Railway engineering construction organization design dynamic management system
Through the railway engineering construction organization design dynamic management system, the dual-code network diagram algorithm and blockchain technology are used to automatically adjust the construction process plan, solving the construction period delay problem caused by changes in objective factors in railway construction, and improving the efficiency of construction process planning and accuracy, and provide high security and transparency data storage.
Patent Information
- Application Number
- CN202411193178.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-12-31
AI Technical Summary
In railway construction, changes in objective factors of the project lead to low efficiency and low accuracy in the adjustment of construction process planning schemes, resulting in delays in construction periods.
Design a dynamic management system for railway engineering construction organization design, through multiple projects, construction process preparation subsystem, construction process planning and review terminal, cloud server and project supervision terminal, and use dual-code network diagram algorithm and blocks Chain technology, automated preparation and update construction process planning schemes, and improve efficiency and accuracy.
It improves the efficiency and accuracy of the preparation and update of construction process planning schemes, ensures that the project is carried out as planned, and provides high security and transparent construction organization scheme storage through blockchain technology.
Smart Images

Figure CN119228295A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of railway construction, and in particular to a dynamic management system for railway engineering construction organization design. Background Art
[0002] Railway construction organization design is divided into general construction organization plan opinions, construction organization plan opinions, construction organization design opinions, guiding construction organization design and implementation construction organization design according to different stages. Railway construction organization design should highlight the two main lines of track laying engineering and joint commissioning and testing and operation test. The track laying engineering line is the control line for the overall arrangement of various railway station pre-projects. In railway engineering, the focus should be on ensuring that the construction period of roadbed, bridges and tunnels does not touch the track laying line; the joint commissioning and testing and operation test line is the control line for the overall arrangement of post-station supporting projects and the adjustment of various subsystems. In post-station projects, the focus should be on ensuring that the construction period of four electricity, building construction, and station facilities does not touch the joint commissioning and testing line.
[0003] During the guiding construction organization design stage and the implementation construction organization design stage, when there are major changes in the objective factors of the project, including major changes in the construction plan, major changes in the total project period or the construction period of important nodes, serious discrepancies between the actual construction progress and the construction progress schedule, and major changes in the supply and demand of machinery, equipment, materials and labor, it will cause the pre-station project to exceed the track laying project line, the post-station project to exceed the joint debugging and operation test line, the railway project construction will not be completed within the specified time, the project cannot be carried out as planned, and the construction period will be delayed. Summary of the invention
[0004] In view of this, the embodiment of the present invention provides a railway engineering construction organization design dynamic management system to eliminate or improve one or more defects existing in the prior art. It solves the problem of low efficiency and low accuracy of manually adjusting the construction process planning scheme when the objective factors in the railway engineering construction have changed significantly and need to compile the construction process planning scheme in the prior art.
[0005] One aspect of the present invention provides a railway engineering construction organization design dynamic management system, the railway engineering construction organization design dynamic management system comprising:
[0006] Multiple railway engineering project import terminals are deployed in multiple project design parties to import railway engineering subject information, construction unit information, supplier information and construction demand information;
[0007] The construction process compilation subsystem includes a database module and a construction organization algorithm module. The database module is used to import or update the construction organization duration index library and the process logic relationship through a specified link; the construction organization algorithm module is used to store and execute a preset construction organization network diagram algorithm to compile a construction process planning scheme based on the railway engineering main body information, the construction unit information, the supplier information, the construction demand information, the construction organization duration index library and the process logic relationship; the construction organization network diagram algorithm is a calculation method for constructing a double-code network diagram according to the calculation time parameters of multiple railway engineering projects;
[0008] The construction process planning review terminal is used to review the construction process planning scheme according to a first preset standard. If the review is passed, the construction process planning scheme is marked with a version number to form a guiding construction organization plan and published, and the guiding construction organization plan is stored in a cloud server that can be remotely accessed.
[0009] In some embodiments, the railway engineering construction organization design dynamic management system also includes multiple project construction terminals and at least one project supervision terminal. The project construction terminal is deployed on the construction entity side, and is used to access the guiding construction organization plan stored in the cloud server, and to feedback construction progress information to the construction process compilation subsystem; the project supervision terminal is deployed on the supervision side, and is used to feedback supervision information to the construction process compilation subsystem, the cloud server and the project construction terminal.
[0010] In some embodiments, the construction process compilation subsystem further updates the completed and unfinished parts of the project engineering main body information based on the construction progress information;
[0011] The construction organization algorithm module is also used to recompile and update the construction process planning scheme according to the updated project engineering main body information, the construction unit information, the supplier information, the construction demand information, the construction organization duration indicator library and the process logic relationship;
[0012] The project supervision terminal is also used to review the updated construction process planning scheme according to the second preset standard, and if the review is passed, the updated construction process planning scheme is forwarded to the construction process planning review terminal;
[0013] The construction process planning review terminal is also used to review the updated construction process planning scheme according to a first preset standard. If the review is passed, the updated construction process planning scheme is marked with a version number to form an implementable construction organization plan and released, and the implementable construction organization plan is stored in a cloud server that can be remotely accessed.
[0014] In some embodiments, the railway engineering construction organization design dynamic management system further includes an early warning subsystem;
[0015] The early warning subsystem includes:
[0016] The construction progress information collection module is used to obtain the construction progress information fed back by the construction terminals of each project;
[0017] A construction organization plan acquisition module, used to obtain the guiding construction organization plan or the immediately updated implementation construction organization plan;
[0018] An early warning processor is used to review the construction progress information according to the guiding construction organization plan or the immediately updated implementation construction organization plan, and when the construction progress falls behind, generate an alarm message and send it to the project supervision terminal.
[0019] In some embodiments, the early warning subsystem further includes:
[0020] A construction environment element information collection component, the construction environment element information collection component includes a geological environment element collection module and a hydrological element collection module; the geological environment element collection module is used to collect geological monitoring data of the construction site of the railway engineering project at a first set time interval, and the hydrological element collection module collects hydrological monitoring data of the construction site of the railway engineering project at a second set time interval;
[0021] The early warning processor is also used to refer to the geological and hydrological standard requirements recorded in the construction demand information, detect the geological monitoring data and the hydrological monitoring data, and generate an alarm message and send it to the project supervision terminal when the geological environment and the hydrological environment do not meet the standards.
[0022] In some embodiments, the construction environment element information collection component further includes a meteorological environment element collection module, which is used to collect meteorological monitoring data of the construction site of the railway engineering project at a third set time interval;
[0023] The early warning processor is also used to perform weather broadcasts and weather early warnings during the construction process according to the weather monitoring data.
[0024] In some embodiments, the railway engineering construction organization design dynamic management system imports the railway engineering project into the terminal, the construction process compilation subsystem, the construction process planning and review terminal, the cloud server, the project construction terminal and the project supervision terminal as nodes to build a blockchain network, and packages the railway engineering main body information, the construction unit information, the supplier information, the construction demand information, the guiding construction organization plan and the implementation construction organization plan into the blockchain for storage.
[0025] In some embodiments, the execution steps of the construction organization network diagram algorithm include:
[0026] Decomposing the railway project into multiple sub-projects, and calculating the construction time parameters of each sub-project according to preset standards, wherein the construction time parameters include the earliest start time, the earliest finish time, the latest start time and the latest finish time;
[0027] The total time difference is calculated based on the latest start time and the earliest start time of each sub-project. The difference between the earliest start time of the latter and the earliest completion time of the former between adjacent sub-projects is taken as the free time difference of the former.
[0028] The sub-project when the total time difference and the free time difference are both zero is the key work, and the line that runs through the entire construction of the railway project and is composed of the sub-projects corresponding to the key work in a sequential order is the key line;
[0029] According to the key routes and based on the main information of the railway project, the construction unit information, the supplier information, the construction demand information, the construction organization period indicator library and the process logic relationship, the sub-projects except the key tasks are deployed into the construction process to compile a complete construction process planning plan.
[0030] In some embodiments, the railway engineering project import terminal is also used to import risk construction project disposal requirements and legal construction disposal requirements;
[0031] The construction organization algorithm module is used to store and execute a preset construction organization network diagram algorithm to prepare a construction process planning scheme based on the main information of the railway project, the construction unit information, the supplier information, the construction demand information, the construction organization period indicator library, the process logical relationship, the risk construction project disposal requirements and the legal construction disposal requirements.
[0032] In some embodiments, the railway engineering construction organization design dynamic management system further includes a cloud server;
[0033] The cloud server also includes:
[0034] A data resource collection and management module, used for storing various versions of the guiding construction organization plan and the implementing construction organization plan for remote access;
[0035] A planning scheme recovery module is used to recover the construction process planning scheme before the update, and the project designer applies for access to the recovered construction process planning scheme according to the construction demand;
[0036] The user management operation module is used by the construction entity to manage the implementable construction organization plan stored in the cloud server and select the implementable construction organization plan that meets the construction needs.
[0037] The beneficial effects of the present invention are at least:
[0038] In the railway engineering construction organization design dynamic management system described in the present invention, railway engineering main body information, construction unit information, supplier information and construction demand information are imported through multiple railway engineering project import terminals, and the construction process planning scheme is compiled and updated using the calculation method of the time parameter of the double-code network diagram. After the construction process planning review terminal reviews and approves the compiled and updated construction process planning scheme, the construction process planning scheme is marked with version numbers to form a guiding construction organization scheme and an implementation construction organization scheme. The guiding construction organization scheme and the implementation construction organization scheme are stored in a cloud server. The guiding construction organization scheme and the implementation construction organization scheme obtained by the cloud server are accessed and displayed through multiple project construction terminals, and the construction progress information is fed back, thereby improving the efficiency and accuracy of the railway engineering construction process planning scheme.
[0039] Furthermore, the main information of the railway project, the construction unit information, the supplier information, the construction demand information, the guiding construction organization plan and the implementable construction organization plan are packaged and stored on a blockchain constructed with the railway project import terminal, the construction process compilation subsystem, the construction process planning and review terminal, the cloud server, the project construction terminal and the project supervision terminal as nodes, providing a high degree of security and transparency for the storage of the construction organization plan.
[0040] Additional advantages, purposes, and features of the present invention will be described in part in the following description, and will become apparent to those skilled in the art after studying the following, or may be learned from the practice of the present invention. The purposes and other advantages of the present invention may be achieved and obtained by the structures specifically indicated in the specification and the accompanying drawings.
[0041] Those skilled in the art will appreciate that the objectives and advantages that can be achieved with the present invention are not limited to the above specific description, and the above and other objectives that can be achieved by the present invention will be more clearly understood from the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] The drawings described herein are used to provide a further understanding of the present invention, constitute a part of the present application, and do not constitute a limitation of the present invention. In the drawings:
[0043] Figure 1 The figure is a schematic diagram of the component modules of the dynamic management system for railway engineering construction organization design according to one embodiment of the present invention.
[0044] Figure 2 It is a component module of the cloud server described in an embodiment of the present invention.
[0045] Figure 3 It is a component module of the early warning subsystem described in an embodiment of the present invention.
[0046] Figure 4 A double-code network diagram drawn according to an embodiment of the present invention. DETAILED DESCRIPTION
[0047] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments and the accompanying drawings. Here, the illustrative embodiments of the present invention and their descriptions are used to explain the present invention, but are not intended to limit the present invention.
[0048] It should also be noted that, in order to avoid obscuring the present invention due to unnecessary details, only structures and / or processing steps closely related to the solutions according to the present invention are shown in the accompanying drawings, while other details that are not closely related to the present invention are omitted.
[0049] It should be emphasized that the term “include / comprises” when used herein refers to the presence of features, elements, steps or components, but does not exclude the presence or addition of one or more other features, elements, steps or components.
[0050] It should also be noted that, unless otherwise specified, the term “connection” herein may refer not only to a direct connection but also to an indirect connection involving an intermediate.
[0051] Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings. In the accompanying drawings, the same reference numerals represent the same or similar components, or the same or similar steps.
[0052] In the prior art, during the guiding construction organization design stage and the implementation construction organization design stage, when there are major changes in the objective factors of the project, including major changes in the construction plan, major changes in the total project period or the important node period, serious discrepancies between the actual construction progress and the construction schedule, and major changes in the supply and demand of machinery, equipment, materials and labor, the track laying project period will exceed the track laying project line, the project cannot be advanced as planned, the construction period is delayed, and manual adjustment is required; the present invention proposes a dynamic management system for railway engineering construction organization design. When there are major changes in the objective factors of railway engineering construction, the system prepares a construction process planning scheme through multiple railway engineering project import terminals, a construction process compilation subsystem, a construction process planning review terminal, a cloud server, multiple project construction terminals, a project supervision terminal and an early warning subsystem in combination with computer development languages and algorithms.
[0053] Figure 1 The figure is a schematic diagram of the components of a railway engineering construction organization design dynamic management system according to an embodiment of the present invention. Specifically, the present invention provides a railway engineering construction organization design dynamic management system, which includes:
[0054] Multiple railway engineering project import terminals 100 are deployed in multiple project design parties and are used to import railway engineering main body information, construction unit information, supplier information and construction demand information. The project design party is a professional unit with sufficient qualifications and experience, responsible for comprehensive survey, design and planning of railway engineering projects, so as to design railway construction projects that meet the project's own construction needs and comply with relevant regulations of railway engineering. The project design party uses the railway engineering project import terminal to import railway engineering main body information, construction unit information, supplier information and construction demand information. Specifically, the railway engineering main body information includes construction location, construction impact range and construction environment, the construction unit information includes construction technology, construction speed and construction quality, the supplier information includes equipment, materials and construction cost required for the project, and the construction demand information includes construction period, construction requirements and construction budget. By integrating the railway engineering main body information, construction unit information, supplier information and construction demand information, the construction process planning scheme of the railway engineering project is assisted in preparation, the construction main body and the project design party are promoted to work together, accurate information support is provided, and the progress, cost, quality and resources of the railway engineering project are efficiently managed and planned and allocated, so as to ensure the quality and efficiency of the construction of the engineering project.
[0055] The construction process compilation subsystem 200 includes a database module and a construction organization algorithm module. The database module is used to import or update the construction organization duration index library and the process logic relationship through a specified link; the construction organization algorithm module is used to store and execute a preset construction organization network diagram algorithm to compile a construction process planning scheme based on the main information of the railway project, the construction unit information, the supplier information, the construction demand information, the construction organization duration index library and the process logic relationship; the construction organization network diagram algorithm is a calculation method for constructing a double-code network diagram based on the calculation time parameters of multiple railway engineering projects.
[0056] The construction period index library in the database is a relationship between engineering quantities and indicators set according to logical relationships to achieve the lowest cost and shortest construction period on key routes. The construction period index library for railway projects includes:
[0057] Critical path analysis indicators: The critical path determines the shortest completion time of the project. When the sub-projects on the critical path are delayed, the entire project will be delayed. Therefore, this indicator is an important indicator for monitoring the progress of the project.
[0058] Project estimated time and actual completion time data: Project estimated time, actual completion time and historical data help to make more accurate and reasonable predictions and plans for future construction progress.
[0059] Resource allocation and utilization indicators: Resources include manpower, materials and equipment. Reasonable allocation of resources and improved resource utilization will help the smooth progress of construction and reduce costs.
[0060] The construction organization algorithm module implements the construction organization network diagram algorithm through the calculation method of the time parameters of the double-code network diagram. The mutual constraints and interdependence between the sub-projects in the engineering project constitute the logical relationship of the double-code network diagram. The logical relationship includes process relationship and organizational relationship. The process relationship is determined by the process or work procedure of each sub-project. The organizational relationship is the sequence relationship determined according to the organizational arrangement needs or resource allocation needs between the sub-projects. The construction process planning scheme is compiled according to the construction organization duration indicator library and the process logical relationship and the calculation method of the double-code network diagram time parameters. In some embodiments, the execution steps of the construction organization network diagram algorithm include steps S101 to S104:
[0061] Step S101: Decompose the railway project into multiple sub-projects, and calculate the construction time parameters of each sub-project according to preset standards. The construction time parameters include the earliest start time, the earliest finish time, the latest start time and the latest finish time.
[0062] Step S102: The total time difference is calculated according to the latest start time and the earliest start time of each sub-project, and the difference between the earliest start time of the latter and the earliest completion time of the former between adjacent sub-projects is used as the free time difference of the former.
[0063] Step S103: The sub-projects when the total time difference and the free time difference are both zero are key tasks, and the sub-projects corresponding to the key tasks are arranged in a sequential order to form a key route that runs through the entire railway project construction.
[0064] Step S104: According to the key lines and based on the main information of the railway project, construction unit information, supplier information, construction demand information, construction organization and duration indicator library and process logic relationship, sub-projects other than key tasks are deployed into the construction process to prepare a complete construction process planning plan.
[0065] Furthermore, a free time difference of zero means that the earliest start time of the latter of the adjacent sub-projects is the same as the earliest completion time of the former, that is, the time interval between the two sub-projects is zero. The critical line of the railway project is the line with the longest total duration among the lines running through the beginning and the end. The critical line is not unique. When the time parameter of a sub-project in the railway project changes, the critical line will also change. The preparation method of the construction schedule of the railway project includes the preparation method of the bar chart schedule and the preparation method of the engineering network plan, wherein the engineering network plan includes the double-code network plan, the single-code network plan, the double-code time-scale network plan and the single-code overlap network plan. In addition to using the double-code network diagram to prepare the construction process planning scheme of the railway project, the construction organization algorithm module also includes: single-code network diagram, double-code time-scale network plan diagram, single-code overlap network plan diagram and bar chart.
[0066] The construction process planning review terminal 300 is used to review the construction process planning scheme according to the first preset standard. If the review is passed, the construction process planning scheme is marked with a version number to form a guiding construction organization plan and published, and the guiding construction organization plan is stored in a cloud server that can be remotely accessed.
[0067] Specifically, the construction process planning and review terminal is deployed in the construction unit. The review departments in the construction unit include the planning department, environmental protection department, land management department and financial department. The planning of the railway project requires the approval of the urban and rural planning department, and the environmental impact assessment report of the railway project requires the approval of the environmental protection department. In addition, the location of the railway project requires the land use right approval of the land management department, and the financial department is responsible for reviewing the use of funds for the railway project. The first preset standards include: the construction plan complies with the safety assessment and risk management requirements, the construction process procedures and time arrangements are reasonable, the use of construction funds is compliant, and the construction operations are safe.
[0068] Figure 2 It is a component module of the cloud server described in an embodiment of the present invention. In some embodiments, the railway engineering construction organization design dynamic management system also includes a cloud server 400.
[0069] The cloud server includes:
[0070] The data resource collection and management module 401 is used to store various versions of the guiding construction organization plan and the implementing construction organization plan for remote access.
[0071] The planning scheme recovery module 402 is used to recover the construction process planning scheme before the update, and the project designer applies for access to the recovered construction process planning scheme according to the construction demand.
[0072] The user management operation module 403 is used by the construction entity to manage the feasible construction organization plans stored in the cloud server and select the feasible construction organization plan that meets the construction needs.
[0073] Specifically, the cloud server collects the construction process planning scheme and the guiding construction organization scheme and implementation construction organization scheme formed after marking and integrates them into the data resource collection and management module, so that users can remotely access the database, and when the same construction requirements appear, they can quickly access the historical construction scheme and select the corresponding construction scheme that meets the construction requirements from the database, thereby improving the efficiency of the railway engineering construction organization design dynamic management system in compiling and updating the construction process planning scheme. The cloud server is a remote server that provides computer services and data storage through the Internet. The existing cloud server platforms include Alibaba Cloud, Amazon AWS (Amazon Web Services) and Microsoft Azure (Microsoft Azure).
[0074] In some embodiments, the railway project import terminal is also used to import risk construction project disposal requirements and legal construction disposal requirements. The construction organization algorithm module is used to store and execute a preset construction organization network diagram algorithm to compile a construction process planning scheme based on railway project subject information, construction unit information, supplier information, construction demand information, construction organization duration index library, process logic relationship, risk construction project disposal requirements and legal construction disposal requirements.
[0075] In some embodiments, the railway engineering construction organization design dynamic management system also includes a plurality of project construction terminals 500 and at least one project supervision terminal 600. The project construction terminal is deployed on the construction subject side, and is used to access the guiding construction organization plan stored in the cloud server, and to feedback the construction progress information to the construction process compilation subsystem; the project supervision terminal is deployed on the supervision side, and is used to feedback the supervision information to the construction process compilation subsystem, the cloud server and the project construction terminal. The supervision information of the project supervision terminal is fed back to the construction process compilation subsystem, the cloud server and the project construction terminal. When there are problems in the supervision information, the construction process compilation subsystem adjusts the construction process planning plan according to the feedback information and saves the supervision information to the cloud server, so as to supervise and adjust the construction project in real time and ensure the safety and punctuality of the construction project.
[0076] Specifically, the construction process plan approved by the construction process planning review terminal is marked as a guiding construction organization plan, which is stored in the cloud server for remote access. The guiding construction process plan in the cloud server can be accessed through the project construction terminal in the main construction party. Users can share the guiding construction process plan in the cloud server. The guiding construction organization plan guides the planning of railway engineering construction work. The disposal of risky construction projects requires monitoring, prediction and early warning of risks based on the risk control of construction projects and the identification and assessment of risks in accordance with the risk management plan. Risk control requires the joint participation of the construction unit, the main construction party and the project design party. The construction unit clarifies the quality risk control responsibilities of each construction party of the project, formulates risk control plans and work implementation methods, implements the specific responsibilities of risk control, and supervises, inspects and evaluates the risk management work of the construction parties. The project design party clarifies the engineering measures for risk control of high-risk construction projects and puts forward guiding suggestions for preventing risks. The main construction party strictly implements the formulated risk control plan and work implementation methods for the construction phase and conducts construction environmental and social environmental risk surveys. It conducts real-time tracking and monitoring of risks during the project construction process, issues early warnings for newly discovered risk events and potential risk factors, conducts timely risk identification and assessment, formulates corresponding countermeasures, strengthens quality control of building components and materials and conducts quality re-inspections to ensure that the building components and materials used on the project meet the construction requirements.
[0077] Furthermore, the construction process compilation subsystem, construction organization algorithm module, construction process planning and review terminal and cloud server are also used to update the project engineering main information, construction unit information, supplier information, construction demand information, construction organization duration indicator library and process logical relationship to form and mark the implementable construction organization plan.
[0078] In some embodiments, the construction process compilation subsystem also updates the completed and unfinished parts in the project engineering main body information based on the construction progress information.
[0079] The construction organization algorithm module is also used to recompile and update the construction process planning plan based on the updated project engineering main information, construction unit information, supplier information, construction demand information, construction organization duration indicator library and process logic relationship.
[0080] The project supervision terminal is also used to review the updated construction process planning scheme according to the second preset standard. If the review is passed, the updated construction process planning scheme is forwarded to the construction process planning review terminal.
[0081] The construction process planning review terminal is also used to review the updated construction process planning scheme according to the first preset standard. If the review is passed, the updated construction process planning scheme is marked with a version number to form an implementable construction organization plan and publish it, and the implementable construction organization plan is stored in a cloud server that can be remotely accessed.
[0082] Specifically, the situations where the construction process planning scheme needs to be updated include: when the guiding construction organization plan or the implementation construction organization plan is prepared, there is a difference between the planned construction period and the calculated construction period; when the geological conditions are beyond the prediction during the construction stage of the railway project; due to special policy reasons, the total construction period of the project or the construction period of important nodes has changed significantly; during the construction stage of the railway project, the on-site project progress is deduced based on the on-site real-time progress data and the deduction algorithm, and the project progress is predicted to exceed the reasonable warning range. The second preset standard includes: the construction process complies with the goals, tasks and responsibilities specified in the supervision outline and supervision plan, and the construction behavior complies with the quality, safety and progress requirements of the supervision unit.
[0083] Furthermore, in some embodiments, the railway engineering construction organization design dynamic management system uses the railway engineering project import terminal, construction process compilation subsystem, construction process planning and review terminal, cloud server, project construction terminal and project supervision terminal as nodes to build a blockchain network, and packages the railway engineering main body information, construction unit information, supplier information, construction demand information, guiding construction organization plan and implementation construction organization plan into the blockchain for storage.
[0084] Specifically, blockchain technology records data in multiple blocks and verifies and stores it through nodes in the network, thereby achieving data transparency, security, and immutability, providing a more reliable storage space for construction organization plans in the dynamic management system of railway engineering construction organization design.
[0085] Figure 3It is a component of the early warning subsystem described in an embodiment of the present invention. In some embodiments, the railway engineering construction organization design dynamic management system also includes an early warning subsystem 700.
[0086] The early warning subsystem includes:
[0087] The construction progress information collection module 701 is used to obtain the construction progress information fed back by the construction terminals of each project.
[0088] The construction organization plan acquisition module 702 is used to obtain a guiding construction organization plan or an immediately updated implementable construction organization plan.
[0089] The early warning processor 703 is used to review the construction progress information according to the guiding construction organization plan or the immediately updated implementation construction organization plan. When the construction progress falls behind, an alarm message is generated and sent to the project supervision terminal.
[0090] In some embodiments, the early warning subsystem further includes:
[0091] The construction environment element information collection component 704 includes a geological environment element collection module 7041 and a hydrological element collection module 7042; the geological environment element collection module is used to collect geological monitoring data of the railway project construction site according to a first set time interval, and the hydrological element collection module is used to collect hydrological monitoring data of the railway project construction site according to a second set time interval.
[0092] The early warning processor is also used to refer to the geological and hydrological standard requirements recorded in the construction demand information, to detect the geological monitoring data and hydrological monitoring data, and to generate an alarm message and send it to the project supervision terminal when the geological environment and hydrological environment do not meet the standards.
[0093] In some embodiments, the construction environment element information collection component further includes a meteorological environment element collection module 7043, which is used to collect meteorological monitoring data of the railway project construction site at a third set time interval. The early warning processor is also used to perform weather broadcasts and weather warnings during the construction process based on the meteorological monitoring data.
[0094] Specifically, the establishment of an early warning subsystem is an important means to maintain the smooth implementation and advancement of the construction process. By real-time monitoring of the construction process and obtaining construction progress information of each project, it helps to review whether the construction is proceeding according to the planned progress in the construction process planning scheme. When the progress is not as planned, it is necessary to generate alarm information and adjust the construction process planning scheme according to the existing problems to solve the problems, ensuring that the project can be completed on time as planned. By obtaining the guiding construction organization plan and the implementation construction organization plan and their problem situations and solutions, the same problems can be avoided under the same circumstances, thereby improving the efficiency and accuracy of project construction and the preparation and updating of construction process planning schemes.
[0095] Furthermore, the impacts of geological, hydrological and meteorological environmental factors include:
[0096] Geological environmental factors include geological structure and soil type. Different geological structures have a direct impact on the foundation design of engineering construction. In earthquake-prone areas or geologically active areas, special foundation treatment measures are needed to improve the seismic resistance of railway engineering buildings.
[0097] Hydrological elements include groundwater level and river flow pattern. The height and changes of groundwater level have a significant impact on construction. Excessively high or changing groundwater level may lead to soil erosion and unstable foundation. For railway projects along or across rivers, the river's flow rate, flow and sediment content will affect the design and construction of the project.
[0098] Meteorological environmental factors include temperature, precipitation, wind and climate. Extreme temperatures will affect the hardening speed and strength of concrete. Temperature changes will cause deformation and damage to building materials. Continuous rainfall will cause mud and water accumulation at the construction site. Too strong winds will affect the stability of high-rise buildings. Extreme weather will affect construction safety. These environmental factors will affect construction operations and progress.
[0099] The present invention is described below in conjunction with a specific embodiment:
[0100] 1. Meaning and symbols of time parameters.
[0101] 1. Working duration (D i―j ): The time from the start to the completion of a task.
[0102] 2. Duration (T): The time required to complete a task, generally there are three types:
[0103] 2.1 Calculation of construction period (T c ), the construction period calculated based on the network planning time parameters.
[0104] 2.2 Required construction period (T r ), the duration required by the task entruster.
[0105] 2.3 Planned construction period (T p ), the construction period determined as the implementation target based on the required construction period and the calculated construction period.
[0106] When the required construction period T is specified r When T p ≤T r ; When the required duration is not specified, the planned duration can be equal to the calculated duration, T p =T c .
[0107] 3. Six time parameters in the parameter annotation table: The three parameters in the first row of the parameter annotation table are, from left to right, the earliest start time, the latest start time, and the total time difference; the three parameters in the second row are, from left to right, the earliest completion time, the latest completion time, and the free time difference.
[0108] 3.1 Earliest start time (ES i―j , Earliest Start), the earliest time when task i-j may start after all the preceding tasks are completed.
[0109] 3.2 Earliest Finish Time (EF i―j , Earliest Finish), the earliest time that task i-j can be completed after all the preceding tasks are completed.
[0110] 3.3 Latest start time (LS i―j , Latest Start), the latest time when task i-j must start without affecting the timely completion of the entire task.
[0111] 3.4 Latest Completion Time (LF i―j , Latest Finish), the latest time when tasks i-j must be completed without affecting the timely completion of the entire task.
[0112] 3.5 Total time difference (TF i―j , Total Float), the flexible time that can be used by tasks i-j without affecting the total construction period.
[0113] 3.6 Free time difference (FF i―j Free Float refers to the free time that can be used by tasks i-j without affecting the earliest start of the subsequent tasks.
[0114] 4. Draw a double-code network diagram according to the network plan work logic relationship and duration table below. Table 1 is a table of the work logic relationship and duration of multiple projects in an example, where the previous work represents the previous stage sub-project of the sub-project, and the next work represents the next stage sub-project of the sub-project. Table 2 is a comparison table of the work logic relationship representation method when drawing a double-code network diagram.
[0115] Table 1 Logical relationship and duration of project work
[0116]
[0117] Table 2 Comparison table of working logic relationship representation methods
[0118]
[0119] Table 2 Comparison table of working logic relationship representation methods
[0120]
[0121] According to the logical relationship of project work and the duration table, it starts from the starting node (node 1) and ends at the end node (node 15). Arrows are used to connect the sub-projects to indicate the logical relationship between the sub-projects. The names of the sub-projects are marked above the arrows, and the duration required to complete the sub-projects is marked below the arrows. The time parameters calculated for each sub-project are marked in the corresponding arrow area in the form of a parameter marking table.
[0122] Position node 1 at the starting position, and determine the intermediate nodes from left to right. The number of inward arrows is the same as the number of preceding tasks of the sub-project. For one inward arrow, the next node can be marked directly at the end of the arrow. For multiple inward arrows, all the inward arrows need to be drawn before the next node can be drawn at the end of the multiple arrows. The number of outward arrows is the same as the number of subsequent tasks. Draw them according to the method of representing the logical relationship of the work until the end of the terminal node.
[0123] 4.1 Calculate the earliest start time and earliest completion time of each task: start from the starting node 1 and calculate one by one along the arrow line to the end node 15.
[0124] 4.1.1 The earliest starting time of each task starting from the starting node of the network plan is zero.
[0125] Earliest start time of work 1-2 ES 1―2 Starting from the starting node, calculate item by item along the arrow line direction, because the earliest starting time ES is not specified 1―2 , so according to the formula ESi ―j =0(i=1)Determine:
[0126] ES 1―2 =0;
[0127] 4.1.2 Earliest start time of work ES i―i Press ES i―j =max{EF h―i}Japanese style ES i―j =max{ES h―i +D h―i}calculate:
[0128] ES 2―3 =ES 1―2 +D 1―2 =0+2=2;
[0129] ES 2―4 =ES 1―2 +D 1―2 =0+2=2;
[0130] ES 3―5 =ES 2―3 +D 2―3 =2+3=5;
[0131] ES 4―5 =ES 2―4 +D 2―4 =2+2=4;
[0132] ES 5―6 =max{ES 3―5 +D 3―5 ,ES 4―5 +D 4―5}=max{5+0,4+0}=max{5,4}=5;
[0133] The earliest completion time of the work is the earliest start time of the work ES i―j Duration of this work D i―j The sum of the two, according to the formula EF i―j =ES i―j +D i―j Calculations such as:
[0134] EF 1―2 =ES 1―2 +D 1―2 =0+2=2;
[0135] ES 2―4 =ES 2―4 +D 2―4 =2+2=4;
[0136] ES 5―6 =ES 5―6 +D 5―6=5+3=8;
[0137] 4.2 Determine the calculation period T c And the planned construction period T p .
[0138] It is known that the planned duration is equal to the calculated duration, that is, the calculated duration of the network plan is T c Take the maximum value of the earliest completion time of work 13-15 and work 14-15 with the end node 15 as the arrow node, and use the formula T c =max{EF i―n}calculate:
[0139] T c =max{EF 13―15 , E.F. 14―15} = max{22, 22} = 22;
[0140] 4.3 Calculate the latest start time and latest completion time of each task: start from the end node 15 and calculate one by one in the opposite direction of the arrow line to the starting node 1.
[0141] 4.3.1 The latest completion time of the work with the network plan end node as the arrow node is equal to the latest completion time of the work i-j at the end of the planned duration network plan, according to the formula LF i―n =T p Calculations such as:
[0142] LF 13―15 =T p =22;
[0143] LF 14―15 =T p =22;
[0144] 4.3.2 The latest completion time of each task is LF i-j =min{LF j―k ―D j―k}calculate:
[0145] LF 13―14 =min{LF 14―15 ―D 14―15}=22―3=19;
[0146] LF 12―13 =min{LF 13―15 ―D 13―15 ,LF 13―14 ―D 13―14}=min{22-3,19-0}=19;
[0147] LF 11―12 =min{LF12―13 ―D 12―13}=19―4=15;
[0148] The latest start time for each task is based on the LS i―j =LF i―j ―D i―j calculate:
[0149] LS 14―15 =LF 14―15 ―D 14―15 =22-3=19;
[0150] LS 13―15 =LF 13―15 ―D 13―15 =22-3=19;
[0151] LS 12―13 =LF 12―13 ―D 12―13 =19-4=15;
[0152] 4.4 Calculate the total time difference for each task: subtract the earliest start time from the latest start time of the task or subtract the earliest finish time from the latest finish time of the task.
[0153] TF 1―2 =LS 1―2 ―ES 1―2 =0-0=0;
[0154] TF 2―3 =LS 2―3 ―ES 2―3 =2-2=0;
[0155] TF 5―6 =LS 5―6 ―ES 5―6 =5-5=0;
[0156] 4.5 Calculate the free time difference of each task: The free time difference of task i-j in the network is equal to the earliest start time of the next task minus the earliest completion time of the task, which can be calculated according to the formula FF i―j =ES j―k ―EF i―j Calculations such as:
[0157] FF 1―2 =ES 2―3 ―EF 1―2 =2-2=0;
[0158] FF 2―3 =ES 3―5 ―EF 2―3 =5-5=0;
[0159] FF 5―6 =ES 6―8 ―EF 5―6 =8-8=0;
[0160] The free time difference between finishing tasks i and j in the network plan is expressed as FF i―n =T p ―EF i―n calculate:
[0161] FF 13―15 =T p ―EF 13―15 =22-22=0;
[0162] FF 14―15 =T p ―EF 14―15 =22-22=0;
[0163] Mark the above calculation results in the corresponding positions in the double-code network diagram.
[0164] 4.6 Determine the key tasks and key routes: In the double-code network diagram, the tasks with both total time difference and free time difference of 0 are key tasks. The key tasks in this diagram are: A 1 , B 1 , B 2 , C 2 , C 3 , E, G, H, I. The key line consisting of key tasks from beginning to end is marked with thick arrows. The final result is as follows Figure 4 A dual-code network diagram.
[0165] 2. Adjustment of construction process planning scheme.
[0166] 1. Situations where construction process planning requires dynamic adjustment include:
[0167] a: During the construction process planning stage, the key routes and total construction period of the railway project are calculated through the double-code network diagram. If the planned total construction period is less than the calculated total construction period, the network plan diagram needs to be adjusted. If the planned total construction period is greater than the calculated total construction period, the calculated total construction period shall be followed.
[0168] b: If unexpected situations occur during the project construction, the construction plan will be adjusted without affecting the original key lines.
[0169] c: Due to special policy reasons, the total project duration or the duration of important nodes has undergone major changes. For example, the total project duration is advanced, and it is necessary to adjust the construction process planning scheme of the existing project volume to speed up the progress.
[0170] d: During the project construction process, the real-time progress data on site and the deduction warning algorithm are used to predict whether the project progress is within a reasonable warning range. If it is not within a reasonable range, the construction process planning plan needs to be adjusted.
[0171] 2. The contents of the construction process planning adjustment include: adjusting the length of the critical route; adjusting the time difference of non-critical work; adding or reducing work items; adjusting logical relationships; re-estimating the duration of certain work; and making corresponding adjustments to resource inputs.
[0172] 3. Methods for adjusting the construction process planning scheme:
[0173] 3.1 Methods for adjusting the length of critical lines include:
[0174] a. When the actual progress of the critical path lags behind the planned progress, the unfinished critical tasks with low resource intensity or low cost should be selected to shorten their duration, and the time parameters of the unfinished parts should be recalculated and implemented as a new plan.
[0175] b. When the actual progress of the critical line is ahead of the planned progress, if the construction period is not advanced, the subsequent critical tasks with large resource consumption or high direct costs should be selected and their duration should be appropriately extended to reduce their resource intensity or costs; if the construction period is advanced, the unfinished part of the plan should be treated as a new plan, and the duration of the critical tasks should be re-determined and implemented according to the new plan.
[0176] 3.2 Methods for adjusting the time difference of non-critical work include: moving the work within the range of its earliest start time and latest completion time; extending the duration of the work; shortening the duration of the work.
[0177] 3.3 When adding or reducing work items, the following regulations should be followed: the overall logical relationship of the original network plan should not be disrupted, and only the local logical relationship should be adjusted; after adding or reducing work, the time parameters should be recalculated and the impact on the original network plan should be analyzed; when there is an impact on the construction period, adjustment measures should be taken to ensure that the planned construction period remains unchanged.
[0178] 3.4 Adjustment of logical relationships: Logical relationships can only be adjusted when actual conditions require changes in construction methods or organizational methods. When making adjustments, the originally planned construction period and other work should not be affected.
[0179] 3.5 Adjust the duration of work: When it is found that the original duration of certain work is incorrectly estimated or the conditions for its implementation are insufficient, its duration should be re-estimated and the time parameters should be recalculated to minimize the impact on the original planned duration.
[0180] 3.6 Adjust resource input: When abnormalities occur in resource supply, resource optimization methods should be used to adjust the plan or take emergency measures to minimize the impact on the construction period.
[0181] In summary, the present invention provides a dynamic management system for railway engineering construction organization design, which imports railway engineering main body information, construction unit information, supplier information and construction demand information through multiple railway engineering project import terminals, and uses the calculation method of double-code network diagram time parameters to compile and update the construction process planning scheme. After the construction process planning review terminal reviews and approves the compiled and updated construction process planning scheme, the construction process planning scheme is marked with version numbers to form a guiding construction organization plan and an implementing construction organization plan. The guiding construction organization plan and the implementing construction organization plan are stored in a cloud server, and the guiding construction organization plan and the implementing construction organization plan obtained by the cloud server are accessed and displayed through multiple project construction terminals, and the construction progress information is fed back.
[0182] Furthermore, the railway project main information, construction unit information, supplier information, construction demand information, guiding construction organization plan and implementation construction organization plan are stored on a blockchain built with railway project import terminals, construction process compilation subsystems, construction process planning and review terminals, cloud servers, project construction terminals and project supervision terminals as nodes, providing a high degree of security and transparency for the storage of construction organization plans.
[0183] An embodiment of the present invention further provides a computer device, which may include a processor and a memory, wherein the processor and the memory may be connected via a bus or in other ways.
[0184] The processor may be a central processing unit (CPU). The processor may also be other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, or a combination of the above chips.
[0185] The memory, as a non-transitory computer-readable storage medium, can be used to store non-transitory software programs, non-transitory computer executable programs and modules, such as the program instructions / modules corresponding to the key shielding method of the vehicle-mounted display device in the embodiment of the present invention. The processor executes various functional applications and data processing of the processor by running the non-transitory software programs, instructions and modules stored in the memory.
[0186] The memory may include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function; the data storage area may store data created by the processor, etc. In addition, the memory may include a high-speed random access memory, and may also include a non-volatile memory, such as at least one disk storage device, a flash memory device, or other non-volatile solid-state storage device. In some embodiments, the memory may optionally include a memory remotely arranged relative to the processor, and these remote memories may be connected to the processor via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0187] The one or more modules are stored in the memory, and when executed by the processor, the method described in this embodiment is performed.
[0188] The embodiment of the present invention also provides a computer-readable storage medium on which a computer program is stored, and when the computer program is executed by a processor, the steps of the aforementioned edge computing server deployment method are implemented. The computer-readable storage medium can be a tangible storage medium, such as a random access memory (RAM), a memory, a read-only memory (ROM), an electrically programmable ROM, an electrically erasable programmable ROM, a register, a floppy disk, a hard disk, a removable storage disk, a CD-ROM, or any other form of storage medium known in the technical field.
[0189] It should be understood by those skilled in the art that the exemplary components, systems and methods described in conjunction with the embodiments disclosed herein can be implemented in hardware, software or a combination of the two. Whether it is performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention. When implemented in hardware, it can be, for example, an electronic circuit, an application specific integrated circuit (ASIC), appropriate firmware, a plug-in, a function card, etc. When implemented in software, the elements of the present invention are programs or code segments used to perform the required tasks. The program or code segment can be stored in a machine-readable medium, or transmitted on a transmission medium or a communication link via a data signal carried in a carrier.
[0190] It should be clear that the present invention is not limited to the specific configuration and processing described above and shown in the figures. For the sake of simplicity, a detailed description of the known method is omitted here. In the above embodiments, several specific steps are described and shown as examples. However, the method process of the present invention is not limited to the specific steps described and shown, and those skilled in the art can make various changes, modifications and additions, or change the order between the steps after understanding the spirit of the present invention.
[0191] In the present invention, features described and / or illustrated for one embodiment may be used in the same or similar manner in one or more other embodiments, and / or combined with features of other embodiments or replace features of other embodiments.
[0192] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the embodiments of the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A railway engineering construction organization design dynamic management system, characterized in that: include: Multiple railway engineering project import terminals are deployed in multiple project design parties to import railway engineering subject information, construction unit information, supplier information and construction demand information; The construction process compilation subsystem includes a database module and a construction organization algorithm module. The database module is used to import or update the construction organization duration index library and the process logic relationship through a specified link; the construction organization algorithm module is used to store and execute a preset construction organization network diagram algorithm to compile a construction process planning scheme based on the railway engineering main body information, the construction unit information, the supplier information, the construction demand information, the construction organization duration index library and the process logic relationship; the construction organization network diagram algorithm is a calculation method for constructing a double-code network diagram according to the construction time parameters of multiple railway engineering projects; The construction process planning review terminal is used to review the construction process planning scheme according to a first preset standard. If the review is passed, the construction process planning scheme is marked with a version number to form a guiding construction organization plan and published, and the guiding construction organization plan is stored in a cloud server that can be remotely accessed.
2. The railway engineering construction organization design dynamic management system according to claim 1 is characterized in that: The system also includes multiple project construction terminals and at least one project supervision terminal. The project construction terminal is deployed on the construction entity side and is used to access the guiding construction organization plan stored in the cloud server and to feedback construction progress information to the construction process compilation subsystem; the project supervision terminal is deployed on the supervision side and is used to feedback supervision information to the construction process compilation subsystem, the cloud server and the project construction terminal.
3. The railway engineering construction organization design dynamic management system according to claim 2 is characterized in that: The construction process compilation subsystem also updates the completed and unfinished parts of the project engineering main body information based on the construction progress information; The construction organization algorithm module is also used to recompile an updated construction process planning scheme based on the updated project engineering main body information, the construction unit information, the supplier information, the construction demand information, the construction organization duration indicator library and the process logic relationship; The project supervision terminal is also used to review the updated construction process planning scheme according to the second preset standard, and if the review is passed, the updated construction process planning scheme is forwarded to the construction process planning review terminal; The construction process planning review terminal is also used to review the updated construction process planning scheme according to a first preset standard. If the review is passed, the updated construction process planning scheme is marked with a version number to form an implementable construction organization plan and released, and the implementable construction organization plan is stored in a cloud server that can be remotely accessed.
4. The railway engineering construction organization design dynamic management system according to claim 3 is characterized in that: The system also includes an early warning subsystem; The early warning subsystem includes: The construction progress information collection module is used to obtain the construction progress information fed back by the construction terminals of each project; A construction organization plan acquisition module, used to obtain the guiding construction organization plan or the immediately updated implementation construction organization plan; An early warning processor is used to review the construction progress information according to the guiding construction organization plan or the immediately updated implementation construction organization plan, and when the construction progress falls behind, generate an alarm message and send it to the project supervision terminal.
5. The railway engineering construction organization design dynamic management system according to claim 4 is characterized in that: The early warning subsystem also includes: A construction environment element information collection component, the construction environment element information collection component includes a geological environment element collection module and a hydrological element collection module; the geological environment element collection module is used to collect geological monitoring data of the construction site of the railway engineering project at a first set time interval, and the hydrological element collection module collects hydrological monitoring data of the construction site of the railway engineering project at a second set time interval; The early warning processor is also used to refer to the geological and hydrological standard requirements recorded in the construction demand information, detect the geological monitoring data and the hydrological monitoring data, and generate an alarm message and send it to the project supervision terminal when the geological environment and the hydrological environment do not meet the standards.
6. The railway engineering construction organization design dynamic management system according to claim 4 is characterized in that: The construction environment factor information collection component also includes a meteorological environment factor collection module, which is used to collect meteorological monitoring data of the construction site of the railway engineering project according to a third set time interval; The early warning processor is also used to perform weather broadcasts and weather early warnings during the construction process according to the weather monitoring data.
7. The railway engineering construction organization design dynamic management system according to claim 3 is characterized in that: The system imports the railway engineering project into the terminal, the construction process compilation subsystem, the construction process planning and review terminal, the cloud server, the project construction terminal and the project supervision terminal as nodes to build a blockchain network, and packages the railway engineering main body information, the construction unit information, the supplier information, the construction demand information, the guiding construction organization plan and the implementation construction organization plan into the blockchain for storage.
8. The railway engineering construction organization design dynamic management system according to claim 3 is characterized in that: The execution steps of the construction organization network diagram algorithm include: Decomposing the railway project into multiple sub-projects, and calculating the construction time parameters of each sub-project according to preset standards, wherein the construction time parameters include the earliest start time, the earliest finish time, the latest start time and the latest finish time; The total time difference is calculated based on the latest start time and the earliest start time of each sub-project. The difference between the earliest start time of the latter and the earliest completion time of the former between adjacent sub-projects is taken as the free time difference of the former. The sub-project when the total time difference and the free time difference are both zero is the key work, and the line that runs through the entire construction of the railway project and is composed of the sub-projects corresponding to the key work in a sequential order is the key line; According to the key routes and based on the main information of the railway project, the construction unit information, the supplier information, the construction demand information, the construction organization period indicator library and the process logic relationship, the sub-projects except the key tasks are deployed into the construction process to compile a complete construction process planning plan.
9. The railway engineering construction organization design dynamic management system according to claim 3 is characterized in that: The railway project import terminal is also used to import risk construction project disposal requirements and legal construction disposal requirements; The construction organization algorithm module is used to store and execute a preset construction organization network diagram algorithm to prepare a construction process planning scheme based on the main information of the railway project, the construction unit information, the supplier information, the construction demand information, the construction organization period indicator library, the process logical relationship, the risk construction project disposal requirements and the legal construction disposal requirements.
10. The railway engineering construction organization design dynamic management system according to claim 1, characterized in that: The system also includes a cloud server; The cloud server includes: A data resource collection and management module, used for storing various versions of the guiding construction organization plan and the implementing construction organization plan for remote access; A planning scheme recovery module is used to recover the construction process planning scheme before the update, and the project designer applies for access to the recovered construction process planning scheme according to the construction demand; The user management operation module is used by the construction entity to manage the feasible construction organization plans stored in the cloud server and select the feasible construction organization plans that meet the construction needs.