Environment-friendly construction management platform for water transportation engineering
By integrating data collection, evaluation and optimization modules in the water transportation engineering construction management platform to analyze terrain and geological data, the problem of low accuracy in water monitoring during construction is solved, ensuring the safety and environmental protection of the construction process.
Patent Information
- Application Number
- CN202411186000.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-27
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-08-27
AI Technical Summary
The existing water transport project construction management platform has low accuracy in monitoring water areas during construction, resulting in possible damage to the water areas.
A water transport engineering environmental protection construction management platform was designed, including data acquisition module, evaluation determination module, risk determination module, evaluation accuracy determination module and process optimization module. By analyzing topographic and topographic data, riverbed height changes and geological staggered momentum, the construction process is evaluated. and adjust the evaluation accuracy and risk assessment model according to the evaluation results to ensure the accuracy and safety of the construction process.
Accurate monitoring of waters during construction is achieved, accurate assessment of environmental damage risks is improved, construction does not cause damage to waters, and construction management is improved.
Smart Images

Figure CN119090270A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of environmental protection construction management, and in particular to an environmental protection construction management platform for water transport engineering. Background Art
[0002] Water transport projects will have a certain impact on the surrounding environment during construction and operation, so effective environmental protection measures and management are needed. Traditional environmental management methods often rely on manual monitoring and reporting, and there are problems such as low accuracy in monitoring water quality during construction. In order to improve the level of environmental management, the water transport project environmental protection construction management platform came into being.
[0003] Chinese patent application publication number: CN108921488A discloses a water transport engineering management platform, which includes: a target cloud platform for storing multiple water transport classification files, wherein each water transport classification file stores a water transport file to be queried; a preset query table, connected to the target cloud platform, for storing the location information corresponding to each water transport file and personnel function, and providing a link location, wherein the link location is used to link to the target cloud platform to obtain multiple target data in the target to-be-queried file. However, there are problems in the prior art that the accuracy of monitoring the water area during the construction process is low, and the construction process will cause damage to the water area. Summary of the invention
[0004] To this end, the present invention provides a water transport engineering environmental protection construction management platform to overcome the problems in the prior art of low accuracy in monitoring the water area during the construction process and damage to the water area during the construction process.
[0005] To achieve the above objectives, the present invention provides a water transport engineering environmental protection construction management platform, comprising:
[0006] The data acquisition module is used to collect the topographic data of the water transport project to be constructed in the BIM software and the river geological data of the water transport project to be constructed during the construction process;
[0007] An assessment and determination module, which is connected to the data acquisition module and is used to assess the risk of environmental damage during the construction process based on the riverbed terrain complexity evaluation value determined by the terrain and geomorphology data;
[0008] a risk determination module, which is connected to the data acquisition module and the assessment determination module respectively, and is used to determine the environmental damage risk of the construction process of the river channel to be constructed based on the assessment result determined by the assessment determination module and according to the height reduction value of the riverbed during the construction process or the displacement amount of the construction geology during the construction process;
[0009] An evaluation accuracy determination module, which is connected to the data acquisition module, and is used to determine the influence of the ratio of the amount of sand and stone excavated from the riverbed to the total amount of sand and stone in the riverbed on the river geology determined by the river geological data of the water transport project to be constructed during the construction process, on the river geology, and to collect data for the construction process with the first evaluation accuracy or the second evaluation accuracy;
[0010] The process optimization module is connected to the evaluation determination module and the evaluation accuracy determination module respectively, and is used to adjust the evaluation accuracy of the evaluation process by using an adjustment coefficient based on the historical geological stability of the river channel to be constructed.
[0011] Furthermore, the assessment and determination module determines a riverbed terrain complexity evaluation value of the water transport project to be constructed according to the height differences of several riverbed areas in the topographic and geomorphological data, and determines, based on a comparison result between the terrain complexity evaluation value and a preset terrain complexity evaluation value, whether to execute a first assessment mode for performing environmental damage risk assessment with a first assessment accuracy or a second assessment mode for performing environmental damage risk assessment with a second assessment accuracy for the environmental damage risk during the construction process.
[0012] Furthermore, in the first assessment mode, the risk determination module determines the eligibility of the environmental damage risk during the construction process based on the comparison result of the riverbed height reduction value during the construction process with the preset height reduction value, and determines that the environmental damage risk during the construction process is unqualified based on the comparison result that the riverbed height reduction value during the construction process is greater than the preset height reduction value.
[0013] Furthermore, the assessment and determination module determines a first damage degree evaluation value based on a difference between a height reduction value of a riverbed during the construction process and a preset height reduction value under the condition that the environmental damage risk during the construction process is determined to be unqualified.
[0014] Furthermore, in the second assessment mode, the risk determination module determines the eligibility of the environmental damage risk during the construction process based on the comparison result of the displacement of the construction geology during the construction process with the preset displacement of the construction geology, and determines that the environmental damage risk during the construction process is unqualified based on the comparison result that the displacement of the geology during the construction process is greater than the preset displacement of the construction geology.
[0015] Furthermore, the assessment accuracy determination module determines a second damage degree evaluation value based on a difference between a geological displacement during the construction process and a preset construction geological displacement under the condition that the environmental damage risk during the construction process is determined to be unqualified.
[0016] Furthermore, the evaluation accuracy determination module determines to collect data for the construction process with the first evaluation accuracy based on a comparison result in which the ratio of the volume of riverbed sand and stone to the total volume of riverbed sand and stone is less than or equal to a preset ratio according to the river geological data of the water transport project to be constructed during the construction process.
[0017] Furthermore, the evaluation accuracy determination module determines to collect data for the construction process with a second evaluation accuracy based on a comparison result that the ratio of the riverbed sand and stone volume determined by the river geological data of the water transport project to be constructed during the construction process to the total riverbed sand and stone volume is greater than a preset ratio.
[0018] Furthermore, the process optimization module determines to adjust the assessment accuracy of the assessment process with a preset reduction adjustment coefficient under the condition that the historical geological stability evaluation value of the river channel to be constructed is greater than a preset stability evaluation value.
[0019] Furthermore, under the condition that the historical geological stability evaluation value of the river channel to be constructed is less than a preset stability evaluation value, the process optimization module determines to adjust the evaluation accuracy of the evaluation process with the accuracy adjustment coefficient, and at the same time adjusts the corresponding destruction evaluation value of the evaluation process with the destruction adjustment coefficient.
[0020] Compared with the prior art, the beneficial effect of the present invention lies in that the water transport engineering environmental protection construction management platform constructed by the present invention through the data acquisition module, the evaluation and determination module, the risk determination module, the evaluation accuracy determination module, and the process optimization module realizes accurate monitoring of the water area during the construction process by analyzing the topographic data, the riverbed height changes and the geological displacement during the construction process, and the construction accuracy, thereby solving the problem of low accuracy in monitoring the water area during the construction process and damage to the water area during the construction process.
[0021] Furthermore, the assessment and determination module determines the environmental damage risk assessment model based on the comparison result of the riverbed terrain complexity evaluation value with the preset terrain complexity evaluation value. The risk determination module evaluates the eligibility of the environmental damage risk by comparing the riverbed height reduction value and the relative momentum of the geological data during the construction process, which helps to improve the accurate assessment of the environmental damage risk during the construction process, timely discover the environmental damage risk, and ensure that the construction process will not cause damage to the water area.
[0022] Furthermore, the assessment accuracy determination module determines the impact of construction on river geology and the environmental damage risk assessment accuracy to more accurately assess the impact of construction on river geology. By dividing the number of data collection sections, it helps to effectively assess the impact that may be caused to river geology during the construction process, thereby ensuring that the construction process will not cause damage to the water area.
[0023] Furthermore, the process optimization module determines the adjustment method based on the comparison between the historical geological stability evaluation value of the river channel to be constructed and the preset stability evaluation value, which helps to flexibly adjust the evaluation process according to the actual situation and improve the accuracy of monitoring the water area during the construction process. The process optimization module adjusts the evaluation accuracy and environmental damage risk assessment mode according to the difference between the geological stability evaluation value of the river channel to be constructed and the preset value to ensure that the problem of damage to the water area during the construction process is solved. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 This is a schematic diagram of module connections of a water transport engineering environmental protection construction management platform according to an embodiment of the present invention;
[0025] Figure 2 A flow chart of determining an assessment model for environmental damage risks during construction according to an embodiment of the present invention;
[0026] Figure 3 A flow chart for determining the eligibility of environmental damage risks during construction according to an embodiment of the present invention;
[0027] Figure 4 The present invention is a flowchart of adjusting the evaluation process in a second adjustment manner according to an embodiment of the present invention. DETAILED DESCRIPTION
[0028] In order to make the objects and advantages of the present invention more clearly understood, the present invention is further described below in conjunction with embodiments; it should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0029] The preferred embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood by those skilled in the art that these embodiments are only used to explain the technical principles of the present invention and are not intended to limit the protection scope of the present invention.
[0030] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.
[0031] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0032] See also Figure 1 - Figure 4 As shown, Figure 1 This is a schematic diagram of module connections of a water transport engineering environmental protection construction management platform according to an embodiment of the present invention; Figure 2 A flow chart of determining an assessment model for environmental damage risks during construction according to an embodiment of the present invention; Figure 3 A flow chart for determining the eligibility of environmental damage risks during construction according to an embodiment of the present invention; Figure 4 The present invention is a flowchart of adjusting the evaluation process in a second adjustment manner according to an embodiment of the present invention.
[0033] The environmental protection construction management platform for water transport engineering according to the embodiment of the present invention comprises:
[0034] The data acquisition module is used to collect the topographic data of the water transport project to be constructed in the BIM software and the river geological data of the water transport project to be constructed during the construction process;
[0035] An assessment and determination module, connected to the data acquisition module, for determining an assessment of the risk of environmental damage during the construction process based on the topographic data;
[0036] A risk determination module, which is connected to the data acquisition module and the assessment determination module respectively, and is used to determine the environmental damage risk of the construction process of the river channel to be constructed based on the assessment result determined by the assessment determination module;
[0037] An assessment accuracy determination module, which is connected to the data acquisition module and is used to determine the assessment accuracy of the assessment process for environmental damage risk based on the degree of impact of the construction process on the river geology;
[0038] A process optimization module is connected to the evaluation determination module and the evaluation accuracy determination module respectively, and is used to determine the optimization of the evaluation process based on the historical geological stability of the river channel to be constructed.
[0039] In the embodiment of the present invention, the topographic data includes but is not limited to the height difference of the riverbed area, the height reduction value of the riverbed during the construction process, the total amount of sand and stone in the riverbed, the depth of the riverbed, and the length of the riverbed; the river channel geological data includes but is not limited to the displacement of the construction geology, the amount of sand and stone excavated from the riverbed during the construction process, the total amount of sand and stone in the riverbed, the depth of the riverbed excavated during the construction process, and the length of the riverbed excavated during the construction process.
[0040] The embodiment of the present invention constructs an environmental protection construction management platform for water transport projects through a data acquisition module, an evaluation and determination module, a risk determination module, an evaluation accuracy determination module, and a process optimization module. By analyzing topographic data, changes in riverbed height and geological displacement during construction, and construction accuracy, the platform achieves accurate monitoring of the water area during the construction process, thereby solving the problem of low accuracy in monitoring the water area during the construction process and damage to the water area during the construction process.
[0041] Specifically, the assessment and determination module determines the riverbed terrain complexity evaluation value of the water transport project to be constructed according to the height difference of several riverbed areas in the topographic data, and determines the assessment mode of the environmental damage risk during the construction process based on the comparison result of the riverbed terrain complexity evaluation value and the preset riverbed terrain complexity evaluation value of 0.8;
[0042] If the riverbed terrain complexity evaluation value is less than or equal to a preset riverbed terrain complexity evaluation value, the evaluation determination module determines to evaluate the environmental damage risk during the construction process in a first evaluation mode;
[0043] If the riverbed terrain complexity evaluation value is greater than a preset riverbed terrain complexity evaluation value, the evaluation determination module determines to evaluate the environmental damage risk during the construction process in a second evaluation mode.
[0044] In the embodiment of the present invention, the preset riverbed terrain complexity evaluation value is 0.8, but the above value is not limited thereto, and those skilled in the art may also adjust the value according to actual needs.
[0045] Specifically, the risk determination module determines the eligibility of the environmental damage risk during the construction process in the first assessment mode according to the comparison result of the height reduction value of the riverbed during the construction process and the preset height reduction value of 0.5dm;
[0046] If the height reduction value of the riverbed during the construction process is less than or equal to the preset height reduction value, it is determined that the environmental damage risk of the construction process is qualified;
[0047] If the height reduction value of the riverbed during the construction process is greater than the preset height reduction value, it is determined that the environmental damage risk of the construction process is unqualified.
[0048] In the embodiment of the present invention, the preset height reduction value is 0.5 dm, but the above value is not limited thereto, and those skilled in the art may also adjust the value according to actual needs.
[0049] Specifically, the risk determination module determines the first damage degree evaluation value C1 according to the ratio of the height reduction value of the riverbed during the construction process to the preset height reduction value, under the condition that it is determined that the environmental damage risk of the construction process is unqualified.
[0050] Specifically, the risk determination module calculates the first damage degree evaluation value according to the following formula, setting:
[0051]
[0052] Among them, C1 represents the first damage degree evaluation value, H represents the height reduction value of the riverbed in the i-th area during the construction process, and H 0 It indicates the preset height reduction value, and n indicates a number of riverbed data collection areas.
[0053] Specifically, the risk determination module determines the eligibility of the environmental damage risk during the construction process in the second assessment mode according to the comparison result of the displacement of the construction geology during the construction process and the preset displacement of the construction geology of 50 mm;
[0054] If the displacement of the construction geology during the construction process is less than or equal to the preset displacement of the construction geology, it is determined that the environmental damage risk of the construction process is qualified;
[0055] If the displacement of the construction geology during the construction process is greater than the preset displacement of the construction geology, it is determined that the environmental damage risk of the construction process is unqualified.
[0056] In the embodiment of the present invention, the displacement value of the preset construction geology is 50 mm, but the above value is not limited thereto, and those skilled in the art can also adjust the value according to actual needs.
[0057] Specifically, the risk determination module determines the second damage degree evaluation value C2 according to the ratio of the displacement of the construction geology during the construction process to the displacement of the preset construction geology, under the condition that it is determined that the environmental damage risk of the construction process is unqualified.
[0058] Specifically, the risk determination module calculates the second damage degree evaluation value according to the following formula, setting:
[0059]
[0060] Among them, C2 represents the second damage degree evaluation value, P represents the geological displacement during the construction process,
[0061] P0 It represents the amount of geological displacement during the preset construction process, and n represents a number of data collection areas on the riverbed.
[0062] In the embodiment of the present invention, the amount of geological displacement during the construction process is the amount of relative displacement of rocks on both sides of the river channel, which is obtained by measuring the tiny displacement of the ground surface using remote sensing technologies such as synthetic aperture radar.
[0063] Specifically, the assessment and determination module determines the environmental damage risk assessment model based on the comparison result of the riverbed terrain complexity evaluation value with the preset terrain complexity evaluation value. The risk determination module evaluates the eligibility of the environmental damage risk by comparing the riverbed height reduction value and the relative momentum of geological data during the construction process. This helps to improve the accurate assessment of the environmental damage risk during the construction process, timely discover the environmental damage risk, and ensure that the construction process will not cause damage to the water area.
[0064] Specifically, the evaluation accuracy determination module calculates the ratio of the volume of riverbed sand and stone excavated during the construction process to the total volume of riverbed sand and stone according to the following formula, and sets:
[0065]
[0066] Wherein, Q represents the ratio of the volume of riverbed sand and stone excavated during the construction process to the total volume of riverbed sand and stone, and h 0 Indicates the depth of the riverbed dug during the construction process, h represents the riverbed depth, d 0 It indicates the width of the riverbed dug during the construction process, d indicates the width of the riverbed, l 0 It indicates the length of the riverbed dug during the construction process, and l indicates the length of the riverbed.
[0067] Specifically, the assessment accuracy determination module determines the degree of influence of the construction process on the river geology and determines the assessment accuracy of the environmental damage risk assessment process during the construction process by comparing the ratio of the excavated riverbed sand and stone volume to the total riverbed sand and stone volume determined by the river geological data of the water transport project to be constructed during the construction process with a preset ratio of 0.83;
[0068] If the ratio is less than or equal to the preset ratio, the evaluation accuracy determination module is determined to collect data on the construction process with the first evaluation accuracy, and divide the data collection section into a plurality of sections with the first evaluation accuracy coefficient 3;
[0069] If the ratio is greater than the preset ratio, the evaluation accuracy determination module is determined to collect data on the construction process with the second evaluation accuracy, and divide the data collection section into several sections with the second evaluation accuracy coefficient 5.
[0070] The preset ratio is set to 0.83, but the above value is not limited thereto, and those skilled in the art may also adjust the value according to actual needs.
[0071] Specifically, the evaluation accuracy determination module calculates the number of divided data collection segments according to the following formula, setting:
[0072] S=L i / ηi
[0073] Wherein, S represents the number of data collection segments, Li represents the i-th evaluation accuracy, ηi represents the i-th evaluation accuracy coefficient, and i takes the value of 1 or 2.
[0074] In the embodiment of the present invention, the assessment accuracy determination module determines the impact degree of construction on river geology and the environmental damage risk assessment accuracy to more accurately assess the impact of construction on river geology. By dividing the number of data collection sections, it is helpful to effectively assess the impact that may be caused to river geology during the construction process, thereby ensuring that the construction process will not cause damage to the water area.
[0075] Specifically, the process optimization module determines the adjustment method of the evaluation process according to the comparison result between the historical geological stability evaluation value of the river channel to be constructed and the preset stability evaluation value of 0.74, under the condition of determining the evaluation mode of the environmental damage risk during the construction process;
[0076] If the historical geological stability evaluation value of the river channel to be constructed is greater than the preset stability evaluation value, determining to adjust the evaluation process in a first adjustment manner;
[0077] If the historical geological stability evaluation value of the river channel to be constructed is less than the preset stability evaluation value, it is determined to adjust the evaluation process in a second adjustment manner.
[0078] Specifically, the first adjustment method is to reduce the first assessment accuracy, and the second adjustment method is to increase the second assessment accuracy, while adjusting the assessment mode of the assessment determination module for the environmental damage risk during the construction process.
[0079] The preset stability evaluation value is set to 0.74, but the above value is not limited thereto, and those skilled in the art may also adjust the value according to actual needs.
[0080] Specifically, the process optimization module calculates the historical geological stability evaluation value according to the following formula, setting:
[0081]
[0082] Among them, F represents the historical geological stability evaluation value, E represents the sand and gravel strength of the river channel to be constructed, E0 represents the historical sand and gravel strength of the river channel to be constructed, S represents the diameter of the sand and gravel of the river channel to be constructed, D represents the i-th historical fluctuation frequency of the riverbed, and n represents a number of collection partitions.
[0083] In the embodiment of the present invention, the historical fluctuation frequency of the riverbed is the periodic change of the riverbed morphology over time, and the sand and gravel strength of the river channel to be constructed is determined by the number of hammer blows according to the penetration depth by using the kinetic energy of the hammer to drive the conical probe into the soil through dynamic probing.
[0084] Specifically, under the condition that the historical geological stability evaluation value of the river channel to be constructed is greater than the preset stability evaluation value, the process optimization module reduces the first evaluation accuracy according to the comparison result of the difference between the historical geological stability evaluation value of the river channel to be constructed and the preset stability evaluation value and the preset difference 0.05;
[0085] If the difference is less than or equal to the preset difference, it is determined to reduce the first evaluation accuracy to a corresponding value using a first accuracy adjustment coefficient of 0.96;
[0086] If the difference is greater than the preset difference, it is determined to reduce the first evaluation accuracy to a corresponding value using a second accuracy adjustment coefficient of 0.93.
[0087] The difference is the difference between the historical geological stability evaluation value of the river channel to be constructed and the preset stability evaluation value.
[0088] In the embodiment of the present invention, the preset difference value is 0.05, but the above value is not limited thereto, and those skilled in the art may also adjust the value according to actual needs.
[0089] In the embodiment of the present invention, the reduced first evaluation accuracy is set to Lc, and Lc=L×Ki is set, where L represents the first evaluation accuracy, Ki represents the i-th preset reduction adjustment coefficient, i takes a value of 1 or 2, K1 is the first preset reduction adjustment coefficient, and K2 is the second preset reduction adjustment coefficient.
[0090] Specifically, under the condition that the historical geological stability evaluation value of the river channel to be constructed is less than a preset stability evaluation value, the process optimization module determines to increase the second evaluation accuracy and adjust the evaluation mode of the evaluation determination module for the environmental damage risk during the construction process based on the comparison result of the preset stability evaluation value and the difference between the historical geological stability evaluation value of the river channel to be constructed and the preset difference.
[0091] If the difference is less than the first preset difference of 0.02, it is determined to increase the second evaluation accuracy to a corresponding value by using an accuracy adjustment coefficient of 1.03;
[0092] If the difference is greater than the first preset difference and less than the second preset difference of 0.04, it is determined to increase the first damage degree evaluation value of the first evaluation mode to a corresponding value by using the first damage degree adjustment coefficient of 1.07;
[0093] If the difference is greater than the second preset difference, it is determined to increase the second damage degree evaluation value of the second evaluation mode to a corresponding value by a second damage degree adjustment coefficient of 1.09;
[0094] In the embodiment of the present invention, the increased second evaluation accuracy is set to Nc, and Nc=N×K is set, where N represents the second evaluation accuracy, and K represents the accuracy adjustment coefficient;
[0095] The increased first damage degree evaluation value is set as Mz, and Mz=C1×K1 is set, wherein C1 represents the first damage degree evaluation value of the first evaluation mode, and K1 represents the first damage degree adjustment coefficient;
[0096] The increased second damage degree evaluation value is set as Tz, and Tz=C2×K2 is set, wherein C2 represents the second damage degree evaluation value of the second evaluation mode, and K2 represents the second damage degree adjustment coefficient.
[0097] In the embodiment of the present invention, the process optimization module determines the adjustment mode according to the comparison between the historical geological stability evaluation value of the river channel to be constructed and the preset stability evaluation value, which helps to flexibly adjust the evaluation process according to the actual situation and improve the accuracy of monitoring the water area during the construction process. The process optimization module adjusts the evaluation accuracy and environmental damage risk assessment mode according to the difference between the geological stability evaluation value of the river channel to be constructed and the preset value to ensure that the problem of damage to the water area during the construction process is solved.
[0098] So far, the technical solutions of the present invention have been described in conjunction with the preferred embodiments shown in the accompanying drawings. However, it is easy for those skilled in the art to understand that the protection scope of the present invention is obviously not limited to these specific embodiments. Without departing from the principle of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will fall within the protection scope of the present invention.
[0099] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A water transport engineering environmental protection construction management platform, It is characterized in that include: The data acquisition module is used to collect the topographic data of the water transport project to be constructed in the BIM software and the river geological data of the water transport project to be constructed during the construction process; An assessment and determination module, which is connected to the data acquisition module and is used to assess the risk of environmental damage during the construction process based on the riverbed terrain complexity evaluation value determined by the terrain and geomorphology data; a risk determination module, which is connected to the data acquisition module and the assessment determination module respectively, and is used to determine the environmental damage risk of the construction process of the river channel to be constructed based on the assessment result determined by the assessment determination module and according to the height reduction value of the riverbed during the construction process or the displacement amount of the construction geology during the construction process; An evaluation accuracy determination module, which is connected to the data acquisition module, and is used to determine the influence of the ratio of the amount of sand and stone excavated from the riverbed to the total amount of sand and stone in the riverbed on the river geology determined by the river geological data of the water transport project to be constructed during the construction process, on the river geology, and to collect data for the construction process with the first evaluation accuracy or the second evaluation accuracy; The process optimization module is connected to the evaluation determination module and the evaluation accuracy determination module respectively, and is used to adjust the evaluation accuracy of the evaluation process by using an adjustment coefficient based on the historical geological stability of the river channel to be constructed.
2. The water transport engineering environmental protection construction management platform according to claim 1, It is characterized in that The assessment and determination module determines a riverbed terrain complexity evaluation value of the water transport project to be constructed according to the height differences of several riverbed areas in the topographic and geomorphic data, and determines, based on a comparison result of the terrain complexity evaluation value with a preset terrain complexity evaluation value, whether to execute a first assessment mode for environmental damage risk assessment with a first assessment accuracy or to execute a second assessment mode for environmental damage risk assessment with a second assessment accuracy for the environmental damage risk during the construction process.
3. The water transport engineering environmental protection construction management platform according to claim 2, It is characterized in that In the first assessment mode, the risk determination module determines the eligibility of the environmental damage risk during the construction process based on the comparison result of the riverbed height reduction value during the construction process with the preset height reduction value, and determines that the environmental damage risk during the construction process is unqualified based on the comparison result that the riverbed height reduction value during the construction process is greater than the preset height reduction value.
4. The water transport engineering environmental protection construction management platform according to claim 3, It is characterized in that The assessment and determination module determines a first damage degree evaluation value based on a difference between a height reduction value of a riverbed during the construction process and a preset height reduction value, under the condition that the environmental damage risk during the construction process is determined to be unqualified.
5. The water transport engineering environmental protection construction management platform according to claim 2, It is characterized in that In the second assessment mode, the risk determination module determines the eligibility of the environmental damage risk during the construction process based on the comparison result of the displacement of the construction geology during the construction process with the preset displacement of the construction geology, and determines that the environmental damage risk during the construction process is unqualified based on the comparison result that the displacement of the geology during the construction process is greater than the preset displacement of the construction geology.
6. The water transport engineering environmental protection construction management platform according to claim 5, It is characterized in that The assessment accuracy determination module determines a second damage degree evaluation value based on a difference between a geological displacement during the construction process and a preset construction geological displacement, under the condition that the environmental damage risk during the construction process is determined to be unqualified.
7. The water transport engineering environmental protection construction management platform according to claim 6, It is characterized in that The evaluation accuracy determination module determines to collect data for the construction process with the first evaluation accuracy based on the comparison result that the ratio of the riverbed sand and stone volume determined by the river geological data of the water transport project to be constructed during the construction process to the total riverbed sand and stone volume is less than or equal to a preset ratio.
8. The water transport engineering environmental protection construction management platform according to claim 7, It is characterized in that The evaluation accuracy determination module determines to collect data for the construction process with a second evaluation accuracy based on a comparison result that the ratio of the riverbed sand and stone volume determined by the river geological data of the water transport project to be constructed during the construction process to the total riverbed sand and stone volume is greater than a preset ratio.
9. The water transport engineering environmental protection construction management platform according to claim 8, It is characterized in that The process optimization module determines to adjust the assessment accuracy of the assessment process with a preset reduction adjustment coefficient under the condition that the historical geological stability evaluation value of the river channel to be constructed is greater than a preset stability evaluation value.
10. The water transport engineering environmental protection construction management platform according to claim 8, It is characterized in that Under the condition that the historical geological stability evaluation value of the river channel to be constructed is less than the preset stability evaluation value, the process optimization module determines to adjust the evaluation accuracy of the evaluation process with the accuracy adjustment coefficient, and at the same time adjusts the corresponding destruction evaluation value of the evaluation process with the destruction adjustment coefficient.
Citation Information
Patent Citations
Water transport engineering management platform
CN108921488A
Road construction management platform and method based on 3DGIS + BIM
CN111783210A
Water conservancy project information management system based on big data and three-dimensional technology
CN113593029A
Hydraulic engineering digital twin modeling early warning system combined with geological data
CN116029217A
Intelligent construction site safety management platform system based on data interaction
CN116911759A