Risk detection method and equipment for engineering project and medium

By obtaining business data of engineering projects, calculating risk scores using preset scoring rules, and generating risk detection results, the problems of low efficiency and insufficient accuracy of risk detection in the existing technology are solved, and more efficient and accurate risk detection is achieved.

CN119090267APending Publication Date: 2024-12-06WUHAN HUAXIN DATA SYST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411122826.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

In the prior art, the risk detection efficiency of engineering projects is low and inaccurate enough, and manual misjudgment is prone to occur, resulting in inaccurate risk detection results.

Method used

By obtaining business data under multiple business indicators of the project, determining the matching risk detection plan, calculating business risk scores using preset scoring rules, generating project risk scores, and then automatically generating risk detection results.

Benefits of technology

It improves the efficiency and accuracy of risk detection of engineering projects, and is more efficient and accurate than manual analysis methods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119090267A_ABST
    Figure CN119090267A_ABST
Patent Text Reader

Abstract

The invention provides an engineering project risk detection method and device and a medium. The engineering project risk detection method comprises the steps of obtaining a to-be-detected target engineering project; determining a target risk detection scheme matched with the target engineering project in a plurality of preset risk detection schemes; obtaining a plurality of different business indexes in the target risk detection scheme; service indexes existing in the target risk detection scheme and the target engineering project at the same time serve as target service indexes; determining a business risk score of business data under a target business index in the target engineering project by using a preset scoring rule associated with the target business index in the target risk detection scheme; determining a project risk score of the target engineering project based on the business risk scores of the business data under all the target business indexes; and generating a risk detection result of the target engineering project based on the project risk score. According to the invention, the efficiency and accuracy of risk detection of the engineering project are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of risk detection, and in particular to a method, equipment and medium for risk detection of an engineering project. Background Art

[0002] In the construction industry, in order to facilitate the management of engineering projects, the various project departments of the construction party generally report the business data such as construction period, technology, quality, business, finance, safety and materials in the engineering projects to the designated information platform. Relevant managers can view these business data on the information platform to make corresponding decisions and allocate resources.

[0003] However, engineering projects may face situations such as insufficient project payments and delayed project schedules, which may cause the construction party to bear too much risk. Therefore, it is necessary to detect the risks in engineering projects so that the construction party can take corresponding safety measures in a timely manner.

[0004] At present, risks in engineering projects are often discovered by manually analyzing business data in the information platform one by one. However, this manual analysis method is inefficient and prone to manual misjudgment when faced with a large number of engineering projects and a large amount of business data, resulting in inaccurate risk detection results. Summary of the invention

[0005] The embodiments of the present application provide a method, device and medium for risk detection of an engineering project, aiming to improve the efficiency and accuracy of risk detection of an engineering project.

[0006] In a first aspect, an embodiment of the present application provides a risk detection method for an engineering project, the risk detection method for an engineering project comprising: Acquire a target engineering project to be detected, wherein the target engineering project includes business data under multiple different business indicators; Determine a target risk detection scheme matching the target engineering project among a plurality of preset risk detection schemes; Acquire multiple different business indicators in the target risk detection scheme; Using the business indicators that exist in both the target risk detection scheme and the target engineering project as target business indicators; Determine the business risk score of the business data under the target business indicator in the target engineering project by using the preset scoring rule associated with the target business indicator in the target risk detection scheme; Determining a project risk score for the target engineering project based on the business risk scores of the business data under all the target business indicators; Based on the project risk score, a risk detection result of the target engineering project is generated.

[0007] In some embodiments of the present application, the use of the preset scoring rules associated with the target business indicator in the target risk detection scheme to determine the business risk score of the business data under the target business indicator in the target engineering project includes: When the business data under the target business indicator is structured data, quantitative calculation processing is performed on the business data under the target business indicator to obtain a numerical result, and a business risk score of the business data under the target business indicator is determined by using a preset scoring rule associated with the target business indicator in the target risk detection scheme and the numerical result; When the business data under the target business indicator is unstructured data, a qualitative analysis is performed on the business data under the target business indicator to obtain a text result, and a business risk score of the business data under the target business indicator is determined by using a preset scoring rule associated with the target business indicator in the target risk detection scheme and the text result.

[0008] In some embodiments of the present application, the quantitative calculation processing of the business data under the target business indicator to obtain a numerical result includes: Determine expected data of business data under the target business indicator; Determining the numerical result based on the ratio of the business data under the target business indicator to the expected data; The qualitative analysis of the business data under the target business indicator is performed to obtain text results, including: Determine, from among a plurality of preset text labels, a target text label corresponding to the business data under the target business indicator; Based on the target text label, the text result is determined.

[0009] In some embodiments of the present application, the business risk score of the target engineering project is determined based on the business risk score of the business data under all the target business indicators, including: In the target risk detection scheme, obtaining an indicator weight associated with each target business indicator; According to the indicator weights, weighted summing is performed on the business risk scores of the business data under all the target business indicators to obtain a weighted summing result; Based on the weighted summation result, the project risk score is determined.

[0010] In some embodiments of the present application, generating the risk detection result of the target engineering project based on the project risk score includes: Determine the business risk score with the largest value among the business risk scores of the business data under all the target business indicators; Determine the product of the sum of the indicator weights associated with each of the target business indicators and the business risk score with the largest value, and use it as the estimated maximum risk score of the target engineering project; Determining a ratio of the project risk score to the estimated maximum risk score; Based on the ratio, determining the risk level of the project; Based on the project risk level, a risk detection result of the target engineering project is generated.

[0011] In some embodiments of the present application, determining the project risk level based on the ratio includes: Obtaining the construction site of the target project; Determining a risk threshold of the target project based on the geographical area where the construction site is located; The project risk level is determined based on the relationship between the ratio and the risk threshold.

[0012] In some embodiments of the present application, determining the project risk score based on the weighted sum result includes: Determine the project delivery object of the target project; Obtaining the object level of the engineering project deliverable object; The weighted sum result is corrected using the risk score correction coefficient associated with the object level to obtain the project risk score.

[0013] In some embodiments of the present application, obtaining a target engineering project to be detected includes: Obtain the construction units to be inspected; All engineering projects undertaken by the construction unit are respectively regarded as the target engineering projects.

[0014] In a second aspect, an embodiment of the present application provides a risk detection device for an engineering project, the risk detection device for the engineering project comprising: A first acquisition module is used to acquire a target engineering project to be detected, wherein the target engineering project includes business data under multiple different business indicators; A first determination module is used to determine a target risk detection scheme matching the target engineering project from among a plurality of preset risk detection schemes; A second acquisition module is used to acquire a plurality of different business indicators in the target risk detection scheme; A second determination module is used to use the business indicators that exist in both the target risk detection scheme and the target engineering project as target business indicators; A third determination module is used to determine the business risk score of the business data under the target business indicator in the target engineering project by using the preset scoring rule associated with the target business indicator in the target risk detection scheme; A fourth determination module, configured to determine a project risk score of the target engineering project based on the business risk scores of the business data under all the target business indicators; The result generation module is used to generate the risk detection result of the target engineering project based on the project risk score.

[0015] In a third aspect, an embodiment of the present application provides an electronic device, the electronic device comprising: one or more processors; Memory; and One or more applications, wherein the one or more applications are stored in the memory and configured to be executed by the processor to implement any of the above-mentioned risk detection methods for engineering projects.

[0016] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium, characterized in that a computer program is stored thereon, and the computer program is loaded by a processor to execute the steps in the risk detection method for an engineering project described in any one of the above items.

[0017] In a fifth aspect, an embodiment of the present application provides a computer program product, including a computer program or instructions, which are executed by a processor to implement a risk detection method for an engineering project as described in any one of the above items.

[0018] Beneficial effects of the embodiments of the present application: In an embodiment of the present application, a target engineering project to be detected is obtained, a target risk detection scheme matching the target engineering project is determined, and business indicators that exist in both the target risk detection scheme and the target engineering project are used as target business indicators. The business risk score of the business data under the target business indicator in the target risk detection scheme is determined by using the preset scoring rules associated with the target business indicator in the target risk detection scheme. Based on the business risk score of the business data under all target business indicators, the project risk score of the target engineering project is determined, and then the risk detection result of the target engineering project is generated. The present application uses a preset target risk detection scheme to automatically generate the risk detection result of the target engineering project. Compared with the manual analysis method, the efficiency and accuracy of the risk detection of the engineering project are higher. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For those skilled in the art, other drawings can be obtained based on these drawings without creative work.

[0020] Figure 1 It is a schematic diagram of an embodiment of a risk detection method for an engineering project provided in an embodiment of the present application; Figure 2 It is a schematic diagram of another embodiment of the process flow of the risk detection method for an engineering project provided in the embodiments of the present application; Figure 3 It is a flow chart of another embodiment of the risk detection method for an engineering project provided in the embodiments of the present application; Figure 4 It is a schematic diagram of the structure of an embodiment of a risk detection device for an engineering project provided in an embodiment of the present application; Figure 5 It is a schematic diagram of the structure of an embodiment of an electronic device provided in the embodiments of the present application. DETAILED DESCRIPTION

[0021] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without making creative work are within the scope of protection of the present application. In addition, in the description of the present application, the meaning of "multiple" is two or more, unless otherwise clearly and specifically limited.

[0022] First, the risk detection method for an engineering project provided by the embodiment of the present application is introduced. The risk detection method for an engineering project uses a risk detection device for an engineering project as an execution subject. For the sake of simplicity and ease of description, the execution subject will be omitted in the subsequent method embodiments.

[0023] See also Figure 1 , Figure 1 The following is a flow chart of an embodiment of a method for detecting a risk of an engineering project provided in an embodiment of the present application. The method for detecting a risk of an engineering project includes: 101. Obtain a target engineering project to be inspected, where the target engineering project includes business data under multiple different business indicators.

[0024] In the embodiments of the present application, a project refers to a project in the construction industry that uses engineering construction as a carrier, with buildings or structures as target outputs, that requires payment of a certain fee, follows a certain procedure, is completed within a certain time, and must meet quality requirements. The target project to be tested is a project that needs to be tested for insufficient project collection, project delays, etc.

[0025] The business indicators in the target project may be business indicators in dimensions such as duration, technology, quality, business, finance, safety and materials in the target project. Each dimension may include multiple business indicators, and the business indicators in different dimensions are different. Taking the financial dimension as an example, the business indicators in the financial dimension of the target project may include business indicators such as project collection, project payment and fund balance. The business data under the business indicator refers to the specific data under the business indicator. For example, the business data under the project collection business indicator may be the specific amount of the project collection.

[0026] In some embodiments, since the same construction unit may undertake a large number of engineering projects, and a large number of engineering projects need to be subject to risk detection, in order to facilitate the risk detection of a large number of engineering projects, relevant personnel can select a single construction unit to perform risk detection of all engineering projects under the construction unit. Specifically, obtaining the target engineering project to be detected may include: obtaining the construction unit to be detected, and the construction unit to be detected may be manually selected by relevant personnel; taking all engineering projects undertaken by the construction unit as target engineering projects, respectively, and using different processes to execute step 102 and subsequent steps. It can be seen that in this embodiment, relevant personnel only need to select the construction unit to be detected to complete the risk detection of all engineering projects undertaken by the construction unit, which makes the user operation more convenient, avoids risk detection of engineering projects one by one, and improves the efficiency of risk detection.

[0027] 102. Determine a target risk detection scheme that matches the target engineering project among multiple preset risk detection schemes.

[0028] In the embodiment of the present application, based on the different actual risk situations of different engineering projects, a plurality of different risk detection schemes are pre-set. Each risk detection scheme includes a plurality of different business indicators, and the business indicators in different risk detection schemes are not completely the same.

[0029] The target risk detection scheme matching the target engineering project can be manually selected based on actual needs, or based on the project type to which the target engineering project belongs, a corresponding risk detection scheme can be determined and used as the target risk detection scheme.

[0030] 103. Obtain multiple different business indicators in the target risk detection plan.

[0031] 104. The business indicators that exist in both the target risk detection plan and the target engineering project shall be used as target business indicators.

[0032] In the embodiment of the present application, the business indicators that exist in both the target risk detection scheme and the target engineering project are the business indicators that need to be used for risk detection in the target engineering project, so these business indicators can be used as target business indicators for subsequent processing. Business indicators that exist in the target engineering project but do not exist in the target risk detection scheme do not need to be used for risk detection.

[0033] 105. Determine the business risk score of the business data under the target business indicator in the target engineering project by using the preset scoring rules associated with the target business indicator in the target risk detection plan.

[0034] In an embodiment of the present application, each risk detection scheme also includes a preset scoring rule associated with each business indicator in the risk detection scheme, and the preset scoring rule is used to calculate a corresponding business risk score based on business data.

[0035] 106. Based on the business risk score of the business data under all target business indicators, determine the project risk score of the target engineering project.

[0036] In the embodiment of the present application, the business risk scores of the business data under all target business indicators can be comprehensively calculated to obtain the project risk score of the target engineering project. For example, the business risk scores of the business data under all target business indicators can be summed up, and the summed result is used as the project risk score of the target engineering project. Of course, it is also possible to use Figure 3 The project risk score of the target engineering project is calculated by the steps in the illustrated embodiment, which is not limited here.

[0037] 107. Based on the project risk score, generate risk detection results for the target engineering project.

[0038] In an embodiment of the present application, the risk detection result of the target engineering project may include a project risk score, and may also include business data and its business risk score under each target business indicator or business data and its business risk score under an abnormal target business indicator, wherein an abnormal target business indicator refers to a target business indicator whose business risk score is greater than a preset score. Of course, the risk detection result of the target engineering project may also include other information further determined based on the project risk score, such as the project risk level of the target engineering project, such as normal, deviation, severe deviation, etc.

[0039] In some embodiments, after the risk detection result of the target engineering project is generated, the risk detection result may also be output to a preset terminal so that relevant personnel of the preset terminal can take corresponding measures in time to reduce the risk of the target engineering project.

[0040] It can be seen that in the above embodiments of the present application, a preset target risk detection scheme is used to automatically generate risk detection results for target engineering projects. Compared with manual analysis, the efficiency and accuracy of risk detection of engineering projects are higher.

[0041] In some embodiments of the present application, Figure 2 As shown, in Figure 1 Based on the illustrated embodiment, the business risk score of the business data under the target business indicator in the target engineering project is determined by using the preset scoring rules associated with the target business indicator in the target risk detection scheme, which may include: 201. When the business data under the target business indicator is structured data, the business data under the target business indicator is quantitatively calculated and processed to obtain a numerical result, and the business risk score of the business data under the target business indicator is determined by using the preset scoring rules associated with the target business indicator in the target risk detection scheme and the numerical result.

[0042] In the embodiments of the present application, the forms of business data under different target business indicators may be different. For example, the business data under some target business indicators are structured data, and the business data under some target business indicators are unstructured data. Therefore, different forms of business data need to be processed differently. Taking structured data as an example, the business data under the target business indicator can be quantitatively calculated and processed to obtain numerical results, and then the preset scoring rules and numerical results associated with the target business indicator in the target risk detection scheme are used to determine the business risk score of the business data under the target business indicator. Among them, structured data can refer to data composed of numbers and values, and unstructured data can include text, pictures, audio, video, etc.

[0043] In some embodiments, quantitative calculation processing is performed on business data under the target business indicator to obtain numerical results, which may include: determining expected data of the business data under the target business indicator, wherein the expected data is pre-set based on previous data of the project, and taking the business data under the target business indicator as the specific amount of project collection as an example, the expected data is the expected amount of project collection; taking the business data under the target business indicator as the number of start days of the project as an example, the expected data is the number of days of the contractual construction period of the project, or the expected data is a pre-set standard threshold; based on the ratio of the business data under the target business indicator to the expected data, determining the numerical result, for example, the ratio of the business data under the target business indicator to the expected data may be used as the completion rate of the target business indicator, and the completion rate may be used as the numerical result of the quantitative calculation processing.

[0044] In some embodiments, determining the business risk score of business data under the target business indicator by using the preset scoring rules and numerical results associated with the target business indicator in the target risk detection scheme may include: obtaining multiple different numerical intervals in the preset scoring rules associated with the target business indicator in the target risk detection scheme, and different data intervals correspond to different business risk scores. Taking the completion rate of the target business indicator as an example, the multiple different numerical intervals include a numerical interval with a completion rate less than 60%, a numerical interval with a completion rate greater than or equal to 60% and less than 80%, and a numerical interval with a completion rate greater than or equal to 80%. The numerical interval with a completion rate less than 60% indicates that the target business indicator has a serious deviation, and its corresponding business risk score is 2. The numerical interval with a completion rate greater than or equal to 60% and less than 80% indicates that the target business indicator has a deviation, and its corresponding business risk score is 1. The numerical interval with a completion rate greater than or equal to 80% indicates that the target business indicator is normal, and its corresponding business risk score is 0; comparing the numerical result with the multiple different numerical intervals to determine the numerical interval where the numerical result is located; and using the business risk score corresponding to the numerical interval where the numerical result is located as the business risk score of the business data under the target business indicator. The risk detection results of the target engineering project may also include information such as whether the target business indicators are seriously deviated, deviated, or normal.

[0045] In other embodiments of the present application, the business risk score of the business data under the target business indicator in the target engineering project is determined by using the preset scoring rules associated with the target business indicator in the target risk detection scheme, which may also include: when the business data under the target business indicator is unstructured data, the business data under the target business indicator is qualitatively analyzed and processed to obtain text results, and the business risk score of the business data under the target business indicator is determined by using the preset scoring rules associated with the target business indicator in the target risk detection scheme and the text results. Among them, the unstructured business data, such as the project safety status and project technical plan described in the target business indicator.

[0046] In some embodiments, qualitative analysis and processing of business data under the target business indicator to obtain text results may include: determining the target text label corresponding to the business data under the target business indicator from a plurality of preset text labels, for example, by extracting key information from the business data under the target business indicator, and corresponding the key information to the target text label, such as key information such as keywords, key words, etc., and for example, identifying the target text label corresponding to the business data under the target business indicator through a preset recognition model of unstructured data, such as a text semantic recognition model, an image recognition model, an audio recognition model, a video recognition model, etc., and the preset plurality of text labels may be, for example, text labels such as normal, deviation, and severe deviation; based on the target text label, determining the text result, for example, the target text label may be directly used as the text result. The risk detection result of the target engineering project may also include the target text label.

[0047] In some embodiments, determining the business risk score of business data under the target business indicator using the preset scoring rules and text results associated with the target business indicator in the target risk detection scheme may include: obtaining business risk scores corresponding to multiple different preset text results in the preset scoring rules associated with the target business indicator in the target risk detection scheme, the multiple different preset text results including preset text results such as normal, deviation, and severe deviation, taking the preset text result of normal as an example, the corresponding business risk score is 0, taking the preset text result of deviation as an example, the corresponding business risk score is 1, and taking the preset text result of severe deviation as an example, the corresponding business risk score is 2; comparing the text result with multiple different preset text results to determine the business risk score corresponding to the preset text result that is the same as the text result; using the business risk score corresponding to the preset text result that is the same as the text result as the business risk score of the business data under the target business indicator.

[0048] It can be seen that in the above embodiments of the present application, different methods are used to determine corresponding business risk scores for structured and unstructured business data, respectively, so that risk detection of target engineering projects is more convenient.

[0049] In some embodiments of the present application, Figure 3 As shown, in Figure 1 or Figure 2 On the basis of the illustrated embodiment, determining the project risk score of the target engineering project based on the business risk scores of the business data under all target business indicators may include: 301. In the target risk detection scheme, obtain the indicator weight associated with each target business indicator.

[0050] In the embodiment of the present application, in the target risk detection scheme, since different target business indicators have different degrees of influence on the target engineering project, corresponding indicator weights can be pre-associated with different target business indicators. The larger the indicator weight, the greater the influence of the corresponding target business indicator on the target engineering project. For example, the indicator weight associated with target business indicator A is 2, the indicator weight associated with target business indicator B is 3, the indicator weight associated with target business indicator C is 3, the indicator weight associated with target business indicator D is 5, and the indicator weight associated with target business indicator E is 1.

[0051] 302. Perform weighted sum processing on the business risk scores of the business data under all target business indicators according to the indicator weights to obtain a weighted sum result.

[0052] In an embodiment of the present application, after obtaining the business risk scores of the business data under all target business indicators, the indicator weights associated with the corresponding target business indicators are used for weighted sum calculation. Taking the business risk score of the business data under target business indicator A as 1, the business risk score of the business data under target business indicator B as 0, the business risk score of the business data under target business indicator C as 2, the business risk score of the business data under target business indicator D as 1, and the business risk score of the business data under target business indicator E as 0 as an example, the weighted sum result is 13.

[0053] 303. Determine the project risk score based on the weighted summation result.

[0054] In the embodiments of the present application, the weighted sum result can be directly used as the project risk score, or the project risk score can be further calculated based on the weighted sum result, which is not limited here.

[0055] In some embodiments, determining a project risk score based on a weighted summation result may include: determining a project delivery object of a target project, where the project delivery object is the object to which the construction party needs to deliver the target project after completing the target project; obtaining the object level of the project delivery object, where the object level of the project delivery object may be pre-set; and correcting the weighted summation result using a risk score correction coefficient associated with the object level to obtain a project risk score. Generally speaking, the higher the object level, the greater the risk score correction coefficient associated with the object level, and the greater the final project risk score, thereby making the risk detection of the target project for the corresponding project delivery object more accurate and reasonable.

[0056] In some embodiments, generating a risk detection result for a target engineering project based on a project risk score may include: determining a business risk score with the largest value among the business risk scores of the business data under all target business indicators. For example, in the above example, the business risk score with the largest value is 2, which is the business risk score of the business data under the target business indicator C; determining the product of the sum of the indicator weights associated with each target business indicator and the business risk score with the largest value, and using it as the estimated maximum risk score for the target engineering project. For example, in the above example, the sum of the indicator weights associated with each target business indicator is 2+3+3+5+1=14, so the estimated maximum risk score for the target engineering project is 14. ×2=28; determine the ratio of the project risk score to the estimated maximum risk score, such as 13 / 28; based on the ratio, determine the project risk level, such as multiple ratio intervals are preset, and different ratio intervals correspond to different project risk levels, such as normal, deviation, severe deviation, etc. Taking the ratio of 13 / 28 as an example, the ratio interval of the ratio is 0.3 to 0.5, and the corresponding project risk level is deviation; based on the project risk level, generate the risk detection results of the target engineering project, such as the risk level of the project can be included in the risk detection results, so that relevant personnel can take corresponding measures in time based on the project risk level to reduce the risk of the target engineering project.

[0057] In some embodiments, determining the project risk level based on the ratio may include: obtaining the construction site of the target project; determining the risk threshold of the target project based on the geographical area where the construction site is located, and different geographical areas have different corresponding risk thresholds. It can be understood that since the target project in a more important geographical area is also more important, it is necessary to conduct more stringent risk detection on the target project, so the risk threshold corresponding to the geographical area with a higher regional importance level is lower; determining the project risk level based on the relationship between the ratio and the risk threshold, taking the risk threshold of 0.3 as an example, when the ratio is less than 0.3, the project risk level is determined to be normal, and taking the risk threshold of 0.5 as an example, when the ratio is greater than or equal to 0.5, the project risk level is determined to be a serious deviation. It can be seen that determining the corresponding risk threshold based on the geographical area where the construction site of the target project is located can make the risk detection of the target project more accurate and reasonable.

[0058] In some embodiments, after determining the project risk level based on the ratio, the following may also be included: if the project risk level is the target level, determining the construction unit and the project delivery object of the target project, the target level is, for example, the level of severe deviation; obtaining all the projects between the construction unit and the project delivery object of the target project; among all the projects, determining the projects with the target risk level; calculating the proportion of the number of projects with the target risk level relative to the number of all the projects; if the proportion is greater than the preset proportion, it indicates that all the projects between the construction unit and the project delivery object of the target project may have a relatively large deviation. Therefore, all projects between the construction unit of the target project and the project delivery object can be regarded as projects with risks, where the value of the preset ratio is determined based on the object level of the project delivery object. The higher the object level of the project delivery object, the smaller the value of the preset ratio. The object level of the project delivery object can be preset; the corresponding prompt information of the project with risks is generated and output to the preset terminal, so that the relevant personnel of the preset terminal can timely manually check all projects between the construction unit of the target project and the project delivery object, and take corresponding measures in time to further reduce the risk of the project as a whole. Compared with the method of manually analyzing all projects, this risk detection method is more efficient and accurate.

[0059] In order to better implement the risk detection method for engineering projects in the embodiment of the present application, on the basis of the risk detection method for engineering projects, the embodiment of the present application also provides a risk detection device for engineering projects. Figure 4 As shown, the risk detection device 400 for an engineering project includes: The first acquisition module 401 is used to acquire a target engineering project to be detected, wherein the target engineering project includes business data under multiple different business indicators; A first determination module 402 is used to determine a target risk detection scheme matching the target engineering project from among a plurality of preset risk detection schemes; The second acquisition module 403 is used to acquire a plurality of different business indicators in the target risk detection scheme; A second determination module 404 is used to use the business indicators that exist in both the target risk detection solution and the target engineering project as target business indicators; A third determination module 405 is used to determine the business risk score of the business data under the target business indicator in the target engineering project by using the preset scoring rule associated with the target business indicator in the target risk detection scheme; A fourth determination module 406 is configured to determine a project risk score of the target engineering project based on the business risk scores of the business data under all the target business indicators; The result generation module 407 is used to generate a risk detection result of the target engineering project based on the project risk score.

[0060] In addition to the above-mentioned project risk detection method and device, the embodiment of the present application also provides an electronic device, which integrates any project risk detection device provided in the embodiment of the present application, such as a PC, a mobile phone, a server, etc. The electronic device includes: one or more processors; Memory; and One or more applications, wherein the one or more applications are stored in a memory and are configured to execute, by a processor, the steps of any one of the embodiments of the risk detection method for an engineering project.

[0061] The present application also provides an electronic device that integrates any of the engineering project risk detection devices provided in the present application. Figure 5 As shown, it shows a schematic diagram of the structure of the electronic device involved in the embodiment of the present application, specifically: The electronic device may include one or more processors 501 of processing cores, one or more computer-readable storage media storage units 502, a power supply 503, an input unit 504 and other components. Those skilled in the art will appreciate that Figure 5 The electronic device structure shown in the figure does not constitute a limitation on the electronic device, and may include more or fewer components than shown in the figure, or combine certain components, or arrange the components differently. The processor 501 is the control center of the electronic device. It uses various interfaces and lines to connect various parts of the entire electronic device. By running or executing software programs and / or modules stored in the storage unit 502 and calling data stored in the storage unit 502, it executes various functions of the electronic device and processes data, thereby monitoring the electronic device as a whole. Optionally, the processor 501 may include one or more processing cores; preferably, the processor 501 may integrate an application processor and a modem processor, wherein the application processor mainly processes the operating system, user interface, and application programs, and the modem processor mainly processes wireless communications. It is understandable that the above-mentioned modem processor may not be integrated into the processor 501.

[0062] The storage unit 502 can be used to store software programs and modules. The processor 501 executes various functional applications and data processing by running the software programs and modules stored in the storage unit 502. The storage unit 502 may mainly include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function (such as a sound playback function, an image playback function, etc.), etc.; the data storage area may store data created according to the use of the electronic device, etc. In addition, the storage unit 502 may include a high-speed random access memory, and may also include a non-volatile memory, such as at least one disk storage device, a flash memory device, or other volatile solid-state storage devices. Accordingly, the storage unit 502 may also include a memory controller to provide the processor 501 with access to the storage unit 502.

[0063] The electronic device also includes a power supply 503 for supplying power to each component. Preferably, the power supply 503 can be logically connected to the processor 501 through a power management system, so as to manage charging, discharging, power consumption and other functions through the power management system. The power supply 503 can also include one or more DC or AC power supplies, recharging systems, power failure detection circuits, power converters or inverters, power status indicators and other arbitrary components.

[0064] The electronic device may further include an input unit 504, which may be used to receive input digital or character information and generate keyboard, mouse, joystick, optical or trackball signal input related to user settings and function control.

[0065] Although not shown, the electronic device may also include a display unit, etc., which will not be described in detail here. Specifically, in the embodiment of the present application, the processor 501 in the electronic device will load the executable file corresponding to the process of one or more application programs into the storage unit 502 according to the following instructions, and the processor 501 will run the application program stored in the storage unit 502, thereby implementing the steps in any of the risk detection methods for engineering projects provided in the embodiment of the present application, for example: Obtain a target engineering project to be detected, the target engineering project includes business data under multiple different business indicators; determine a target risk detection scheme matching the target engineering project among multiple preset risk detection schemes; obtain multiple different business indicators in the target risk detection scheme; use business indicators that exist in both the target risk detection scheme and the target engineering project as target business indicators; determine the business risk score of the business data under the target business indicator in the target engineering project by using preset scoring rules associated with the target business indicator in the target risk detection scheme; determine the project risk score of the target engineering project based on the business risk score of the business data under all target business indicators; and generate a risk detection result for the target engineering project based on the project risk score.

[0066] To this end, the embodiment of the present application provides a computer-readable storage medium, which may include: a read-only memory (ROM), a random access memory (RAM), a disk or an optical disk, etc. The computer-readable storage medium stores a plurality of instructions, which can be loaded by a processor to execute the steps in any of the risk detection methods for engineering projects provided in the embodiment of the present application, for example: Obtain a target engineering project to be detected, the target engineering project includes business data under multiple different business indicators; determine a target risk detection scheme matching the target engineering project among multiple preset risk detection schemes; obtain multiple different business indicators in the target risk detection scheme; use business indicators that exist in both the target risk detection scheme and the target engineering project as target business indicators; determine the business risk score of the business data under the target business indicator in the target engineering project by using preset scoring rules associated with the target business indicator in the target risk detection scheme; determine the project risk score of the target engineering project based on the business risk score of the business data under all target business indicators; and generate a risk detection result for the target engineering project based on the project risk score.

[0067] In addition, an embodiment of the present application further provides a computer program product or a computer program, the computer program product or the computer program including computer instructions, the computer instructions being stored in a computer-readable storage medium. A processor of an electronic device reads the computer instructions from the computer-readable storage medium, and the processor executes the computer instructions, so that the electronic device executes to implement the risk detection method for an engineering project as described in any one of the above items, for example: Obtain a target engineering project to be detected, the target engineering project includes business data under multiple different business indicators; determine a target risk detection scheme matching the target engineering project among multiple preset risk detection schemes; obtain multiple different business indicators in the target risk detection scheme; use business indicators that exist in both the target risk detection scheme and the target engineering project as target business indicators; determine the business risk score of the business data under the target business indicator in the target engineering project by using preset scoring rules associated with the target business indicator in the target risk detection scheme; determine the project risk score of the target engineering project based on the business risk score of the business data under all target business indicators; and generate a risk detection result for the target engineering project based on the project risk score.

[0068] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0069] The above is a detailed introduction to the risk detection method, equipment and medium for an engineering project provided in an embodiment of the present application. Specific examples are used in this article to illustrate the principles and implementation methods of the present application. The description of the above embodiments is only used to help understand the method of the present application and its core idea; at the same time, for technical personnel in this field, according to the idea of ​​the present application, there will be changes in the specific implementation method and application scope, and the content of this specification should not be understood as a limitation on the present application.

Claims

1. A risk detection method for an engineering project, characterized in that: The risk detection method of the engineering project includes: Acquire a target engineering project to be detected, wherein the target engineering project includes business data under multiple different business indicators; Determine a target risk detection scheme matching the target engineering project among a plurality of preset risk detection schemes; Acquire multiple different business indicators in the target risk detection scheme; Using the business indicators that exist in both the target risk detection scheme and the target engineering project as target business indicators; Determine the business risk score of the business data under the target business indicator in the target engineering project by using the preset scoring rule associated with the target business indicator in the target risk detection scheme; Determining a project risk score for the target engineering project based on the business risk scores of the business data under all the target business indicators; Based on the project risk score, a risk detection result of the target engineering project is generated.

2. The risk detection method for an engineering project according to claim 1, characterized in that: The method of using the preset scoring rules associated with the target business indicator in the target risk detection scheme to determine the business risk score of the business data under the target business indicator in the target engineering project includes: When the business data under the target business indicator is structured data, quantitative calculation processing is performed on the business data under the target business indicator to obtain a numerical result, and a business risk score of the business data under the target business indicator is determined by using a preset scoring rule associated with the target business indicator in the target risk detection scheme and the numerical result; When the business data under the target business indicator is unstructured data, a qualitative analysis is performed on the business data under the target business indicator to obtain a text result, and a business risk score of the business data under the target business indicator is determined by using a preset scoring rule associated with the target business indicator in the target risk detection scheme and the text result.

3. The risk detection method for an engineering project as claimed in claim 2, characterized in that: The quantitative calculation of the business data under the target business indicator to obtain a numerical result includes: Determine expected data of business data under the target business indicator; Determining the numerical result based on the ratio of the business data under the target business indicator to the expected data; The qualitative analysis of the business data under the target business indicator is performed to obtain text results, including: Determine, from among a plurality of preset text labels, a target text label corresponding to the business data under the target business indicator; Based on the target text label, the text result is determined.

4. The risk detection method for an engineering project as claimed in claim 1, characterized in that: The business risk scoring of the business data under all the target business indicators is used to determine the project risk score of the target engineering project, including: In the target risk detection scheme, obtaining an indicator weight associated with each target business indicator; According to the indicator weights, weighted summing is performed on the business risk scores of the business data under all the target business indicators to obtain a weighted summing result; Based on the weighted summation result, the project risk score is determined.

5. The risk detection method for an engineering project as claimed in claim 4, characterized in that: The step of generating a risk detection result of the target engineering project based on the project risk score includes: Determine the business risk score with the largest value among the business risk scores of the business data under all the target business indicators; Determine the product of the sum of the indicator weights associated with each of the target business indicators and the business risk score with the largest value, and use it as the estimated maximum risk score of the target engineering project; Determining a ratio of the project risk score to the estimated maximum risk score; Based on the ratio, determining the risk level of the project; Based on the project risk level, a risk detection result of the target engineering project is generated.

6. The risk detection method for an engineering project as claimed in claim 5, characterized in that: Determining the project risk level based on the ratio includes: Obtaining the construction site of the target project; Determining a risk threshold of the target project based on the geographical area where the construction site is located; The project risk level is determined based on the relationship between the ratio and the risk threshold.

7. The risk detection method for an engineering project as claimed in claim 4, characterized in that: Determining the project risk score based on the weighted sum result includes: Determine the project delivery object of the target project; Obtaining the object level of the engineering project deliverable object; The weighted sum result is corrected using the risk score correction coefficient associated with the object level to obtain the project risk score.

8. The risk detection method for an engineering project as claimed in claim 1, characterized in that: The step of obtaining the target engineering project to be detected includes: Obtain the construction units to be inspected; All engineering projects undertaken by the construction unit are respectively regarded as the target engineering projects.

9. An electronic device, characterized in that: The electronic device comprises: one or more processors; Memory; and One or more applications, wherein the one or more applications are stored in the memory and configured to be executed by the processor to implement the risk detection method for an engineering project according to any one of claims 1 to 8.

10. A computer-readable storage medium, characterized in that: A computer program is stored thereon, and the computer program is loaded by a processor to execute the steps in the risk detection method for an engineering project as described in any one of claims 1 to 8.