PC column rib positioning control device and construction method thereof

By designing an adjustable PC column bar positioning control device, the problem of inapplicable column bar positioning in the existing technology is solved, and the accurate positioning and fixation of PC column bars of different sizes and specifications is achieved, ensuring the position of steel bars after concrete pouring Stability, suitable for a variety of PC column members, and can be reused, reducing costs.

CN119308521APending Publication Date: 2025-01-14CHINA CONSTR EIGHTH ENG DIV CORP LTD ZHEJIANG CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411370033.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-29
Publication Date
2025-01-14

AI Technical Summary

Technical Problem

In the cast-in-place structure of the existing PC column, the column bar positioning method cannot be applied to PC columns with different cross-sectional sizes, different steel bar specifications, numbers and positions, resulting in steel bar spacing and position deviation problems, affecting the connection between the upper PC column and the lower bar. .

Method used

A PC cylindrical rib positioning control device is designed, including a support frame, a moving upper beam, a moving lower beam and a moving seat. By adjusting the position of these components, it is fixed by adjusting the position of these components, and it is fixed by using elastic clamps and locking beams. Vertical main bars ensure the accuracy of the position of the steel bars.

Benefits of technology

The positioning of PC column steel bars of different cross-sectional sizes, specifications and positions is achieved, avoiding the problem of steel bar deviation, ensuring the fixation of the steel bar position after concrete pouring, facilitating subsequent PC column hoisting, and the device can be reused, reducing costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119308521A_ABST
    Figure CN119308521A_ABST
Patent Text Reader

Abstract

The invention discloses a PC column rib positioning control device and a construction method thereof.The PC column rib positioning control device comprises a bearing frame and a positioning device, the bearing frame comprises four stand columns, two transverse beams and two longitudinal beams, the four stand columns, the two transverse beams and the two longitudinal beams are arranged in a matrix mode, the transverse beams are connected to the two stand columns in the first horizontal direction, and the longitudinal beams are connected to the two stand columns in the second horizontal direction; the two movable upper beams are mounted on the two transverse beams in a position-adjustable manner; the two movable lower beams are mounted on the two longitudinal beams in a position-adjustable manner; the movable upper beam and the movable lower beam are each provided with the multiple movable bases in a position-adjustable mode, two elastic clamping plates are formed on one side of each movable base, and a clamping space is formed between the two elastic clamping plates; the locking beams are detachably installed on the upper movable beam and the lower movable beam respectively, and the locking beams abut against one sides of the vertical main ribs in a pressing mode. The method solves the problem that the positioning of the column ribs of the cast-in-place structure at the lower part of the PC column cannot be suitable for the positioning of the column ribs of the PC columns with various section sizes due to the adoption of a perforated steel plate for positioning.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a PC column reinforcement positioning control device and a construction method thereof. Background Art

[0002] In the column reinforcement construction of the lower cast-in-place structure of the PC column, the positioning and deviation of the column reinforcement play a vital role in the installation of the upper PC column. The current construction method commonly used is: according to the cross-sectional dimensions of the PC column and the specifications, quantity, and position of the column reinforcement, a steel plate is customized and a hole is opened in the steel plate. The column reinforcement is fixed by using the holes in the steel plate. This method is not applicable to the column reinforcement positioning of PC columns with different cross-sectional dimensions, different steel bar specifications, steel bar quantities, and steel bar positions. Summary of the invention

[0003] In order to overcome the defects of the prior art, a PC column reinforcement positioning control device and a construction method thereof are provided to solve the problem that the column reinforcement positioning of the lower cast-in-place structure of the existing PC column adopts perforated steel plate positioning, which cannot be applied to the column reinforcement positioning of PC columns with various cross-sectional sizes.

[0004] In order to achieve the above object, a PC column reinforcement positioning control device is provided, comprising:

[0005] A support frame, comprising four columns arranged in a matrix, two oppositely disposed transverse beams and two oppositely disposed longitudinal beams, wherein the transverse beams are connected between the two columns in a first horizontal direction, the longitudinal beams are connected between the two columns in a second horizontal direction, the second horizontal direction is perpendicular to the first horizontal direction, and the transverse beams are disposed above the longitudinal beams;

[0006] Two movable upper beams are arranged in the same direction, and two ends of the movable upper beams can be respectively installed on the two transverse beams in an adjustable manner along the length direction of the transverse beam;

[0007] Two movable lower beams are arranged in the same direction, and the two ends of the movable lower beams can be respectively installed on the two longitudinal beams in an adjustable manner along the length direction of the longitudinal beam;

[0008] A plurality of movable seats, the movable upper beam and the movable lower beam are respectively installed with the plurality of movable seats in an adjustable manner, two elastic clamping plates are formed on one side of the movable seat, and a clamping space for clamping the vertical main reinforcement of the cast-in-place foundation of the PC column is formed between the two elastic clamping plates;

[0009] The locking beam is detachably mounted on the movable upper beam and the movable lower beam, respectively, and the locking beam is pressed against a side of a plurality of vertical main ribs on the plurality of movable seats away from the movable seats.

[0010] Furthermore, a connecting beam is connected between the tops of the four columns.

[0011] Furthermore, the transverse beam is provided with a first screw rod, which is arranged along the length direction of the transverse beam. The movable upper beam is connected to a base, and the base is provided with a through hole. The first screw rod can be movably inserted into the through hole. The first screw rod is screwed with two positioning parts, and the two positioning parts are respectively against the opposite sides of the base.

[0012] Furthermore, the movable seat is provided with a through hole, and the movable upper beam or the movable lower beam can be movably inserted into the through hole. The movable seat is provided with a threaded hole, and the threaded hole is arranged on the other side of the movable seat. The threaded hole is connected to the through hole, and a locking screw is threaded into the threaded hole. The locking screw extends into the through hole and presses against the movable upper beam or the movable lower beam.

[0013] Furthermore, both ends of the movable upper beam and the movable lower beam are respectively connected with pull rods, and both ends of the locking beam are respectively provided with locking holes, and the pull rods can be movably inserted into the locking holes. The ends of the pull rods are detachably provided with pressure pieces, and the pressure pieces are pressed against the side of the locking beam away from the vertical main reinforcement.

[0014] The present invention provides a construction method of a PC column reinforcement positioning control device, comprising the following steps:

[0015] Install the support frame on the upper part of the cast-in-place foundation of the PC column;

[0016] Adjust the positions of the two movable upper beams and the two movable lower beams so that the distance of the clamping spaces on the two movable upper beams and the two movable lower beams is adapted to the distance between the column bars on the opposite sides of the PC column;

[0017] Adjust the positions of the movable seats on the movable upper beam and the movable lower beam so that the distance between the clamping spaces on two adjacent movable seats is adapted to the distance between two adjacent column bars of the PC column;

[0018] Multiple vertical main reinforcements of the cast-in-place foundation are embedded in the clamping spaces of multiple movable seats one by one;

[0019] The locking beams are detachably mounted on the movable upper beam and the movable lower beam, respectively, so that the locking beams are pressed against a side of the plurality of vertical main ribs on the plurality of movable seats away from the movable seats.

[0020] The beneficial effect of the present invention is that the PC column reinforcement positioning control device of the present invention is installed on the upper part of the vertical main reinforcement of the cast-in-place foundation of the PC column, and the positions of the movable upper beam and the movable lower beam are adjusted according to the cross-sectional size of the column and the spacing of the reinforcements, and the position of the component moving seat is adjusted according to the specifications of the reinforcements. After the adjustment is completed, the device is fixed and concrete pouring is carried out. After the concrete is poured, the device can be recovered after the concrete strength meets the requirements. At this time, the position of the reinforcement has been fixed, and the subsequent PC column can be directly hoisted, avoiding the problem that the PC column and the lower reinforcement cannot be connected due to the spacing and position of the reinforcements. The PC column reinforcement positioning control device of the present invention can protect the quality of the finished product of the vertical main reinforcement and avoid forced position adjustment due to the deviation of the vertical main reinforcement of the cast-in-place foundation and the inability to connect with the upper PC column. The PC column reinforcement positioning control device of the present invention is suitable for PC column components with different cross-sectional sizes, different reinforcement specifications, quantities, and positions, and can be repeatedly recycled. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:

[0022] Figure 1 It is a structural schematic diagram of a PC column reinforcement positioning control device according to an embodiment of the present invention.

[0023] Figure 2 for Figure 1 A local enlarged schematic diagram of point A in the figure.

[0024] Figure 3 Schematic diagram of the structure of the support frame according to an embodiment of the present invention. DETAILED DESCRIPTION

[0025] The present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant invention, rather than to limit the invention. It is also necessary to explain that, for ease of description, only the parts related to the invention are shown in the accompanying drawings.

[0026] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0027] Reference Figures 1 to 3 As shown, the present invention provides a PC column reinforcement positioning control device, comprising: a support frame 1, a movable upper beam 2, a movable lower beam 3, a movable seat 4, and a locking beam 5.

[0028] In this embodiment, the support frame 1 includes a column 11 , a transverse beam 12 and a longitudinal beam 13 .

[0029] Specifically, there are four columns 11, which are arranged in a matrix.

[0030] As a preferred embodiment, a connecting beam 14 is connected between the tops of the four columns 11. A connecting beam is connected between the tops of two adjacent columns.

[0031] There are two transverse beams 12 and two longitudinal beams 13. The two transverse beams 12 are arranged opposite to each other. The two longitudinal beams 13 are arranged opposite to each other. The transverse beam 12 is connected between two columns 11 in the first horizontal direction. The longitudinal beam 13 is connected between two columns 11 in the second horizontal direction. The second horizontal direction is perpendicular to the first horizontal direction. The transverse beam 12 is arranged above the longitudinal beam 13. The transverse beam is located in the middle of the column. The longitudinal beam is located at the bottom of the column.

[0032] There are two movable upper beams 2. The two movable upper beams 2 are arranged in the same direction. The two ends of the movable upper beam 2 can be respectively installed on the two transverse beams 12 in an adjustable manner along the length direction of the transverse beam 12.

[0033] There are two movable lower beams 3. The two movable lower beams 3 are arranged in the same direction. The two ends of the movable lower beam 3 can be respectively installed on the two longitudinal beams 13 in an adjustable position along the length direction of the longitudinal beam 13.

[0034] There are multiple movable seats 4. The movable upper beam 2 and the movable lower beam 3 are respectively installed with multiple movable seats 4 in an adjustable manner. The movable upper beam 2 is installed with multiple movable seats 4 in an adjustable manner. The movable lower beam 3 is installed with multiple movable seats 4 in an adjustable manner.

[0035] See also Figure 1 and Figure 2 As shown, two elastic clamps 41 are formed on one side of the movable seat 4. A clamping space for clamping the vertical main reinforcement 6 of the cast-in-place foundation of the PC column is formed between the two elastic clamps. The elastic clamps can be adapted to vertical main reinforcements of various specifications and diameters.

[0036] The locking beam 5 is arranged opposite to the movable upper beam or the movable lower beam. Each movable upper beam and each movable lower beam is respectively provided with a locking beam. The movable upper beam 2 and the movable lower beam 3 are respectively detachably provided with the locking beam 5. The locking beam 5 is pressed against the side of the plurality of vertical main ribs 6 on the plurality of movable seats 4 away from the movable seats 4.

[0037] As a preferred embodiment, the transverse beam 12 is provided with a first screw rod 121. The first screw rod 121 is arranged along the length direction of the transverse beam 12. The movable upper beam 2 is connected with a base. The base is provided with a through hole. The first screw rod 121 can be movably inserted into the through hole. The first screw rod 121 is screwed with two positioning members. The two positioning members are respectively against opposite sides of the base.

[0038] In this embodiment, the longitudinal beam is provided with a second screw rod. The second screw rod is arranged along the length direction of the longitudinal beam. The movable lower beam is connected with a base. The base is provided with a through hole. The second screw rod can be movably inserted into the through hole. The second screw rod is screwed with two positioning members. The two positioning members are respectively against opposite sides of the base.

[0039] Continue reading Figure 2 As shown, the movable seat 4 is provided with a through hole. The movable upper beam 2 or the movable lower beam 3 can be movably inserted into the through hole. The movable seat 4 is provided with a threaded hole. The threaded hole is arranged on the other side of the movable seat 4. The threaded hole is connected to the through hole. A locking screw 42 is screwed into the threaded hole. The locking screw extends into the through hole and presses against the movable upper beam 2 or the movable lower beam 3.

[0040] Continue reading Figure 1 and Figure 3 As shown, the two ends of the movable upper beam 2 and the movable lower beam 3 are respectively connected with a pull rod 51. The two ends of the locking beam 5 are respectively provided with a locking hole. The pull rod 51 can be movably inserted into the locking hole. The end of the pull rod 51 is detachably mounted with a pressing member 52. The pressing member 52 presses against the side of the locking beam 5 away from the vertical main reinforcement 6.

[0041] The present invention provides a construction method of a PC column reinforcement positioning control device, comprising the following steps:

[0042] S1. Install the support frame 1 on the upper part of the cast-in-place foundation of the PC column.

[0043] S2. Adjust the positions of the two movable upper beams 2 and the two movable lower beams 3 so that the distance of the clamping spaces on the two movable upper beams 2 and the two movable lower beams 3 is adapted to the distance between the column reinforcements on the opposite sides of the PC column.

[0044] S3. Adjust the positions of the movable seats 4 on the movable upper beam 2 and the movable lower beam 3 so that the distance between the clamping spaces on two adjacent movable seats 4 is adapted to the distance between two adjacent column bars of the PC column.

[0045] S4. Embed multiple vertical main reinforcements 6 of the cast-in-place foundation in the clamping spaces of multiple movable seats 4 in a one-to-one correspondence.

[0046] S5, the locking beam 5 is detachably installed on the movable upper beam 2 and the movable lower beam 3, so that the locking beam 5 is pressed against the side of the multiple vertical main reinforcements 6 on the multiple movable seats 4 away from the movable seats 4.

[0047] The PC column reinforcement positioning control device of the present invention can be used for positioning PC columns with different cross-sectional sizes, different reinforcement specifications, reinforcement quantities, and reinforcement positions.

[0048] The PC column reinforcement positioning control device of the present invention mainly consists of three parts: a supporting frame, a movable upper beam, a movable lower beam, and a movable seat.

[0049] The support frame is an integral frame. The movable upper beam and the movable lower beam are bidirectional reinforcement positioning devices for the column, which can slide in both directions to fix a row of vertical main reinforcements in the same direction (the first horizontal direction or the second horizontal direction). The movable seat is a detailed adjustment device, which is suitable for micro-adjustment of the same row of reinforcements with different specifications.

[0050] After the steel bars of the cast-in-place foundation at the bottom of the PC component to be installed are tied (generally the first-floor columns), before pouring concrete, first straighten the PC column anchor steel bars above the pouring surface, and then install the PC column reinforcement positioning control device of the present invention (the anchoring length of the cast-in-place column steel bars and the PC column is generally about 20 cm, and the specific length is determined according to the steel bar specifications).

[0051] After the support frame is fixed, adjust the position of the movable upper beam, movable lower beam and movable seat. After the position of the vertical main reinforcement is fixed, pour the concrete, and after curing until the strength meets the requirements and the vertical main reinforcement basically does not deviate, the positioning device can be retracted and the mud can be cleaned for the next use.

[0052] The PC column reinforcement positioning control device of the present invention is installed on the upper part of the vertical main reinforcement. The positions of the movable upper beam and the movable lower beam are adjusted according to the cross-sectional size of the column and the spacing of the reinforcement bars. The position of the component movable seat is adjusted according to the specifications of the reinforcement bars. After the adjustment is completed, the device is fixed and concrete pouring is carried out.

[0053] After pouring concrete, the device can be recovered when the concrete strength meets the requirements. At this time, the position of the steel bars has been fixed, and the subsequent PC columns can be directly hoisted, avoiding the problem of the PC column and the lower bars being unable to connect due to the spacing and position of the steel bars.

[0054] The PC column reinforcement positioning control device of the present invention can protect the quality of the finished product of the vertical main reinforcement and avoid forced position adjustment due to the deviation of the vertical main reinforcement steel bars of the cast-in-place foundation and the inability to connect with the upper PC column.

[0055] The PC column reinforcement positioning control device of the present invention is suitable for PC column components with different cross-sectional sizes, different reinforcement specifications, quantities and positions, and can be repeatedly utilized.

[0056] The PC column reinforcement positioning control device of the present invention can be mass-produced and processed, and can be used in a turnover manner, with lower cost.

[0057] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the inventive concept. For example, the above features are replaced with (but not limited to) technical features with similar functions disclosed in the present application.

Claims

1. A PC column reinforcement positioning control device, characterized in that: include: A support frame, comprising four columns arranged in a matrix, two oppositely disposed transverse beams and two oppositely disposed longitudinal beams, wherein the transverse beams are connected between the two columns in a first horizontal direction, the longitudinal beams are connected between the two columns in a second horizontal direction, the second horizontal direction is perpendicular to the first horizontal direction, and the transverse beams are disposed above the longitudinal beams; Two movable upper beams are arranged in the same direction, and two ends of the movable upper beams can be respectively installed on the two transverse beams in an adjustable manner along the length direction of the transverse beam; Two movable lower beams are arranged in the same direction, and the two ends of the movable lower beams can be respectively installed on the two longitudinal beams in an adjustable manner along the length direction of the longitudinal beam; A plurality of movable seats, the movable upper beam and the movable lower beam are respectively installed with the plurality of movable seats in an adjustable manner, two elastic clamping plates are formed on one side of the movable seat, and a clamping space for clamping the vertical main reinforcement of the cast-in-place foundation of the PC column is formed between the two elastic clamping plates; The locking beam is detachably mounted on the movable upper beam and the movable lower beam, respectively, and the locking beam is pressed against a side of a plurality of vertical main ribs on the plurality of movable seats away from the movable seats.

2. The PC column reinforcement positioning control device according to claim 1 is characterized in that: A connecting beam is connected between the tops of the four columns.

3. The PC column reinforcement positioning control device according to claim 1 is characterized in that: The transverse beam is provided with a first screw rod, which is arranged along the length direction of the transverse beam. The movable upper beam is connected to a base, and the base is provided with a through hole. The first screw rod can be movably inserted into the through hole. The first screw rod is screwed with two positioning parts, and the two positioning parts are respectively against the opposite sides of the base.

4. The PC column reinforcement positioning control device according to claim 1, characterized in that: The movable seat is provided with a through hole, and the movable upper beam or the movable lower beam can be movably inserted into the through hole. The movable seat is provided with a threaded hole, and the threaded hole is arranged on the other side of the movable seat. The threaded hole is connected to the through hole, and a locking screw is threaded in the threaded hole. The locking screw extends into the through hole and presses against the movable upper beam or the movable lower beam.

5. The PC column reinforcement positioning control device according to claim 1, characterized in that: The two ends of the movable upper beam and the movable lower beam are respectively connected with pull rods, and the two ends of the locking beam are respectively provided with locking holes, and the pull rods can be movably inserted into the locking holes. The ends of the pull rods are detachably installed with pressing parts, and the pressing parts press against the side of the locking beam away from the vertical main reinforcement.

6. A construction method of the PC column reinforcement positioning control device according to any one of claims 1 to 5, characterized in that: The following steps are involved: Install the support frame on the upper part of the cast-in-place foundation of the PC column; Adjust the positions of the two movable upper beams and the two movable lower beams so that the distance of the clamping spaces on the two movable upper beams and the two movable lower beams is adapted to the distance between the column bars on the opposite sides of the PC column; Adjust the positions of the movable seats on the movable upper beam and the movable lower beam so that the distance between the clamping spaces on two adjacent movable seats is adapted to the distance between two adjacent column bars of the PC column; Multiple vertical main reinforcements of the cast-in-place foundation are embedded in the clamping spaces of multiple movable seats one by one; The locking beams are detachably mounted on the movable upper beam and the movable lower beam, respectively, so that the locking beams are pressed against a side of the plurality of vertical main ribs on the plurality of movable seats away from the movable seats.