Traditional transformer monitoring systems have problems with low detection efficiency, resulting in delayed fault handling or unnecessary power outages, increasing operation and maintenance costs and possibly missing the best fault handling opportunity.
A equipment processing system is designed, including equipment detection system, fault processing system, production monitoring system and scheduling command platform. Through collaborative operation and acquisition of the operating status of the transformer, a patrol plan and adjustment plan are generated, fault processing is automatically handled, and fault processing efficiency is improved.
It realizes timely and accurate detection and handling of transformer failures, improves the processing efficiency of electrical equipment, reduces labor costs, and reduces misjudgment and resource waste.
Smart Images

Figure CN119298357A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of equipment detection or other related fields, and in particular, to a processing system and method for an equipment. Background Art
[0002] With the rapid development of the power system and the continuous expansion of the power grid, the transformer, as the core equipment of the power system, is of great importance to the safe and stable operation of the entire power system. The failure of the transformer will not only lead to power supply interruption, but also may cause significant economic losses and social impact. Therefore, real-time monitoring and fault diagnosis of the transformer become particularly important. In order to ensure the safe and stable operation of the transformer and provide timely and accurate fault warning and diagnosis information for operation and maintenance personnel, substations with voltage levels above 220kV are generally equipped with online monitoring systems to monitor the operating status of the transformer in real time.
[0003] However, traditional transformer monitoring has multiple problems: when the online monitoring system finds that the transformer is abnormal, manual judgment is required to determine whether a power outage is required. For defects that require power outage, the operation and maintenance personnel need to apply to the dispatcher for a power outage. After receiving the power outage application, the dispatcher instructs the operation and maintenance personnel to carry out the power outage operation. That is, once the online monitoring system detects that the transformer is operating abnormally, the operation and maintenance personnel are required to make manual judgments. This process is time-consuming and may delay the best time for fault handling, which not only increases the workload of the operation and maintenance personnel, but also increases labor costs. At the same time, manual judgment may be affected by subjective factors, resulting in misjudgment, which may miss the best time for fault handling, or unnecessary power outages may cause waste of resources. In addition, due to the lack of an effective data sharing and integration mechanism, information communication between different operation and maintenance personnel and dispatchers may be delayed or inaccurate, affecting the efficiency and accuracy of fault handling.
[0004] With regard to the problem of low detection efficiency when monitoring electrical equipment in related technologies, no effective solution has been proposed so far. Summary of the invention
[0005] The main purpose of the present application is to provide a device processing system and method to solve the problem of low detection efficiency when monitoring electrical equipment in the related art.
[0006] In order to achieve the above-mentioned purpose, according to one aspect of the present application, a device processing system is provided. The system includes: an equipment detection system, which is used to collect the equipment operation status of the transformer equipment and send the equipment operation status to the fault processing system, wherein the equipment operation status at least includes the partial discharge, temperature, oil chromatogram and gas content of the transformer equipment; the fault processing system includes an inference engine, which is used to generate an equipment inspection plan according to the equipment operation status when receiving the equipment operation status sent by the equipment detection system, send the equipment inspection plan to the production monitoring system, and receive the equipment inspection result returned by the production monitoring system according to the equipment inspection plan, and when the equipment inspection result indicates that the transformer equipment is in the first abnormal state, generate an equipment adjustment plan according to the equipment inspection result, and send the equipment adjustment plan to the dispatching command platform, wherein the equipment inspection result is obtained after the production monitoring system performs an inspection operation on the transformer equipment, and the dispatching command platform is used to process the transformer equipment according to the equipment adjustment plan.
[0007] Furthermore, the dispatching and commanding platform is communicatively connected to the fault handling system through the forward and reverse isolation devices, and is used to generate processing instructions according to the equipment adjustment plan when receiving the equipment adjustment plan, and send the processing instructions to the equipment operating system.
[0008] Furthermore, the equipment operating system includes a Baoxin main station, which is connected to the dispatching and commanding platform through a firewall device. The Baoxin main station is used to extract a first sub-processing instruction from the processing instruction, and perform equipment adjustment processing on the transformer equipment according to the first sub-processing instruction, wherein the equipment adjustment processing at least includes fixed value modification, fixed value zone switching, and soft pressure plate insertion and withdrawal.
[0009] Furthermore, the equipment operating system also includes a dispatching system, which is communicatively connected to the dispatching command platform via a firewall device. The dispatching system is used to extract a second sub-processing instruction from the processing instruction, and control the remote motor to perform equipment operation on the transformer equipment according to the second sub-processing instruction, wherein the equipment operation at least includes opening and closing the knife switch operation.
[0010] Furthermore, the fault handling system is associated with the office system through the firewall device. After sending the equipment adjustment plan to the dispatching and command platform, the fault handling system generates an operation abnormality report based on the equipment inspection results, and sends the operation abnormality report to the office system. The office system is used to forward the operation abnormality report to the client used by the management personnel when receiving the operation abnormality report.
[0011] Furthermore, the production monitoring system is associated with a monitoring and patrol device, and the production monitoring system sends a patrol instruction to the monitoring and patrol device according to the equipment patrol plan, wherein the monitoring and patrol device performs a patrol operation on the transformer equipment when receiving the patrol instruction, and generates an equipment patrol result.
[0012] Furthermore, when the equipment inspection result indicates that the transformer equipment is in the second abnormal state, the equipment inspection result is sent to the dispatching command platform.
[0013] Furthermore, controlling the remote motor to perform equipment operations on the transformer equipment according to the second sub-processing instruction includes: obtaining an electrical wiring architecture diagram of the transformer equipment, identifying M switches and N circuit breakers from the electrical wiring architecture diagram, where M and N are positive integers; obtaining an operation list, and adjusting each switch and each circuit breaker in turn according to the operation list.
[0014] In order to achieve the above-mentioned purpose, according to another aspect of the present application, a method for processing equipment is provided. The method comprises: obtaining the equipment operation status of the transformer equipment, determining the equipment inspection plan according to the equipment operation status, and sending the equipment inspection plan to the production monitoring system, wherein the production monitoring system is used to perform inspection operations on the transformer equipment according to the equipment inspection plan and generate equipment inspection results; when receiving the equipment inspection results sent by the production monitoring system, generating an equipment adjustment plan according to the equipment inspection results, and sending the equipment adjustment plan to the dispatching command platform.
[0015] Furthermore, upon receiving the equipment adjustment plan, the dispatching command platform generates a processing instruction according to the equipment adjustment plan, and sends the processing instruction to the equipment operating system, wherein the equipment operating system adjusts the transformer equipment according to the processing instruction.
[0016] Through the present application, the following steps are adopted: an equipment detection system is used to collect the equipment operation status of the transformer equipment and send the equipment operation status to the fault processing system, wherein the equipment operation status at least includes the partial discharge, temperature, oil chromatography and gas content of the transformer equipment; the fault processing system includes an inference engine, which is used to generate an equipment inspection plan according to the equipment operation status when receiving the equipment operation status sent by the equipment detection system, send the equipment inspection plan to the production monitoring system, and receive the equipment inspection result returned by the production monitoring system according to the equipment inspection plan. When the equipment inspection result indicates that the transformer equipment is in a first abnormal state, an equipment adjustment plan is generated according to the equipment inspection result, and the equipment adjustment plan is sent to the dispatching command platform, wherein the equipment inspection result is obtained after the production monitoring system performs an inspection operation on the transformer equipment, and the dispatching command platform is used to process the transformer equipment according to the equipment adjustment plan, which solves the problem of low detection efficiency when monitoring electrical equipment in the related technology, and performs fault processing on the electrical equipment by using the equipment detection system and the fault processing system for collaborative operation, thereby improving the processing efficiency of the electrical equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The drawings constituting a part of the present application are used to provide a further understanding of the present application. The illustrative embodiments and descriptions of the present application are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0018] Figure 1 is a schematic diagram of a processing system of a device provided according to an embodiment of the present application;
[0019] Figure 2 is a wiring diagram of an electrical device provided according to an embodiment of the present application;
[0020] Figure 3 is a flowchart of a processing method of a device provided in an embodiment of the present application;
[0021] Figure 4 is a schematic diagram of a processing system of an optional device provided according to an embodiment of the present application;
[0022] Figure 5 is a schematic diagram of an optional device processing method provided according to an embodiment of the present application;
[0023] Figure 6 is a schematic diagram of a processing device of a device provided according to an embodiment of the present application;
[0024] Figure 7 is a schematic diagram of an electronic device provided according to an embodiment of the present application. DETAILED DESCRIPTION
[0025] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0026] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.
[0027] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0028] It should be noted that the relevant information (including but not limited to user device information, user personal information, etc.) and data (including but not limited to data for display, data for analysis, etc.) involved in this disclosure are all information and data authorized by the user or fully authorized by all parties. For example, an interface is set between this system and the relevant user or organization. Before obtaining relevant information, it is necessary to send an acquisition request to the aforementioned user or organization through the interface, and obtain relevant information after receiving the consent information fed back by the aforementioned user or organization.
[0029] It should be noted that the collected information used in this application is information and data authorized by the user or fully authorized by all parties, and the collection, storage, use, processing, transmission, provision, disclosure and application of the relevant data comply with the relevant laws, regulations and standards of the relevant regions, take necessary confidentiality measures, do not violate public order and good morals, and provide corresponding operation entrances for users to choose to authorize or refuse to use it.
[0030] The present invention is described below in conjunction with preferred implementation steps. Figure 1 is a schematic diagram of a processing system of a device provided in an embodiment of the present application, such as Figure 1 As shown, the system includes:
[0031] The equipment detection system 101 is used to collect the equipment operation status of the transformer equipment and send the equipment operation status to the fault processing system 102, wherein the equipment operation status at least includes partial discharge, temperature, oil chromatography and gas content of the transformer equipment.
[0032] Specifically, the equipment detection system 101 is deployed in the area for implementing the collection of transformer equipment, and can detect in real time the partial discharge of the transformer equipment, the equipment temperature, the equipment oil chromatography, the gas content in the transformer equipment and other information, and then obtain the equipment operation status of the transformer equipment. In order to help the operation and maintenance personnel to know the fault situation in time, it can be connected with the fault handling system 102 through the firewall communication, and then the collected equipment operation status can be sent to the fault handling system 102 in time.
[0033] The fault handling system 102 includes an inference engine, which is used to generate an equipment inspection plan according to the equipment operation status when receiving the equipment operation status sent by the equipment detection system 101, send the equipment inspection plan to the production monitoring system, and receive the equipment inspection results returned by the production monitoring system according to the equipment inspection plan. When the equipment inspection results indicate that the transformer equipment is in a first abnormal state, an equipment adjustment plan is generated according to the equipment inspection results, and the equipment adjustment plan is sent to the dispatching and commanding platform, wherein the equipment inspection results are obtained after the production monitoring system performs an inspection operation on the transformer equipment, and the dispatching and commanding platform is used to process the transformer equipment according to the equipment adjustment plan.
[0034] Specifically, the fault handling system 102 can be a virtual device used to perform plan inference based on the equipment operating status. The fault handling system 102 can include an inference engine. When receiving the above-mentioned equipment operating status, the inference engine can generate an equipment patrol plan based on the abnormal alarm, and then send the generated equipment patrol plan to the production monitoring system, and the production monitoring system will implement the patrol operation.
[0035] Furthermore, after the production monitoring system completes the equipment inspection operation, it can generate equipment inspection results. At this time, the fault handling system 102 can receive the equipment inspection results sent by the production monitoring system, and after analyzing the equipment inspection results, it determines whether the abnormal condition of the transformer equipment is more serious and whether it is necessary to perform maintenance strategies such as power outage on the transformer equipment. When the transformer equipment failure is more serious, an equipment adjustment plan can be generated based on the equipment inspection results, such as an adjustment plan for powering off the transformer equipment, and the equipment adjustment plan can be sent to the dispatching and command platform, which then performs programmed operations on the equipment based on the equipment adjustment plan.
[0036] The equipment processing system provided in the embodiment of the present application is used to collect the equipment operation status of the transformer equipment through the equipment detection system 101, and send the equipment operation status to the fault processing system 102, wherein the equipment operation status at least includes the partial discharge, temperature, oil chromatography and gas content of the transformer equipment; the fault processing system 102 includes an inference engine, which is used to generate an equipment inspection plan according to the equipment operation status when receiving the equipment operation status sent by the equipment detection system 101, send the equipment inspection plan to the production monitoring system, and receive the equipment inspection result returned by the production monitoring system according to the equipment inspection plan. When the equipment inspection result indicates that the transformer equipment is in the first abnormal state, an equipment adjustment plan is generated according to the equipment inspection result, and the equipment adjustment plan is sent to the dispatching command platform, wherein the equipment inspection result is obtained after the production monitoring system performs an inspection operation on the transformer equipment, and the dispatching command platform is used to process the transformer equipment according to the equipment adjustment plan, which solves the problem of low detection efficiency when monitoring electrical equipment in the related art, and performs fault processing on the electrical equipment by using the equipment detection system 101 and the fault processing system 102 for collaborative operation, thereby improving the processing efficiency of the electrical equipment.
[0037] Optionally, in the processing system of the equipment provided in the embodiment of the present application, the dispatching and command platform is communicatively connected to the fault handling system 102 through a forward and reverse isolation device, and is used to generate processing instructions according to the equipment adjustment plan when receiving the equipment adjustment plan, and send the processing instructions to the equipment operating system.
[0038] Specifically, the dispatching and commanding platform can be a DICP (Dynamic Internet Content Provider) system, which can be connected to the fault handling system 102 through an isolation device. Since the transformer equipment can include primary equipment and secondary equipment, the primary equipment can refer to the electrical equipment that directly participates in the production, transmission, and distribution of electric energy. The equipment can constitute the main body of the power system and can include main transformers, circuit breakers, disconnectors, busbars, lightning arresters, current transformers, etc.; secondary equipment can refer to electrical equipment that monitors, controls, adjusts, and protects the operation of primary equipment. For example, secondary equipment can include protection equipment, safety equipment, etc. The processing methods of the above-mentioned different equipment can be different, so the dispatching and commanding platform can generate different types of processing instructions according to the equipment adjustment plan, and then package these processing instructions and send them to the equipment operating system.
[0039] There may be multiple ways to process transformer equipment. Optionally, in the processing system of the equipment provided in the embodiment of the present application, the equipment operating system includes a security control main station, which is communicated with the dispatching and commanding platform through a firewall device. The security control main station is used to extract the first sub-processing instruction from the processing instruction, and perform equipment adjustment processing on the transformer equipment according to the first sub-processing instruction, wherein the equipment adjustment processing includes at least fixed value modification, fixed value zone switching, and soft pressure plate insertion and withdrawal.
[0040] Specifically, since the transformer equipment can include two types of primary equipment and secondary equipment, the processing of different types of equipment can be performed using different device operating systems. When processing the secondary equipment, the security master station in the device operating system can receive the processing instruction, and then extract the first sub-processing instruction for instructing the processing of the secondary equipment from the processing instruction, and then adjust the parameters of the transformer equipment according to the first sub-processing instruction.
[0041] It should be noted that the parameter adjustment of the equipment can be achieved based on different devices in the Baoxin master station. For example, the Baoxin master station can be associated with intelligent recorders, control substations and remote motors. These devices can collect the equipment parameters of secondary equipment and then send the equipment parameters to the Baoxin master station, which will perform data analysis.
[0042] Optionally, in the processing system of the device provided in the embodiment of the present application, the device operating system also includes a scheduling system, which is communicated with the scheduling command platform through a firewall device, and the scheduling system is used to extract a second sub-processing instruction from the processing instruction, and control the remote motor to perform equipment operation on the transformer equipment according to the second sub-processing instruction, wherein the equipment operation at least includes opening the knife switch operation and closing the knife switch operation.
[0043] Specifically, the dispatching system can be an OCS (Open Compute System) system, which is communicated with the dispatching command platform through a firewall device. In addition to performing equipment processing on secondary equipment, the dispatching device in the equipment operating system can also be used to adjust the primary equipment. At this time, the dispatching system needs to extract the second sub-processing instruction used to characterize the processing of the primary equipment from the processing instruction, and then implement the adjustment operation of components such as knife switches in the primary equipment through the remote motor associated with the system.
[0044] Optionally, in the processing system of the device provided in the embodiment of the present application, the fault handling system 102 is associated with the office system through the firewall device. After sending the equipment adjustment plan to the dispatching and command platform, the fault handling system 102 generates an operation abnormality report based on the equipment inspection results, and sends the operation abnormality report to the office system, wherein the office system is used to forward the operation abnormality report to the client used by the management personnel when receiving the operation abnormality report.
[0045] Specifically, in order to help managers view equipment inspection results in a timely manner, the fault handling system 102 can generate an operation abnormality report based on the equipment inspection results, and send the operation abnormality report to the office system, which then sends the above operation abnormality report to relevant personnel in the form of a document.
[0046] Optionally, in the processing system of the equipment provided in the embodiment of the present application, the production monitoring system is associated with a monitoring and patrol device, and the production monitoring system sends a patrol instruction to the monitoring and patrol device according to the equipment patrol plan, wherein the monitoring and patrol device, upon receiving the patrol instruction, performs a patrol operation on the transformer equipment and generates an equipment patrol result.
[0047] Specifically, the inspection of a primary equipment can be processed using monitoring and inspection equipment. For example, the production monitoring system can send inspection instructions to the monitoring and inspection equipment, and then control drones, smart cameras and inspection robots to conduct inspection operations on the transformer equipment. The production monitoring system then receives and processes the inspection photos and results sent back by the inspection, archives them, and generates equipment inspection results.
[0048] Optionally, in the processing system of the device provided in the embodiment of the present application, when the equipment inspection result indicates that the transformer equipment is in the second abnormal state, the equipment inspection result is sent to the dispatching command platform.
[0049] Specifically, when the transformer equipment indicates a defect that requires a power outage to be handled, that is, when the transformer equipment is in the second abnormal state, the equipment inspection results can be sent to the dispatching command platform, and then corresponding power outage operations can be performed based on the inspection results.
[0050] Optionally, in the processing system of the device provided in the embodiment of the present application, controlling the remote motor to perform equipment operations on the transformer device according to the second sub-processing instruction includes: obtaining an electrical wiring architecture diagram of the transformer device, identifying M switches and N knife switches from the electrical wiring architecture diagram, where M and N are positive integers; obtaining an operation list, and adjusting each switch and each knife switch in turn according to the operation list.
[0051] Specifically, when the remote motor in the dispatching system performs equipment operation on the primary equipment, for example, when the second sub-processing instruction is an instruction to convert the transformer equipment "220kV example station #1 main transformer" from the running state to the cold standby state, the electrical wiring diagram of the transformer equipment can be first obtained, and multiple transformer switches and circuit breakers can be determined therefrom, and then the switch operations on these switches and circuit breakers can be performed according to the operation list, for example, Figure 2 is a wiring diagram of an electrical device provided according to an embodiment of the present application, such as Figure 2 As shown, the operation steps can be as follows:
[0052] Operation step 1: Remotely disconnect the 1101 switch in the 110kV transformer of the 220kV#1 main transformer of the example station in the OCS system;
[0053] Operation step 2: Close the 10kV#1 section 5012 switch of the example station remotely in the OCS system;
[0054] Operation step 3: Remotely disconnect the 10kV lower 5501 switch of the 220kV#1 main transformer of the example station in the OCS system;
[0055] Operation step 4: Remotely disconnect the 52QB switch of the 10kV#1 grounding transformer of the example station in the OCS system;
[0056] Operation step 5: Remotely disconnect the 220kV #1 main transformer high-voltage 2201 switch of the example station in the OCS system;
[0057] Operation step 6: Remotely open the 220kV #1 main transformer 22014 switch of the example station in the OCS system;
[0058] Operation step 7: Remotely open the 220kV #1 main transformer 22011 switch of the example station in the OCS system;
[0059] Operation step 8: Remotely open the 11014 switch in the 220kV#1 main transformer of the example station in the OCS system;
[0060] Operation step 9: Remotely open the 11011 switch in the 220kV#1 main transformer of the example station in the OCS system;
[0061] Operation step 10: Remotely open the 5501 trolley of the 220kV#1 main transformer in the example station through the OCS system;
[0062] Operation step 11: Remotely pull open the 52QB trolley of the 10kV#1 grounding transformer in the example station through the OCS system;
[0063] Operation step 12: Remotely exit the example station 220kV bus differential protection #1 main transformer high start failure receiving soft pressure plate at the Baoxin master station;
[0064] Operation step 13: Remotely exit the example station 220kV bus differential protection No. 2 #1 main transformer high start failure receiving soft pressure plate at the Baoxin master station;
[0065] Operation step 14: Remotely exit the example station 220kV#1 main transformer protection at the Baoxin master station and send a soft pressure plate when the #1 main transformer fails to start at high speed;
[0066] Operation step 15: Remotely exit the example station 220kV#1 main transformer protection at the Baoxin master station and send a soft pressure plate by switching on the 2012 switch;
[0067] Operation step 16: Remotely exit the example station 220kV#1 main transformer protection at the Baoxin master station and send a soft pressure plate by switching on the 1012 switch;
[0068] Operation step 17: Remotely exit the example station 220kV#1 main transformer protection at the Baoxin master station and send a soft pressure plate by tripping the 5012 switch;
[0069] Operation step 18: Remotely exit the example station 220kV#1 main transformer protection 2#1 main transformer high start failure and send soft pressure plate at the Baoxin master station;
[0070] Operation step 19: Remotely exit the example station 220kV#1 main transformer protection second trip 2012 switch and send a soft pressure plate at the Baoxin master station;
[0071] Operation step 20: Remotely exit the example station 220kV#1 main transformer protection second trip 1012 switch and send a soft pressure plate at the Baoxin master station;
[0072] Operation step 21: Remotely exit the example station 220kV#1 main transformer protection second trip 5012 switch and send a soft pressure plate at the Baoxin master station.
[0073] The embodiment of the present application also provides a device processing method, which is applied to the processing system of the above-mentioned device. Figure 3 is a flowchart of a processing method of a device provided in an embodiment of the present application, such as Figure 3 As shown, the method comprises the following steps:
[0074] Step S301, obtain the equipment operation status of the transformer equipment, determine the equipment inspection plan according to the equipment operation status, and send the equipment inspection plan to the production monitoring system, wherein the production monitoring system is used to inspect the transformer equipment according to the equipment inspection plan and generate equipment inspection results.
[0075] Specifically, in order to realize the inspection and equipment processing of transformer equipment, we can first obtain the equipment operation status of the transformer equipment, determine the abnormal alarm after analyzing the above status, and then generate an equipment inspection plan based on the abnormal alarm, and then send the generated equipment inspection plan to the production monitoring system, and the production monitoring system will implement the inspection operation.
[0076] Step S302, upon receiving the equipment inspection results sent by the production monitoring system, an equipment adjustment plan is generated according to the equipment inspection results, and the equipment adjustment plan is sent to the dispatching command platform.
[0077] Specifically, after the production monitoring system completes the equipment inspection operation, it can generate equipment inspection results. At this time, the fault handling system can receive the equipment inspection results sent by the production monitoring system. After analyzing the equipment inspection results, it determines whether the abnormal condition of the transformer equipment is more serious and whether it is necessary to perform maintenance strategies such as power outage on the transformer equipment, that is, generate an equipment adjustment plan.
[0078] The equipment processing method provided in the embodiment of the present application obtains the equipment operating status of the transformer equipment, determines the equipment inspection plan according to the equipment operating status, and sends the equipment inspection plan to the production monitoring system, wherein the production monitoring system is used to perform inspection operations on the transformer equipment according to the equipment inspection plan and generate equipment inspection results; when receiving the equipment inspection results sent by the production monitoring system, an equipment adjustment plan is generated according to the equipment inspection results, and the equipment adjustment plan is sent to the dispatching command platform, which solves the problem of low detection efficiency when monitoring electrical equipment in related technologies, and uses the equipment detection system and the fault handling system to perform collaborative operations, thereby performing fault handling on the electrical equipment, thereby improving the processing efficiency of the electrical equipment.
[0079] Optionally, in the processing method of the equipment provided in the embodiment of the present application, the dispatching and command platform generates a processing instruction according to the equipment adjustment plan when receiving the equipment adjustment plan, and sends the processing instruction to the equipment operating system, wherein the equipment operating system adjusts the transformer equipment according to the processing instruction.
[0080] Specifically, the dispatching and command platform may be a DICP (Dynamic Internet Content Provider) system. When the transformer equipment failure is serious, an equipment adjustment plan may be generated based on the equipment inspection results. For example, the equipment adjustment plan may be to shut down the transformer equipment. The equipment adjustment plan is then sent to the dispatching and command platform, which then performs programmed operations on the equipment based on the equipment adjustment plan.
[0081] The dispatching and commanding platform can generate different types of processing instructions according to the equipment adjustment plan, and then package these processing instructions and send them to the equipment operating system. The equipment operating system determines multiple sub-processing instructions according to the processing instructions, and processes the transformer equipment based on these sub-processing instructions. This embodiment uses the dispatching and commanding platform to generate processing instructions, and then the processing instructions perform processing operations on multiple devices, thereby improving the processing efficiency of the equipment and greatly reducing labor costs.
[0082] It should be noted that the steps shown in the flowcharts of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and that, although a logical order is shown in the flowcharts, in some cases, the steps shown or described can be executed in an order different from that shown here.
[0083] The present application also provides a processing system for a device. Figure 4 is a schematic diagram of a processing system of an optional device provided according to an embodiment of the present application, such as Figure 4 As shown, the system includes: a device detection system and a fault handling system. Since different devices in the system can be deployed in different areas, the system can be divided into zone one, zone two, zone three and zone four.
[0084] Specifically, the fault handling system is deployed in the third area. A defect handling inference engine is deployed in the equipment. It is connected to the dispatching and commanding platform (i.e., DICP system) deployed in the second area through the forward and reverse isolation devices and the office system through the firewall device. When the equipment operation status sent by the equipment detection system is received, an equipment inspection plan can be generated according to the equipment operation status, and the equipment inspection plan is sent to the production monitoring system. The equipment inspection results returned by the production monitoring system according to the equipment inspection plan are received. When the equipment inspection results indicate that the transformer equipment is in the first abnormal state, an equipment adjustment plan is generated according to the equipment inspection results, and the equipment adjustment plan is sent to the dispatching and commanding platform; the equipment detection system can collect the equipment operation status of the transformer equipment, and can monitor the partial discharge, temperature, oil chromatography, gas content, etc. of the transformer online, and then send the equipment operation status to the fault handling system to ensure the safe and stable operation of the transformer and provide timely and accurate fault warning and diagnosis information for the operation and maintenance personnel; the production monitoring system is deployed in the third area, and can send inspection instructions to the monitoring and inspection equipment, and then can remotely The drones, smart cameras and patrol robots associated with the program control carry out patrol operations on the transformer equipment, and then the production monitoring system receives and processes the patrol photos and results sent back by the patrol, archives them and generates equipment patrol results; after receiving the equipment adjustment plan, the command and dispatch platform generates processing instructions according to the equipment adjustment plan, and sends the processing instructions to the equipment operating system, and the equipment operating system includes the Baoxin master station and the dispatching system (also known as the OCS system). The Baoxin master station and the dispatching system are deployed in the first area, and can patrol and process the transformer equipment through the dispatching data network. The dispatching system extracts the second sub-processing instruction for characterizing the processing of the primary equipment from the processing instruction, and then realizes the adjustment operation of the knife switch and other components in the primary equipment through the remote motor associated with the system. The Baoxin master station can complete the fixed value modification, fixed value zone switching, soft pressure plate insertion and withdrawal and other operations of the secondary equipment through the Baoxin substation. Among them, the Baoxin substation includes intelligent recorders, control substations, intelligent remote motors, etc.; the office system is deployed in the fourth area, which can refer to the power grid-specific office information transmission system, which can publish the operation abnormality report to relevant personnel in the form of documents.
[0085] When using the above system to process transformer equipment, Figure 5 is a schematic diagram of an optional device processing method provided according to an embodiment of the present application, such as Figure 5 As shown, the method includes: the equipment detection system collects the equipment operation status of the transformer equipment, and finds that the main transformer is operating abnormally according to the operation status, wherein the main transformer operation abnormality includes but is not limited to high transformer winding temperature, high oil temperature, abnormal oil level, abnormal partial discharge, abnormal vibration, abnormal oil pressure, abnormal oil chromatography analysis, etc., and then sends the equipment operation status to the fault handling system.
[0086] When the fault handling system receives the above-mentioned equipment operating status, it establishes a connection between the equipment operating status and the defect handling inference engine. The defect handling inference engine determines whether an inspection is required. If the judgment result is that an inspection is required, an equipment inspection plan is generated according to the equipment operating status, and the equipment inspection plan is sent to the production monitoring system, and the equipment inspection result returned by the production monitoring system based on the equipment inspection plan is received; if the judgment result is that an inspection is not required, an operation report is directly generated according to the equipment operating status, and it is sent to relevant personnel through the office system. The equipment inspection plan may include the substation name, main transformer number and inspection task.
[0087] Furthermore, the production monitoring system is associated with a monitoring and patrol device. At this time, a patrol instruction can be sent to the monitoring and patrol device according to the equipment patrol plan. When the monitoring and patrol device receives the patrol instruction, it patrols the transformer equipment and generates equipment patrol results. The fault handling system analyzes the equipment patrol results. If the equipment patrol results indicate that the transformer equipment is in the first abnormal state, that is, it determines whether the transformer equipment needs to be shut down to handle the defect. If a power outage is required, an equipment adjustment plan can be generated according to the equipment patrol results, and the equipment adjustment plan is sent to the dispatching command platform. At the same time, the operation abnormality report and the equipment adjustment plan are sent to relevant personnel through the office system, where the equipment adjustment plan can include substations, main transformers that need to be shut down, operation tasks, etc. If a power outage is not required, an operation abnormality report can be generated according to the equipment patrol results, and the operation abnormality report can be sent to the office system, and then the office system sends the above-mentioned operation abnormality report to relevant personnel in the form of a document. When the dispatching and command platform receives the equipment adjustment plan, it generates processing instructions according to the equipment adjustment plan and sends different processing instructions to different equipment operating systems. For example, the dispatching system in the equipment operating system can obtain the electrical wiring architecture diagram and operation list of the transformer equipment, and then adjust each switch and knife switch of the transformer equipment in turn according to the operation list. The security master station extracts the sub-processing instructions from the processing instructions and performs equipment adjustment processing on the transformer equipment according to the sub-processing instructions.
[0088] This embodiment utilizes the equipment detection system and the fault processing system to perform coordinated operations to process the faults of the electrical equipment, thereby improving the processing efficiency of the electrical equipment.
[0089] The embodiment of the present application also provides a device processing apparatus. It should be noted that the device processing apparatus of the embodiment of the present application can be used to execute the device processing method provided in the embodiment of the present application. The device processing apparatus provided in the embodiment of the present application is introduced below.
[0090] Figure 6is a schematic diagram of a processing device according to an embodiment of the present application, such as Figure 6 As shown, the device includes: an acquisition unit 60 and a generation unit 61.
[0091] An acquisition unit 60 is used to acquire the equipment operation status of the transformer equipment, determine the equipment inspection plan according to the equipment operation status, and send the equipment inspection plan to the production monitoring system, wherein the production monitoring system is used to perform inspection operations on the transformer equipment according to the equipment inspection plan and generate equipment inspection results;
[0092] The generating unit 61 is used to generate an equipment adjustment plan according to the equipment inspection result when receiving the equipment inspection result sent by the production monitoring system, and send the equipment adjustment plan to the dispatching command platform.
[0093] The processing device of the equipment provided in the embodiment of the present application obtains the equipment operation status of the transformer equipment through the acquisition unit 60, determines the equipment inspection plan according to the equipment operation status, and sends the equipment inspection plan to the production monitoring system, wherein the production monitoring system is used to perform inspection operations on the transformer equipment according to the equipment inspection plan, and generate equipment inspection results; the generation unit 61 generates an equipment adjustment plan according to the equipment inspection results when receiving the equipment inspection results sent by the production monitoring system, and sends the equipment adjustment plan to the dispatching command platform, which solves the problem of low detection efficiency when monitoring electrical equipment in related technologies, and uses the equipment detection system and the fault handling system to perform collaborative operations, and then handle the faults of the electrical equipment, thereby improving the processing efficiency of the electrical equipment.
[0094] Optionally, in the processing device of the equipment provided in the embodiment of the present application, the dispatching and command platform generates a processing instruction according to the equipment adjustment plan when receiving the equipment adjustment plan, and sends the processing instruction to the equipment operating system, wherein the equipment operating system adjusts the transformer equipment according to the processing instruction.
[0095] The processing device of the above-mentioned device includes a processor and a memory. The above-mentioned acquisition unit 60, generation unit 61, etc. are all stored in the memory as program units, and the processor executes the above-mentioned program units stored in the memory to realize corresponding functions.
[0096] The processor includes a kernel, which retrieves the corresponding program unit from the memory. One or more kernels can be set, and the problem of low detection efficiency when monitoring electrical equipment in related technologies can be solved by adjusting kernel parameters.
[0097] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory, such as read-only memory (ROM) or flash RAM, and the memory includes at least one memory chip.
[0098] An embodiment of the present invention provides a computer storage medium, which is used to store a program. When the program is running, the device where the computer storage medium is located is controlled to execute a device processing method.
[0099] Figure 7 is a schematic diagram of an electronic device provided according to an embodiment of the present application, such as Figure 7 As shown, an embodiment of the present invention provides an electronic device, the electronic device 70 includes a processor, a memory, and a program stored in the memory and executable on the processor, the processor is used to execute computer-readable instructions, wherein the computer-readable instructions execute a processing method of a device when they are executed. The device in this article can be a server, a PC, a PAD, a mobile phone, etc.
[0100] The present application also provides a computer program product, including a computer program, which, when executed by a processor, implements the steps of a processing method of a device in each embodiment of the present application.
[0101] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.
[0102] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0103] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0104] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0105] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.
[0106] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.
[0107] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tape disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.
[0108] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.
[0109] The above are only embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included within the scope of the claims of the present application.
Claims
1. A processing system for a device, characterized in that: include: An equipment detection system, used for collecting the equipment operation status of the transformer equipment and sending the equipment operation status to the fault handling system, wherein the equipment operation status at least includes partial discharge, temperature, oil chromatogram and gas content of the transformer equipment; The fault handling system includes an inference engine, which is used to generate an equipment inspection plan according to the equipment operation status when receiving the equipment operation status sent by the equipment detection system, send the equipment inspection plan to the production monitoring system, and receive the equipment inspection result returned by the production monitoring system based on the equipment inspection plan. When the equipment inspection result indicates that the transformer equipment is in a first abnormal state, an equipment adjustment plan is generated according to the equipment inspection result, and the equipment adjustment plan is sent to the dispatching and commanding platform, wherein the equipment inspection result is obtained after the production monitoring system performs an inspection operation on the transformer equipment, and the dispatching and commanding platform is used to process the transformer equipment according to the equipment adjustment plan.
2. The system according to claim 1, characterized in that The dispatching and commanding platform is communicatively connected to the fault handling system via a forward and reverse isolation device, and is used for generating a processing instruction according to the equipment adjustment plan upon receiving the equipment adjustment plan, and sending the processing instruction to the equipment operating system.
3. The system according to claim 2, characterized in that The equipment operating system includes a trust-protecting main station, which is communicatively connected to the dispatching and commanding platform via a firewall device. The trust-protecting main station is used to extract a first sub-processing instruction from the processing instruction, and perform equipment adjustment processing on the transformer equipment according to the first sub-processing instruction, wherein the equipment adjustment processing at least includes fixed value modification, fixed value zone switching, and soft pressure plate insertion and withdrawal.
4. The system according to claim 2, characterized in that The equipment operating system also includes a dispatching system, which is communicatively connected to the dispatching command platform via a firewall device. The dispatching system is used to extract a second sub-processing instruction from the processing instruction, and control the remote motor to perform equipment operation on the transformer equipment according to the second sub-processing instruction, wherein the equipment operation at least includes opening and closing the knife switch operation.
5. The system according to claim 1, characterized in that The fault handling system is associated with the office system through the firewall device. After sending the equipment adjustment plan to the dispatching command platform, the fault handling system generates an operation abnormality report according to the equipment inspection result, and sends the operation abnormality report to the office system, wherein the office system is used to forward the operation abnormality report to the client used by the management personnel when receiving the operation abnormality report.
6. The system according to claim 1, characterized in that The production monitoring system is associated with a monitoring and patrol device, and the production monitoring system sends a patrol instruction to the monitoring and patrol device according to the equipment patrol plan. When the monitoring and patrol device receives the patrol instruction, it performs a patrol operation on the transformer equipment and generates the equipment patrol result.
7. The system according to claim 1, characterized in that When the equipment inspection result indicates that the transformer equipment is in the second abnormal state, the equipment inspection result is sent to the dispatching command platform.
8. The system according to claim 4, characterized in that Controlling the remote motor to perform equipment operation on the transformer device according to the second sub-processing instruction includes: Obtain an electrical wiring diagram of the transformer device, and identify M switches and N switches from the electrical wiring diagram, where M and N are positive integers; An operation list is obtained, and each switch and each knife switch are adjusted in sequence according to the operation list.
9. A method for processing a device, characterized in that: The processing method of the device is applied to the processing system of the device according to any one of claims 1 to 8, comprising: Acquire the equipment operation status of the transformer equipment, determine the equipment inspection plan according to the equipment operation status, and send the equipment inspection plan to the production monitoring system, wherein the production monitoring system is used to perform inspection operations on the transformer equipment according to the equipment inspection plan and generate equipment inspection results; When the equipment inspection result sent by the production monitoring system is received, an equipment adjustment plan is generated according to the equipment inspection result, and the equipment adjustment plan is sent to the dispatching command platform.
10. The method according to claim 9, characterized in that When receiving the equipment adjustment plan, the dispatching and command platform generates a processing instruction according to the equipment adjustment plan, and sends the processing instruction to the equipment operating system, wherein the equipment operating system adjusts the transformer equipment according to the processing instruction.