end of the threaded section 301 and coaxial with the threaded section 301. The thread of the threaded section 301 is an external thread, and the lower end of the hollow main shaft 102 is provided with an internal thread used in conjunction with the threaded section 301. The diameter of the threaded section 301 gradually decreases in the direction away from the shoulder 302, so as to be screwed into the hollow main shaft 102 and inserted into the hollow main shaft 102; the shoulder 302 is cylindrical, and its diameter is larger than the diameter of the threaded section 301. The thickness of the shoulder 302 is not limited, and it only needs to have a certain thickness to enable it to be located outside the hollow main shaft 102. A sealing groove 303 is provided on the side of the shoulder 302 facing the hollow main shaft 102. When the threaded section 301 is inserted into the hollow main shaft 102, a sealing strip or a sealing gasket is installed in the sealing groove 303 to improve the sealing effect of the plug 3 on the lower end of the hollow main shaft 102.

[0039] Continue to refer to Figure 1 , 2 The fixing mechanism 2 includes two fixing frames 201 arranged in parallel and at intervals. Both fixing frames 201 are rectangular frames, and the two fixing frames 201 are arranged vertically. A connecting component is rotatably arranged on each fixing frame 201. Figure 4 As shown, the connecting assembly includes a flange 204 and a rotating shaft 207 fixed on the outside of the flange 204. The inner sides of the two flanges 204 are arranged to face each other to form an installation space for fixing the power head 10 to be tested. When the test system is in use, the two flanges 204 are respectively fixed on both sides of the gear reducer 101 of the power head 10. The flange 204 and the gear reducer 101 are fixed by fixing bolts 203. The power head 10 can rotate around the rotating shaft 207 with the flange 204. When installing the power head 10, the installation position of the flange 204 on the gear reducer 101 is controlled so that the rotation axis of the rotating shaft 207 roughly coincides with the center of gravity of the power head 10, which can reduce the turning resistance. In the subsequent process of adjusting the angle of the power head 10, the power head 10 can be manually pushed to rotate around the rotating shaft 207.

[0040] The rotating shaft 207 is rotatably mounted on the fixing frame 201, and a locking assembly capable of limiting the rotation of the rotating shaft 207 is arranged between the fixing frame 201 and the flange 204. When the locking assembly is locked, the power head 10 remains fixed on the fixing mechanism 2. After the locking assembly is unlocked, the power head 10 can rotate around the rotating shaft 207.

[0041] As a specific arrangement of the locking assembly, the locking assembly includes a locking bolt 202, at least one first positioning hole 209 provided on the fixing frame 201, and a plurality of second positioning holes 208 provided at intervals on the flange 204, wherein the first positioning hole 209 is located on a rotation track of the second positioning hole 208 rotating around the rotating shaft 207. When the first positioning hole 209 and the second positioning hole 208 are aligned, the locking bolt 202 sequentially passes through the first positioning hole 209 and the second positioning hole 208, thereby locking the flange 204 on the fixing frame 201, thereby fixing the power head 10 at the current position.

[0042] like Figure 3 As shown, the second positioning hole 208 is a long hole, which can be easily matched with the first positioning hole 209. Only a part of the opening area of ​​the long hole needs to be aligned with the first positioning hole 209 to pass the locking bolt 202. The locking bolt 202 can be tightened to lock the position of the flange 204 on the fixing frame 201. Therefore, setting the second positioning hole 208 as a long hole can improve the work efficiency of the locking work.

[0043] The power mechanism for driving the gear reduction box 101 to move is the driving motor 4, and the driving motor 4 and the gear reduction box 101 are connected in transmission through the transmission belt 9. Specifically, a first pulley 5 is provided on the output shaft of the driving motor 4, and the first pulley 5 is connected in transmission with the pulley coupling 7 provided on the gear reduction box 101, so as to provide power for the operation of the gear reduction box 101.

[0044] As a specific structure of the pulley coupling 7, Figure 7 As shown, the pulley coupling 7 includes a transmission shaft 702 and a second pulley 701 arranged at one end of the transmission shaft 702, the second pulley 701 is connected to the first pulley 5 through a transmission belt 9, and the other end of the transmission shaft 702 is connected to the gear reduction box 101. The transmission shaft 702 is installed in a support frame 705 through a bearing 704 and an end cover 703, and the end cover 703 is fixed to the support frame 705 by bolt connection. A first sealing ring 706 is arranged between the transmission shaft 702 and the support frame 705, and a second sealing ring 707 is arranged between the transmission shaft 702 and the end cover 703. The support frame 705 is installed on the housing of the gear reduction box 101 by bolt connection, and the transmission shaft 702 is connected to the gear in the gear reduction box 101.

[0045] In addition, a pulley coupling of the prior art may also be used, and it is only necessary to ensure that the transmission connection between the gear reduction box 101 and the motor 4 can be achieved.

[0046] The control mechanism 6 is connected to the pressurizing mechanism and the power mechanism. The control mechanism 6 includes an integrated control console. The integrated control console centrally controls the start and stop, speed, and steering of the motor 4, as well as the start and stop and output oil pressure of the hydraulic station 1. All preset parameters and monitoring data are monitored in real time on the central control screen in the form of digital display.

[0047] Example 2

[0048] This embodiment further describes the structure of the fixing frame 201 based on the embodiment 1:

[0049] Continue reading Figure 1 , 2 The fixing frame 201 includes a bracket and a mounting plate 205 arranged on the bracket, the bracket includes a mounting surface 2012 and a plurality of legs 2011 for supporting the mounting surface 2012, in this embodiment, each bracket includes two legs 2011, a connecting beam is arranged at the upper ends of the two legs 2011, and the connection method between the connecting beam and the legs 2011 is welding; the cross section of the connecting beam is square, the upper surface of the connecting beam is the mounting surface 2012 of the bracket, and the mounting surface 2012 is a long strip.

[0050] The mounting plate 205 is a strip plate and is vertically arranged on the mounting surface 2012. The length direction of the mounting plate 205 is consistent with the length direction of the mounting surface 2012, and the plate surface of the mounting plate 205 and the mounting surface 2012 are perpendicular to each other. The lower end surface of the mounting plate 205 and the mounting surface 2012 are respectively provided with corresponding bolt holes, so the mounting plate 205 and the mounting surface 2012 are fixed by bolt connection. It can be understood that the mounting plate 205 and the mounting surface 2012 can also be fixed by other methods, such as welding. The upper end surface of the mounting plate 205 is provided with an arc groove 206 for mounting the rotating shaft 207, and the arc groove 206 is located in the middle of the mounting plate 205. The first positioning hole 209 of the locking assembly is provided on the plate body of the mounting plate 205. In this embodiment, two first positioning holes 209 are provided, and the two first positioning holes 209 are symmetrically arranged on both sides of the arc groove 206. Any first positioning hole 209 corresponds to the second positioning hole 208 to realize the locking of the locking assembly.

[0051] In order to improve the stability of the fixing frame 201, the fixing frame 201 is set on a fixed base, and the fixed base includes two parallel connecting cross bars 2013 and two parallel connecting longitudinal bars 2014. The two connecting longitudinal bars 2014 are set at the lower ends of two supporting legs 2011 of the same fixing frame 201, and the length of the two connecting longitudinal bars 2014 is greater than the distance between the two supporting legs 2011. The two connecting cross bars 2013 are set between the two corresponding supporting legs 2011 of the two fixing frames 201.

[0052] Furthermore, a diagonal brace 2015 is provided between the connecting cross bar 2013 and the supporting leg 2011 , thereby further improving the stability of the fixing frame 201 .

[0053] Example 3

[0054] This embodiment discloses a routine test method for a deep well drilling rig power head 10. The method is based on the test system described in Embodiment 1 or 2 and includes the following steps:

[0055] S1: The power head 10 is placed between two fixing frames 201, and both sides of the gear reduction box 101 are fixed to the flanges 204 of the two fixing mechanisms 2 respectively;

[0056] S2: Remove the locking bolt 202 from the first positioning hole 209 and the second positioning hole 208, and rotate the power head 10 to adjust the inclination angle of the hollow main shaft 102:

[0057] When the lower end of the hollow main shaft 102 is adjusted to the target height and the first positioning hole 209 and the second positioning hole 208 correspond, the locking bolt 202 is sequentially passed through the first positioning hole 209 and the second positioning hole 208 to lock the flange 204 and the fixing frame 201, and then the lower end of the hollow main shaft 102 is blocked with the plug 3; the power head 10 is continued to rotate, and when the upper end of the hollow main shaft 102 is adjusted to the target height and the first positioning hole 209 and the second positioning hole 208 correspond, the locking bolt 202 is again sequentially passed through the first positioning hole 209 and the second positioning hole 208 to lock the flange 204 and the fixing frame 201, and the upper end of the hollow main shaft 102 is blocked with the sealing cover plate 8, and the hydraulic station 1 is connected with the oil filling hole 802 of the sealing cover plate 8;

[0058] S3: Finally, the power head 10 is adjusted and fixed to the target tilt angle, high-pressure oil is applied to the hollow main shaft 102 through the hydraulic station 1 for pressurization test, and the power mechanism is started to keep the hollow main shaft 102 in a rotating state for test run;

[0059] S4: After the pressure in the hollow main shaft 102 is pressurized to stabilize, the pressure is maintained for 15-30 minutes to observe whether the high-pressure oil in the hollow main shaft 102 leaks. Specifically, the leakage of the high-pressure oil in the hollow main shaft 102 can be detected by a leakage detector, which is a commercially available product.

[0060] Since the total height of the power head 10 is close to 2 meters, during the assembly process, the staff needs to install the plug 3 on the lower end and then install the sealing cover 8 on the upper end. Therefore, when installing the sealing cover 8 on the upper end, the staff needs to move to a higher position, which is inconvenient to operate and has potential safety risks. Through the test method of the present invention, the power head 10 is rotatably set on the fixing mechanism 2, and the part to be assembled can be adjusted to a lower position during the assembly process, and then the power head 10 is fixed by the locking assembly, which is convenient for the staff to perform assembly operations.

[0061] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A routine test system for a deep well drilling rig power head, the power head (10) comprising a hollow main shaft (102) and a gear reduction box (101) for driving the hollow main shaft (102) to rotate, characterized in that: The test system comprises a pressurizing mechanism for applying high pressure to the inner cavity of a hollow main shaft (102), a power mechanism for driving a gear reduction box (101), and a fixing mechanism (2) for fixing a power head (10) to be tested; The pressurizing mechanism comprises a hydraulic station (1), a plug (3) and a sealing cover plate (8); the plug (3) and the sealing cover plate (8) are respectively sealed at two ends of the hollow main shaft (102); an oil injection hole (802) communicating with the hydraulic station (1) is provided on the sealing cover plate (8); the plug (3) comprises a threaded section (301) for inserting into the hollow main shaft (102) and a stop shoulder (302) located outside the hollow main shaft (102); a sealing groove (303) is provided on a side of the stop shoulder (302) facing the hollow main shaft (102); The fixing mechanism (2) comprises two fixing frames (201) arranged at intervals, each fixing frame (201) being rotatably provided with a connecting assembly, the connecting assembly comprising a flange (204) and a rotating shaft (207) fixed on the outside of the flange (204), the inner sides of the two flanges (204) being arranged facing each other to form an installation space for fixing the power head (10) to be tested, the rotating shaft (207) being rotatably installed on the fixing frame (201), and a locking assembly capable of limiting the rotation of the rotating shaft (207) being arranged between the fixing frame (201) and the flange (204).

2. A routine test system for a deep well drilling rig power head as claimed in claim 1, characterized in that: The locking assembly comprises a locking bolt (202), at least one first positioning hole (209) provided on a fixing frame (201), and a plurality of second positioning holes (208) provided at intervals on a flange (204), wherein the first positioning hole (209) is located on a rotation trajectory of the second positioning hole (208) rotating around a rotating shaft (207).

3. A routine test system for a deep well drilling rig power head as claimed in claim 2, characterized in that: The second positioning hole (208) is a strip-shaped hole.

4. A routine test system for a deep well drilling rig power head as claimed in claim 2, characterized in that: The fixing frame (201) comprises a bracket and a mounting plate (205) arranged on the bracket, an arc groove (206) for mounting a rotating shaft (207) is provided on the mounting plate (205), and the first positioning hole (209) is provided on the mounting plate (205).

5. A routine test system for a deep well drilling rig power head as claimed in claim 4, characterized in that: The bracket comprises a support leg (2011) and a mounting surface (2012), and the mounting plate (205) is arranged on the mounting surface (2012).

6. A routine test system for a deep well drilling rig power head as claimed in claim 6, characterized in that: An oil filling joint (803) is arranged in the oil filling hole (802), and the end of the oil outlet pipe of the hydraulic station (1) is connected to the oil inlet end of the oil filling joint (803).

7. A routine test system for a deep well drilling rig power head as claimed in claim 1, characterized in that: The power mechanism is a driving motor (4), and the driving motor (4) and the gear reduction box (101) are connected via a belt drive.

8. A routine test system for a deep well drilling rig power head as claimed in claim 1, characterized in that: It also includes a control mechanism (6), and the pressurizing mechanism and the power mechanism are both connected to the control structure (6).

9. A routine test method for a deep well drilling rig power head, characterized in that: The method is based on the test system described in any one of claims 1 to 8, and comprises the following steps: S1: The power head (10) is placed between two fixing frames (201), and the two sides of the gear reduction box (101) are fixed to the flanges (204) of the two fixing mechanisms (2) respectively; S2: Rotate the power head (10) to adjust the tilt angle of the hollow main shaft (102): When the lower end of the hollow main shaft (102) is adjusted to a target height, the flange (204) and the fixing frame (201) are locked, and the lower end of the hollow main shaft (102) is sealed with a plug (3); When the upper end of the hollow main shaft (102) is adjusted to the target height, the flange (204) and the fixing frame (201) are locked, the upper end of the hollow main shaft (102) is sealed with a sealing cover plate (8), and the oil filling hole (802) of the hydraulic station (1) and the sealing cover plate (8) are connected; S3: applying high-pressure oil to the hollow main shaft (102) through the hydraulic station (1) and starting the power mechanism; S4: Maintain the pressure and observe whether the high-pressure oil in the hollow main shaft (102) leaks.

10. A routine test method for a deep well drilling rig power head (10) according to claim 9, characterized in that: In step S4, a leakage detector is used to detect whether the high-pressure oil in the hollow main shaft (102) is leaking.