Construction method of assembly type plant building machine matching system of concrete plant
Through the construction method of the supporting system of the prefabricated factory building machine of concrete factory building, the side wall column mold frame, early dismantling support and truss platform system are used to solve the problems of safety and efficiency of high-supporting form construction, and low-supporting form construction is achieved. Improve construction safety and efficiency.
Patent Information
- Application Number
- CN202411420480.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-12
- Publication Date
- 2024-12-27
AI Technical Summary
In construction, higher full-house scaffolding is required during construction of high-supported forms to ensure safety, but construction is troublesome and there are many consumables, making it difficult to improve construction efficiency.
The construction method adopts the supporting system of the prefabricated factory building machine, including the side wall column mold frame system, early dismantling support system, truss platform system and transfer truck system. The support height is reduced through grid layout and fragmented dismantling and assembly. Improve construction efficiency.
Turning high-supported molds into low-supported molds improves construction safety and efficiency, and reduces construction costs and time.
Smart Images

Figure CN119195475A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of building construction, and in particular to a construction method for a concrete plant assembly machine supporting system. Background Art
[0002] For example, the Chinese invention patent application publication number CN 109610816 A discloses an aluminum alloy quick formwork system, including a formwork system, a support system and a connection system. The formwork system includes a plurality of mutually spliced quick-release formworks, and the quick-release formworks are provided with corner bars at the four corners. The support system includes support components connected to the corner bars at the four corners of the quick-release formworks, and early-release heads connecting two adjacent quick-release formworks. The construction method of the aluminum alloy quick-release formwork system includes the following steps: a. After the wall reinforcement is tied, the wall board beam and corner member are installed first; b. Assemble the single support with the first wall side support, the second wall side support, the first formwork edge support, the second formwork edge support, and the early-release head; c. Set up a single support at an appropriate position and equip it with the first wall side support, the second wall side support, the first formwork edge support or the second formwork edge support. It is completed with a higher bracket. When building a higher factory building, it is necessary to rely on a higher full-floor scaffolding to ensure safety, and the full-floor scaffolding is troublesome to build and consumes a lot of materials. Summary of the invention
[0003] The purpose of the present invention is to provide a construction method for a concrete plant assembly-type plant construction machine supporting system, which converts high-support formwork into low-support formwork construction, effectively ensures construction safety, and can improve construction efficiency.
[0004] In order to achieve the above purpose, a construction method of a concrete plant assembly plant machine supporting system is adopted, which includes the following steps:
[0005] S1: Use the side wall and side column formwork system to construct the side walls and side columns around the factory building along the outer edge of the grid. After removing the formwork, reserve door openings on the side walls, install the side lifting point embedded parts along the outer grid points and lines, and install the side brackets along the grid lines perpendicular to the side walls and side columns;
[0006] S2: Installing an early-removal support system, which is divided into an early-removal support column base system and an early-removal support column system installed on the early-removal support column base system; the early-removal support column base system is arranged according to grid points, and inner corbels are installed on the early-removal support column system along the grid line direction, so that two groups of relatively spaced corbels are formed along the grid line longitudinally and transversely;
[0007] S3: Install the truss platform system, and lay the split single-piece truss platform on the ground between the relatively spaced corbels along the longitudinal and transverse directions of the grid;
[0008] S4: Install a lifting system on the corbel, and use the lifting system to lift the single-piece truss platform. After the single-piece truss platform is lifted to the height of the corbel, it is spliced with the corbel to form the truss platform of this workstation;
[0009] S5: Set up the roof formwork system on the truss platform, and remove the formwork after constructing the roof of the factory building at this workstation;
[0010] S6: Place the parts of the transfer trolley system under the single-piece truss platform, disassemble the single-piece truss platform piece by piece, lower the single-piece truss platform to the installation position of the transfer trolley system, install the transfer trolley system at the bottom of the single-piece truss platform, and transport it to the next workstation or door opening by the transfer trolley system;
[0011] S7: After completing the construction of all workstation roofs, dismantle the early dismantling support system.
[0012] The present invention can transform high-support formwork into low-support formwork construction, effectively ensuring construction safety and improving construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 This is a schematic diagram of the plan layout of the corbel.
[0014] Figure 2 Schematic diagram of the splicing structure of the early dismantling support system
[0015] Figure 3 This is a top view of the steel column.
[0016] Figure 4 It is a structural schematic diagram of an early dismantling support column base system.
[0017] Figure 5 for Figure 4 Schematic diagram of the structure of the early dismantling support column base system without the pad.
[0018] Figure 6 A schematic diagram of the structure of a triangular block.
[0019] Figure 7 This is a structural diagram of the early removal support column system.
[0020] Figure 8 Schematic diagram of lifting and dismantling of steel columns.
[0021] Fig. 9 This is a schematic diagram of the column top node.
[0022] Fig.10 This is a schematic diagram of the structure of the corbel.
[0023] Fig.11 Schematic diagram of the installation structure of the tension screw assembly.
[0024] Fig.12It is a schematic diagram of the connection relationship between the tension screw assembly and the first base plate.
[0025] Fig.13 This is a schematic diagram of the partition installation structure.
[0026] Fig.14 The figure is a schematic diagram of the installation structure of a clamp and an ear plate.
[0027] Fig.15 Schematic diagram of the installation structure of the second base plate.
[0028] Fig.16 Schematic diagram of the truss platform system splicing structure.
[0029] Fig.17 Schematic diagram of the main truss structure.
[0030] Fig.18 Schematic diagram of the local structure of the secondary truss.
[0031] Fig.19 It is a structural diagram of the transfer vehicle system.
[0032] Fig. 20 It is a schematic diagram of the partially enlarged structure of the axle position.
[0033] Fig.21 It is a structural diagram of the screw lift.
[0034] Fig. 22 It is a schematic diagram of the structure of the second screw.
[0035] Fig.23 This is a schematic diagram of the installation of brackets and purlins.
[0036] Fig.24 To enhance the basic principle diagram of the system.
[0037] Fig.25 Schematic diagram of the truss platform disassembly process.
[0038] Fig.26 This is a schematic diagram of the disassembly process of the early dismantling support system.
[0039] Fig. 27 Install the plan view for the truss platform.
[0040] Figure numerals: 1. Early dismantling support system; 101. Early dismantling support column base system; 10101. Horizontal I-beam; 10102. Longitudinal I-beam; 10103. Cross-shaped I-beam; 10104. Triangular plate; 10105. Pad; 10106. First bolt and nut assembly; 10107. Positioning rib; 10108. First rib; 10109. First ear plate; 10110. Tie rod; 10111. Triangular block; 10112. Tie screw; 10113. First nut; 10114. Washer; 10115. Track; 10116. Rib; 10117. Groove; 10118. Side rib block; 10119. Middle rib block; 10120. U-shaped groove; 10121. Slot grid; 10122. Roller;
[0041] 102. Early dismantling support column system; 10201. Steel column; 10202. Flange; 10203. Reinforcement plate; 10204. Corbel; 102401. Upper chord; 102402. Lower chord; 102403. Vertical web bar; 102404. Diagonal web bar; 102405. First bottom plate; 102406. Second bottom plate; 102407. Second lifting ring; 1024 08. Rib plate; 10205. Second bolt and nut assembly; 10206. First clamp; 10207. Second ear plate; 10208. First lifting ring; 10209. Sealing ring; 10210. Tension screw assembly; 10211. Partition plate; 10212. First screw; 10213. Second nut; 10214. Cross plate; 10215. Vertical plate; 10216. Cover plate.
[0042] 2. Transfer trolley system; 201. Truss platform; 202. Axle seat; 203. Axle; 204. Wheel; 205. First turbine reduction box; 206. First motor; 207. Screw lift; 20701. Middle support; 208. Slipper; 20801. Shell; 20802. Limit roller; 209. Connecting rod; 2010. Internal threaded sleeve; 2011. Second screw; 2012. Second turbine reduction box; 2013. Second motor; 2014. Arc track; 2015. Third turbine reduction box; 2016. Third motor.
[0043] 3. Truss platform system; 301. Main truss; 302. Secondary truss; 30201. Positioning sleeve; 303. First splicing plate; 304. Second clamp; 30401. Second splicing plate; 305. Third bolt and nut assembly; 306. Fourth bolt and nut assembly; 307. Lifting ear; 308. Angle steel; 309. Fifth bolt and nut assembly; 3010. Bolt; 3011. Second rib; 3012. End plate.
[0044] 4. Improvement system;
[0045] 5. Side wall and side column;
[0046] 6. Roof. DETAILED DESCRIPTION
[0047] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0048] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as limiting the present invention; the terms "first", "second", and "third" are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance; in addition, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0049] Example 1
[0050] like Figure 1-Figure 27 As shown, a construction method of a concrete plant assembly plant machine supporting system comprises the following steps:
[0051] S1: Use the side wall and side column formwork system to construct the side wall and side columns 5 around the workshop along the outer edge of the grid. After removing the formwork, reserve door openings on the side walls, install the side lifting point embedded parts along the outer grid points and lines, and install the side brackets along the grid lines perpendicular to the side wall and side columns;
[0052] S2: Install the early demolition support system 1, which is divided into an early demolition support column base system 101 and an early demolition support column system 102 installed on the early demolition support column base system 101; the early demolition support column base system 101 is arranged according to grid points, and inner corbels are installed on the early demolition support column system 102 along the grid line direction; so that two groups of relatively spaced corbels are formed along the grid line longitudinally and transversely;
[0053] S3: Install the truss platform system 3, and lay the split single-piece truss platform on the ground between the relatively spaced corbels along the longitudinal and transverse directions of the grid;
[0054] S4: Install a lifting system 4 on the corbel, and use the lifting system to lift the single-piece truss platform. After the single-piece truss platform is lifted to the height of the corbel, it is spliced with the corbel to form a truss platform at this workstation;
[0055] S5: Set up the roof formwork system on the truss platform, and remove the formwork after constructing the roof of the factory building at this station;
[0056] S6: placing parts of the transfer trolley system 2 under the single-piece truss platform, disassembling the single-piece truss platform piece by piece, lowering the single-piece truss platform to the installation position of the transfer trolley system 2, installing the transfer trolley system 2 at the bottom of the single-piece truss platform, and transporting it to the next workstation or door opening by the transfer trolley system 2;
[0057] S7: After completing the construction of all the workstation roofs 6, the early dismantling support system 1 is dismantled.
[0058] The early removal support column base system 101 comprises:
[0059] Transverse I-beams 10101 are laid in parallel intervals;
[0060] The longitudinal I-beams 10102 are laid in parallel at intervals and are vertically fixed between two adjacent parallel transverse I-beams 1, and form a closed area with the transverse I-beams 1;
[0061] A cross-shaped I-beam 10103, which is disposed inside the closed area and has its ends fixed to the transverse I-beam 10101 and the longitudinal I-beam 10102;
[0062] The triangle plate 10104 is welded to the corner of the upper flange in the middle of the cross-shaped I-beam 10103, and a gap is reserved between the triangle plate 10104 and the transverse I-beam 10101, and between the triangle plate 10104 and the longitudinal I-beam 10102;
[0063] The backing plate 10105 is placed in the middle of the cross-shaped I-beam 10103 and covers the triangular plate 10104, with a space reserved between the backing plate 10105 and the transverse I-beam 10101 and the longitudinal I-beam 10102;
[0064] The first bolt and nut assembly 10106 penetrates the backing plate 10105 and the triangular plate 10104 and is tightened, with the bolt head at the upper end and the nut at the lower end.
[0065] The positioning ribs 10107 are fixedly arranged on the pad 10105 at an annular spacing angle.
[0066] With such a structure, the positioning rib 10107 facilitates the positioning of the early-removal support column. The lower end of the early-removal support column has a flange plate connected to the positioning rib. The triangular plate 10104 can prevent the first bolt and nut assembly 10106 from drilling holes in the cross-shaped I-beam 10103, thereby preventing the cross-shaped I-beam 10103 from reducing the bearing capacity of the cross-shaped I-beam 10103. Intervals are reserved between the triangular plate 10104 and the transverse I-beam 10101, as well as between the triangular plate 10104 and the longitudinal I-beam 10102, so as to reserve sufficient space for the installation and removal of the first bolt and nut assembly 10106. The positioning rib 10107 positions the early-removal support column and is also convenient for welding with the early-removal support column.
[0067] In this embodiment, a first rib 10108 is provided in the transverse I-beam 10101 and the longitudinal I-beam 10102 .
[0068] With such a structure, the first rib 10108 strengthens and supports the transverse I-beam 10101 and the longitudinal I-beam 10102 .
[0069] In this embodiment, a first ear plate 10109 is provided on the transverse I-beam 10101 and the longitudinal I-beam 10102 .
[0070] With such a structure, it is convenient to support the inclined pull rod 10110 on the first ear plate 10109 .
[0071] In this embodiment, a pull rod 10110 is hinged on the first ear plate 10109 .
[0072] With such a structure, the pull rod 10110 is convenient for hinged early dismantling of the root of the support column.
[0073] In this embodiment, a triangular block 10111 is arranged between the cross-shaped I-beam 10103 and the pad 10105. The triangular block 10111 is located on two coaxial branches of the cross-shaped I-beam 10103. A pair of triangular blocks 10111 are connected by tension screws 10112 and are tightened with a first nut 10113 and a gasket 10114. The pad 10105 abuts against the inclined surface of the triangular block 10111.
[0074] Such a structure makes it easier to remove the root of the early-removal support column during subsequent disassembly, so that the disassembly efficiency is improved.
[0075] In this embodiment, rails 10115 are provided on both sides of the triangular block 10111 , and the rails 10115 are welded to the branches of the cross-shaped I-beam 10103 .
[0076] Such a structure makes it easy for the triangular block 10111 to retreat along a predetermined route when the supporting column is removed early.
[0077] In this embodiment, the triangular block 10111 is inserted into the rib 16 , and the rib 10116 passes through a pair of triangular blocks 10111 and is placed under the pad 10105 .
[0078] With such a structure, when disassembling the early disassembly support column, first pull out the rib 10116 and then remove the early disassembly support column, and the rib 10116 is convenient for supporting the middle part of the pad 10105.
[0079] In this embodiment, a groove 10117 is provided on the outer side of the rib 10116 to insert the side rib 10118 .
[0080] With such a structure, the side ribs 10118 are placed on the sides of the pad 10105 to better support the pad 10105 , and the grooves 10117 facilitate positioning of the side ribs 10118 .
[0081] In this embodiment, a middle rib block 10119 is arranged between the two ribs 10116 , and a U-shaped groove 10120 is provided on the upper surface of the middle rib block 10119 for the tension screw 10112 to pass through, and the upper surface of the middle rib block 10119 is spaced apart from the lower surface of the pad 10105 .
[0082] With such a structure, after the pad 10105 is removed, it is supported by the middle rib 10119.
[0083] In this embodiment, a groove 10121 is formed on the bottom surface of the triangular block 10111 , and rollers 10122 are distributed in the groove 10121 .
[0084] With such a structure, the bottom surface of the triangular block 10111 is easy to slide, thereby reducing the friction during unloading.
[0085] First, the early removal support column base system 101 is removed, and then the early removal support column system 102 and the early removal support column base system 101 are removed from bottom to top. The specific steps are as follows:
[0086] When the early dismantling support column is dismantled in sections, the flanges of the middle section steel column and the top section steel column are first unbolted, and then the early dismantling support column base system 101 is used to complete the unloading operation, so that a gap is reserved between the middle section steel column and the top section steel column, and then the bolts of the middle section steel column and the bottom section steel column are unbolted, and then the middle section steel column is lifted out, and then the top section steel column and the bottom section steel column are dismantled. After the gap is reserved, the middle section steel column and the top section steel column will not get stuck, so as to prevent the middle section steel column from being pushed up against the top section steel column when dismantling, which may damage the bottom surface of the roof, or may cause the top section steel column to shake, affecting construction safety, or when the base is dismantled first, the lower section of the middle section steel column is vacant and is easy to swing in the wind. The longer the length, the greater the swing amplitude, which may put construction workers in danger during dismantling. If the middle section steel column is dismantled first, each section of the steel column will be relatively short, and the swing amplitude in the wind will be small, which is safer during dismantling.
[0087] The early removal support column system 102 of this embodiment includes:
[0088] The multi-section steel column 10201 is arranged in upper and lower sections and spliced;
[0089] A flange 10202 is fixedly mounted on the end of the single-section steel column 10201;
[0090] A reinforcing plate 10203, which is welded between the steel column 10201 and the flange 10202;
[0091] Corbel 10204, which is fixedly connected to both sides of the top section steel column 10201;
[0092] Bolt and nut assembly 10205, which is fastened to the adjacent spliced flange 10202;
[0093] A first clamp 10206, which is fixed on the bottom steel column 10201;
[0094] The second ear plate 10207 is arranged on the first clamp 10206.
[0095] With this structure, multiple sections of steel columns 10201 are spliced up and down through flanges 10202 and bolt and nut assemblies 10205, which is convenient for disassembly and assembly. The first clamp 10206 is fastened to the bottom steel column 10201.
[0096] In this embodiment, a first hanging ring 10208 is distributed on the steel column 10201.
[0097] With such a structure, when the steel column 10201 is disassembled in sections, the first lifting ring 10214 cooperates with the lifting rope to facilitate the disassembly and lowering of the segmented steel column 10201.
[0098] In this embodiment, the corbel 10204 includes an upper chord 102401, a lower chord 102402, a vertical web 102403 and a diagonal web 102404. The first bottom plate 102405 is fixed to the end of the upper chord 102401 and the lower chord 102402 close to the steel column 10201, and the second bottom plate 102406 is fixed to the end away from the steel column 10201. The first bottom plate 102405 is fixed to the steel column 10201.
[0099] With such a structure, the first base plate 102405 and the second base plate 102406 are used to splice the steel column 10201 and the truss respectively.
[0100] In this embodiment, a sealing ring 10209 is arranged between adjacent flanges 10202 .
[0101] Adopting such a structure is beneficial to waterproofing the interior of steel column 10201.
[0102] In this embodiment, the lower chord 102402 is shorter than the upper chord 102401 , and the second suspension ring 102407 is fixedly connected to the portion of the upper chord 102401 that exceeds the lower chord 102402 .
[0103] With such a structure, the second lifting ring 102407 facilitates lifting the truss, and the lower chord 102402 is shorter than the upper chord 102401, which does not affect the verticality of the pull rope during the lifting process.
[0104] In this embodiment, the rib plate 102408 is welded to the first bottom plate 102405 and the second bottom plate 102406, the rib plate 102408 is fixedly connected to the first bottom plate 102405 and the upper chord 102401, and the rib plate 102408 is also fixedly connected to the first bottom plate 102405 and the lower chord 102402; the rib plate 102408 is also fixedly connected to the second bottom plate 102406 and the upper chord 102401, and the rib plate 102408 is further fixedly connected to the second bottom plate 102406 and the lower chord 102402.
[0105] With such a structure, the rib plate is welded to the first bottom plate and the upper chord, and the rib plate is also welded to the first bottom plate and the lower chord to stabilize the corbel.
[0106] With such a structure, the rib plate 102408 is welded to the first bottom plate 102405 and the upper chord 102401 and then to the steel column 10201. The rib plate 102408 is also welded to the first bottom plate 102405 and the lower chord 102402 and then to the steel column 10201 to stabilize the corbel 10204.
[0107] In this embodiment, the tension screw assembly 10210 is connected to the first bottom plate 102405, and the tension screw assembly 10210 is connected to the steel column 10201 and the first bottom plates 102405 on both sides thereof.
[0108] By adopting such a structure, the bearing capacity of the upper corbel of steel column 10201 is higher.
[0109] In this embodiment, partitions 10211 are provided in the top steel column 10201. The partitions 10211 are welded in layers in the top steel column 10211 and are located below and above the tension screw assembly 10210. Holes are opened in the upper partitions 10211 and concrete is poured to make them dense.
[0110] With such a structure, the deformation of concrete due to thermal expansion and contraction is small, and after pouring, the tension screw assembly 10210 is further strengthened to prevent it from loosening.
[0111] In this embodiment, the first clamps 10206 are arranged in layers, and the first screw 10212 is fixed between the upper and lower first clamps 10206. The first screw 10212 is slidably connected to the second ear plate 10207, and the second ear plate 10207 is threadedly connected to the second nut 10213 on the upper and lower sides.
[0112] With such a structure, the tightness of the pull rod can be adjusted to ensure that it is in a tight state during use.
[0113] In this embodiment, a horizontal plate 10214 is arranged inside the column head of the top section steel column 1, a vertical plate 10215 is fixedly connected to the horizontal plate 10214, a cover plate 10216 is fixedly connected to the vertical plate 10215, and concrete is poured densely between the horizontal plate 10214 and the cover plate 10216.
[0114] With such a structure, it is convenient to install the bracket on the cover plate 10216, and the vertical plate 10215 prevents the cover plate 10216 from being concave, so that the deformation is smaller after pouring the concrete.
[0115] In this embodiment, the bottom section of the steel pipe column is convenient for connection with the base, and is convenient for pre-fixing the bottom section of the steel pipe column before welding or bolting, which is beneficial to improving construction efficiency, improving the quality of welding or bolting, and ensuring that the steel column is vertical during the fixing process to prevent tilting.
[0116] The truss platform system 3 used in this embodiment includes:
[0117] The main trusses 301 are arranged in parallel at intervals;
[0118] The secondary truss 302 is arranged vertically and crosswise with the main truss 301, and its upper and lower chords are made of square steel pipes. Positioning sleeves 30201 are fixed in the ends of the square steel pipes. The positioning sleeves 30201 are pressed against the upper and lower sides of the ends of the square steel pipes. The third bolt and nut assembly 305 is passed through the positioning sleeves. The third bolt and nut assembly 305 is tightened on the upper and lower sides of the ends of the square steel pipes.
[0119] The first splicing plate 303 is fixed to the upper chord and the lower chord of the secondary truss 302, one end of which is built into the square steel tube and is pressed against the side of the positioning sleeve 30201;
[0120] The second clamp 304 is fixed at intervals on the upper chord and the lower chord of the main truss 301 , and a second splicing plate 30401 is arranged on its side and is fixed to the first splicing plate 303 through a fourth bolt and nut assembly 306 .
[0121] By adopting such a structure, the position of the second clamp 304 on the main truss 301 can be adjusted and then tightened. The clamp 304 is used to splice with the secondary truss 302, so as to facilitate the adjustment of the position of the secondary truss 302. After the side of the positioning sleeve 30201 is pressed against the first splicing plate 303, it is convenient for the welding and fixation of the first splicing plate 303. After the first splicing plate 303 and the second splicing plate 30401 are fixed, the cross-splicing of the main truss 301 and the secondary truss 302 is realized.
[0122] In this embodiment, end plates 3012 are fixed at both ends of the upper chord and the lower chord of the main truss 301 , and bolt holes are provided on the end plates 3012 .
[0123] With such a structure, the end plate 3012 is easy to be spliced with the corbel.
[0124] In this embodiment, two ends of the lower chord of the main truss 301 extend beyond two ends of the upper chord, and lifting ears 307 are fixed to the extending portions.
[0125] Adopting such a structure makes it easy to lift the whole truss and to assemble it.
[0126] In this embodiment, the first splicing plate 303 is U-shaped, and the central space thereof is penetrated by the positioning sleeve 30201 . The second splicing plate 30401 is pressed against the positioning sleeve 30201 and then spliced with the first splicing plate 303 by the fourth bolt and nut assembly 306 .
[0127] With such a structure, the U-shaped first splicing plate 303 is more compatible with the positioning sleeve 30201, and after the second splicing plate 30401 is pressed against the positioning sleeve 30201 and then spliced with the first splicing plate 303, the first splicing plate 303, the second splicing plate 30401 and the positioning sleeve 30201 form a self-locking structure, and can be fastened without welding.
[0128] In this embodiment, an angle steel 308 is fixedly arranged between the second splicing plate 30401 and the side of the second clamp 304 , one limb of the angle steel 308 is tightened to the second splicing plate 30401 by a fourth bolt and nut assembly 306 , and the other limb is tightened to the side of the second clamp 304 by a bolt 3010 .
[0129] Such a structure is adopted to facilitate strengthening and fixing the second splicing plate 30401 and the second clamp 304.
[0130] In this embodiment, a second rib 3011 is welded to the angle steel 308 .
[0131] With such a structure, the second rib 3011 further strengthens the angle steel 308 .
[0132] The transfer vehicle system 2 used in this embodiment includes:
[0133] Truss platform 201;
[0134] Axle seat 202, which is installed at the bottom of the truss platform 201;
[0135] An axle 203, which is rotatably connected to the axle seat 202, and a worm is arranged in the middle thereof;
[0136] Wheels 204, which are coaxially fixed to both ends of the axle 203;
[0137] A first turbine reduction box 205, which is connected to the middle part of the axle 203 by a worm gear;
[0138] The first motor 206, whose output end extends into the first turbine reduction box 205 for transmission connection;
[0139] The screw lift 207 is spaced front and rear from the axle 203 and has a middle support 20701 fixed to the lower chord of the truss platform 201;
[0140] Sliding shoe 208, which is fixed to the lower output end of the screw lift 207;
[0141] The connecting rod 209 is hinged on one side of the sliding shoe 206
[0142] An internal threaded sleeve 2010, which is hinged to one side of the connecting rod 207;
[0143] A second screw 2011, one end of which is threadedly connected to the internal threaded sleeve 2010, and the other end of which is coaxially provided with a worm;
[0144] A second turbine reduction box 2012, which is connected to the worm gear at the other end of the second screw 2011;
[0145] The second motor 2013, the output end of which extends into the second turbine reduction box 2012 for transmission connection;
[0146] The arc track 2014 slidably mounts the sliding shoe 208 and is installed on the lower side of the second turbine reduction box 2012.
[0147] With such a structure, when the trolley is moving, the screw lift 207 lifts the arc track 2014, and when turning, the arc track 2014 is lowered, driven by the second motor 2013 and transmitted by the second turbine reducer 2012; the second screw 2011 and the internal threaded sleeve 2010 can achieve the telescopic function, so that the sliding shoe 208 can move along the arc track 2014, thereby realizing the in-situ horizontal turning function. When the turn is completed, the arc track 2014 is lifted again and the sliding shoe 208 is reset.
[0148] In this embodiment, the axle seat 202 , the axle 203 , the wheel 204 , the first turbine reduction box 205 and the first motor 206 are arranged in parallel in multiple groups at intervals on the bottom surface of the truss platform 201 .
[0149] Such a structure can ensure that the truss platform 201 is transported smoothly.
[0150] In this embodiment, the screw lifts 207 are arranged in a row of two and are linked by a transmission rod. The transmission rod is driven by a third turbine reducer 2015. The third turbine reducer 2015 is arranged between the two screw lifts 207. The third turbine reducer 2015 is transmission-connected to the output end of the third motor 2016. The third motor 2016 is installed on the truss platform 201.
[0151] With such a structure, two screw lifts 207 in a row are linked together, and the lifting of the truss platform 201 is more stable.
[0152] In this embodiment, the sliding shoe 208 includes a shell 20801, in which two upper and lower rows of limiting rollers 20802 are installed. The arc track 2014 is made of I-beams, and the two ends of the upper row of limiting rollers 20802 are respectively mounted on the two side walls of the shell 20801 and pressed against the upper flange of the arc track 2014; one end of the lower row of limiting rollers 20802 is mounted on the side wall of the shell 20801, and the other end faces the web of the arc track 2014, and the upper side of the lower row of limiting rollers 20802 presses against the lower side of the upper flange of the arc track 2014.
[0153] With such a structure, the limiting roller 20802 can easily move along the arc track 2014 and drive the arc track 2014 to move up and down.
[0154] In this embodiment, the second turbine reducer 2012 is transmission-connected to the second screw rods 2011 on both sides, and the transmission method is such that when the second screw rod 2011 on one side is contracted in the internal threaded sleeve 2010, the second screw rod 2011 on the other side is extended from the internal threaded sleeve 2010 on the other side.
[0155] Such a structure is adopted to ensure the overall translation and rotation of the truss platform.
[0156] In this embodiment, the screw lift 207, the sliding shoe 208, the connecting rod 209, the internal threaded sleeve 2010, the second screw 2011, the second turbine reducer 2012, the second motor 2013 and the arc track 2014 are arranged in groups, and every two groups are paired and distributed on the front and rear sides of the truss platform 201 in the form of concentric circles.
[0157] With such a structure, the components are distributed in concentric circles, and when rotating, the centers of the circles are the same, so the rotation is more stable.
[0158] The truss platform 201 includes a plurality of rows of main trusses 301 arranged at intervals, and secondary trusses 302 arranged crosswise and vertically between adjacent main trusses 301 .
[0159] In this embodiment, a bracket is installed on the truss platform and the corbel, the lower end of the bracket is a U-shaped plate, both sides of the U-shaped plate are fastened to the truss platform and the upper chord of the corbel by bolts and other fasteners, and the upper end of the bracket is a U-shaped support with adjustable height to set up the purlins required by the roof formwork system, such as Figure 7 and Fig.23 shown.
[0160] The lifting system used in this embodiment is:
[0161] 1. Lifting principle
[0162] The lifting system of this embodiment uses an electric hoist as the lifting power. The upper hook of the electric hoist is installed on the corbel at the upper end of the support column removed early on the inner side of the wall column, and the lower hook of the electric hoist is hooked on the lifting point of the lower chord of the main truss of the truss platform. The chain is driven by the electric hoist to make the truss platform move up and down relatively, thereby realizing the lifting function. After each lifting is completed, the electric hoist is transferred to the next lifting platform unit to prepare for the next lifting.
[0163] The lifting system 4 in this embodiment includes:
[0164] The intelligent master control box is connected to the main power line, and the power output line and the communication line are connected. The power output line is connected to the surrounding branch cable, and multiple extension power lines are configured on the surrounding branch cable, and multiple branch communication lines are configured on the communication line;
[0165] Intelligent extension, which is connected to the extension power line and branch communication line, and connected to the hoist power line;
[0166] Electric hoist, which is connected to the hoist power line and installed on the corbel;
[0167] The gravity sensor is arranged on the hanging point of the electric hoist and is electrically connected to the intelligent extension.
[0168] Among them, there is 1 intelligent master control box, which issues raising, lowering, stopping and other commands to the intelligent extensions.
[0169] Intelligent extension: n units (Note: n represents the number of positions, and a maximum of 100 intelligent extension units can be controlled). The real-time load data of each position is collected and comprehensively analyzed to identify various faults and make corresponding automated operations in a timely manner, such as early warning and shutdown.
[0170] Gravity sensor: n sets (Note: n represents the number of positions)
[0171] With 5-core shielded cable and 5-core aviation socket: It is the direct bearer of the aircraft suspension point load. It measures the load in real time and generates corresponding analog signals for collection by the single-chip microcomputer of the intelligent extension.
[0172] Surround branch cable: It adopts bus control mode, connects multiple communication lines, connects each intelligent extension together, and surrounds one branch cable.
[0173] The lifting system is also equipped with an alarm device
[0174] Alarm mode: buzzer alarm, color-changing light displays three alarm colors: red, yellow, and blue.
[0175] When the load value collected at a certain position exceeds the design value by 15%, an automatic alarm should be given in the form of sound and light. When it exceeds 30%, the electric hoist should be able to stop automatically.
[0176] Unload value alarm (SR1): When the load value collected in each position is less than the unload value, the intelligent extension and the intelligent main control box will send out intermittent alarm sounds (short sounds) and display the weight of the heavy object on the corresponding display.
[0177] Overload value alarm (SR2): When the maximum load value collected by each position reaches the overload value, the intelligent extension and the intelligent main control box will send out intermittent alarm sounds (long sounds) and display the weight of the heavy object.
[0178] Overload limit value alarm (SR3): When the load value collected by any machine position reaches the overload limit value, the intelligent extension and the intelligent master control box will issue a continuous alarm sound, and within 1 second, the relay output switch signal of the intelligent master control box will cut off the main control circuit, and the PC will display the status of each machine position when the cut-off occurs.
[0179] The overall construction process of this embodiment:
[0180] 1) Use a small lifting platform to hoist the bracket to the designed elevation, and then connect and fix it with the pre-buried anchor bolts of the wall column; at the same time, use a crane to hoist the steel column into place, and hoist the segmented truss platform between the steel columns into place; after the steel column is installed in place, use a guy rope to fix it.
[0181] 2) Assemble the first truss platform on the ground;
[0182] 3) Use the group hoist electric hoist to lift the first truss platform.
[0183] 4) Assemble the second truss platform on the ground.
[0184] 5) Use the group hoist electric hoist to lift the second truss platform.
[0185] 6) Assemble the third truss platform on the ground.
[0186] 7) Use the group hoist electric hoist to lift the third truss platform.
[0187] When the concrete strength of the roof reaches 75%, the first, second and third truss platforms and corbels are removed in sequence using the lifting system.
[0188] The first, second and third truss platforms are moved to the next construction station using the transfer trolley system (2), and the lifting system is used to accurately adjust the lifting position of the truss platform to ensure the accuracy of the lifting position. The above steps are repeated until the construction of the unit structure roof is completed; then the transfer trolley system 2 is used to move to the next unit and continue the above steps for construction.
[0189] After the roof concrete strength reaches 100%, the steel columns and truss platforms are removed in sequence.
[0190] The disassembly steps of first disassembling the early disassembly support column base system 101 and then disassembling the early disassembly support column system 102 from bottom to top are as follows:
[0191] 1) Use a small lifting platform to weld the hooks on the embedded parts at the bottom of the roof truss.
[0192] 2) Remove the truss platform between steel columns;
[0193] 3) Using the fall chain to dismantle the early dismantling support column base system 101, and then dismantle the steel column from bottom to top;
[0194] The present invention effectively solves the problem of high formwork construction for the entire hall, converts high formwork into low formwork construction, and effectively ensures construction safety.
[0195] The above contents are further detailed descriptions of the present invention in combination with specific preferred embodiments, and it cannot be determined that the specific implementation of the present invention is limited to these descriptions. For those skilled in the art of the present invention, several equivalent substitutions or obvious variations can be made without departing from the concept of the present invention, and the performance or use is the same, which should be regarded as belonging to the protection scope of the present invention.
Claims
1. A construction method for a concrete plant assembly plant machine supporting system, characterized in that The steps include: S1: Use the side wall and side column formwork system to construct the side wall and side columns (5) around the factory building along the outer edge of the grid. After removing the formwork, reserve door openings on the side walls, install side lifting point embedded parts along the outer grid points and lines, and install side brackets along the grid lines perpendicular to the side wall and side columns; S2: installing an early demolition support system (1), wherein the early demolition support system (1) is divided into an early demolition support column base system (101) and an early demolition support column system (102) installed on the early demolition support column base system (101); the early demolition support column base system (101) is arranged according to grid points, and inner corbels are installed on the early demolition support column system (102) along the grid line direction, so that corbels are formed in pairs along the grid line longitudinally and transversely; S3: installing the truss platform system (3), laying the split single-piece truss platform on the ground between the relatively spaced corbels along the longitudinal and transverse directions of the grid; S4: installing a lifting system (4) on the corbel, and using the lifting system to lift the single-piece truss platform; after the single-piece truss platform is lifted to the height of the corbel, it is spliced with the corbel to form a truss platform at this workstation; S5: erecting a roof formwork system on the truss platform, constructing the roof (6) of the factory building at this workstation, and then removing the formwork; S6: placing the parts of the transfer trolley system (2) under the single-piece truss platform, disassembling the single-piece truss platform piece by piece, lowering the single-piece truss platform to the installation position of the transfer trolley system (2), installing the transfer trolley system (2) at the bottom of the single-piece truss platform, and transporting it to the next workstation or door opening by the transfer trolley system (2); S7: After completing the construction of all the workstation roofs (6), dismantle the early dismantling support system (1).
2. The construction method of the concrete plant assembly plant machine supporting system according to claim 1 is characterized in that The early dismantling support column base system (101) comprises: Transverse I-beams (10101), which are laid in parallel intervals; Longitudinal I-beams (10102) are laid in parallel at intervals and vertically fixed between two adjacent parallel transverse I-beams (10101), and enclose a closed area with the transverse I-beams (10101); A cross-shaped I-beam (10103) is arranged inside the closed area, and its ends are fixed to the transverse I-beam (10101) and the longitudinal I-beam (10102); A triangular plate (10104) is welded to the corner of the upper flange in the middle of the cross-shaped I-beam (10103), with a space reserved between the triangular plate (10104) and the transverse I-beam (10101), and between the triangular plate (10104) and the longitudinal I-beam (10102); A pad (10105) is placed in the middle of the cross-shaped I-beam (10103) and covers the triangular plate (10104), with a space reserved between the pad and the transverse I-beam (10101) and between the pad and the longitudinal I-beam (10102); A first bolt and nut assembly (10106) is inserted through the backing plate (10105) and the triangular plate (10104) and tightened, with the bolt head at the upper end and the nut at the lower end; Positioning ribs (10107) are fixedly arranged on the backing plate (10105) at angular intervals along the annular direction; A first rib (10108) is provided in the transverse I-beam (10101) and the longitudinal I-beam (10102); A first ear plate (10109) is provided on the transverse I-beam (10101) and the longitudinal I-beam (10102); The first ear plate (10109) is hingedly connected to a pull rod (10110); A triangular block (10111) is arranged between the cross-shaped I-beam (10103) and the pad (10105), the triangular block (10111) being located on two coaxial branches of the cross-shaped I-beam (10103), a pair of triangular blocks (10111) being connected by tension screws (10112) and being tightened by a first nut (10113) and a gasket (10114); the pad (10105) is in contact with the inclined surface of the triangular block (10111); Tracks (10115) are arranged on both sides of the triangular block (10111), and the tracks (10115) are welded to the branches of the cross-shaped I-beam (10103); The triangular blocks (10111) are inserted into the ribs (10116), and the ribs (10116) pass through a pair of triangular blocks (10111) and are placed under the pad (10105); A groove (10117) is arranged on the outer side of the rib (10116) to insert the side rib block (10118); A middle rib block (10119) is arranged between the two ribs (10116), a U-shaped groove (10120) is provided on the upper surface of the middle rib block (10119) for the tension screw (10112) to pass through, and the upper surface of the middle rib block (10119) is spaced from the lower surface of the pad (10105); A groove (10121) is formed on the bottom surface of the triangular block (10111), and rollers (10122) are distributed in the groove (10121).
3. The construction method of the concrete plant assembly plant machine supporting system according to claim 1 is characterized in that The early removal support column system (102) comprises: Multiple steel columns (10201) are arranged in upper and lower sections and spliced together; A flange (10202) is fixedly mounted on the end of the single-section steel column (10201); A reinforcing plate (10203) welded between the steel column (10201) and the flange (10202); Corbels (10204) are fixedly connected to both sides of the top steel column (10201); A second bolt and nut assembly (10205) fastened to the adjacent spliced flange (10202); A first clamp (10206), which is fixed on the bottom steel column (10201); A second ear plate (10207), which is arranged on the first hoop (10206); The steel column (10201) is provided with a first suspension ring (10208); The corbel (10204) comprises an upper chord (102401), a lower chord (102402), a vertical web member (102403) and an oblique web member (102404); a first bottom plate (102405) is fixed to one end of the upper chord (102401) and the lower chord (102402) close to the steel column (10201), and a second bottom plate (102406) is fixed to one end away from the steel column (10201); and the first bottom plate (102405) is fixed to the steel column (10201); A sealing ring (10209) is arranged between adjacent flanges (10202); The lower chord (102402) is shorter than the upper chord (102401), and a second suspension ring (102407) is fixedly connected to the portion of the upper chord (102401) that exceeds the lower chord (102402); A rib plate (102408) is welded on the first bottom plate (102405) and the second bottom plate (102406), the rib plate (102408) is fixedly connected to the first bottom plate (102405) and the upper chord (102401), and the rib plate (102408) is also fixedly connected to the first bottom plate (102405) and the lower chord (102402); the rib plate (102408) is also fixedly connected to the second bottom plate (102406) and the upper chord (102401), and the rib plate (102408) is also fixedly connected to the second bottom plate (102406) and the lower chord (102402); The first bottom plate (102405) is connected to a tension screw assembly (10210), and the tension screw assembly (10210) is connected to the steel column (10201) and the first bottom plates (102405) on both sides thereof; A partition (10211) is arranged in the top steel column (10201), the partition (10211) is welded in layers in the top steel column (10201), and is located below and above the tension screw assembly (10210), and a hole is opened in the upper partition (10211), and concrete is poured to make it dense; The first clamps (10206) are arranged in layers, the first screw rod (10212) is fixedly connected between the upper and lower first clamps (10206), the second ear plate (10207) is slidably connected to the first screw rod (10212), and the upper and lower sides of the second ear plate (10207) are threadedly connected to the second nut (10213); A horizontal plate (10214) is arranged inside the column head of the top section steel column (10201), a vertical plate (10215) is fixedly connected to the horizontal plate (10214), and a cover plate (10216) is fixedly connected to the vertical plate (10215).
4. The construction method of the concrete plant assembly plant machine supporting system according to claim 1 is characterized in that The truss platform system (3) comprises: The main trusses (301) are arranged in parallel at intervals; The secondary truss (302) is arranged vertically and crosswise with the main truss (301), and its upper chord and lower chord are made of square steel pipes. Positioning sleeves (30201) are fixed in the ends of the square steel pipes. The positioning sleeves (30201) are pressed against the upper and lower sides of the ends of the square steel pipes. A third bolt and nut assembly (305) is passed through the positioning sleeves. The third bolt and nut assembly (305) is tightened on the upper and lower sides of the ends of the square steel pipes. A first splicing plate (303) is fixed to both ends of the upper chord and the lower chord of the secondary truss (302), one end of which is embedded in the square steel tube and is pressed against the side of the positioning sleeve (30201); A second hoop (304) is fixed at intervals on the upper chord and the lower chord of the main truss (301), and a second splicing plate (30401) is arranged on the side thereof and is fixed to the first splicing plate (303) by a fourth bolt and nut assembly (306); End plates (3012) are fixed at both ends of the upper chord and the lower chord of the main truss 1, and bolt holes are provided on the end plates (3012); The two ends of the lower chord of the main truss 1 extend beyond the two ends of the upper chord, and the extending parts are fixed with lifting ears (307); The first splicing plate (303) is U-shaped, and the middle space thereof is penetrated by a positioning sleeve (30201); the second splicing plate (30401) is pressed against the positioning sleeve (30201) and then spliced with the first splicing plate (303) by a fourth bolt and nut assembly (306); An angle steel (308) is fixedly arranged between the second splicing plate (30401) and the side of the hoop (304); one leg of the angle steel (308) is tightened to the second splicing plate (30401) through a fifth bolt and nut assembly (309), and the other leg is tightened to the side of the hoop (304) through a bolt (3010); A second rib plate (3011) is welded to the angle steel (308).
5. The construction method of the concrete plant assembly plant machine supporting system according to claim 1 is characterized in that The transfer vehicle system (2) comprises: Truss platform (201); An axle seat (202) is installed at the bottom of the truss platform (201); An axle (203) is rotatably connected to the axle seat (202), and a worm is disposed in the middle thereof; Wheels (204) are coaxially fixed to both ends of the axle (203); A first turbine reduction box (205) is connected to the worm gear in the middle of the axle (203); A first motor (206), an output end of which extends into the first turbine reduction box (205) for transmission connection; A screw lift (207) is spaced apart from the axle (203) in front and rear, and has a middle support (20701), wherein the middle support (20701) is fixed to the lower chord of the truss platform (201); A sliding shoe (208) fixed to the lower output end of the lead screw elevator (207); A connecting rod (209), one end of which is hinged to one side of the sliding shoe (206); An internally threaded sleeve (2010) is hinged to the other end of the connecting rod (207); A second screw (2011), one end of which is threadedly connected to the internal threaded sleeve (10), and the other end of which is coaxially provided with a worm; A second turbine reduction box (2012) is connected to the worm gear at the other end of the second screw (2011); A second motor (2013), the output end of which extends into the second turbine reduction box (2012) for transmission connection; An arc-shaped track (2014) on which the sliding shoe (208) is slidably mounted and which is mounted on the lower side of the second turbine reduction box (2012); The axle seat (202), the axle (203), the wheel (204), the first turbine reduction box (205) and the first motor (206) are arranged in parallel in multiple groups at intervals on the bottom surface of the truss platform (1); The screw lifts (207) are arranged in a row of two and are linked by a transmission rod, the transmission rod is driven by a third turbine reduction box (2015), the third turbine reduction box (2015) is arranged between the two screw lifts (207), the third turbine reduction box (2015) is transmission-connected to the output end of a third motor (2016), and the third motor (2016) is installed on the truss platform (201); The sliding shoe (208) comprises a shell (20801), in which two upper and lower rows of limiting rollers (20802) are installed, and the arc track (2014) is made of I-beams, and the two ends of the upper row of limiting rollers (20802) are respectively mounted on the two side walls of the shell (20801) and pressed against the upper flange of the arc track (2014); one end of the lower row of limiting rollers (20802) is mounted on the side wall of the shell (20801), and the other end faces the web of the arc track (2014), and the upper side of the lower row of limiting rollers (20802) presses against the lower side of the upper flange of the arc track (2014); The second turbine reduction box (2012) is transmission-connected to the second screw rods (2011) on both sides, and the transmission method is such that when the second screw rod (2011) on one side is contracted in the internal thread sleeve (2010), the second screw rod (2011) on the other side is extended from the internal thread sleeve (2010) on the other side; The screw lift (207), the sliding shoe (208), the connecting rod (209), the internal threaded sleeve (2010), the second screw (2011), the second turbine reducer (2012), the second motor (2013) and the arc track (2014) are arranged in groups, and every two groups are paired and distributed on the front and rear sides of the truss platform (201) in the form of concentric circles; The truss platform (201) comprises a plurality of rows of main trusses (301) arranged at intervals, and secondary trusses (302) arranged crosswise and vertically between adjacent main trusses (301).
6. The construction method of the concrete plant assembly plant machine supporting system according to claim 1 is characterized in that The lifting system (4) comprises: The intelligent master control box is connected to the main power line, and the power output line and the communication line are connected. The power output line is connected to the surrounding branch cable, and multiple extension power lines are configured on the surrounding branch cable, and multiple branch communication lines are configured on the communication line; Intelligent extension, which is connected to the extension power line and branch communication line, and connected to the hoist power line; Electric hoist, which is connected to the hoist power line and installed on the corbel; The gravity sensor is arranged on the hanging point of the electric hoist and is electrically connected to the intelligent extension.
7. The construction method of the concrete plant assembly plant machine supporting system according to claim 1 is characterized in that The intelligent master control box and the intelligent extension are also electrically connected with an alarm device.
8. The construction method of the concrete plant assembly plant machine supporting system according to claim 7 is characterized in that The alarm mode is specifically as follows: When the load value collected by a certain intelligent extension position exceeds the design value by 15%, an automatic alarm should be given in the form of sound and light, and when it exceeds 30%, the electric hoist should be automatically shut down; Set the load loss alarm: When the load value collected by each intelligent extension position is less than the load loss alarm value, the intelligent extension and the intelligent master control box will emit intermittent short-term alarm sounds, and the weight of the heavy object will be displayed on the corresponding display; Set overload value alarm: When the maximum load value collected by each position reaches the overload value, the intelligent extension and the intelligent main control box will emit a long alarm sound and display the weight of the heavy object on the corresponding display; Set the overload limit value: When the load value collected by any machine position reaches the overload limit value, the intelligent extension and the intelligent master control box will issue a continuous alarm sound, and within 1 second, the relay output switch signal of the intelligent master control box will cut off the main control circuit, and the PC will display the status of each machine position when the cut-off occurs.
9. The construction method of the concrete plant assembly plant machine supporting system according to claim 1 is characterized in that The process of disassembling the early disassembly support system (1) is as follows: First, the early dismantling support column base system (101) is dismantled, and then the early dismantling support column system (102) is dismantled from bottom to top.
10. The construction method of the concrete plant assembly plant machine supporting system according to claim 2 is characterized in that The process of disassembling the early disassembly support system (1) is as follows: First, the early dismantling support column base system (101) is allowed to complete the unloading operation, and then the early dismantling support column system (102) and the early dismantling support column base system (101) are dismantled from bottom to top.
Citation Information
Patent Citations
Aluminum alloy rapid template system and construction method thereof
CN109610816A