Anti-slide pile model generation method and construction method based on BIM

The digital twin model of anti-sliding piles is generated through BIM technology, which solves the problem of inconvenient parameter acquisition in anti-sliding pile construction, and realizes smarter construction guidance and precise construction operations.

CN119129198AActive Publication Date: 2024-12-13CHINA RAILWAY BEIJING ENG GRP CO LTD +1
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411112665.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-12-13
Estimated Expiration
2044-08-14

AI Technical Summary

Technical Problem

In the construction of anti-sliding piles, manual cannot intuitively understand the construction parameters, resulting in the construction being not intelligent enough and lack of intelligent construction guidance.

Method used

Using the anti-sliding pile model generation method based on BIM technology, by obtaining the slope support project plan and three-dimensional model during the earth and stone filling process, a digital twin model indicating the construction of anti-sliding piles is generated, and provided to the construction personnel for their convenience of viewing and Perform construction.

Benefits of technology

The intelligence of anti-sliding pile construction has been improved, the operation guidance of construction personnel has been enhanced, and the accuracy and efficiency of construction have been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119129198A_ABST
    Figure CN119129198A_ABST
Patent Text Reader

Abstract

The invention provides an anti-slide pile model generation method and construction method based on BIM, and the method comprises the steps: obtaining a slope retaining engineering plan in an earth-rock filling process; obtaining a three-dimensional model of the earth-rock filling site; based on the BIM technology, an anti-slide pile model is generated according to the slope retaining engineering plan and the three-dimensional model of the earth-rock filling site; the slide-resistant pile model is displayed to constructors; and after the display is completed, the anti-slide pile construction process of constructors is supervised. According to the anti-slide pile model generation method based on the BIM and the construction method, the slope retaining engineering plan in the earth and stone filling process is obtained, meanwhile, the three-dimensional model of the earth and stone filling site is obtained, the BIM technology is introduced, the digital twinborn model indicating anti-slide pile construction is generated, follow-up constructors can conveniently check the digital twinborn model, and the method is more intelligent.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of BIM, and in particular to a BIM-based anti-slide pile model generation method and a construction method. Background Art

[0002] Anti-slide piles are an engineering structure that is mainly used to enhance the stability of slopes or slopes to prevent landslides and soil instability. Anti-slide piles can be a single pile, a double pile, or a combination of multiple piles, and are sometimes used in conjunction with other retaining structures (such as retaining walls, anchors, etc.). When designing, factors such as geological conditions, soil type, slope, and loads (such as additional loads caused by earthquakes, rainfall, etc.) need to be considered.

[0003] When carrying out anti-slip pile construction, the anti-slip piles of a project are characterized by a large number, great construction difficulty, great construction period pressure and high quality requirements.

[0004] The invention patent with application number: CN202311689634.8 discloses a construction method for a combination of concrete replacement and anti-slide piles on a channel slope, the method comprising: without changing the top and toe lines of the channel slope, the area with rich soft interlayer development in the channel slope is reinforced with a combination of concrete replacement and anti-slide piles, and the concrete replacement amount and anti-slide pile construction parameters are reasonably determined to achieve the purpose of comprehensively improving the anti-slide stability requirements of the channel slope. The above method is based on the strength reduction method, by reducing the strength parameters of the channel slope body and the soft interlayer, introducing the concrete replacement ratio and the anti-slide pile bearing coefficient, combining the two to form a variety of working conditions and calculating the corresponding safety factor, comprehensively determining the combination of concrete replacement amount and anti-slide pile parameters from the perspective of construction difficulty and economy, and completing the reinforcement construction of the channel slope.

[0005] However, when constructing anti-slide piles in the above-mentioned prior art, humans cannot intuitively know the construction parameters of the anti-slide piles, and need to construct according to the design data, which is not smart enough.

[0006] In view of this, there is an urgent need for a BIM-based anti-slide pile model generation method and construction method to at least solve the above-mentioned deficiencies. Summary of the invention

[0007] One of the purposes of the present invention is to provide a BIM-based anti-slide pile model generation method and construction method to obtain the slope support engineering plan during the earth and stone filling process. At the same time, a three-dimensional model of the earth and stone filling site is obtained, and BIM technology is introduced to generate a digital twin model indicating the construction of anti-slide piles, which is convenient for subsequent construction personnel to view and is more intelligent.

[0008] The method for generating an anti-slide pile model based on BIM provided by an embodiment of the present invention includes:

[0009] Step 1: Obtain the slope support engineering plan during the earthwork filling process;

[0010] Step 2: Obtain a three-dimensional model of the earthwork filling site;

[0011] Step 3: Based on BIM technology, generate an anti-slide pile model according to the slope support engineering plan and the three-dimensional model of the earthwork filling site.

[0012] Preferably, step 1: obtaining a slope support engineering plan during earthwork filling, including:

[0013] During the earthwork filling process, the necessity of slope support analysis should be carried out;

[0014] If the result of the slope support necessity analysis is that it is necessary to carry out slope support, the target slope is determined;

[0015] Determine the slope characteristics of the target slope;

[0016] Determine the slope support engineering plan based on the slope characteristics of the target slope.

[0017] Preferably, the slope support engineering plan is determined according to the slope characteristics of the target slope, including:

[0018] Perform slope feature clustering on the slope features to obtain slope feature clustering results;

[0019] Determine at least one first retaining platform according to the slope feature clustering result;

[0020] Traverse each first retaining platform in turn, take the first retaining platform being traversed as the second retaining platform, and take the slope characteristics corresponding to the second retaining platform as the basis for formulating the first slope retaining engineering plan of the second retaining platform;

[0021] According to the basis for the first slope retaining project plan, determine the target plan for the second retaining platform;

[0022] When all the first retaining platforms are traversed, the target plan is summarized as the slope retaining project plan.

[0023] Preferably, according to the basis for formulating the first slope retaining engineering plan, the target plan for the second retaining platform is determined, including:

[0024] Obtain anti-slide pile support records;

[0025] Analyze the anti-slide pile support records to obtain the basis for the second slope support project plan;

[0026] Determine whether the basis for formulating the second slope support engineering plan is similar to the basis for formulating the first slope support engineering plan;

[0027] If there is a similarity, obtain the first anti-slide pile specification parameters and the first anti-slide pile support point corresponding to the corresponding second slope support engineering plan formulation basis, and determine the target plan according to the first anti-slide pile specification parameters and the first anti-slide pile support point;

[0028] If there is no similarity, the anti-slide pile support strategy formulation model is trained based on the anti-slide pile support records;

[0029] Obtaining specification parameters of the second anti-slide pile;

[0030] Based on the anti-slide pile support strategy formulation model, the specification parameters of the third anti-slide pile and the second anti-slide pile support point are determined according to the specification parameters of the second anti-slide pile and the second support platform;

[0031] Retrieving the anti-slide pile simulation entity according to the third anti-slide pile specification parameters and the anti-slide pile simulation entity library;

[0032] Construct a third retaining platform simulating the second retaining platform;

[0033] Based on the relative position of the second anti-sliding pile support point in the second support platform, simulate the anti-sliding pile simulation entity supporting in the third support platform to obtain a first simulation result;

[0034] Obtain simulation parameters of instability factors;

[0035] Determining a second simulation result according to the instability factor simulation parameter and the first simulation result;

[0036] If the second simulation result meets the simulation expectations, the target plan is determined according to the specification parameters of the third anti-sliding pile and the support points of the second anti-sliding pile; otherwise, the second simulation result is attributed and the specification parameters of the third anti-sliding pile and the support points of the second anti-sliding pile are adjusted based on the attribution results, and the target plan is determined according to the adjusted specification parameters of the third anti-sliding pile and the support points of the second anti-sliding pile.

[0037] Preferably, obtaining the instability factor simulation parameters includes:

[0038] Obtain subsequent application information of the second support platform;

[0039] The instability factors are obtained according to the subsequent application information, and the simulation parameters of the instability factors are determined according to the conversion rules of the instability factors on the simulation platform.

[0040] Preferably, step 2: obtaining a three-dimensional model of the earthwork filling site includes:

[0041] Acquire first three-dimensional scanning data collected by a first three-dimensional scanning data acquisition party of the earthwork filling site; wherein the first three-dimensional scanning data acquisition party includes: site staff and / or site operation drones;

[0042] A three-dimensional model is constructed according to the first three-dimensional scanning data.

[0043] Preferably, step 3: based on BIM technology, according to the slope support engineering plan and the three-dimensional model of the earthwork filling site, an anti-slide pile model is generated, including:

[0044] According to the slope support engineering plan, the second three-dimensional scanning data and the anti-sliding pile support points of each second support platform are determined; the second three-dimensional scanning data are: the three-dimensional parameters of the anti-sliding piles used in the second support platform;

[0045] Based on BIM technology, the anti-slide pile model is rendered in the 3D model according to the anti-slide pile support points and the second 3D scanning data.

[0046] The anti-slide pile construction method based on BIM provided in an embodiment of the present invention includes:

[0047] Demonstrate the anti-slide pile model to construction workers;

[0048] After the demonstration, supervise the construction workers’ anti-slide pile construction process;

[0049] Wherein, the anti-slide pile model is a model generated according to any one of the above-mentioned BIM-based anti-slide pile model generation methods.

[0050] Preferably, the anti-slide pile model is displayed to the construction personnel, including:

[0051] Obtain the construction area that the construction personnel are responsible for;

[0052] Determine the local anti-slide pile model according to the construction area;

[0053] Obtaining the first anti-slide pile simulation point, the construction personnel simulation point, and the construction personnel's simulated sight distance in the local anti-slide pile model;

[0054] According to the construction worker's simulated point, the construction worker's sight direction and the simulated sight distance, an observation circle is constructed; wherein the observation circle is perpendicular to the sight direction and tangent to the straight line passing through the construction worker's simulated point, and the tangent point is the construction worker's simulated point; the construction worker's virtual sight point falls into the observation circle, and the diameter of the observation circle is equal to the simulated sight distance;

[0055] Acquire the first anti-sliding pile simulation point that falls into the observation circle and use it as the second anti-sliding pile simulation point;

[0056] The remaining first anti-slide pile simulation points except the second anti-slide pile simulation point in the first anti-slide pile simulation points are used as third anti-slide pile simulation points;

[0057] Based on the minimum observation circle projection rule, the minimum observation circle that can include all the third anti-slide pile simulation points is determined, and the projected observation circle is used as the area to be observed;

[0058] Plan the shortest arrival distance trajectory based on the regional boundary points of the area to be observed and the simulated points of the construction personnel;

[0059] The shortest reach distance trajectory is sent to the construction workers as navigation information.

[0060] The BIM-based anti-slide pile construction method provided in an embodiment of the present invention further includes:

[0061] When the construction personnel arrive at the area boundary point corresponding to the shortest arrival distance trajectory, the area center of the area to be observed corresponding to the area boundary point arrived at is obtained;

[0062] Based on the center of the area and the area boundary points reached by the construction workers, a viewing vector is constructed and the construction workers are instructed.

[0063] The beneficial effects of the present invention are:

[0064] The present invention obtains the slope support engineering plan during the earth and stone filling process, and at the same time obtains the three-dimensional model of the earth and stone filling site, introduces BIM technology, and generates a digital twin model indicating the construction of anti-sliding piles, which is convenient for subsequent construction personnel to view and is more intelligent.

[0065] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures specifically pointed out in the present application documents.

[0066] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0067] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0068] Figure 1 It is a schematic diagram of a method for generating an anti-slide pile model based on BIM in an embodiment of the present invention. DETAILED DESCRIPTION

[0069] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.

[0070] The embodiment of the present invention provides a method for generating an anti-slide pile model based on BIM, such as Figure 1 As shown, including:

[0071] Step 1: Obtain the slope support engineering plan during the earthwork filling process; the earthwork filling process is: in the construction project, the process of changing the original terrain by digging, transporting and filling earth and stone materials; the slope support engineering plan is: the engineering plan for preventing the sliding and collapse of the slope surface soil using anti-slide piles on the slope or slope;

[0072] Step 2: Obtain a three-dimensional model of the earthwork filling site; wherein the three-dimensional model is: a 3D model constructed based on the scanning results of the earthwork filling site;

[0073] Step 3: Based on BIM technology, generate an anti-slide pile model according to the slope support engineering plan and the three-dimensional model of the earthwork filling site. The anti-slide pile model is a digital twin model in which the BIM information of the anti-slide piles to be constructed is annotated in the three-dimensional model of the earthwork filling site.

[0074] The working principle and beneficial effects of the above technical solution are:

[0075] The present invention obtains the slope support engineering plan during the earth and stone filling process, and at the same time obtains the three-dimensional model of the earth and stone filling site, introduces BIM technology, and generates a digital twin model indicating the construction of anti-sliding piles, which is convenient for subsequent construction personnel to view and is more intelligent.

[0076] In one embodiment, step 1: obtaining a slope support engineering plan during earthwork filling, includes:

[0077] During the earthwork filling process, the necessity analysis of slope support is carried out; the necessity analysis of slope support is to analyze whether slope support is necessary by considering factors such as geological conditions, slope and soil stability;

[0078] If the result of the slope support necessity analysis is that it is necessary to support the slope, the target slope is determined; wherein the target slope is: the slope that needs to be supported;

[0079] Determine the slope characteristics of the target slope; wherein the slope characteristics are: physical and geological properties of the target slope;

[0080] Determine the slope support engineering plan based on the slope characteristics of the target slope.

[0081] The working principle and beneficial effects of the above technical solution are:

[0082] The invention performs a necessity analysis of slope support during earth and stone filling, and when the analysis shows that it is necessary, determines the target slope and extracts the slope characteristics of the target slope. Based on the slope characteristics, the slope support engineering plan is determined, thereby improving the rationality of the slope support engineering plan.

[0083] In one embodiment, according to the slope characteristics of the target slope, a slope support engineering plan is determined, including:

[0084] Perform slope feature clustering on the slope features to obtain slope feature clustering results; wherein slope feature clustering refers to classifying slopes with similar features into one category;

[0085] According to the clustering result of the slope characteristics, at least one first retaining platform is determined; wherein the first retaining platform is: a slope with similar characteristics;

[0086] Traverse each first retaining platform in turn, take the first retaining platform being traversed as the second retaining platform, and take the slope characteristics corresponding to the second retaining platform as the basis for formulating the first slope retaining engineering plan of the second retaining platform;

[0087] According to the basis for the formulation of the first slope retaining project plan, determine the target plan for the second retaining platform; the target plan is: the anti-sliding pile model setting plan for the second retaining platform, such as: where to set the anti-sliding piles with what specifications and parameters;

[0088] When all the first retaining platforms are traversed, the target plan is summarized as the slope retaining project plan.

[0089] The working principle and beneficial effects of the above technical solution are:

[0090] Since different slope features correspond to different strategies for setting anti-slide piles, the slope features are clustered, and the retaining platforms are divided according to the slope feature clustering results. According to the first slope support engineering plan formulation basis of each second retaining platform, the target plan is formulated separately, and the target plan is summarized as the slope support engineering plan, which improves the accuracy of the slope support engineering plan formulation.

[0091] In one embodiment, according to the basis for formulating the first slope retaining engineering plan, determining the target plan for the second retaining platform includes:

[0092] Obtaining the anti-sliding pile support record; wherein the anti-sliding pile support record is: the process record of the anti-sliding pile support in history;

[0093] Analyze the anti-sliding pile support record to obtain the basis for formulating the second slope support project plan; the basis for formulating the second slope support project plan is: the basis for formulating the support operation plan in the anti-sliding pile support record;

[0094] Determine whether the basis for formulating the second slope support engineering plan is similar to the basis for formulating the first slope support engineering plan;

[0095] If there is similarity, obtain the first anti-slide pile specification parameters and the first anti-slide pile support point corresponding to the corresponding second slope support engineering plan formulation basis, and determine the target plan according to the first anti-slide pile specification parameters and the first anti-slide pile support point; wherein the first anti-slide pile specification parameters are: when the second slope support engineering plan formulation basis is similar to the first slope support engineering plan formulation basis, the specification parameters of the anti-slide piles recorded in the corresponding anti-slide pile support record; the first anti-slide pile support point is: when the second slope support engineering plan formulation basis is similar to the first slope support engineering plan formulation basis, the distribution position of the anti-slide piles recorded in the corresponding anti-slide pile support record in the corresponding building entity;

[0096] If there is no similarity, the anti-sliding pile support strategy formulation model is trained according to the anti-sliding pile support record; wherein the anti-sliding pile support strategy formulation model is: an AI model trained according to the anti-sliding pile support record and replacing manual anti-sliding pile support strategy formulation;

[0097] Obtaining specification parameters of the second anti-slide pile; wherein the specification parameters of the second anti-slide pile are: specification parameters of all locally applicable anti-slide piles that can be obtained by big data;

[0098] Based on the anti-sliding pile support strategy formulation model, according to the second anti-sliding pile specification parameters and the second support platform, determine the third anti-sliding pile specification parameters and the second anti-sliding pile support point; wherein the third anti-sliding pile specification parameters and the second anti-sliding pile support point are: the anti-sliding pile support strategy formulation model determines the anti-sliding pile support strategy (the selected anti-sliding pile specification parameters and support position) based on the first slope support engineering plan formulation basis of the second support platform for which the anti-sliding pile support strategy formulation is required;

[0099] According to the third anti-slide pile specification parameter and the anti-slide pile simulation entity library, the anti-slide pile simulation entity is retrieved; wherein the anti-slide pile simulation entity library is: a database storing simulation data of anti-slide piles with different specification parameters in a simulation platform of a construction project; the anti-slide pile simulation entity is: simulation parameters corresponding to the third anti-slide pile specification parameter;

[0100] Constructing a third retaining platform simulating the second retaining platform; wherein the third retaining platform is: the second retaining platform simulated in the simulation platform of the construction project;

[0101] Based on the relative position of the second anti-sliding pile support point in the second support platform, simulate the anti-sliding pile simulation entity supporting in the third support platform to obtain a first simulation result; wherein the first simulation result is: a simulation model obtained after simulating the setting of the anti-sliding pile in the third support platform based on the relative position of the second anti-sliding pile support point in the second support platform;

[0102] Acquire instability factor simulation parameters; wherein the instability factor simulation parameters are: simulation data of environmental factors that affect the stability of the second retaining platform;

[0103] Determine a second simulation result according to the instability factor simulation parameter and the first simulation result; wherein the second simulation result is: a simulation result of the corresponding simulation model after applying the interference of the instability factor simulation parameter on the basis of the first simulation result;

[0104] If the second simulation result meets the simulation expectation, the target plan is determined according to the third anti-slide pile specification parameters and the second anti-slide pile support point. Otherwise, the second simulation result is attributed and the third anti-slide pile specification parameters and the second anti-slide pile support point are adjusted based on the attribution result, and the target plan is determined according to the adjusted third anti-slide pile specification parameters and the second anti-slide pile support point. Among them, meeting the simulation expectation means that the third support platform does not collapse, a large amount of soil erosion, and other phenomena that do not meet the construction standards.

[0105] The working principle and beneficial effects of the above technical solution are:

[0106] The present invention introduces the anti-sliding pile support records of the anti-sliding pile support in history. The basis for formulating the second slope support engineering plan in the anti-sliding pile support record is obtained, and the basis for formulating the first slope support engineering plan and the basis for formulating the second slope support engineering plan are matched to determine whether there is a similarity in the formulation basis. If there is a similarity, the target plan can be determined based on the same logic as the corresponding second slope support engineering plan. Otherwise, the anti-sliding pile support strategy formulation model is trained based on the anti-sliding pile support record; the third anti-sliding pile specification parameters and the second anti-sliding pile support point are determined according to the available second anti-sliding pile specification parameters and the second support platform, and a simulation platform for construction engineering is introduced to simulate the anti-sliding pile simulation entity supporting in the third support platform. After the simulated support, the simulation data of the environmental factors that affect the stability of the second support platform are also introduced to determine the support effect; when the support effect meets expectations, the target plan corresponding to the simulation strategy is output, otherwise adaptive adjustments are made to improve the rationality of the target plan formulation.

[0107] In one embodiment, obtaining the instability factor simulation parameters includes:

[0108] Obtaining subsequent application information of the second supporting platform; wherein the subsequent application information is: subsequent use information of the second supporting platform, such as: use as a helipad;

[0109] The instability factor is obtained according to the subsequent application information, and the instability factor simulation parameter is determined according to the conversion rule of the instability factor in the simulation platform. Among them, the instability factor is: for example: the rollover of the aircraft.

[0110] The working principle and beneficial effects of the above technical solution are:

[0111] The present invention introduces subsequent application information of the second retaining platform to determine the instability factor, and introduces the conversion rule of the instability factor in the simulation platform to determine the simulation parameters of the instability factor, thereby improving the standardization of the acquisition of the simulation parameters of the instability factor.

[0112] In one embodiment, step 2: obtaining a three-dimensional model of the earthwork filling site includes:

[0113] Acquire first three-dimensional scanning data collected by a first three-dimensional scanning data acquisition party of the earthwork filling site; wherein the first three-dimensional scanning data acquisition party includes: site staff and / or site operation drones;

[0114] A three-dimensional model is constructed according to the first three-dimensional scanning data.

[0115] The working principle and beneficial effects of the above technical solution are:

[0116] The present invention obtains first three-dimensional scanning data by site staff and site operation drones to construct a three-dimensional model, and the construction process of the three-dimensional model is more suitable.

[0117] In one embodiment, step 3: based on BIM technology, according to the slope support engineering plan and the three-dimensional model of the earthwork filling site, an anti-slide pile model is generated, including:

[0118] According to the slope support engineering plan, the second three-dimensional scanning data and the anti-sliding pile support points of each second support platform are determined; the second three-dimensional scanning data are: the three-dimensional parameters of the anti-sliding piles used in the second support platform;

[0119] Based on BIM technology, the anti-slide pile model is rendered in the 3D model according to the anti-slide pile support points and the second 3D scanning data.

[0120] The working principle and beneficial effects of the above technical solution are:

[0121] The present invention constructs a BIM model based on a slope retaining engineering plan, thereby improving the rationality of rendering.

[0122] The embodiment of the present invention provides a BIM-based anti-slide pile construction method, including:

[0123] Displaying the anti-slide pile model to the construction personnel; wherein, displaying the anti-slide pile model to the construction personnel means displaying the construction parameters of the anti-slide pile in the earthwork filling site (such as the specifications and positions of the anti-slide pile) to the construction personnel through the BIM information display device;

[0124] After the demonstration is completed, the construction workers are supervised in the anti-slide pile construction process; among them, supervising the construction workers' anti-slide pile construction process means supervising whether the construction workers carry out standardized anti-slide pile construction, that is, whether the construction results meet the planned requirements;

[0125] Wherein, the anti-slide pile model is a model generated by the BIM-based anti-slide pile model generation method described in any of the above embodiments.

[0126] The working principle and beneficial effects of the above technical solution are:

[0127] The present invention displays the anti-sliding pile model to the construction personnel to instruct the anti-sliding pile construction, which is more intelligent; the anti-sliding pile construction process is supervised in time, and the accuracy of the construction is improved.

[0128] In one embodiment, the anti-slide pile model is displayed to construction personnel, including:

[0129] Obtain the construction area that the construction personnel are responsible for; the responsible construction area is: the earthwork filling site that the construction personnel need to be responsible for construction;

[0130] Determine a local anti-slide pile model according to the responsible construction area; wherein the local anti-slide pile model is: a local model for simulating the anti-slide pile construction in the responsible construction area;

[0131] The first anti-slide pile simulation point, the construction personnel simulation point and the construction personnel's simulated sight distance in the local anti-slide pile model are obtained; wherein the first anti-slide pile simulation point is: the distribution of the simulated anti-slide piles in the local anti-slide pile model; the construction personnel simulation point is: the real-time position of the construction personnel corresponds to the simulated position in the local anti-slide pile model; the construction personnel's simulated sight distance is: the construction personnel's sight distance in the display device;

[0132] According to the construction worker's simulated point, the construction worker's sight direction and the simulated sight distance, an observation circle is constructed; wherein the observation circle is perpendicular to the sight direction and tangent to the straight line passing through the construction worker's simulated point, and the tangent point is the construction worker's simulated point; the construction worker's virtual sight point falls into the observation circle, and the diameter of the observation circle is equal to the simulated sight distance;

[0133] The first anti-slide pile simulation point falling into the observation circle is obtained and used as the second anti-slide pile simulation point; the remaining first anti-slide pile simulation points except the second anti-slide pile simulation point in the first anti-slide pile simulation point are used as the third anti-slide pile simulation point;

[0134] Based on the minimum observation circle projection rule, the minimum observation circle that can include all the third anti-slide pile simulation points is determined, and the projected observation circle is used as the area to be observed;

[0135] According to the regional boundary points of the area to be observed and the simulated points of the construction personnel, the shortest arrival distance trajectory is planned; wherein each regional boundary point on the shortest arrival distance trajectory has only one corresponding area to be observed, and the areas to be observed are different from each other;

[0136] The shortest reach distance trajectory is sent to the construction workers as navigation information.

[0137] The working principle and beneficial effects of the above technical solution are:

[0138] The present invention obtains a local anti-slip pile model of the construction area in which the construction personnel are responsible. Considering that the construction area is too large and the construction personnel cannot see all the BIM information of the construction they are responsible for at one time, an observation circle is constructed according to the construction personnel's simulation points, the construction personnel's line of sight direction and the simulated line of sight distance; the anti-slip pile monomer model corresponding to the second anti-slip pile simulation point falling into the observation circle is able to be viewed in time by the construction personnel, and the anti-slip pile monomer model corresponding to the third anti-slip pile simulation point is waiting for the construction personnel to view; in order to improve the observation efficiency, the minimum observation circle projection rule is introduced to determine the area to be observed, and the shortest arrival distance trajectory is planned according to the regional boundary points of the area to be observed and the construction personnel's simulation points, and the navigation information is sent to the construction personnel. The construction personnel can subsequently view their own construction tasks with the greatest efficiency in the construction site based on the shortest arrival distance trajectory, which is more humane.

[0139] The embodiment of the present invention provides a BIM-based anti-slide pile construction method, which also includes:

[0140] When the construction personnel arrive at the area boundary point corresponding to the shortest arrival distance trajectory, the area center of the area to be observed corresponding to the area boundary point arrived at is obtained;

[0141] According to the center of the area and the boundary point of the area reached by the construction personnel, a viewing vector is constructed and the construction personnel are instructed. The direction of the viewing vector is the direction from the boundary point of the area reached by the construction personnel to the center of the area.

[0142] The working principle and beneficial effects of the above technical solution are:

[0143] After the construction workers arrive at the actual position corresponding to the boundary point of the area, there is a situation where the line of sight does not fall into the area to be observed. Therefore, a viewing vector is constructed based on the center of the area and the boundary point of the area reached by the construction workers. The vector angle is calculated based on the current viewing vector of the construction workers and the viewing vector, and the construction workers are prompted to adjust the rotation of their line of sight, which further improves the display efficiency.

[0144] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. Anti-slide pile model generation method based on BIM, It is characterized in that include: Step 1: Obtain the slope support engineering plan during the earthwork filling process; Step 2: Obtain a three-dimensional model of the earthwork filling site; Step 3: Based on BIM technology, generate an anti-slide pile model according to the slope support engineering plan and the three-dimensional model of the earthwork filling site.

2. The method for generating an anti-slide pile model based on BIM according to claim 1, It is characterized in that Step 1: Obtain the slope support engineering plan during the earthwork filling process, including: During the earthwork filling process, the necessity of slope support analysis should be carried out; If the result of the slope support necessity analysis is that it is necessary to carry out slope support, the target slope is determined; Determine the slope characteristics of the target slope; Determine the slope support engineering plan based on the slope characteristics of the target slope.

3. The method for generating an anti-slide pile model based on BIM as claimed in claim 2, It is characterized in that According to the slope characteristics of the target slope, determine the slope support engineering plan, including: Perform slope feature clustering on the slope features to obtain slope feature clustering results; Determine at least one first retaining platform according to the clustering result of the slope characteristics; Traverse each first retaining platform in turn, take the first retaining platform being traversed as the second retaining platform, and take the slope characteristics corresponding to the second retaining platform as the basis for formulating the first slope retaining engineering plan of the second retaining platform; According to the basis for the first slope retaining project plan, determine the target plan for the second retaining platform; When all the first retaining platforms are traversed, the target plan is summarized as the slope retaining project plan.

4. The method for generating an anti-slide pile model based on BIM as claimed in claim 3, It is characterized in that According to the basis for the first slope retaining project plan, determine the target plan for the second retaining platform, including: Obtain anti-slide pile support records; Analyze the anti-slide pile support records to obtain the basis for the second slope support project plan; Determine whether the basis for formulating the second slope support engineering plan is similar to the basis for formulating the first slope support engineering plan; If there is a similarity, obtain the first anti-slide pile specification parameters and the first anti-slide pile support point corresponding to the corresponding second slope support engineering plan formulation basis, and determine the target plan according to the first anti-slide pile specification parameters and the first anti-slide pile support point; If there is no similarity, the anti-slide pile support strategy formulation model is trained based on the anti-slide pile support records; Obtaining specification parameters of the second anti-slide pile; Based on the anti-slide pile support strategy formulation model, the specification parameters of the third anti-slide pile and the second anti-slide pile support point are determined according to the specification parameters of the second anti-slide pile and the second support platform; Retrieving the anti-slide pile simulation entity according to the third anti-slide pile specification parameters and the anti-slide pile simulation entity library; Construct a third retaining platform simulating the second retaining platform; Based on the relative position of the second anti-sliding pile support point in the second support platform, simulate the anti-sliding pile simulation entity supporting in the third support platform to obtain a first simulation result; Obtain simulation parameters of instability factors; Determining a second simulation result according to the instability factor simulation parameter and the first simulation result; If the second simulation result meets the simulation expectations, the target plan is determined according to the specification parameters of the third anti-sliding pile and the support points of the second anti-sliding pile; otherwise, the second simulation result is attributed and the specification parameters of the third anti-sliding pile and the support points of the second anti-sliding pile are adjusted based on the attribution results, and the target plan is determined according to the adjusted specification parameters of the third anti-sliding pile and the support points of the second anti-sliding pile.

5. The method for generating an anti-slide pile model based on BIM as claimed in claim 4, It is characterized in that Get the simulation parameters of instability factors, including: Obtain subsequent application information of the second support platform; The instability factors are obtained according to the subsequent application information, and the simulation parameters of the instability factors are determined according to the conversion rules of the instability factors on the simulation platform.

6. The method for generating an anti-slide pile model based on BIM according to claim 1, It is characterized in that Step 2: Obtain a 3D model of the earthwork filling site, including: Acquire first three-dimensional scanning data collected by a first three-dimensional scanning data acquisition party of the earthwork filling site; wherein the first three-dimensional scanning data acquisition party includes: site staff and / or site operation drones; A three-dimensional model is constructed according to the first three-dimensional scanning data.

7. The method for generating an anti-slide pile model based on BIM as claimed in claim 1, It is characterized in that Step 3: Based on BIM technology, generate an anti-slide pile model according to the slope support engineering plan and the 3D model of the earthwork filling site, including: According to the slope support engineering plan, determine the second three-dimensional scanning data and the anti-sliding pile support point of each second support platform; the second three-dimensional scanning data is: the three-dimensional parameters of the anti-sliding pile used in the second support platform; Based on BIM technology, the anti-slide pile model is rendered in the 3D model according to the anti-slide pile support points and the second 3D scanning data.

8. Anti-slide pile construction method based on BIM, It is characterized in that include: Demonstrate the anti-slide pile model to construction workers; After the demonstration, supervise the construction workers’ anti-slide pile construction process; Wherein, the anti-slide pile model is a model generated according to the BIM-based anti-slide pile model generation method according to any one of claims 1 to 7.

9. The anti-slide pile construction method based on BIM as claimed in claim 8, It is characterized in that The anti-slide pile model was presented to the construction personnel, including: Obtain the construction area that the construction personnel are responsible for; Determine the local anti-slide pile model according to the construction area; Obtaining the first anti-slide pile simulation point, the construction personnel simulation point, and the construction personnel's simulated sight distance in the local anti-slide pile model; According to the construction worker's simulated point, the construction worker's sight direction and the simulated sight distance, an observation circle is constructed; wherein the observation circle is perpendicular to the sight direction and tangent to the straight line passing through the construction worker's simulated point, and the tangent point is the construction worker's simulated point; the construction worker's virtual sight point falls into the observation circle, and the diameter of the observation circle is equal to the simulated sight distance; Acquire the first anti-sliding pile simulation point that falls into the observation circle and use it as the second anti-sliding pile simulation point; The remaining first anti-slide pile simulation points except the second anti-slide pile simulation point in the first anti-slide pile simulation points are used as third anti-slide pile simulation points; Based on the minimum observation circle projection rule, the minimum observation circle that can include all the third anti-slide pile simulation points is determined, and the projected observation circle is used as the area to be observed; Plan the shortest arrival distance trajectory based on the regional boundary points of the area to be observed and the simulated points of the construction personnel; The shortest reach distance trajectory is sent to the construction workers as navigation information.

10. The anti-slide pile construction method based on BIM as claimed in claim 9, It is characterized in that Also includes: When the construction personnel arrive at the area boundary point corresponding to the shortest arrival distance trajectory, the area center of the area to be observed corresponding to the area boundary point arrived at is obtained; Based on the center of the area and the area boundary points reached by the construction workers, a viewing vector is constructed and the construction workers are instructed.

Citation Information

Patent Citations

  • Supporting and retaining structure of existing retaining wall straight penetrated by large-span tunnel and construction method thereof

    CN107130613A

  • Method for quickly and finely valuing slope rock mass joint orientation in open pit mines based on digital photogrammetry

    CN108830317A

  • Support structure slope stability evaluation method based on finite element strength reduction method

    CN111368483A

  • Slope reinforcement scheme optimization method, device and equipment and readable storage medium

    CN115329645A

  • Construction method for channel slope concrete replacement and anti-slide pile combination

    CN117604975A