Reusable reinforcement cage anti-floating device capable of detecting over-filling of concrete
By designing a reinforced cage anti-floating device combining base, extended components and test components, the problems of floating steel cages and overfilling detection errors caused by excessive empty piles are solved, and efficient construction quality control and cost reduction are achieved. Continuity of the pouring process is ensured in the event of a failure.
Patent Information
- Application Number
- CN202411291789.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-14
- Publication Date
- 2024-12-13
- Estimated Expiration
- 2044-09-14
AI Technical Summary
In the construction of cast-in piles, the length of the empty piles causes the steel cage to float up during the concrete pouring process, and the traditional rope measurement method has large errors in the over-filling height test of concrete.
Design a rebar cage anti-floating device including base, lengthened assembly, mounting base, rope measuring assembly and test assembly. It is installed on the rebar cage through base movable card, and the combined lengthened assembly and test assembly are used to realize the detection of concrete overfilling. And prevent the steel cage from floating, and improve the traditional rope measurement method through rope measurement components to ensure the continuity of the pouring process.
It effectively solves the problem of floating steel cages, ensures the control of overfilling of concrete, improves construction quality, reduces project costs, provides reliable engineering construction solutions, and ensures the continuity of the pouring process when testing component failures.
Smart Images

Figure CN119121939A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of concrete pouring equipment, and in particular relates to a reusable steel cage anti-floating device capable of detecting over-pouring of concrete. Background Art
[0002] Bored piles are a common process for reinforcing the foundation of buildings. In urban development, the demand for basements is becoming increasingly common, and the basements are deeper. However, the top elevation of the bored piles is usually lower than the bottom elevation of the basement. For the convenience of construction, the original ground rotary drilling process is often used. This practice easily leads to the problem of bored piles being too long. If the empty piles are too long, the steel cage may float up during the concrete pouring process. In addition, if the traditional rope measuring method is used to test the over-pouring height of concrete, there may be a large error, so we hope to design a steel cage anti-floating device with a new structure to solve this problem. Summary of the invention
[0003] In view of the deficiencies in the prior art, the present invention aims to provide a reusable anti-floating device for a steel cage that can detect over-pouring of concrete, so as to solve the problems raised in the above-mentioned background technology.
[0004] The present invention is realized by the following technical scheme: a reusable steel cage anti-floating device capable of detecting over-pouring of concrete, comprising: a base, an extension component, a mounting seat, a rope measuring component and a testing component, wherein the base is movably mounted on the upper side of the upper end of the steel cage body, the upper end of the extension component at the uppermost end of the base is fixedly connected to the inner wall of the upper end of the external steel casing through a U-shaped buckle, and a plurality of extension components for adjusting the length are movably mounted on the upper side of the base;
[0005] A test assembly for detecting over-filling of concrete is fixed at the lower end of the base, a mounting seat is movably inserted at the upper end of the extension assembly, and a rope measuring assembly for detecting over-filling of concrete is movably mounted on the upper side of the mounting seat.
[0006] As a preferred embodiment, the base comprises a channel steel 1, a steel ring 1 and a reinforcing rib 1, the inner wall of the steel ring 1 is welded with a reinforcing rib 1, the reinforcing rib 1 is a regular hexagonal structure, three channel steels 1 distributed in three equal parts are welded on the inner side of the reinforcing rib 1, and the three channel steels 1 are welded to the inner wall of the steel ring 1 in three equal parts through the reinforcing rib 1;
[0007] A baffle plate 1 is welded to the inner side of the upper ends of the three channel steels 1, and the upper ends of the three channel steels 1 are designed to be open, and one side of the opening of the channel steel is flush with the outer wall of the baffle plate 1, and the upper end of the channel steel 1 is away from the baffle plate. There are three linearly distributed fixing holes 1 from top to bottom;
[0008] A positioning plate 1 is horizontally welded inside the upper side of the channel steel 1, the outer end of the positioning plate 1 is flush with the outer wall of the baffle plate 1, the distance between the upper side of the positioning plate 1 and the lower end of the baffle plate is not less than 15 cm, and the middle of the lower ends of the three channel steels are recessed upward to form a slot;
[0009] The slot is an inverted V-shaped structural slot. The lower ends of the three channel steels are clamped with the circular steel bar ring at the upper end of the steel cage body through the slot. In actual use, the reinforcement ribs 1 and 2 are welded by six threaded steel bars with a diameter of 18 mm to form a regular hexagonal structure. The length and diameter of the threaded steel bars can be flexibly selected according to actual use. Channel steel 1 and channel steel 2 both adopt a 14a model channel steel, and its model can also be selected according to other needs. Steel ring 1 and steel ring 2 are both formed by rolling and welding flat steel with a width of 100 mm and a thickness of 2 mm, and its diameter can be made according to actual use requirements.
[0010] As a preferred embodiment, the extension assembly includes two channel steels, two steel rings and two reinforcing ribs. The inner wall of the two steel rings is welded with two reinforcing ribs. The two reinforcing ribs are a regular hexagonal structure. Three two channel steels distributed in three equal parts are welded on the inner side of the two reinforcing ribs. The three two channel steels are welded to the inner wall of the two steel rings in three equal parts through the two reinforcing ribs.
[0011] Baffle plates 2 are welded to the inner sides of the upper ends of the three channel steels 2. The upper ends of the three channel steels 2 are open in design. One side of the opening on the side of the channel steel 2 is flush with the outer wall of the baffle plate 2. Three linearly distributed fixing holes 2 are opened from top to bottom on the upper end of the channel steel 2 away from the baffle plate 2. In actual use, a circular hole with a diameter of 10 cm is opened on the side of the top of each channel steel 2 close to the steel ring 2. A U-shaped clip is used to connect the top of the channel steel 2 to the external steel casing through the circular hole. The circular hole is used to fix the extension component, so as to position the base and the steel cage body to improve the anti-floating performance of the entire device.
[0012] As a preferred embodiment, a second positioning plate is transversely welded inside the upper side of the second channel steel, the outer end of the second positioning plate is flush with the outer wall of the second baffle, and the distance between the upper side of the second positioning plate and the lower end of the second baffle is not less than 15 cm;
[0013] The structure and size of the steel ring 2 are the same as those of the steel ring 1, the structure and size of the reinforcing rib 2 are the same as those of the reinforcing rib 1, and the structure and size of the upper end of the channel steel 1 are the same as those of the upper end of the channel steel 2;
[0014] The length of the channel steel two is greater than that of the channel steel one. A square tube is welded to the lower end of each of the three channel steel twos. The length and width of the cross-section of the square tube match the length and width of the inner wall of the baffle two welded to the upper end of the channel steel two. The height of the square tube matches the distance between the baffle two and the top of the channel steel two.
[0015] As a preferred embodiment, the mounting seat includes an insert plate, a mounting ring and an insert tube, and the inner wall of the mounting ring is welded with three insert plates distributed in three equal parts, and the welding positions of the three insert plates match the welding positions of the three slots 2;
[0016] The cross-sectional dimension of the plug plate matches that of the square tube, the height of the plug plate is greater than the height of the square tube, an insert tube is welded on the right side of the upper surface of the mounting ring, and an angular hole is arranged inside the upper end of the insert tube.
[0017] As a preferred embodiment, the test assembly includes round steel 1, a steel buoy, round steel 2, flat steel and an axial pressure sensor, the lower end of the flat steel is fixed with an axial pressure sensor, the lower end of the axial pressure sensor is installed with round steel 2, and the axis of the round steel 2 is collinear with the axis of the axial pressure sensor;
[0018] A steel buoy is fixed at the lower end of the round steel No. 2, and a round steel No. 1 is welded to the inner part of the flat steel near the channel steel No. 1. The side of the round steel No. 1 near the channel steel No. 1 is fixedly connected to the inner wall of the channel steel No. 1. The height of the lower end of the steel buoy is flush with the height of the lower end of the channel steel. In actual use, the diameters of the round steel No. 1 and the round steel No. 2 are both 8mm, the diameter of the flat steel is 100mm, the size of the steel buoy is an outer diameter of 100mm, an inner diameter of 10mm, a height of 100mm, and a wall thickness of 2.35mm. It has an outer closed and inner hollow structure. The steel buoy is fixed to the bottom of the base by a round steel No. 1 with a diameter of 8mm, so that it can float up and down along the steel cage body. The top of the concrete overfilling test device adopts a 100mm diameter The flat steel is connected to the axial pressure sensor, and the flat steel is fixed to the bottom of one of the channel steels on the base through welding with a round steel with a diameter of 8mm. The axial pressure sensor is connected to an external control system for real-time monitoring of the over-filling of concrete. The connection method and signal transmission method of the axial pressure sensor and the external control system are existing and will not be repeated here. The size of the steel pontoon can be adjusted according to the specific gravity of the mud, and the weight of the steel pontoon and the buoyancy generated by the mud on it can be equal. The main principle is to use the different buoyancy of concrete and cement slurry. The force of the steel pontoon to float and squeeze the axial pressure sensor is different. The different signals sent by the axial pressure sensor are used to judge whether the concrete over-filling height meets the requirements.
[0019] As a preferred embodiment, the rope measuring assembly includes a plug rod, a crank handle, a mounting frame, an I-shaped wheel and a plumb bob. The lower end of the mounting frame is welded with a plug rod, and the lower end of the plug rod is provided with a ridge rod. The lower end of the plug rod is movably inserted into the upper end of the insert tube through the ridge rod.
[0020] A crank is rotatably mounted on the front side of the mounting frame, a rotating shaft is rotatably mounted on the left side of the mounting frame, the rotating connection portion between the crank and the mounting frame is fixedly connected to the front end of the rotating shaft, and a pinion is keyed to the outer wall of one end of the rotating shaft near the crank.
[0021] As a preferred embodiment, an I-shaped wheel is rotatably installed inside the right side of the mounting frame, a large gear is connected to the front key of the I-shaped wheel, and the large gear is meshed and connected with the small gear. A guide hole is formed by penetrating downward at the bottom of the left end of the mounting frame, and a guide cylinder is welded on the upper side of the inner wall of the left front end of the mounting frame;
[0022] A locking rod is slidably inserted inside the guide cylinder, a tip is provided at the lower end of the rod, a handle is provided at the upper end of the rod, and the tip is movably inserted in the tooth groove of the pinion gear;
[0023] A rope is wound in the middle of the I-shaped wheel, and the I-shaped wheel is fixedly connected to the upper end of the plumb bob through the rope and a lifting ring. The plumb bob is in a teardrop-shaped structure as a whole. The rope is movably inserted into the guide hole, and a distance mark is arranged on the outer wall of the rope.
[0024] After adopting the above technical scheme, the beneficial effects of the present invention are as follows: by setting a base, an extension component and a test component, the test component of the concrete over-pouring that can be tested is combined with the base and the extension component of the steel cage anti-floating. This innovative design not only solves the problem that the empty pile is too long and easily causes the steel cage body to float, but also ensures the control of the concrete over-pouring amount, thereby ensuring the construction quality of the engineering pile. In addition, the materials of the device are all common materials on the market, which effectively reduces the project cost, improves the project efficiency, and provides a reliable solution for engineering construction;
[0025] The setting of the rope test component improves the traditional rope test method. This method is only used temporarily when the test component fails. It can ensure that the entire pouring process continues and does not need to be stopped for maintenance due to test component failure, providing protection for engineering construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0027] Figure 1 The present invention is a schematic diagram of the overall structure of a reusable steel cage anti-floating device capable of detecting concrete overfilling.
[0028] Figure 2 The present invention is a schematic diagram of the connection between a base and an extension component of a reusable steel cage anti-floating device capable of detecting concrete overfilling.
[0029] Figure 3 The present invention is a schematic diagram of a base structure of a reusable steel cage anti-floating device capable of detecting concrete overfilling.
[0030] Figure 4 The schematic diagram of the extended component structure of a reusable steel cage anti-floating device capable of detecting concrete overfilling according to the present invention.
[0031] Figure 5 The present invention is a schematic diagram of the connection between a mounting base and a rope measuring component of a reusable steel cage anti-floating device capable of detecting concrete overfilling.
[0032] Figure 6 The present invention is a schematic diagram of a rope measuring component structure of a reusable steel cage anti-floating device capable of detecting over-filling of concrete.
[0033] Figure 7 The present invention is a schematic diagram of a test component structure of a reusable steel cage anti-floating device capable of detecting concrete overfilling.
[0034] Figure 8 The present invention is a schematic diagram of a plumb bob structure of a reusable steel cage anti-floating device capable of detecting over-filling of concrete.
[0035] Fig. 9 It is a schematic diagram of the connection between the extension component of the present invention and the external steel casing.
[0036] In the figure, 100-reinforcement cage body;
[0037] 200-base, 210-channel steel one, 211-baffle one, 212-fixing hole one, 213-positioning plate one, 214-slot, 220-steel ring one, 230-reinforcement rib one;
[0038] 300- extension assembly, 310- channel steel 2, 311- baffle 2, 312- fixing hole 2, 313- positioning plate 2, 314- square tube, 315- fixing hole 3, 320- steel ring 2, 330- reinforcing rib 2;
[0039] 400-mounting seat, 410-insertion plate, 420-mounting ring, 430-insertion tube;
[0040] 500-rope measuring assembly, 510-insertion rod, 520-crank handle, 530-mounting frame, 531-guide hole, 532-guide cylinder, 540-I-shaped wheel, 550-locking rod, 560-rotating shaft, 570-small gear, 580-large gear, 590-plumb bob, 591-lifting ring, 592-rope;
[0041] 600-test assembly, 610-round steel 1, 620-steel buoy, 630-round steel 2, 640-flat steel, 650-axial pressure sensor. DETAILED DESCRIPTION
[0042] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0043] See also Figures 1 to 9 The present invention provides a technical solution: a reusable steel cage anti-floating device capable of detecting over-pouring of concrete, comprising: a base 200, an extension component 300, a mounting seat 400, a rope measuring component 500 and a testing component 600, wherein the base 200 is movably mounted on the upper side of the upper end of the steel cage body 100, and the upper end of the extension component 300 at the uppermost end of the base 200 is fixedly connected to the inner wall of the upper end of the external steel casing through a U-shaped buckle, and a plurality of extension components 300 for adjusting the length are movably mounted on the upper side of the base 200;
[0044] A test assembly 600 for detecting over-filling of concrete is fixed at the lower end of the base 200, a mounting seat 400 is movably inserted at the upper end of the extension assembly 300, and a rope measuring assembly 500 for detecting over-filling of concrete is movably mounted on the upper side of the mounting seat 400.
[0045] See also Figures 1 to 4 The base 200 includes a channel steel 210, a steel ring 220 and a reinforcing rib 230. The inner wall of the steel ring 220 is welded with a reinforcing rib 230. The reinforcing rib 230 is a regular hexagonal structure. Three channel steels 210 distributed in three equal parts are welded on the inner side of the reinforcing rib 230. The three channel steels 210 are welded to the inner wall of the steel ring 220 in three equal parts through the reinforcing rib 230.
[0046] A baffle plate 211 is welded to the inner side of the upper ends of the three channel steels 210. The upper ends of the three channel steels 210 are designed to be open. One side of the opening of the side of the channel steel 210 is flush with the outer wall of the baffle plate 211. The upper end of the channel steel 210 away from the baffle plate 211 is provided with three linearly distributed fixing holes 212 from top to bottom.
[0047] A positioning plate 213 is welded horizontally inside the upper side of the channel steel 210, the outer end of the positioning plate 213 is flush with the outer wall of the baffle 211, the distance between the upper side of the positioning plate 213 and the lower end of the baffle 211 is not less than 15 cm, and the middle of the lower end of the three channel steels 210 is recessed upward to form a slot 214;
[0048] The clamping groove 214 is an inverted V-shaped structural groove. The lower ends of the three channel steels 210 are clamped with the circular steel bar ring at the uppermost end of the steel cage body 100 through the clamping groove 214. In actual use, the reinforcing ribs 230 and 330 are both welded by six threaded steel bars with a diameter of 18 mm to form a regular hexagonal structure. The length and diameter of the threaded steel bars can be flexibly selected according to actual use. The channel steels 210 and 310 both adopt a 14a type channel steel, and its model can also be selected as needed. The steel ring 220 and the steel ring 320 are both formed by rolling and welding the flat steel 640 with a width of 100 mm and a thickness of 2 mm, and its diameter can be made according to actual use requirements.
[0049] The extension component 300 includes a second channel steel 310, a second steel ring 320 and a second reinforcing rib 330. The inner wall of the second steel ring 320 is welded with a second reinforcing rib 330. The second reinforcing rib 330 is a regular hexagonal structure. Three second channel steels 310 distributed in three equal parts are welded on the inner side of the second reinforcing rib 330. The three second channel steels 310 are welded to the inner wall of the second steel ring 320 in three equal parts through the second reinforcing rib 330.
[0050] Baffle plates 311 are welded to the inner sides of the upper ends of the three channel steels 310. The upper ends of the three channel steels 310 are designed to be open. One side of the opening on the side of the channel steel 310 is flush with the outer wall of the baffle plate 311. Three linearly distributed fixing holes 312 are opened from top to bottom on the upper end of the channel steel 310 away from the baffle plate 311. In actual use, a circular hole with a diameter of 10 cm is opened on the side of the top of each channel steel 310 close to the steel ring 320. A U-shaped clip is used to connect the top of the channel steel 310 to the external steel casing through the circular hole. The circular hole is used to fix the extension component 300, so as to position the base 200 and the steel cage body 100 to improve the anti-floating performance of the entire device.
[0051] A second positioning plate 313 is horizontally welded inside the upper side of the second channel steel 310, the outer end of the second positioning plate 313 is flush with the outer wall of the second baffle 311, and the distance between the upper side of the second positioning plate 313 and the lower end of the second baffle 311 is not less than 15 cm;
[0052] The structure and size of the second steel ring 320 are the same as those of the first steel ring 220, the structure and size of the second reinforcing rib 330 are the same as those of the first reinforcing rib 230, and the structure and size of the upper end of the first channel steel 210 are the same as those of the upper end of the second channel steel 310;
[0053] The length of the second channel steel 310 is greater than that of the first channel steel 210. A square tube 314 is welded to the lower end of each of the three second channel steels 310. The cross-sectional length and width of the square tube 314 match the length and width of the inner wall of the baffle 2 311 welded to the upper end of the second channel steel 310. The height of the square tube 314 matches the distance between the baffle 2 311 and the top of the second channel steel 310.
[0054] As the first embodiment of the present invention, by setting a base 200 and an extension component 300, in actual use, the base 200 is abutted against the steel bars at the upper end of the steel cage through the three channel steels 210 thereon to achieve the purpose of fixing the steel cage, and the overall length of the extension component 300 and the base 200 can be adjusted according to the actual empty pile length. When the extension component 300 is added on the upper side of the base 200, the upper side of the three channel steels 210 on the base 200 is aligned with the square tube 314 at the lower end of the three channel steels 2 310 on the extension component 300, and the three square tubes 314 are processed and inserted into the upper side of the three channel steels 210, respectively, until the bottom of the three square tubes 314 are abutted against the upper side of the positioning plate 213 on the upper side of the channel steel 210. At this time, the surface extension component 300 is aligned with the base 200, and can be fixed by bolts through the fixing hole 212 on the channel steel 210 and the fixing hole 315 on the square tube 314;
[0055] After the installation is completed, the baffle plate 211 located on the upper side of the channel steel 210 can limit and strengthen the square tube 314 to improve the bending resistance. If an extension component 300 needs to be added to the upper side of the base 200, the installation method is the same as the above method, and the square tube 314 at the lower end of the subsequent extension component 300 is inserted into the upper side of the required extension component 300 until it abuts against the baffle plate 2 311, and then fixed in the same way. The present invention only needs to weld and assemble the raw materials as required, without other complicated processes. After the production of the present invention is completed, When the steel cage body 100 is lowered to the bottom of the hole, a sling is used to place it on the top of the steel cage body 100, and then the U-shaped buckle is used to connect and fix it with the steel casing. By dividing the entire reusable steel cage anti-floating device into a base 200 and a plurality of extension components 300, the entire device has strong flexibility in use, can cope with empty pile lengths of different sizes, greatly improves the reusability of the entire device, and does not need to be subsequently produced on site to match the steel cage anti-floating devices of different sizes of empty pile lengths, which saves production time and helps to improve engineering casting efficiency;
[0056] The following is a demonstration of the steps in the actual construction of the present invention:
[0057] 1. Measurement and setting out
[0058] Before construction, GPS is used to measure the position of each pile. Before drilling, a total station is used to determine the center position of the pile. During drilling, control points are often used to check the position of the pile hole using a total station or a cross line.
[0059] 2. Casing burial
[0060] The casing adopts a 9m deep casing and is buried according to the measured pile position (using a cross-controlled pile position). The casing needs to be 0.3m above the ground, with a grout opening left on the top of the casing. The center of the casing should coincide with the center of the measured pile position, and the deviation should be controlled within 50mm.
[0061] 3. Mud Preparation
[0062] During the drilling process, the mud indicators should be adjusted in time with the geological changes; before pouring concrete, the relative density of the mud within 500mm of the bottom of the hole should be less than 1.25; the sand content should not be greater than 8%, and the viscosity should not be greater than 28s.
[0063] 4. Hole forming construction
[0064] A rotary drilling rig is used to drill holes for foundation pit engineering piles. After the rotary drilling rig is in place, the pile position is checked to ensure accurate positioning. After slurrying is completed, drilling is started at a low speed. Normal drilling begins after the entire drill bit enters the soil layer. During the drilling process, the deviation of the pile position is checked regularly and corrected in time to ensure that the pile position deviation, axis and vertical axis direction do not exceed 50mm, and the verticality deviation is not more than 1%.
[0065] 5. Clear the hole
[0066] (1) First hole cleaning: After the hole reaches the required depth, the diameter, depth and verticality are fully inspected and qualified. Then the hole is cleaned by positive cycle method. After the hole cleaning is completed and the self-inspection is qualified, the various parameters of the pile hole are measured together with the supervision engineer.
[0067] (2) Second hole cleaning: After hoisting in the steel cage and conduit and before pouring underwater concrete, the performance indicators of the mud in the hole and the thickness of the sediment at the bottom of the hole should be checked again. If the requirements are not met, a second hole cleaning should be carried out.
[0068] The mud indicators and the thickness of the sludge in the open space after the above-mentioned primary and secondary hole cleaning should meet the design requirements.
[0069] 6. Fabrication and splicing of steel cage
[0070] The existing base 200 and the extension assembly 300 are assembled according to the actual length of the empty pile (if none of the splicing schemes meet the requirements of the empty pile length, the steel cage can be manufactured on site according to the design drawings).
[0071] 7. Steel cage hoisting
[0072] According to the weight of the steel cage and on-site working conditions, select appropriate cranes and slings to hoist and lower the steel cage.
[0073] 8. Steel cage anti-floating
[0074] After the steel cage is lowered to the designed elevation and fixed with the hanging rod, the crane for hoisting the steel cage is used to lift the device of the present invention (attached to the specification) Figure 1 ) is hoisted and lowered to the top of the steel cage.
[0075] 9. Concrete pouring
[0076] Calculate the first pouring volume according to the actual construction situation on site, and pour the bored piles. During the pouring process, the buried depth of the conduit needs to be controlled at 2 to 6 meters. After the concrete is poured to a certain height, the concrete will fill the steel buoy 620 (attached to the instruction manual) of the device. Figure 3 ) After floating, the axial pressure sensor 650 is squeezed, and pouring can be stopped when the pressure gauge data changes (if the axial pressure sensor 650 fails, the mounting base 400 and the rope measuring assembly 500 can be installed, and the rope measuring assembly 500 can be used for detection to ensure that pouring can proceed smoothly).
[0077] Please refer to 1 to Figure 3 , Figure 7 The mounting seat 400 includes an insert plate 410, a mounting ring 420 and an insert tube 430. Three insert plates 410 distributed in three equal parts are welded to the inner wall of the mounting ring 420. The welding positions of the three insert plates 410 match the welding positions of the three slots 2.
[0078] The cross-sectional dimension of the plug plate 410 matches that of the square tube 314 . The height of the plug plate 410 is greater than that of the square tube 314 . An insert tube 430 is welded on the right side of the upper surface of the mounting ring 420 . An angular hole is provided inside the upper end of the insert tube 430 .
[0079] The test assembly 600 includes a round steel 1 610, a steel buoy 620, a round steel 2 630, a flat steel 640 and an axial pressure sensor 650. The axial pressure sensor 650 is fixed at the lower end of the flat steel 640. The round steel 2 630 is installed at the lower end of the axial pressure sensor 650. The axis of the round steel 2 630 is collinear with the axis of the axial pressure sensor 650.
[0080] The lower end of round steel 630 is fixed with steel buoy 620, and the inner part of flat steel 640 close to channel steel 210 is welded with round steel 610, and the side of round steel 610 close to channel steel 210 is fixedly connected to the inner wall of channel steel 210, and the height of the lower end of steel buoy 620 is flush with the height of the lower end of channel steel 210. In actual use, the diameters of round steel 610 and round steel 630 are both 8mm, the diameter of flat steel 640 is 100mm, and the dimensions of steel buoy 620 are 100mm in outer diameter, 10mm in inner diameter, 100mm in height, and 2.3mm in wall thickness. 5mm, with an outer closed and inner hollow structure, the steel buoy 620 is fixed to the bottom of the base 200 by a round steel 610 with a diameter of 8mm, so that it can float up and down along the steel cage body 100, and the top of the concrete over-pouring test device is connected to the axial pressure sensor 650 by a flat steel 640 with a diameter of 100mm, and the flat steel 640 is fixed to the bottom of one of the channel steels 210 on the base 200 by welding with a round steel 630 with a diameter of 8mm, and the axial pressure sensor 650 is connected to the external control system for real-time monitoring of the concrete over-pouring situation;
[0081] The connection method and signal transmission method of the axial pressure sensor 650 and the external control system are existing and will not be elaborated here. The size of the steel float 620 can be adjusted according to the specific gravity of the mud, and the weight of the steel float 620 and the buoyancy generated by the mud on it can be equal. The main principle is to use the difference between the buoyancy of concrete and the buoyancy of cement slurry. The force of the steel float 620 to float and squeeze the axial pressure sensor 650 is different. The different signals sent by the axial pressure sensor 650 are used to judge whether the concrete over-filling height meets the requirements.
[0082] As the second embodiment of the present invention, based on the above-mentioned first embodiment, the setting of the test component 600, the test component 600 in combination with the base 200 and the extension component 300 can effectively prevent the occurrence of the steel cage floating phenomenon. At the same time, the concrete over-pouring height test replaces the traditional manual combined with the measuring rope method, improves the accuracy of the test, ensures the quality of the pile foundation, reduces the consumption of concrete, and increases the benefits of the project. The main raw materials are 14a channel steel, flat steel 640, steel bars and axial pressure sensors 650, and the materials are all common materials on the market, which makes the manufacturing cost of the entire device lower, which helps to reduce the construction cost of engineering construction.
[0083] See also Figure 1 , Figure 2 , Figures 5 to 8 The rope measuring assembly 500 includes an insert rod 510, a crank handle 520, a mounting frame 530, an I-shaped wheel 540 and a plumb bob 590. The insert rod 510 is welded to the lower end of the mounting frame 530. The lower end of the insert rod 510 is provided with a ridge rod. The lower end of the insert rod 510 is movably inserted into the upper end of the insert tube 430 through the ridge rod.
[0084] A crank 520 is rotatably mounted on the front side of the mounting frame 530, and a rotating shaft 560 is rotatably mounted on the left side of the mounting frame 530. The rotating connection part between the crank 520 and the mounting frame 530 is fixedly connected to the front end of the rotating shaft 560, and a pinion 570 is keyed to the outer wall of the rotating shaft 560 near one end of the crank 520.
[0085] An I-shaped wheel 540 is rotatably mounted inside the right side of the mounting frame 530, a large gear 580 is keyed to the front side of the I-shaped wheel 540, the large gear 580 is meshed and connected with the small gear 570, a guide hole 531 is formed by penetrating downwards at the bottom of the left end of the mounting frame 530, and a guide cylinder 532 is welded to the upper side of the inner wall of the left front end of the mounting frame 530;
[0086] A locking rod 550 is slidably inserted inside the guide cylinder 532, a tip is provided at the lower end of the insertion rod 510, a handle is provided at the upper end of the insertion rod 510, and the tip is movably inserted in the tooth groove of the pinion gear 570;
[0087] A rope 592 is wound around the middle of the I-shaped wheel 540, and the I-shaped wheel 540 is fixedly connected to the upper end of the plumb bob 590 through the rope 592 and the ring 591. The plumb bob 590 is in a teardrop-shaped structure as a whole. The rope 592 is movably inserted into the guide hole 531, and a distance mark is set on the outer wall of the rope 592.
[0088] As the third embodiment of the present invention, based on the above second embodiment, the setting of the rope measuring component 500 improves the traditional rope measuring method. In actual use, if the pressure shaft pressure sensor 650 fails, the user can directly quickly insert the mounting seat 400 installed with the test component 600 into the upper end of the extension component 300, so that the plug plate 410 is plugged into the upper end of the second channel steel 310, and the mounting ring 420 is abutted against the upper end of the second channel steel 310, so that the mounting seat 400 is quickly installed on the upper end of the extension component 300, and then the handle 5 can be shaken. 20 drives the small gear 570 on the front side of the rotating shaft 560 to rotate. Since the small gear 570 is meshed and connected with the large gear 580, the large gear 580 is driven to rotate and then drives the I-shaped wheel 540 to rotate to lower the rolled rope 592. The rope 592 enters the guide hole 531 through the rotating shaft 560 and vertically downward under the action of the plumb bob 590 at the end (the plumb bob 590 will not contact any parts on the extension component 300 and the base 200 when it falls, and will not affect the pouring of concrete). The length of the rope 592 lowered is determined according to the length of the pile hole.
[0089] After being lowered to a specified length, the locking rod 550 is inserted downward to lock the pinion 570, thereby fixing the length of the rope 592. Since the outer wall of the rope 592 is provided with a distance mark (the distance mark can be provided with a conspicuous mark, and the distance mark can be accurate to centimeters, so as to facilitate the control of the retracted and released length of the rope 592), after the concrete reaches the bottom of the plumb bob 590, the bottom of the plumb bob 590 has a supporting force, and its downward pulling and retracting force will be weakened, and the part of the rope 592 located at the rotating shaft 560 will be loose. Once the loosening phenomenon occurs, it means that the concrete has been poured to the bottom position of the plumb bob 590, and the pouring can be stopped. This method is only used temporarily when the test component 600 fails, and can ensure that the entire pouring process continues, and there is no need to stop for maintenance due to the failure of the test component 600, thereby providing protection for engineering construction.
[0090] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A reusable steel cage anti-floating device capable of detecting overfilling of concrete, include: A base (200), an extension component (300), a mounting seat (400), a rope measuring component (500) and a testing component (600), wherein the base (200) is movably mounted on the upper side of the upper end of the steel cage body (100), and the upper end of the extension component (300) at the uppermost end of the base (200) is fixedly connected to the inner wall of the upper end of the external steel casing through a U-shaped buckle, and is characterized in that a plurality of extension components (300) for adjusting the length are movably mounted on the upper side of the base (200); A test assembly (600) for detecting over-pouring of concrete is fixed at the lower end of the base (200), a mounting seat (400) is movably inserted at the upper end of the extension assembly (300), and a rope measuring assembly (500) for detecting over-pouring of concrete is movably mounted on the upper side of the mounting seat (400).
2. A reusable steel cage anti-floating device capable of detecting overfilling of concrete as claimed in claim 1, Features: The base (200) comprises a channel steel (210), a steel ring (220) and a reinforcing rib (230); the inner wall of the steel ring (220) is welded with a reinforcing rib (230); the reinforcing rib (230) is a regular hexagonal structure; three channel steels (210) distributed in three equal parts are welded inside the reinforcing rib (230); the three channel steels (210) are welded to the inner wall of the steel ring (220) in three equal parts through the reinforcing rib (230); A baffle plate (211) is welded to the inner side of the upper ends of the three channel steels (210); the upper ends of the three channel steels (210) are designed to be open, and one side of the side opening of the channel steel (210) is flush with the outer wall of the baffle plate (211); and three fixing holes (212) are opened from top to bottom on the upper end of the channel steel (210) away from the baffle plate (211); A positioning plate (213) is welded transversely inside the upper side of the channel steel (210), the outer end of the positioning plate (213) is flush with the outer wall of the baffle plate (211), the distance between the upper side of the positioning plate (213) and the lower end of the baffle plate (211) is not less than 15 cm, and the middle of the lower ends of the three channel steels (210) are recessed upward to form a slot (214); The clamping groove (214) is an inverted V-shaped structural groove, and the lower ends of the three channel steels (210) are clamped with the circular steel bar ring at the uppermost end of the steel cage body (100) through the clamping groove (214).
3. A reusable steel cage anti-floating device capable of detecting overfilling of concrete as claimed in claim 1, Features: The extension component (300) comprises a second channel steel (310), a second steel ring (320) and a second reinforcing rib (330), the inner wall of the second steel ring (320) is welded with a second reinforcing rib (330), the second reinforcing rib (330) is a regular hexagonal structure, three second channel steels (310) distributed in three equal parts are welded on the inner side of the second reinforcing rib (330), and the three second channel steels (310) are welded to the inner wall of the second steel ring (320) in three equal parts through the second reinforcing rib (330); Baffle plates 2 (311) are welded to the inner sides of the upper ends of the three channel steels 2 (310); the upper ends of the three channel steels 2 (310) are designed to be open, and one side of the side opening of the channel steel 2 (310) is flush with the outer wall of the baffle plate 2 (311); and three fixing holes 2 (312) are opened from top to bottom on the upper end of the channel steel 2 (310) away from the side of the baffle plate 2 (311).
4. A reusable steel cage anti-floating device capable of detecting overfilling of concrete as claimed in claim 3, Features: A second positioning plate (313) is welded transversely inside the upper side of the second channel steel (310), the outer end of the second positioning plate (313) is flush with the outer wall of the second baffle plate (311), and the distance between the upper side of the second positioning plate (313) and the lower end of the second baffle plate (311) is not less than 15 cm; The structure and size of the second steel ring (320) are the same as those of the first steel ring (220), the structure and size of the second reinforcing rib (330) are the same as those of the first reinforcing rib (230), and the structure and size of the upper end of the first channel steel (210) are the same as those of the upper end of the second channel steel (310); The length of the second channel steel (310) is greater than that of the first channel steel (210). A square tube (314) is welded to the lower end of each of the three second channel steels (310). The cross-sectional length and width of the square tube (314) match the length and width of the inner wall of the second baffle plate (311) welded to the upper end of the second channel steel (310). The height of the square tube (314) matches the distance between the second baffle plate (311) and the top of the second channel steel (310).
5. A reusable steel cage anti-floating device capable of detecting overfilling of concrete as claimed in claim 4, Features: The mounting seat (400) comprises an insert plate (410), a mounting ring (420) and an insert tube (430); three insert plates (410) distributed in three equal parts are welded on the inner wall of the mounting ring (420); the welding positions of the three insert plates (410) match the welding positions of the three slots 2; The cross-sectional dimensions of the plug plate (410) match those of the square tube (314); the height of the plug plate (410) is greater than the height of the square tube (314); an insert tube (430) is welded on the right side of the upper surface of the mounting ring (420); and an angular hole is provided inside the upper end of the insert tube (430).
6. A reusable steel cage anti-floating device capable of detecting overfilling of concrete as claimed in claim 2, Features: The test assembly (600) includes round steel one (610), a steel buoy (620), round steel two (630), a flat steel (640) and an axial pressure sensor (650), wherein the axial pressure sensor (650) is fixed at the lower end of the flat steel (640), and round steel two (630) is installed at the lower end of the axial pressure sensor (650), and the axis of the round steel two (630) is collinear with the axis of the axial pressure sensor (650); A steel buoy (620) is fixed to the lower end of the round steel 2 (630), and the flat steel (640) is welded to the round steel 1 (610) near the inner side of the channel steel 1 (210). The side of the round steel 1 (610) near the channel steel 1 (210) is fixedly connected to the inner wall of the channel steel 1 (210), and the height of the lower end of the steel buoy (620) is flush with the height of the lower end of the channel steel 1 (210).
7. A reusable steel cage anti-floating device capable of detecting overfilling of concrete as claimed in claim 5, Features: The rope measuring assembly (500) comprises an insertion rod (510), a crank handle (520), a mounting frame (530), an I-shaped wheel (540) and a plumb bob (590); the insertion rod (510) is welded to the lower end of the mounting frame (530); a prism is provided at the lower end of the insertion rod (510); the lower end of the insertion rod (510) is movably inserted into the interior of the upper end of the insertion tube (430) via the prism; A crank handle (520) is rotatably mounted on the front side of the mounting frame (530), a rotating shaft (560) is rotatably mounted on the left side of the mounting frame (530), a rotatably connected portion between the crank handle (520) and the mounting frame (530) is fixedly connected to the front end of the rotating shaft (560), and a pinion gear (570) is keyed to the outer wall of one end of the rotating shaft (560) close to the crank handle (520).
8. A reusable steel cage anti-floating device capable of detecting overfilling of concrete as claimed in claim 7, Features: An I-shaped wheel (540) is rotatably mounted inside the right side of the mounting frame (530), a large gear (580) is keyed to the front side of the I-shaped wheel (540), the large gear (580) is meshed and transmission-connected with a small gear (570), a guide hole (531) is formed through the bottom of the left end of the mounting frame (530), and a guide cylinder (532) is welded to the upper side of the inner wall of the left front end of the mounting frame (530); A locking rod (550) is slidably inserted inside the guide cylinder (532), a tip is provided at the lower end of the insertion rod (510), a handle is provided at the upper end of the insertion rod (510), and the tip is movably inserted in the tooth groove of the pinion gear (570); A rope (592) is wound around the middle of the I-shaped wheel (540). The I-shaped wheel (540) is fixedly connected to the upper end of a plumb bob (590) through the rope (592) and a hanging ring (591). The plumb bob (590) is in a teardrop-shaped structure as a whole. The rope (592) is movably inserted into the guide hole (531). A distance mark is provided on the outer wall of the rope (592).
Citation Information
Patent Citations
Construction method for test pile with ultra-buried depth in rock stratum
CN111519613A
Device of keyhole bored concrete pile steel reinforcement cage come -up
CN208219629U
Steel reinforcement cage lifting and positioning device
CN211849454U
Pile concrete buoyancy controller
CN220132973U
Anti-floating structure of cast-in-situ bored pile reinforcement cage
CN220377257U
Cited By
Reinforcement cage positioning device for cement pile foundation construction
CN121519491A