Rail transit station area collaborative management method and system
By dividing the rail transit station area into central stations and satellite stations, and implementing resource allocation and data exchange, the problems of low operational efficiency and uneven resource allocation under the traditional model are solved, and scheduling efficiency and safe response capabilities are improved.
Patent Information
- Application Number
- CN202411187835.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2025-01-10
AI Technical Summary
Traditional rail transit operation models face problems such as overcrowding of stations, inefficient operation and uneven resource allocation in response to changing passenger demand and urban traffic pressures, especially in the difficulty of effectively serving passengers on urban edges or suburbs.
Adopting the coordinated management method of rail transit stations, the station is divided into central stations and satellite stations, resource allocation and management are performed through central stations, passenger flow is predicted and passenger flow is allocated, redundant communication front-end machines and real-time servers are set up to realize data collection and Switch, control the center site through the line center, and achieve seamless connection through 100M/1000M industrial Ethernet, for driving planning and video surveillance.
It greatly improves the efficiency of conveying dispatching orders, reduces the probability of dispatchers' omissions, improves operational efficiency, reduces management costs, and can more effectively deal with large-scale driving or safety issues.
Smart Images

Figure CN119294704A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of rail transit design optimization, and more specifically, relates to a rail transit station area collaborative management method and system. Background Art
[0002] With the rapid development of my country's economy and the acceleration of urbanization, urban rail transit has ushered in unprecedented development opportunities and has shown a good development trend. In the next few years, my country's urban rail transit will enter a new stage of network operation. In order to better meet the needs of urban rail transit construction, the number of operating lines continues to increase and the operating mileage is also increasing. Against this background, advanced network sharing facilities have gradually been put into use and have achieved remarkable results. However, the traditional rail transit operation mode faces a series of challenges in responding to the ever-changing passenger needs and urban traffic pressure. Overcrowding at some stations has led to safety hazards, poor passenger experience, and difficulty in evacuation in emergency situations. At the same time, some stations have low operating efficiency and uneven resource allocation, which cannot effectively serve passengers in different areas of the city, especially those on the edge of the city or in the suburbs.
[0003] Therefore, there is an urgent need for a technical solution that can improve the operating efficiency of urban rail transit and reduce management costs. Summary of the invention
[0004] In order to solve the above technical problems, the present invention proposes a rail transit station area collaborative management method, comprising:
[0005] The stations in the rail transit station area are divided into central stations and satellite stations, and each central station is used to manage and control one or more satellite stations;
[0006] The central site allocates and manages resources for one or more satellite sites, wherein the predicted passenger flow of each site is calculated, and the central site allocates passenger flow to each satellite site according to the predicted passenger flow.
[0007] Furthermore, the central site is provided with redundant communication front-end processors and redundant real-time servers to realize data collection and data exchange of one or more satellite sites belonging to the central site.
[0008] Furthermore, a line center is set up, and the central site is controlled by the line center.
[0009] Furthermore, the driving plan is compiled through the central site and the satellite sites are monitored by video.
[0010] Furthermore, the central site and the satellite site are seamlessly connected via 100M / 1000M industrial Ethernet.
[0011] The present invention also proposes a rail transit station area collaborative management system, comprising:
[0012] A site division module is used to divide the stations in the rail transit station area into central sites and satellite sites, and each central site is used to manage and control one or more satellite sites;
[0013] The resource allocation module is used to allocate and manage resources to one or more satellite sites through the central site, wherein the predicted passenger flow of each site is calculated, and the central site allocates passenger flow to each satellite site according to the predicted passenger flow.
[0014] Furthermore, the central site is provided with redundant communication front-end processors and redundant real-time servers to realize data collection and data exchange of one or more satellite sites belonging to the central site.
[0015] Furthermore, a line center is set up, and the central site is controlled by the line center.
[0016] Furthermore, the driving plan is compiled through the central site and the satellite sites are monitored by video.
[0017] Furthermore, the central site and the satellite site are seamlessly connected via 100M / 1000M industrial Ethernet.
[0018] Compared with the prior art, the above technical solution conceived by the present invention has the following beneficial effects:
[0019] In the traditional station operation mode, if there are 30 stations, the OCC dispatcher needs to command 30 stations at the same time. In the central station operation mode, the dispatcher of the entire line commands 10 central stations. In the central station operation mode, the Longgang Line dispatcher only needs to command 10 central stations, while in the traditional station operation mode, the dispatcher has to command 30 stations. The dispatcher's command range is reduced by two-thirds, which greatly improves the efficiency of the dispatching order, especially when large-scale driving or safety problems occur, which can effectively reduce the probability of dispatchers' omissions.
[0020] Under the group operation mode, the central dispatcher only needs to command 10 central stations, while under the traditional station operation mode, the dispatcher has to command 30 stations. The dispatcher's command range is reduced by two-thirds, which greatly improves the efficiency of conveying dispatch orders, especially when large-scale driving or safety problems occur, which can effectively reduce the probability of dispatchers' omissions. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 is a flow chart of the method of embodiment 1 of the present invention;
[0022] Figure 2 is a system structure diagram of Embodiment 2 of the present invention;
[0023] Figure 3 is a schematic diagram of an optimized integrated monitoring system according to Embodiment 5 of the present invention; DETAILED DESCRIPTION
[0024] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0025] The method provided by the present invention can be implemented in the following terminal environment, and the terminal may include one or more of the following components: a processor, a storage medium, and a display screen. The storage medium stores at least one instruction, and the instruction is loaded and executed by the processor to implement the method described in the following embodiment.
[0026] The processor may include one or more processing cores. The processor uses various interfaces and lines to connect various parts in the entire terminal, and executes various functions of the terminal and processes data by running or executing instructions, programs, code sets or instruction sets stored in the storage medium, and calling data stored in the storage medium.
[0027] The storage medium may include a random access memory (RAM) or a read-only memory (ROM). The storage medium may be used to store instructions, programs, codes, code sets or instructions.
[0028] The display is used to show the interactive cross-section of each application.
[0029] All subscripts in the formulas of the present invention are only used to distinguish parameters and have no actual meaning.
[0030] In addition, those skilled in the art can understand that the structure of the above terminal does not constitute a limitation on the terminal, and the terminal may include more or fewer components, or combine certain components, or arrange the components differently. For example, the terminal also includes components such as a radio frequency circuit, an input unit, a sensor, an audio circuit, and a power supply, which will not be described in detail here.
[0031] Example 1
[0032] like Figure 1 As shown, an embodiment of the present invention provides a rail transit station area collaborative management method, including:
[0033] Step 101, dividing the stations in the rail transit station area into central stations and satellite stations, each of the central stations is used to manage and control one or more satellite stations;
[0034] Step 102: Allocate and manage resources for one or more satellite sites through the central site, wherein the predicted passenger flow of each site is calculated, and the central site allocates passenger flow to each satellite site according to the predicted passenger flow.
[0035] Specifically, the central site is provided with redundant communication front-end processors and redundant real-time servers to realize data collection and data exchange of one or more satellite sites belonging to the central site.
[0036] Specifically, a line center is set up, and the central site is controlled by the line center.
[0037] Specifically, the driving plan is compiled through the central site and the satellite sites are monitored by video.
[0038] Specifically, the central site and the satellite site are seamlessly connected via 100M / 1000M industrial Ethernet.
[0039] Specifically, calculating the predicted passenger flow of each station includes the following steps:
[0040] Carry out passenger flow prediction for all stations and obtain the predicted passenger flow for each station, specifically:
[0041]
[0042] Among them, P i,t is the predicted passenger flow of the ith station in period t, α i is the first passenger flow adjustment factor of the i-th station, β i is the second passenger flow adjustment factor of the ith station, γ i is the third passenger flow adjustment factor of the ith station, H i,t-1 is the historical passenger flow of the ith station in period t-1, θ i is the passenger flow cycle amplitude coefficient of the i-th station, ω i is the passenger flow cycle angular frequency parameter of the i-th station, δ i is the fourth passenger flow adjustment factor of the ith station, i is the total passenger flow of the ith station, η i is the fifth passenger flow adjustment factor of the ith station, E t Indicates whether a special event occurs during period t. If so, then E t is 1, otherwise it is 0, φ i is the sixth passenger flow adjustment factor of the ith station, is the set of neighboring sites of the ith site, P j,t is the passenger flow of the jth adjacent satellite site in period t, μ j is the historical average passenger flow of the jth adjacent satellite site.
[0043] According to the predicted passenger flow, a passenger flow distribution model is set, specifically including:
[0044]
[0045] Among them, d i,j To distribute the passenger flow from the i-th station to the j-th adjacent satellite station, x i,j is the number of satellite sites that distribute the passenger flow of the i-th site to the j-th adjacent site, λ j is the over-capacity penalty coefficient of the jth adjacent satellite site, C j is the upper limit of the capacity of the jth adjacent satellite site.
[0046] The conditions for setting the passenger flow distribution model specifically include:
[0047]
[0048] x i,j ≥0 and is an integer,
[0049] Among them, ρ i is the maximum diversion ratio of the i-th site, R j (t) is the capacity reserve of the jth adjacent satellite station in period t, L(t) is the total capacity upper limit of the entire station in period t, for all sites i and all adjacent satellite sites j.
[0050] Example 2
[0051] like Figure 2 As shown, the embodiment of the present invention further proposes a rail transit station area collaborative management system, including:
[0052] A site division module is used to divide the stations in the rail transit station area into central sites and satellite sites, and each central site is used to manage and control one or more satellite sites;
[0053] The resource allocation module is used to allocate and manage resources to one or more satellite sites through the central site, wherein the predicted passenger flow of each site is calculated, and the central site allocates passenger flow to each satellite site according to the predicted passenger flow.
[0054] Specifically, the central site is provided with redundant communication front-end processors and redundant real-time servers to realize data collection and data exchange of one or more satellite sites belonging to the central site.
[0055] Specifically, a line center is set up, and the central site is controlled by the line center.
[0056] Specifically, the driving plan is compiled through the central site and the satellite sites are monitored by video.
[0057] Specifically, the central site and the satellite site are seamlessly connected via 100M / 1000M industrial Ethernet.
[0058] Example 3
[0059] An embodiment of the present invention further proposes a storage medium storing a plurality of instructions, wherein the instructions are used to implement the method for collaborative management of rail transit stations.
[0060] Optionally, in this embodiment, the above storage medium may be located in any computer terminal in a computer terminal group in a computer network, or in any mobile terminal in a mobile terminal group.
[0061] Optionally, in this embodiment, the storage medium is configured to store program codes for executing the following steps: Step 101, dividing the stations in the rail transit station area into central stations and satellite stations, each of the central stations being used to manage and control one or more satellite stations belonging to it;
[0062] Step 102: Allocate and manage resources for one or more satellite sites through the central site, wherein the predicted passenger flow of each site is calculated, and the central site allocates passenger flow to each satellite site according to the predicted passenger flow.
[0063] Specifically, the central site is provided with redundant communication front-end processors and redundant real-time servers to realize data collection and data exchange of one or more satellite sites belonging to the central site.
[0064] Specifically, a line center is set up, and the central site is controlled by the line center.
[0065] Specifically, the driving plan is compiled through the central site and the satellite sites are monitored by video.
[0066] Specifically, the central site and the satellite site are seamlessly connected via 100M / 1000M industrial Ethernet.
[0067] Specifically, calculating the predicted passenger flow of each station includes the following steps:
[0068] Carry out passenger flow prediction for all stations and obtain the predicted passenger flow for each station, specifically:
[0069]
[0070] Among them, Pi,t is the predicted passenger flow of the ith station in period t, α i is the first passenger flow adjustment factor of the i-th station, β i is the second passenger flow adjustment factor of the ith station, γ i is the third passenger flow adjustment factor of the ith station, H i,t-1 is the historical passenger flow of the ith station in period t-1, θ i is the passenger flow cycle amplitude coefficient of the i-th station, ω i is the passenger flow cycle angular frequency parameter of the i-th station, δ i is the fourth passenger flow adjustment factor of the ith station, D i is the total passenger flow of the ith station, η i is the fifth passenger flow adjustment factor of the ith station, E t Indicates whether a special event occurs during period t. If so, then E t is 1, otherwise it is 0, φ i is the sixth passenger flow adjustment factor of the ith station, is the set of neighboring sites of the ith site, P j,t is the passenger flow of the jth adjacent satellite site in period t, μ j is the historical average passenger flow of the jth adjacent satellite site.
[0071] According to the predicted passenger flow, a passenger flow distribution model is set, specifically including:
[0072]
[0073] Among them, d i,j To distribute the passenger flow from the i-th station to the j-th adjacent satellite station, x i,j is the number of satellite sites that distribute the passenger flow of the i-th site to the j-th adjacent site, λ j is the over-capacity penalty coefficient of the jth adjacent satellite site, C j is the upper limit of the capacity of the jth adjacent satellite site.
[0074] The conditions for setting the passenger flow distribution model specifically include:
[0075]
[0076] tj is 0 and an integer,
[0077] Among them, ρ i is the maximum diversion ratio of the i-th site, R j(t) is the capacity reserve of the jth adjacent satellite station in period t, L(t) is the total capacity upper limit of the entire station in period t, for all sites i and all adjacent satellite sites j.
[0078] Example 4
[0079] An embodiment of the present invention also proposes an electronic device, including a processor and a storage medium connected to the processor, wherein the storage medium stores a plurality of instructions, and the instructions can be loaded and executed by the processor so that the processor can execute a method for collaborative management of rail transit stations.
[0080] Specifically, the electronic device of this embodiment may be a computer terminal, and the computer terminal may include: one or more processors, and a storage medium.
[0081] Among them, the storage medium can be used to store software programs and modules, such as a rail transit station area collaborative management method in an embodiment of the present invention, and the corresponding program instructions / modules. The processor executes various functional applications and data processing by running the software programs and modules stored in the storage medium, that is, realizing the above-mentioned rail transit station area collaborative management method. The storage medium may include high-speed random storage media, and may also include non-volatile storage media, such as one or more magnetic storage systems, flash memory, or other non-volatile solid-state storage media. In some instances, the storage medium may further include storage media remotely arranged relative to the processor, and these remote storage media may be connected to the terminal via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, corporate intranets, local area networks, mobile communication networks, and combinations thereof.
[0082] The processor may call the information and application program stored in the storage medium through the transmission system to execute the steps: Step 101, dividing the stations in the rail transit station area into central stations and satellite stations, each of the central stations being used to manage and control one or more satellite stations;
[0083] Step 102: Allocate and manage resources for one or more satellite sites through the central site, wherein the predicted passenger flow of each site is calculated, and the central site allocates passenger flow to each satellite site according to the predicted passenger flow.
[0084] Specifically, the central site is provided with redundant communication front-end processors and redundant real-time servers to realize data collection and data exchange of one or more satellite sites belonging to the central site.
[0085] Specifically, a line center is set up, and the central site is controlled by the line center.
[0086] Specifically, the driving plan is compiled through the central site and the satellite sites are monitored by video.
[0087] Specifically, the central site and the satellite site are seamlessly connected via 100M / 1000M industrial Ethernet.
[0088] Specifically, calculating the predicted passenger flow of each station includes the following steps:
[0089] Carry out passenger flow prediction for all stations and obtain the predicted passenger flow for each station, specifically:
[0090]
[0091] Among them, P i,t is the predicted passenger flow of the ith station in period t, α i is the first passenger flow adjustment factor of the i-th station, β i is the second passenger flow adjustment factor of the ith station, γ i is the third passenger flow adjustment factor of the ith station, H i,t-1 is the historical passenger flow of the ith station in period t-1, θ i is the passenger flow cycle amplitude coefficient of the i-th station, ω i is the passenger flow cycle angular frequency parameter of the i-th station, δ i is the fourth passenger flow adjustment factor of the ith station, D i is the total passenger flow of the ith station, η i is the fifth passenger flow adjustment factor of the ith station, E t Indicates whether a special event occurs during period t. If so, then E t is 1, otherwise it is 0, φ i is the sixth passenger flow adjustment factor of the ith station, is the set of neighboring sites of the ith site, P j,t is the passenger flow of the jth adjacent satellite site in period t, μ j is the historical average passenger flow of the jth adjacent satellite site.
[0092] According to the predicted passenger flow, a passenger flow distribution model is set, specifically including:
[0093]
[0094] Among them, d i,j To distribute the passenger flow from the i-th station to the j-th adjacent satellite station, x i,j is the number of satellite sites that distribute the passenger flow of the i-th site to the j-th adjacent site, λ j is the over-capacity penalty coefficient of the jth adjacent satellite site, Cj is the upper limit of the capacity of the jth adjacent satellite site.
[0095] The conditions for setting the passenger flow distribution model specifically include:
[0096]
[0097] x i,j ≥0 and is an integer,
[0098] Among them, ρ i is the maximum diversion ratio of the i-th site, R j (t) is the capacity reserve of the jth adjacent satellite station in period t, L(t) is the total capacity upper limit of the entire station in period t, for all sites i and all adjacent satellite sites j.
[0099] Example 5
[0100] (1) Optimization of station business management processes
[0101] Specifically, the new operation mode will select some stations on the entire line as "central stations" and other stations as "satellite stations". Under normal circumstances, the line center only controls the central station, and the central station is responsible for controlling the satellite stations; in emergency situations, the line center directly controls all stations.
[0102] The original station services of each station, including customer service, equipment control, and switch stations, were uniformly adjusted to the central station's "centralized customer service in the station area", "centralized equipment control", and "unified switch station". The central station is also responsible for the emergency response coordination of the satellite stations under its jurisdiction, and the satellite stations handle emergencies under the coordination of the central station (while retaining the ability to communicate with the line center dispatch for emergency response). On the one hand, the line center dispatch has adjusted the daily jurisdiction of all stations to only the central station, and at the same time has added the functions of central station management, satellite station management, and station area operation coordination.
[0103] (2) Optimization of equipment and facility matching mode
[0104] 1) Function matching mode
[0105] A.Central Function
[0106] The center adds comprehensive decision-making functions to the traditional equipment functions, realizing intensive management of multiple lines and network management of equipment, and realizing the people-oriented and network-intensive subway network; two-level management and control, integration of sectors and blocks; central overall control, on-site comprehensive management; integration of peacetime and wartime, efficient and resilient intelligent operation. It includes network operation monitoring, parallel scenario simulation, system situation analysis, comprehensive decision optimization, emergency consultation and command, and other functions.
[0107] B. Station Function
[0108] The central station smart passenger transport control platform is a control over the intelligent application of passenger transport, and needs to realize functions such as smart cockpit, station area collaborative management, passenger flow monitoring and prediction, driving plan preparation, video surveillance intelligent analysis, centralized equipment control, and intelligent customer service.
[0109] 2) Single system matching mode
[0110] A. Comprehensive monitoring system, such as Figure 3 As shown:
[0111] a. Central level
[0112] The central level is used to monitor the operating status of each station subsystem along the entire line. At the central level, a redundant real-time server is set up as the information center of the entire line to collect information from each station and support the supervision function of each dispatcher workstation; a redundant communication front-end is set up for real-time data collection, and the data exchange between each subsystem is completed in the communication front-end through various general protocols; a historical data server is set up to store and manage the historical data of the system to reduce the burden on the real-time server; an electric dispatch workstation is set up to realize power monitoring of the entire line; and an environmental dispatch workstation is set up to realize environmental and equipment monitoring of the entire line.
[0113] b. Central Station
[0114] The central station is used to monitor the operating status of each station subsystem in the group. In the central station AIS, redundant communication front-ends and redundant real-time servers are set up to realize data collection and data exchange of each station in the group, and support the supervision function of each operation workstation; duty stationmaster workstations and maintenance workstations are set up to allow administrators to query system information and perform maintenance operations on the system.
[0115] c. Satellite station
[0116] The satellite station is used to monitor the operating status of each subsystem of the station. In the satellite station, a redundant communication front-end is set up to collect data. The data exchange between the subsystems of the station is completed in the communication front-end through various general protocols. A duty workstation is set up to allow the administrator to query system information and perform maintenance operations on the system. The satellite station is seamlessly connected with the central station and the central level through 100M / 1000M industrial Ethernet.
[0117] C. Other equipment and facilities
[0118] The monitoring of conventional equipment in traditional subway stations is based on natural stations. The independent monitoring system does not have the function of cross-station monitoring, while the central station systems have added the function of cross-station monitoring. The monitoring management mode is shown in the following table:
[0119]
[0120]
[0121] The serial numbers of the above embodiments of the present invention are only for description and do not represent the advantages or disadvantages of the embodiments.
[0122] In the above embodiments of the present invention, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0123] In the several embodiments provided by the present invention, it should be understood that the disclosed technical content can be implemented in other ways. Among them, the system embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of units or modules, which can be electrical or other forms.
[0124] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0125] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0126] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for a computer device (which can be a personal computer, a server or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, read-only storage medium (ROM, Read-Only Memory), random access storage medium (RAM, Random Access Memory), mobile hard disk, magnetic disk or optical disk and other media that can store program codes.
[0127] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention.
Claims
1. A rail transit station area collaborative management method, characterized in that: include: The stations in the rail transit station area are divided into central stations and satellite stations, and each central station is used to manage and control one or more satellite stations; The central site allocates and manages resources for one or more satellite sites, wherein the predicted passenger flow of each site is calculated, and the central site allocates passenger flow to each satellite site according to the predicted passenger flow.
2. A rail transit station area collaborative management method as claimed in claim 1, characterized in that: The central site is provided with redundant communication front-end processors and redundant real-time servers to realize data collection and data exchange of one or more satellite sites belonging to the central site.
3. A rail transit station area collaborative management method as claimed in claim 1, characterized in that: A line center is set up, and the central site is controlled by the line center.
4. A rail transit station area collaborative management method as claimed in claim 1, characterized in that: The driving plan is compiled through the central site and the satellite sites are monitored by video.
5. A rail transit station area collaborative management method as claimed in claim 1, characterized in that: The central site and the satellite site are seamlessly connected via 100M / 1000M industrial Ethernet.
6. A rail transit station area collaborative management system, characterized in that: include: A site division module is used to divide the stations in the rail transit station area into central sites and satellite sites, and each central site is used to manage and control one or more satellite sites; The resource allocation module is used to allocate and manage resources to one or more satellite sites through the central site, wherein the predicted passenger flow of each site is calculated, and the central site allocates passenger flow to each satellite site according to the predicted passenger flow.
7. A rail transit station area collaborative management system as claimed in claim 6, characterized in that: The central site is provided with redundant communication front-end processors and redundant real-time servers to realize data collection and data exchange of one or more satellite sites belonging to the central site.
8. A rail transit station area collaborative management system as claimed in claim 6, characterized in that: A line center is set up, and the central site is controlled by the line center.
9. A rail transit station area collaborative management system as claimed in claim 6, characterized in that: The driving plan is compiled through the central site and the satellite sites are monitored by video.
10. A rail transit station area collaborative management system as claimed in claim 6, characterized in that: The central site and the satellite site are seamlessly connected via 100M / 1000M industrial Ethernet.
Citation Information
Cited By
Rail transit station area collaborative management method and system based on Beidou positioning
CN120562784A