Detachable fixing device and method for transportation and installation of offshore platform

By designing a detachable fixture in the transportation and installation of offshore platforms, and using reinforcement mechanisms and connection mechanisms to achieve stable fixation of the primary and secondary beams, the problems of the inability to disassemble existing fixtures and poor scene flexibility are solved, and flexibility in multiple scenarios is achieved Stable fixation and reuse of resources.

CN119305687APending Publication Date: 2025-01-14SHANDONG ELECTRIC POWER ENG CONSULTING INST CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411383243.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-30
Publication Date
2025-01-14

AI Technical Summary

Technical Problem

The existing fixtures for transportation and installation of offshore platforms cannot be disassembled, resulting in unrepeatable, high cost and space-consuming, and it is difficult to design flexible fixtures suitable for multiple scenarios.

Method used

A detachable fixing device is designed to fix the main and secondary beams through a reinforcement mechanism, and the first connecting mechanism and the second connecting mechanism are used to realize the removable connection of the reinforcement mechanism, and through the slide groove and the slide rail, the screw and the fixing groove, etc. The structure realizes flexible and stable connection of multiple reinforcement mechanisms, and combines the web fastening mechanism to stabilize the main and secondary beams.

Benefits of technology

It realizes detachable fixing of offshore platform transportation and installation, ensures flexibility and stability of scene use, avoids waste of fixtures and space occupation, and is suitable for deck binding points, platform column deck rooting and hoisting points, etc. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119305687A_ABST
    Figure CN119305687A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of fixing devices, and provides a detachable fixing device and method for transportation and installation of an offshore platform, and the detachable fixing device comprises at least two reinforcing mechanisms, and a first connecting mechanism and a second connecting mechanism which are respectively arranged at two ends of the reinforcing mechanisms (1); the primary beam and the secondary beam are fixed through the reinforcing mechanism, and the two ends of the reinforcing mechanism are detachably connected through the first connecting mechanism and the second connecting mechanism; moreover, through the arrangement of a first connecting hole, a first screw rod and a fixing groove on each reinforcing mechanism, a through hole, a first screw rod and a second connecting hole on the first connecting mechanism, a sliding groove and a sliding rail, the flexible and stable connection of the plurality of reinforcing mechanisms can be quickly realized; webs of the primary beam and the secondary beam can be stably fastened through the web fastening mechanism, and detachable fixation of transportation and installation of the offshore platform is achieved on the basis that stability is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of fixing devices, and in particular relates to a detachable fixing device and method for transporting and installing an offshore platform. Background Art

[0002] In fields such as offshore wind power generation, during the transportation and installation of offshore platforms, considering the complex marine transportation conditions, large equipment on offshore platforms needs to be temporarily tied up. The tying requires setting fixed points on the platform structural components. The traditional fixing method is to weld stiffening ribs and tying plates on the structural components.

[0003] At present, the fixing devices used for the transportation and installation of offshore platforms cannot be disassembled. This is mainly because connection methods such as welding can achieve stable connection with the main beam, beam wing and web of structural members to ensure installation stability, and it is necessary to consider the fixation in multiple scenarios such as deck lashing points, platform column deck rooting and lifting points. It is not easy to design a flexible and detachable fixing device that can be applied to multiple scenarios. Although fixing methods such as welding can achieve stable fixation, the fixing device cannot be recycled and reused, the cost is high, and it occupies on-site space, which will affect the normal operation of the platform and other equipment in the later stage. In summary, there is a lack of a detachable offshore platform fixing device with good fixing stability and high flexibility in scene use. Summary of the invention

[0004] In order to solve the above problems, the present invention proposes a detachable fixing device and method for offshore platform transportation and installation, wherein the primary and secondary beams are fixed by a reinforcement mechanism, and the two ends of the reinforcement mechanism are detachably connected by a first connecting mechanism and a second connecting mechanism; and, through the first connecting hole, the first screw and the fixing groove on each reinforcement mechanism, the through hole, the first screw and the second connecting hole on the first connecting mechanism, as well as the setting of the slide groove and the slide rail, a plurality of reinforcement mechanisms can be quickly and flexibly connected. The webs of the primary and secondary beams can be stably fastened by the web fastening mechanism, thereby achieving detachable fixation for offshore platform transportation and installation while ensuring stability.

[0005] In order to achieve the above-mentioned purpose, in a first aspect, the present invention provides a detachable fixing device for transporting and installing an offshore platform, which adopts the following technical solution:

[0006] A detachable fixing device for transporting and installing an offshore platform comprises at least two reinforcement mechanisms, and a first connecting mechanism and a second connecting mechanism respectively arranged at two ends of the reinforcement mechanisms;

[0007] Each reinforcement mechanism is provided with a first connection hole, and a web fastening mechanism is provided on the reinforcement mechanism through the first connection hole;

[0008] The first connecting mechanism is provided with a through hole, the reinforcing mechanism is located at one end of the first connecting mechanism and is provided with a first screw and a fixing groove, and the fixing groove is provided with a second connecting hole matching the first screw;

[0009] The reinforcement mechanism is provided with a slide groove at one end of the second connection mechanism, and the second connection mechanism is provided with a slide rail matched with the slide groove.

[0010] Furthermore, the reinforcement mechanism includes a first reinforcement rod, and a second reinforcement rod vertically arranged at both ends of the first reinforcement rod; sliding grooves are arranged on the side surfaces at both ends of the first reinforcement rod, and the first screw rod is arranged at one end of the second reinforcement rod away from the first reinforcement rod; a plurality of first connecting holes are opened on the first reinforcement rod and the second reinforcement rod.

[0011] Furthermore, the first connecting mechanism includes a connecting transverse plate and a connecting vertical plate vertically arranged on the connecting transverse plate; the connecting transverse plate is provided with the through hole, the connecting vertical plate is provided with a fixing hole, and a reinforcing ring is provided at the fixing hole.

[0012] Furthermore, the connecting vertical plate is provided with an auxiliary fixing mechanism, which includes a first plug plate and a second plug plate vertically arranged on the first plug plate; the fixing groove is provided with a second slot adapted to the auxiliary fixing mechanism.

[0013] Furthermore, the connecting transverse plate is a channel steel.

[0014] Furthermore, the fixing groove is provided with a first slot, and a plug hole is provided on a side wall of the first slot.

[0015] Furthermore, a side panel is provided on the fixing groove, and a side panel connecting hole is provided on the side panel.

[0016] Furthermore, a through hole is provided on the second connecting mechanism.

[0017] Furthermore, the web fastening mechanism includes a bolt, a bolt head and a fastening head arranged at both ends of the bolt, and an adjusting nut arranged on the bolt.

[0018] In order to achieve the above-mentioned purpose, in a second aspect, the present invention also provides a detachable fixing method for offshore platform transportation and installation, which adopts the following technical solution:

[0019] A detachable fixing method for offshore platform transportation and installation uses the detachable fixing device for offshore platform transportation and installation as described in Example 1, including: fixing primary and secondary beams using a reinforcement mechanism, and connecting multiple reinforcement mechanisms via a first connecting mechanism and a second connecting mechanism.

[0020] Compared with the prior art, the present invention has the following beneficial effects:

[0021] 1. In the present invention, the primary and secondary beams are fixed by a reinforcement mechanism, and the two ends of the reinforcement mechanism are detachably connected by a first connection mechanism and a second connection mechanism; and, by providing a first connection hole, a first screw and a fixing groove on each reinforcement mechanism, a through hole, a first screw and a second connection hole on the first connection mechanism, and a slide groove and a slide rail, a plurality of reinforcement mechanisms can be quickly and flexibly connected stably, and the webs of the primary and secondary beams can be stably fastened by a web fastening mechanism, thereby achieving detachable fixation for transportation and installation of an offshore platform while ensuring stability;

[0022] 2. The detachable fixing device in the present invention can be used for fixing the offshore platform during transportation and installation in multiple scenarios, such as deck lashing points, platform column deck rooting, and lifting points, thus ensuring the flexibility of scene usage. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] The drawings in the specification that constitute a part of this embodiment are used to provide a further understanding of this embodiment. The schematic embodiments of this embodiment and their descriptions are used to explain this embodiment and do not constitute improper limitations on this embodiment.

[0024] Figure 1 This is a schematic diagram of the structure of the device according to Embodiment 1 of the present invention;

[0025] Figure 2 Schematic diagram of the reinforcement mechanism of Example 1 of the present invention;

[0026] Figure 3 The first connecting mechanism of Embodiment 1 of the present invention;

[0027] Figure 4 This is a schematic diagram of a fixing groove according to Embodiment 1 of the present invention;

[0028] Figure 5 Schematic diagram of the web fastening mechanism of Example 1 of the present invention;

[0029] Figure 6 This is a schematic diagram of a fastening plug according to Embodiment 1 of the present invention;

[0030] Figure 7 This is a schematic diagram of the primary and secondary beams of Example 1 of the present invention;

[0031] Figure 8 This is a schematic diagram of the installation of the reinforcement mechanism of Example 1 of the present invention;

[0032] Fig. 9 This is a schematic diagram of the installation of the second connecting mechanism of Example 1 of the present invention;

[0033] Fig.10This is a schematic diagram of the installation of the web fastening mechanism of Example 1 of the present invention;

[0034] Fig.11 This is a schematic diagram of the installation of the first connecting mechanism of Example 1 of the present invention;

[0035] Fig.12 Schematic diagram of the state after installation of embodiment 1 of the present invention

[0036] Fig.13 This is a schematic diagram of the device in non-working state according to Embodiment 1 of the present invention;

[0037] Fig.14 This is a schematic diagram of a first connecting mechanism of Embodiment 3 of the present invention;

[0038] Fig.15 This is a schematic diagram of a fixing groove according to Embodiment 3 of the present invention;

[0039] Fig.16 This is a schematic diagram of the post-installation state of Embodiment 3 of the present invention;

[0040] Fig.17 This is a schematic diagram of the use status of Example 3 of the present invention;

[0041] Fig.18 This is a schematic diagram of a first connecting mechanism of Example 4 of the present invention;

[0042] Fig.19 This is a schematic diagram of the state after installation of Embodiment 4 of the present invention;

[0043] Among them, 1. reinforcement mechanism; 11. first reinforcement rod; 12. second reinforcement rod; 13. slide groove; 14. first connection hole; 15. first screw rod; 16. fixing groove; 1601. first slot; 1602. jack; 1603. second connection hole; 1604. second slot; 1605. side plate; 2606. side plate connection hole; 17. first nut; 18. second screw rod; 19. second nut; 2. first connection mechanism; 21. Connecting horizontal plate; 22. Connecting vertical plate; 23. Through hole; 24. Auxiliary fixing mechanism; 2401. First plug plate; 2402. Second plug plate; 25. Fixing hole; 26. Reinforcement ring; 3. Second connecting mechanism; 31. Slide rail; 32. Through hole; 4. Web fastening mechanism; 41. Bolt; 42. Bolt head; 43. Adjusting nut; 44. Fastening head; 5. Primary and secondary beams; 51. Main beam; 52. Web; 6. Steel support. DETAILED DESCRIPTION

[0044] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

[0045] It should be noted that the following detailed descriptions are exemplary and are intended to provide further explanation of the present application. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present application belongs.

[0046] Embodiment 1:

[0047] Traditional fixing devices used for offshore platform transportation and installation, such as wind turbine platform transportation and installation fixing methods, have stiffening ribs and lashing plates welded on structural members that cannot be removed, resulting in a waste of steel, and taking up space that affects subsequent operations. They have a single function and no other functions.

[0048] In response to the above problems, Figure 1 As shown, this embodiment provides a detachable fixing device for offshore platform transportation and installation, including at least two reinforcement mechanisms 1, a first connecting mechanism 2 and a second connecting mechanism 3 respectively arranged at two ends of the reinforcement mechanism 1, and a web fastening mechanism 4 arranged on the reinforcement mechanism 1.

[0049] like Figure 1 and Figure 2 As shown, the reinforcement mechanism 1 includes a first reinforcement rod 11, a second reinforcement rod 12 vertically arranged at both ends of the first reinforcement rod 11, a slide groove 13 arranged on the side surfaces of both ends of the first reinforcement rod 11, a plurality of first connecting holes 14 opened in the first reinforcement rod 11 and the second reinforcement rod 12, and a first screw rod 15 arranged at one end of the second reinforcement rod 12 away from the first reinforcement rod 11.

[0050] Optionally, the first reinforcement rod 11 and the second reinforcement rod 12 are square steel or other structures; the first connecting hole 14 can be used to install components such as screws; the ends of the two second reinforcement rods 12 away from the first reinforcement rod 11 can be connected by a fixing groove 16, and a first nut 17 can be provided on the first screw 15.

[0051] like Figure 1 and Figure 3 As shown, the first connecting mechanism 2 includes a connecting transverse plate 21 and a connecting vertical plate 22 vertically arranged on the connecting transverse plate 21; a through hole 23 is formed on the connecting transverse plate 21, and a fixing hole 25 is formed on the connecting vertical plate 22, and a reinforcing ring 26 is provided at the fixing hole 25.

[0052] Specifically, the connecting cross plate 21 is used to interact with the primary and secondary beams 5 , and the second reinforcing rod 12 can pass through the through hole 23 ; the fixing hole 25 is used to connect with other structures, and the reinforcing ring 26 improves the strength of the fixing hole 25 .

[0053] Optionally, an auxiliary fixing mechanism 24 is provided on the connecting vertical plate 22, and the auxiliary fixing mechanism 24 includes a first plug plate 2401 and a second plug plate 2402 vertically arranged on the first plug plate 2401; a second slot 1604 adapted to the auxiliary fixing mechanism 24 is provided on the fixing groove 16; through the cooperation between the auxiliary fixing mechanism 24 and the second slot 1604, the connection stability is improved.

[0054] like Figure 1 and Figure 4 As shown, the fixing slot 16 is provided with a first slot 1601 for matching with the end of the second reinforcing rod 12; the first slot 1601 is provided with a second connection hole 1603 matching with the first screw rod 15, and the first screw rod 15 passes through the second connection hole 1603 and is connected by the first nut 17. The side wall of the first slot 1601 is provided with an insertion hole 1602, and the insertion hole 1602 can be aligned with the corresponding first connection hole 14 and then the second screw rod 18 can be inserted, and the second nut 19 can be used for reinforcement to improve stability.

[0055] like Figure 1 and Figure 2 As shown, the second connecting mechanism 3 is provided with a slide rail 31 cooperating with the slide groove 13 to facilitate the installation and disassembly of the second connecting mechanism 3, and a through hole 32 is opened on the second connecting mechanism 3. The through hole 32 can be aligned with the corresponding first connecting hole 14 and the second screw rod 18 can be inserted into it, and it can be reinforced by the second nut 19 to improve stability.

[0056] like Figure 1 , Figure 5 and Figure 6 As shown, the web fastening mechanism 4 includes a bolt 41, a bolt head 42 and a fastening head 44 provided at both ends of the bolt 41, and an adjusting nut 43 provided on the bolt 41. Specifically, by rotating the bolt head 42, under the action of the adjusting nut 43, the fastening head 44 can be pressed against and away from the web 52. The fixing stability of the web 52 can be ensured, and flexible separation can be achieved during disassembly.

[0057] One of the working processes and principles of this embodiment is:

[0058] like Figure 7 to Figure 13As shown, take the example of adding a connection point to a connection node of a primary and secondary beam 5 at a deck lashing point; insert two U-shaped reinforcement mechanisms 1 from the bottom of the main beam 51 from bottom to top, so that the reinforcement mechanism 1 is tightly attached to the beam flange. Insert the second connection mechanism 3 between the two reinforcement mechanisms 1 along the slide groove 13, insert the second screw rod 18 into the first connection hole 14 at the corresponding position on the reinforcement mechanism 1, and the through hole 32, and use the second nut 19 to fix the bolt 41. Insert the bolt 41 into the first connection hole 14 at the corresponding position, pass through the second reinforcement rod 12 and insert it into the reserved socket of the fastening head 44. Tighten all the components, install the top fixing groove 16 at the end of the second reinforcement rod 12, and insert the auxiliary fixing mechanism 24 into the second slot 1604 at the same time. After the first screw rod 15 is inserted into the second connection hole 1603 at the top, set the first nut 17 on the first screw rod 15.

[0059] In other embodiments, the components may also be welded to the original steel structure to form a permanent structure.

[0060] In this embodiment, mechanical connections are used between the components to achieve the purpose of non-fire disassembly; various fastening devices can be used to cooperate with the original structure to ensure the safety and stability of the structure. The U-shaped reinforcement mechanism 1 is in surface contact with the original structure to avoid stress concentration and component damage. The U-shaped reinforcement mechanism 1 structure adopts a closed section or a solid section, which is conducive to resisting the strong corrosion environment at sea.

[0061] Embodiment 2:

[0062] This embodiment provides a detachable fixing method for offshore platform transportation and installation, using the detachable fixing device for offshore platform transportation and installation as described in Example 1, including: using a reinforcement mechanism 1 to fix the main and secondary beams, and multiple reinforcement mechanisms 1 are connected by a first connecting mechanism 2 and a second connecting mechanism 3.

[0063] Embodiment 3:

[0064] This embodiment provides a detachable fixing device for offshore platform transportation and installation, comprising at least two reinforcement mechanisms 1, a first connection mechanism 2 and a second connection mechanism 3 respectively arranged at two ends of the reinforcement mechanism 1, and a web fastening mechanism 4 arranged on the reinforcement mechanism 1. Fig.14 and Fig.15 As shown, different from Example 1, the connecting vertical plate 22 in this embodiment is a channel steel or other steel sections, the fixing groove 16 is provided with a side plate 1605, and the side plate 1605 is provided with a side plate connecting hole 2606.

[0065] like Fig.16 and Fig.17 As shown, one of the working processes or principles of this embodiment is:

[0066] Taking the rooting environment of the platform column deck as an example, two U-shaped reinforcement mechanisms 1 are installed from the bottom of the main beam 51 upward, so that the reinforcement mechanism 1 is tightly attached to the beam flange. The second connection mechanism 3 is inserted between the two reinforcement mechanisms 1 along the slide groove 13, and the second screw rod 18 is inserted into the first connection hole 14 at the corresponding position on the reinforcement mechanism 1, and the through hole 32, and the second nut 19 is used for fixing. The bolt 41 is inserted into the first connection hole 14 at the corresponding position, penetrates the second reinforcement rod 12 and is inserted into the reserved socket of the fastening head 44. Tighten all parts, install the top fixing groove 16 at the end of the second reinforcement rod 12, and insert the auxiliary fixing mechanism 24 into the second slot 1604 at the same time. After the first screw rod 15 is inserted into the second connection hole 1603 at the top, the first nut 17 is set on the first screw rod 15. Connect the steel support 6 through the side plate 1605 and the side plate connection hole 2606 to build the deck platform.

[0067] Embodiment 4:

[0068] This embodiment provides a detachable fixing device for offshore platform transportation and installation, comprising at least two reinforcement mechanisms 1, a first connection mechanism 2 and a second connection mechanism 3 respectively arranged at two ends of the reinforcement mechanism 1, and a web fastening mechanism 4 arranged on the reinforcement mechanism 1. Fig.18 As shown, different from Example 1, the first connecting mechanism 2 in this embodiment is located at the bottom; or, the connecting vertical plate 22 in this embodiment is a channel steel or other steel section, and a side plate 1605 is provided on the fixing groove 16, and a side plate connecting hole 2606 is provided on the side plate 1605.

[0069] As shown in 19, one of the working processes or principles of this embodiment is:

[0070] Taking the hoisting point environment as an example, move two U-shaped reinforcement mechanisms 1 from the bottom of the main beam 51 from bottom to top, so that the reinforcement mechanism 1 is tightly attached to the beam flange. Insert the second connection mechanism 3 along the slide groove 13 between the two reinforcement mechanisms 1, insert the second screw rod 18 into the first connection hole 14 at the corresponding position on the reinforcement mechanism 1, and the through hole 32, and use the second nut 19 to fix the bolt 41. Insert the bolt 41 into the first connection hole 14 at the corresponding position, pass through the second reinforcement rod 12 and insert it into the reserved socket of the fastening head 44. Tighten all the components, install the top fixing groove 16 at the end of the second reinforcement rod 12, and insert the auxiliary fixing mechanism 24 into the second slot 1604 at the same time. After the first screw rod 15 is inserted into the second connection hole 1603 at the top, set the first nut 17 on the first screw rod 15.

[0071] The present invention provides a variety of functional modules and installation methods, which can solve the problems of temporary binding of main equipment during the transportation of offshore platforms, connection of offshore platform movable platforms, movable supports and hangers, movable lifting points, etc.; after disassembly, it does not occupy platform space, which is convenient for later operation; it is not only suitable for offshore platform structures, but can also be used in buildings with other structural forms.

[0072] The above description is only a preferred embodiment of the present embodiment and is not intended to limit the present embodiment. For those skilled in the art, the present embodiment may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present embodiment shall be included in the protection scope of the present embodiment.

Claims

1. A detachable fixing device for transporting and installing an offshore platform, characterized in that: It comprises at least two reinforcement mechanisms (1), and a first connection mechanism (2) and a second connection mechanism (3) respectively arranged at two ends of the reinforcement mechanism (1); Each reinforcement mechanism (1) is provided with a first connection hole (14), and a web fastening mechanism (4) is provided on the reinforcement mechanism (1) through the first connection hole (14); The first connecting mechanism (2) is provided with a through hole (23); the reinforcing mechanism (1) is provided with a first screw rod (15) and a fixing groove (16) at one end of the first connecting mechanism (2); and the fixing groove (16) is provided with a second connecting hole (1603) matching with the first screw rod (15); The reinforcement mechanism (1) is provided with a slide groove (13) at one end of the second connection mechanism (3), and the second connection mechanism (3) is provided with a slide rail (31) that cooperates with the slide groove (13).

2. A detachable fixing device for offshore platform transportation and installation as claimed in claim 1, characterized in that: The reinforcement mechanism (1) comprises a first reinforcement rod (11) and a second reinforcement rod (12) vertically arranged at both ends of the first reinforcement rod (11); both end sides of the first reinforcement rod (11) are provided with a slide groove (13), and the first screw rod (15) is provided at one end of the second reinforcement rod (12) away from the first reinforcement rod (11); and a plurality of first connection holes (14) are provided on the first reinforcement rod (11) and the second reinforcement rod (12).

3. A detachable fixing device for offshore platform transportation and installation as claimed in claim 1, characterized in that: The first connecting mechanism (2) comprises a connecting transverse plate (21) and a connecting vertical plate (22) vertically arranged on the connecting transverse plate (21); the connecting transverse plate (21) is provided with the through hole (23), the connecting vertical plate (22) is provided with a fixing hole (25), and a reinforcing ring (26) is arranged at the fixing hole (25).

4. A detachable fixing device for offshore platform transportation and installation as claimed in claim 3, characterized in that: The connecting vertical plate (22) is provided with an auxiliary fixing mechanism (24), and the auxiliary fixing mechanism (24) comprises a first plug plate (2401) and a second plug plate (2402) vertically arranged on the first plug plate (2401); the fixing groove (16) is provided with a second slot (1604) adapted to the auxiliary fixing mechanism (24).

5. A detachable fixing device for offshore platform transportation and installation as claimed in claim 3, characterized in that: The connecting transverse plate (21) is a channel steel.

6. A detachable fixing device for offshore platform transportation and installation as claimed in claim 1, characterized in that: The fixing groove is provided with a first slot (1601), and a plug hole (1602) is provided on the side wall of the first slot (1601).

7. A detachable fixing device for offshore platform transportation and installation as claimed in claim 1, characterized in that: The fixing groove (16) is provided with a side plate (1605), and the side plate (1605) is provided with a side plate connecting hole (2606).

8. A detachable fixing device for offshore platform transportation and installation as claimed in claim 1, characterized in that: The second connecting mechanism (3) is provided with a through hole (32).

9. A detachable fixing device for offshore platform transportation and installation as claimed in claim 1, characterized in that: The web fastening mechanism (4) comprises a bolt (41), a bolt head (42) and a fastening head (44) arranged at both ends of the bolt (41), and an adjusting nut (43) arranged on the bolt (41).

10. A detachable fixing method for offshore platform transportation and installation, characterized in that: A detachable fixing device for offshore platform transportation and installation as described in any one of claims 1 to 9 is used, comprising: fixing the primary and secondary beams using a reinforcement mechanism (1), and connecting a plurality of reinforcement mechanisms (1) via a first connection mechanism (2) and a second connection mechanism (3).