Intelligent operation and maintenance system for power distribution room equipment based on sensor
By obtaining and analyzing the temperature and working power data of the distribution room equipment, calculating the heat dissipation performance coefficient and effect characterization value, fitting the curve to predict the heat dissipation effect, and adaptively adjusting the working power of the heat dissipation system, solving the problem of untimely heat dissipation in the existing technology in the existing technology , achieving the guarantee of equipment stability and safety and reducing operation and maintenance costs.
Patent Information
- Application Number
- CN202411578548.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-07
- Publication Date
- 2024-12-06
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
When determining the working power of the cooling system, the existing technology relies on real-time monitoring data, resulting in the heat dissipation of the distribution room equipment in time, increasing the aging rate and failure probability of equipment, unable to ensure the stability and safety of equipment operation, and increasing operation and maintenance costs. .
By obtaining the temperature data sequence and working power sequence of the current monitoring time period, calculate the heat dissipation performance coefficient and heat dissipation effect characterization value, fit the curve to predict the heat dissipation effect at the next moment, and adaptively adjust the working power of the heat dissipation system to ensure timely heat dissipation and Avoid unnecessary work.
It achieves accurate prediction of the heat dissipation effect, ensures timely heat dissipation of the heat dissipation system, extends the service life of the equipment, ensures the stability and safety of the distribution room equipment, and reduces resource waste and operation and maintenance costs.
Smart Images

Figure CN119090489A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power distribution room equipment operation and maintenance, and in particular to a sensor-based intelligent power distribution room equipment operation and maintenance system. Background Art
[0002] Distribution room equipment refers to various types of equipment used for power distribution and management, usually including transformers, circuit breakers and protective devices, etc. Its main function is to convert high-voltage power into low-voltage power and distribute it to different power consumption areas or equipment to ensure safe, stable and reliable power supply. However, during the operation of distribution room equipment, a certain amount of heat will be generated due to the thermal effect of the current. If the heat generated by these equipment is not dissipated in time, the aging rate of the equipment and the probability of failure will increase, thereby affecting the stability and safety of the operation of the distribution room equipment and increasing the operation and maintenance costs.
[0003] At present, in order to ensure the stability and safety of the operation of the distribution room equipment and to reduce the operation and maintenance costs, temperature sensors are usually used to monitor the temperature values inside the distribution room equipment, and feedback heat dissipation is performed based on the monitoring results. If the temperature monitored by the sensor reaches the threshold or interval required for heat dissipation, the heat dissipation system will be started and heat will be dissipated at a certain heat dissipation power. However, in the prior art, when determining the working power of the heat dissipation system, it is usually determined only based on real-time monitored data. However, this determination method will result in the failure to dissipate heat in time when the heat generated by the distribution room equipment is dissipated. When this happens, the aging rate of the equipment and the probability of failure will increase, thereby failing to achieve the purpose of ensuring the stability and safety of the operation of the distribution room equipment and reducing the operation and maintenance costs. For example, when the distribution room equipment continues to have a negative high load phenomenon during the power distribution operation, if the heat is dissipated according to the working power determined by the existing method, the problem of not being able to dissipate heat in time will occur. Therefore, it is an urgent problem to adaptively obtain or determine the working frequency of the heat dissipation system to ensure that the heat dissipation system can dissipate the heat generated by the distribution room equipment in time, while avoiding too much unnecessary work of the heat dissipation system. Summary of the invention
[0004] In order to solve the above problems, the present invention provides a sensor-based intelligent operation and maintenance system for power distribution room equipment. The technical solutions adopted are as follows: An embodiment of the present invention provides a sensor-based intelligent operation and maintenance system for power distribution room equipment, including a processor and a memory, wherein the processor executes a computer program stored in the memory to implement the following steps: Obtaining a temperature data sequence corresponding to each monitoring sub-time period in the current monitoring time period and an actual working power sequence corresponding to each monitoring sub-time period, wherein the data in the temperature data sequence is the temperature data in the power distribution room collected by the sensor, and the data in the actual working power sequence is the working power of the cooling system, which belongs to the power distribution room. The current monitoring time period includes the current monitoring moment; According to the adjacent temperature data in the temperature data sequence corresponding to each monitoring sub-time period, a heat dissipation performance coefficient of the heat dissipation system in each monitoring sub-time period is obtained; according to the heat dissipation performance coefficient and the actual working power sequence, a heat dissipation effect characterization value of the heat dissipation system in each monitoring sub-time period is obtained; According to the heat dissipation effect characterization value, a heat dissipation effect characterization value fitting curve is obtained by fitting, and according to the heat dissipation effect characterization value fitting curve, a predicted heat dissipation effect characterization value of the heat dissipation system at the next monitoring moment is predicted; According to the predicted heat dissipation effect characterization value, the working power of the heat dissipation system at the next monitoring moment is obtained.
[0005] Beneficial effects: The present invention first obtains the temperature data sequence corresponding to each monitoring sub-time period in the current monitoring time period and the actual working power sequence corresponding to each monitoring sub-time period; then, according to the adjacent temperature data in the temperature data sequence corresponding to each monitoring sub-time period, the heat dissipation performance coefficient of the heat dissipation system in each monitoring sub-time period is obtained, and according to the heat dissipation performance coefficient and the actual working power sequence, the heat dissipation effect characterization value of the heat dissipation system in each monitoring sub-time period is obtained; then, according to the heat dissipation effect characterization value, a heat dissipation effect characterization value fitting curve is fitted, and according to the heat dissipation effect characterization value fitting curve, the predicted heat dissipation effect characterization value of the heat dissipation system at the next monitoring moment is predicted; finally, according to the predicted heat dissipation effect characterization value, the working power of the heat dissipation system at the next monitoring moment is obtained. And the present invention can accurately predict the predicted heat dissipation effect characterization value of the heat dissipation system at the next monitoring moment according to the heat dissipation effect characterization value fitting curve, and the working power of the heat dissipation system at the next monitoring moment obtained according to the predicted heat dissipation effect characterization value not only enables the heat dissipation system to dissipate the heat generated by the power distribution room equipment in a timely manner, but also avoids the heat dissipation system from generating more unnecessary work, thereby achieving the purpose of extending the life of the equipment related to the heat dissipation system, ensuring the stability and safety of the operation of the power distribution room equipment, avoiding resource waste and reducing the operation and maintenance cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0006] In order to more clearly illustrate the technical solutions and advantages in the embodiments of the present invention or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0007] Figure 1 The present invention is a flow chart of a sensor-based intelligent operation and maintenance method for power distribution room equipment. DETAILED DESCRIPTION
[0008] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the embodiments of the present invention.
[0009] Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention pertains.
[0010] This embodiment provides a sensor-based intelligent operation and maintenance system for power distribution room equipment, including a processor and a memory, wherein the processor executes a computer program stored in the memory to implement a sensor-based intelligent operation and maintenance method for power distribution room equipment, such as Figure 1 As shown, the sensor-based intelligent operation and maintenance method for power distribution room equipment includes the following steps: like Figure 1 As shown, the sensor-based intelligent operation and maintenance method for power distribution room equipment includes the following steps: Step S001, obtaining a temperature data sequence corresponding to each monitoring sub-time period in a current monitoring time period and a working power sequence corresponding to each monitoring sub-time period.
[0011] The main purpose of this embodiment is to adaptively obtain or determine the operating frequency of the cooling system, so that the cooling system can dissipate the heat generated by the equipment in the power distribution room in a timely manner, while avoiding unnecessary work for the cooling system. In addition, for the convenience of analysis and understanding, this embodiment will be analyzed by taking any power distribution room as an example. The power distribution room is equipped with a cooling system, and avoiding unnecessary work for the cooling system can not only extend the life of the equipment related to the cooling system, but also avoid waste of resources and reduce operation and maintenance costs.
[0012] In this embodiment, in order to obtain or determine the working frequency of the cooling system, while being able to dissipate the heat generated by the equipment in the power distribution room in a timely manner, and also avoid the cooling system from generating more unnecessary work, this embodiment will first analyze the cooling effect of different time periods, and predict the cooling effect at future monitoring times based on the cooling effect obtained by the analysis, and determine the working frequency of the cooling system at future monitoring times through the prediction results; therefore, based on the above, it can be seen that this embodiment needs to first analyze the cooling effect, and the cooling effect can be characterized by the cooling performance coefficient of different time periods and the working power of the cooling system, and because the cooling performance coefficient is mainly determined by analyzing the temperature data in the power distribution room, that is, by analyzing the temperature data sequence in different time periods, therefore, this embodiment first needs to obtain the temperature data sequence corresponding to each monitoring sub-time period in the current monitoring time period and the actual working power sequence corresponding to each monitoring sub-time period, and the specific acquisition process is: First, the current monitoring time period is obtained, and then the current monitoring time period is divided, and each time period obtained by the division is recorded as a monitoring sub-time period in the current monitoring time period. The purpose of dividing the current monitoring time period in this embodiment is that the equipment in the distribution room needs to undertake related tasks such as current transportation and power distribution, and the loads borne by these devices may be different in different time periods, so the heat generated will also be different, that is, the temperature performance inside the distribution room in different time periods may be different. Therefore, in order to understand the heat dissipation performance inside the distribution room in different time periods, and to enable the heat dissipation system in the distribution room to adaptively change the working power according to the temperature pressure inside the distribution room, it is necessary to perform segmented analysis.
[0013] Then, the temperature data in the distribution room and the actual working power of the heat dissipation system at each monitoring moment in each monitoring sub-time period are obtained, and the heat dissipation system at this time is the heat dissipation system in the distribution room; then, all the temperature data and the actual working power of the heat dissipation system obtained in each monitoring sub-time period are sorted in chronological order, and the sequences after sorting are recorded as the temperature data sequence corresponding to each monitoring sub-time period and the actual working power sequence corresponding to each monitoring sub-time period, and the temperature data in the distribution room is obtained by a temperature sensor; for example, for any monitoring sub-time period, the time series sequence constructed by all the temperature data and the actual working power of the heat dissipation system obtained in the monitoring sub-time period are the temperature data sequence and the actual working power sequence corresponding to the monitoring sub-time period, that is, the data in the temperature data sequence is the temperature data in the distribution room collected by the sensor, and the data in the actual working power sequence is the working power of the heat dissipation system; in addition, the method for obtaining the actual working power of the heat dissipation system is a well-known technology, so this embodiment will not be described in detail.
[0014] In this embodiment, the implementer needs to set the current monitoring time period according to the actual situation. For example, in this embodiment, the time length of the current monitoring time period can be set to 3 hours or 6 hours, and in this embodiment, the last monitoring moment in the current monitoring time period is the current monitoring moment, that is, the current monitoring time period includes the current monitoring moment; in this embodiment, the implementer also needs to set the method for dividing the current monitoring time period according to the actual situation. For example, in this embodiment, the current monitoring time period can be evenly divided into a preset time length, and the preset time length is required to be much smaller than the length of the current monitoring time period. If the time length of the current monitoring time period is 6 hours, then in this embodiment, the preset time length can be set to 10 minutes, and if the preset time length is 10 minutes, then the time length of the monitoring sub-time period is 10 minutes.
[0015] In addition, in this embodiment, the implementer also needs to set the time interval between adjacent monitoring moments according to actual conditions. For example, in this embodiment, the time interval between adjacent monitoring moments can be set to 1 second or 5 seconds.
[0016] Therefore, this embodiment can obtain the temperature data sequence and the corresponding actual working power sequence corresponding to each monitoring sub-time period in the current monitoring time period through the above process.
[0017] Step S002, obtaining the heat dissipation performance coefficient of the heat dissipation system in each monitoring sub-time period according to the adjacent temperature data in the temperature data sequence corresponding to each monitoring sub-time period; obtaining the heat dissipation effect characterization value of the heat dissipation system in each monitoring sub-time period according to the heat dissipation performance coefficient and the actual working power sequence.
[0018] Based on the analysis in step S001, it can be known that in order to adaptively obtain or determine the working frequency of the cooling system, and in order to make the adaptively obtained working frequency of the cooling system be able to dissipate the heat generated by the equipment in the power distribution room in a timely manner, while also avoiding the cooling system from generating more unnecessary work, this embodiment needs to analyze and obtain the cooling effect characterization value of the cooling system in different monitoring sub-time periods, and before obtaining the cooling effect characterization value, this embodiment needs to first obtain the cooling performance coefficient of the cooling system in each monitoring sub-time period according to the adjacent temperature data in the temperature data sequence corresponding to each monitoring sub-time period; and for ease of understanding, this embodiment will next take the acquisition process of the cooling performance coefficient of the cooling system in the fth monitoring sub-time period in the current monitoring time period as an example to describe, that is, the acquisition process of the cooling performance coefficient of the cooling system in the fth monitoring sub-time period is: First, the temperature data sequence corresponding to the f-th monitoring sub-time period is recorded as sequence A, and then the first ratio sequence of sequence A is obtained, and then the mean of the first ratio sequence of sequence A is obtained and recorded as the first index value under the f-th monitoring sub-time period; then the maximum value in sequence A is obtained and recorded as the second index value under the f-th monitoring sub-time period; then the product of the first index value and the second index value under the f-th monitoring sub-time period is calculated and recorded as the heat dissipation performance coefficient of the heat dissipation system under the f-th monitoring sub-time period, and the a-th first ratio in the first ratio sequence of sequence A is the ratio of the a-th temperature data in sequence A to the a+1-th temperature data in sequence A; and in this embodiment, the expression for obtaining the heat dissipation performance coefficient of the heat dissipation system under the f-th monitoring sub-time period is:
[0019] in, is the heat dissipation performance coefficient of the heat dissipation system in the fth monitoring sub-time period, is the total number of first ratios in the first ratio sequence A, is the a first ratio in the first ratio sequence of sequence A, is the maximum value in sequence A, and , is the ath temperature data in sequence A, It is the a+1th temperature data in sequence A.
[0020] In addition, when and The larger the value of The larger the value of The larger the value of is, the better the cooling performance or effect of the cooling system may be in the fth monitoring sub-time period; on the contrary, and The smaller the value of The smaller the value of The smaller the value is, the worse the heat dissipation performance or effect of the heat dissipation system may be in the fth monitoring sub-time period.
[0021] Therefore, this embodiment can obtain the heat dissipation performance coefficient of the heat dissipation system in each monitoring sub-time period through the above process; and because not only the heat dissipation performance coefficient can reflect the heat dissipation effect, but the working power of the heat dissipation system can also reflect the heat dissipation effect, this embodiment will then combine the actual working power and the heat dissipation performance coefficient of the heat dissipation system acquired through the above collection to obtain the heat dissipation effect characterization value, that is, this embodiment will then obtain the heat dissipation effect characterization value of the heat dissipation system in each monitoring sub-time period according to the heat dissipation performance coefficient and the actual working power sequence; in addition, for ease of understanding, this embodiment will then take the acquisition process of the heat dissipation effect characterization value of the heat dissipation system in the f-th monitoring sub-time period as an example for description, that is, the acquisition process of the heat dissipation effect characterization value of the heat dissipation system in the f-th monitoring sub-time period is: First, the mean of the actual working power sequence corresponding to the f-th monitoring sub-time period is obtained and recorded as the first mean; then the first mean is added to the preset first constant, and the reciprocal of the value obtained after the addition is recorded as the power characterization value corresponding to the f-th monitoring sub-time period; then the power characterization value corresponding to the f-th monitoring sub-time period is multiplied by the heat dissipation performance coefficient of the heat dissipation system in the f-th monitoring sub-time period, and the multiplication result is recorded as the heat dissipation effect characterization value of the heat dissipation system in the f-th monitoring sub-time period; and when the mean of the actual working power sequence corresponding to the f-th monitoring sub-time period is smaller and the heat dissipation performance coefficient of the heat dissipation system in the f-th monitoring sub-time period is larger, it indicates that the heat dissipation effect of the heat dissipation system in the f-th monitoring sub-time period is better, and conversely, when the mean of the actual working power sequence corresponding to the f-th monitoring sub-time period is larger and the heat dissipation performance coefficient of the heat dissipation system in the f-th monitoring sub-time period is smaller, it indicates that the heat dissipation effect of the heat dissipation system in the f-th monitoring sub-time period is worse.
[0022] In a specific application, the implementer needs to set the preset first constant according to the actual situation. For example, in this embodiment, the preset first constant is set to 0.01, and the preset first constant exists to prevent the denominator from being zero.
[0023] Therefore, this embodiment can obtain the heat dissipation effect characterization value of the heat dissipation system in each monitoring sub-time period through the above process.
[0024] Step S003, according to the heat dissipation effect characterization value, a heat dissipation effect characterization value fitting curve is fitted, and according to the heat dissipation effect characterization value fitting curve, a predicted heat dissipation effect characterization value of the heat dissipation system at the next monitoring moment is predicted; according to the predicted heat dissipation effect characterization value, the working power of the heat dissipation system at the next monitoring moment is obtained.
[0025] After obtaining the heat dissipation effect characterization value, this embodiment will then perform curve fitting on the heat dissipation effect characterization value. However, since the heat dissipation effect of the heat dissipation system in different monitoring time periods may be interfered by external environmental factors, such as the external temperature of the power distribution room, if the heat dissipation effect characterization value that is more interfered by the external environment is used in the subsequent curve fitting, the fitted curve will be relatively unreliable, and thus the subsequent prediction value will also be relatively unreliable and inaccurate. In order to make the subsequent fitting curve more reliable and to obtain a more reliable and accurate prediction result, this embodiment will then analyze the heat dissipation effect in the same historical time period as the time interval corresponding to the monitoring sub-time period to determine the heat dissipation effect characterization value to be fitted for each monitoring sub-time period, and subsequently use the heat dissipation effect characterization value to be fitted for the monitoring sub-time period to participate in curve fitting, so that the fitted curve can be more reliable. Therefore, in this embodiment, it is necessary to first obtain the heat dissipation effect characterization value to be fitted for the monitoring sub-time period; and for ease of understanding, this embodiment will take the acquisition process of the heat dissipation effect characterization value to be fitted for the f-th monitoring sub-time period as an example for description, that is, the acquisition process of the heat dissipation effect characterization value to be fitted for the f-th monitoring sub-time period is: First, the historical monitoring time period is obtained. In specific applications, the implementer needs to set the historical monitoring time period according to the actual situation. However, the historical monitoring time period is required not to overlap with the current monitoring time period, and the length of the historical monitoring time period is much longer than the current monitoring time period. If the length of the current monitoring time period is 3 hours in this embodiment, then this embodiment can use the month before the initial monitoring time of the current monitoring time period as the historical monitoring time period.
[0026] In obtaining the historical monitoring time period, this embodiment will obtain all time periods that are the same as the time interval corresponding to the f-th monitoring sub-time period in the historical monitoring time period, and record them as the historical sub-time period corresponding to the f-th monitoring sub-time period, and the time interval between the historical sub-time period corresponding to the f-th monitoring sub-time period and the f-th monitoring sub-time period is a multiple of 24 hours; for example, if the current monitoring time period is from 6:00 a.m. to 9:00 a.m. on the same day, and the time interval corresponding to the f-th monitoring sub-time period is from 6:30 a.m. to 40 a.m., then all time periods belonging to the interval from 6:30 a.m. to 40 a.m. in the historical monitoring time period are the historical sub-time periods corresponding to the f-th monitoring sub-time period, such as the time period from 6:30 a.m. to 40 a.m. on the day before the current day is a historical sub-time period corresponding to the f-th monitoring sub-time period.
[0027] Next, this embodiment records the set constructed by all historical sub-time periods corresponding to the f-th monitoring sub-time period as a historical sub-time period set, and then obtains the heat dissipation effect characterization value of the heat dissipation system in each historical sub-time period in the historical sub-time period set. The method for obtaining the heat dissipation effect characterization value of the heat dissipation system in the historical sub-time period is the same as the method for obtaining the heat dissipation effect characterization value of the heat dissipation system in the above-mentioned monitoring sub-time period, so this embodiment will not be described in detail. Then, a set constructed by the heat dissipation effect characterization values of the heat dissipation system in all historical sub-time periods in the historical sub-time period set and the heat dissipation effect characterization values of the heat dissipation system in the f-th monitoring sub-time period is recorded as the heat dissipation effect characterization value set to be sorted; then, all the data in the obtained heat dissipation effect characterization value set to be sorted are sorted in ascending order, and the sorted sequence is recorded as the first sequence, and then the median of the first sequence is obtained, and the obtained median is used as the heat dissipation effect characterization value to be fitted for the f-th monitoring sub-time period; and because the median can reflect the overall level of a group of data and is not affected by extreme values, using the median as the heat dissipation effect characterization value to be fitted for the monitoring sub-time period can minimize the influence of interference from external environmental factors on subsequent curve fitting, such as avoiding the problem that the subsequent fitted curve is relatively unreliable due to extreme weather outside the distribution room; in addition, if the number of data in the first sequence is an even number, then the median is the average of the two middle numbers.
[0028] Therefore, this embodiment can obtain the heat dissipation effect characterization value to be fitted for each monitoring sub-time period through the above process. After obtaining the heat dissipation effect characterization value to be fitted, a bar graph is constructed based on the heat dissipation effect characterization values to be fitted for all the monitoring sub-time periods obtained, and the horizontal axis of the coordinate space of the bar graph is time, and the vertical axis is the heat dissipation effect characterization value to be fitted. After that, the obtained bar graph is curve fitted, and the fitting result is recorded as the heat dissipation effect characterization value fitting curve; in addition, since the process of curve fitting the bar graph to obtain the fitting curve is a well-known technology, it will not be described in detail in this embodiment.
[0029] Then, based on the obtained heat dissipation effect characterization value fitting curve, the predicted heat dissipation effect characterization value of the heat dissipation system at the next monitoring moment is predicted; and if the time corresponding to the current monitoring moment is t, and the time interval between adjacent monitoring moments is t0, then the predicted heat dissipation effect characterization value of the heat dissipation system at the next monitoring moment refers to the vertical coordinate value of the data point with the horizontal coordinate value of t+t0 on the heat dissipation effect characterization value fitting curve.
[0030] Next, the working power of the cooling system at the next monitoring moment is obtained according to the predicted cooling effect characterization value of the cooling system at the next monitoring moment. The specific acquisition process is as follows: First, the power adjustment coefficient corresponding to the next monitoring moment is obtained, and the method for obtaining the power adjustment coefficient corresponding to the next monitoring moment is: on the heat dissipation effect characterization value fitting curve, the horizontal coordinate value is obtained as the vertical coordinate value of the data point corresponding to the time of the current monitoring moment, and it is recorded as the fitted heat dissipation effect characterization value of the heat dissipation system at the current monitoring moment; then, the ratio of the fitted heat dissipation effect characterization value of the heat dissipation system at the current monitoring moment to the predicted heat dissipation effect characterization value of the heat dissipation system at the next monitoring moment is obtained, and it is recorded as the characteristic ratio, and then the characteristic ratio is multiplied by the preset second constant, and the result of the multiplication is recorded as the power adjustment coefficient corresponding to the next monitoring moment; in addition, when the characteristic ratio is larger, it means that the heat dissipation effect of the heat dissipation system at the next monitoring moment may be poor, then it is necessary to increase the working power of the heat dissipation system at the current monitoring moment, otherwise it means that the heat dissipation effect of the heat dissipation system at the next monitoring moment may be better, then it is necessary to reduce the working power of the heat dissipation system at the current monitoring moment.
[0031] In a specific application, the implementer needs to set the preset second constant according to the actual situation. For example, in this embodiment, the preset second constant is set to 0.5, and the preset second constant exists to limit the adjustment rate of the subsequent working power.
[0032] Then, based on the power adjustment coefficient, the working power of the cooling system at the next monitoring moment is obtained. The specific process is: first, the actual working power of the cooling system at the current monitoring moment is obtained, and recorded as the current actual working power. In this embodiment, the current actual working power is the value of the last data in the actual working power sequence corresponding to the last monitoring sub-time period in the current monitoring time period; then, the current actual working power is multiplied by the power adjustment coefficient corresponding to the next monitoring moment, and the multiplication result is recorded as the working power of the cooling system at the next monitoring moment.
[0033] Then the working power of the cooling system at the current monitoring moment is adjusted to the working power of the cooling system at the next monitoring moment, and the specific adjustment process is: according to the working power adjustment of the cooling system at the current monitoring moment and the working power of the cooling system at the next monitoring moment, the control parameters of the PID control system in the cooling system are first obtained, including proportional parameters, integral parameters and differential parameters, and then finally, the control system feeds back the obtained control parameters to the cooling motor drive system of the cooling system, and the driving system inputs the voltage and current of the motor through the radiator, so that the output power of the motor gradually approaches and reaches the predicted value, that is, reaches the target value, and the target value refers to the working power of the cooling system at the next monitoring moment.
[0034] In summary, the present embodiment first obtains the temperature data sequence corresponding to each monitoring sub-time period in the current monitoring time period and the actual working power sequence corresponding to each monitoring sub-time period; then, according to the adjacent temperature data in the temperature data sequence corresponding to each monitoring sub-time period, the heat dissipation performance coefficient of the heat dissipation system in each monitoring sub-time period is obtained, and according to the heat dissipation performance coefficient and the actual working power sequence, the heat dissipation effect characterization value of the heat dissipation system in each monitoring sub-time period is obtained; then, according to the heat dissipation effect characterization value, a heat dissipation effect characterization value fitting curve is fitted, and according to the heat dissipation effect characterization value fitting curve, the predicted heat dissipation effect characterization value of the heat dissipation system at the next monitoring moment is predicted; finally, according to the predicted heat dissipation effect characterization value, the working power of the heat dissipation system at the next monitoring moment is obtained. Moreover, according to the heat dissipation effect characterization value fitting curve, the present embodiment can accurately predict the predicted heat dissipation effect characterization value of the heat dissipation system at the next monitoring moment, and according to the working power of the heat dissipation system at the next monitoring moment obtained by the predicted heat dissipation effect characterization value, not only enables the heat dissipation system to dissipate the heat generated by the power distribution room equipment in a timely manner, but also avoids the heat dissipation system from generating more unnecessary work, thereby achieving the purpose of extending the life of the equipment related to the heat dissipation system, ensuring the stability and safety of the operation of the power distribution room equipment, avoiding resource waste and reducing the operation and maintenance cost.
[0035] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.
Claims
1. A sensor-based intelligent operation and maintenance system for power distribution room equipment, comprising a processor and a memory, characterized in that: The processor executes the computer program stored in the memory to implement the following steps: Obtaining a temperature data sequence corresponding to each monitoring sub-time period in the current monitoring time period and an actual working power sequence corresponding to each monitoring sub-time period, wherein the data in the temperature data sequence is the temperature data in the power distribution room collected by the sensor, and the data in the actual working power sequence is the working power of the cooling system, which belongs to the power distribution room. The current monitoring time period includes the current monitoring moment; According to the adjacent temperature data in the temperature data sequence corresponding to each monitoring sub-time period, a heat dissipation performance coefficient of the heat dissipation system in each monitoring sub-time period is obtained; according to the heat dissipation performance coefficient and the actual working power sequence, a heat dissipation effect characterization value of the heat dissipation system in each monitoring sub-time period is obtained; According to the heat dissipation effect characterization value, a heat dissipation effect characterization value fitting curve is obtained by fitting, and according to the heat dissipation effect characterization value fitting curve, a predicted heat dissipation effect characterization value of the heat dissipation system at the next monitoring moment is predicted; According to the predicted heat dissipation effect characterization value, the working power of the heat dissipation system at the next monitoring moment is obtained.
2. The sensor-based intelligent operation and maintenance system for power distribution room equipment according to claim 1, characterized in that: The method for obtaining the heat dissipation performance coefficient of the heat dissipation system in each monitoring sub-time period includes: For any monitoring sub-time period, the temperature data sequence corresponding to the monitoring sub-time period is recorded as sequence A, the first ratio sequence of the sequence A is obtained, and the mean of the first ratio sequence is recorded as the first index value, and the maximum value in the sequence A is recorded as the second index value; the product of the first index value and the second index value is recorded as the heat dissipation performance coefficient of the heat dissipation system in the monitoring sub-time period, and the a-th first ratio value in the first ratio sequence is the ratio of the a-th temperature data in the sequence A to the a+1-th temperature data in the sequence A.
3. The sensor-based intelligent operation and maintenance system for power distribution room equipment according to claim 1, characterized in that: The method for obtaining the heat dissipation effect characterization value of the heat dissipation system in each monitoring sub-time period includes: For any monitoring sub-time period, the mean of the actual working power sequence corresponding to the monitoring sub-time period is added to the preset first constant, and the inverse of the addition result is recorded as the power characterization value; the product of the power characterization value and the heat dissipation performance coefficient of the heat dissipation system in the monitoring sub-time period is recorded as the heat dissipation effect characterization value of the heat dissipation system in the monitoring sub-time period.
4. The sensor-based intelligent operation and maintenance system for power distribution room equipment according to claim 1, characterized in that: The method for obtaining the heat dissipation effect characterization value fitting curve includes: For any monitoring sub-time period: in the historical monitoring time period, obtain all time periods that are the same as the time interval corresponding to the monitoring sub-time period, and record them as the historical sub-time periods corresponding to the monitoring sub-time period; obtain the heat dissipation effect characterization value of the heat dissipation system in the historical sub-time period, and construct a set of the heat dissipation effect characterization values of the heat dissipation system in all historical sub-time periods corresponding to the monitoring sub-time period and the heat dissipation effect characterization values of the heat dissipation system in the monitoring sub-time period, and record them as the heat dissipation effect characterization value set to be sorted; sort the data in the heat dissipation effect characterization value set to be sorted, and record the sorted sequence as the first sequence; use the median of the first sequence as the heat dissipation effect characterization value to be fitted for the monitoring sub-time period; A histogram is constructed according to the heat dissipation effect characterization values to be fitted in each monitoring sub-time period, wherein the horizontal axis of the coordinate space of the histogram is time and the vertical axis is the heat dissipation effect characterization values to be fitted; A curve fitting is performed on the histogram, and the fitting result is recorded as a heat dissipation effect characterization value fitting curve.
5. The sensor-based intelligent operation and maintenance system for power distribution room equipment according to claim 4, characterized in that: The method for obtaining the working power of the heat dissipation system at the next monitoring moment includes: On the heat dissipation effect characterization value fitting curve, obtain the ordinate value of the data point whose abscissa value corresponds to the time at the current monitoring moment, and record it as the fitted heat dissipation effect characterization value of the heat dissipation system at the current monitoring moment; record the ratio of the fitted heat dissipation effect characterization value to the predicted heat dissipation effect characterization value as the characteristic ratio, and record the product of the characteristic ratio and the preset second constant as the power adjustment coefficient corresponding to the next monitoring moment; According to the power adjustment coefficient, the working power of the heat dissipation system at the next monitoring moment is obtained.
6. The sensor-based intelligent operation and maintenance system for power distribution room equipment according to claim 5, characterized in that: The method for obtaining the working power of the heat dissipation system at the next monitoring moment according to the power adjustment coefficient includes: The actual working power of the cooling system at the current monitoring moment is obtained and recorded as the current actual working power; the product of the current actual working power and the power adjustment coefficient is recorded as the working power of the cooling system at the next monitoring moment.
Citation Information
Patent Citations
Safety intelligent monitoring method and system for nuclear power distribution cabinet
CN116169786A
Power electronic equipment heat dissipation adjusting method and device based on model prediction, and equipment
CN117355102A
Intelligent radiator control system based on data analysis
CN117724551A
Vehicle-mounted battery management method and system under cold condition and readable storage medium
CN118107502A
Intelligent electric fan control system and method based on Internet of Things technology
CN118224112A
Cited By
Intelligent water cooling system energy efficiency analysis and optimization scheduling system
CN120215656A
Ring main unit monitoring method
CN121123816A