Enterprise-level project version commissioning delivery process control method and device

By introducing a collaborative working mechanism and dynamically determining the general control manager and verification and review terminal in the enterprise-level project version commissioning and delivery process, the problems of timeliness and efficiency in the enterprise-level project version commissioning process are solved, and high quality and Efficient production and delivery.

CN119398699APending Publication Date: 2025-02-07CHINA CONSTRUCTION BANK +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411490778.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-24
Publication Date
2025-02-07

AI Technical Summary

Technical Problem

The enterprise-level project version production process is difficult to meet the timeliness requirements for branch version production, and the production inspection process is long, resulting in serious timeliness problems.

Method used

Provide an enterprise-level project version production and delivery process control method, through the coordinated work of the system manager terminal, the target production general control manager terminal, the PIO manager terminal, the project group terminal and the target verification and review terminal, it is determined based on whether the project involves the head office collaboration. The corresponding general control manager terminal and verification and review terminal should be optimized for the production and delivery process.

Benefits of technology

By optimizing the production and delivery process, it can take into account the high-quality delivery and timeliness requirements of enterprise-level project versions, improving the efficiency and effectiveness of the production process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119398699A_ABST
    Figure CN119398699A_ABST
Patent Text Reader

Abstract

The invention discloses an enterprise-level project version commissioning delivery process control method and device, relates to the technical field of version control and can also be used in the financial field, and the method comprises the steps that a system manager terminal responds to a created version plan, determines a corresponding target commissioning general control manager terminal according to a judgment result identifier, and sends the target commissioning general control manager terminal to a server; sending the version plan to a target commissioning general control manager terminal; in response to production base line information published by the target production general control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates delivery confirmation information according to the production base line information, and sends the delivery confirmation information to the PIO manager terminal; and the PIO manager terminal sends approved delivery confirmation information to the project group terminal, and the project group terminal uploads a target deliverable and sends the target deliverable to the target verification auditing terminal according to the judgment result identifier. According to the method and the device provided by the embodiment of the invention, high-quality delivery and production and timeliness can be considered.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of version control technology and can also be used in the financial field, and in particular to a method and device for controlling the production and delivery process of enterprise-level project versions. Background Art

[0002] Enterprise-level projects have their own unique characteristics, including:

[0003] High complexity: Enterprise-level projects often involve multiple sub-projects, each with its own unique goals, requirements, and challenges. These sub-projects require effective coordination and integration to ensure the overall success of the project. For example, a large software development project may include multiple phases such as requirements analysis, design, development, testing, and deployment, each of which requires different skills and resources.

[0004] Cross-departmental coordination is required: Enterprise-level project management requires coordination of the work of multiple departments and teams. Different departments may have different goals, priorities, and resource constraints. Establish a cross-departmental collaboration mechanism to promote communication and collaboration between departments by sharing tasks, progress, and resource information to ensure the consistency and achievement of project goals.

[0005] Difficulty in resource management: Enterprise-level projects usually require a large amount of resources, including human, financial and material resources. The rational allocation and effective use of resources are the key to project success. Through functions such as resource planning, allocation and scheduling, we can ensure the rational use and optimal configuration of resources.

[0006] High risk control requirements: Enterprise-level projects usually face high risks, including technical risks, market risks, financial risks, and management risks. Effective risk management is an important guarantee for project success. Through risk identification, assessment, and response functions, we can ensure the smooth progress of the project.

[0007] Clear goals: Each project is designed to achieve a specific, clear goal. This clarity helps allocate resources appropriately, ensuring that the project can be effectively promoted and ultimately achieve the established goals.

[0008] Time constraints: Almost every project has a clear deadline, which means that the project team needs to complete all work within a limited time. Effective time management is an important part of project management.

[0009] Uniqueness: Each project is unique, with specific goals, environments, people involved, technologies and methods used, etc. This uniqueness requires project managers to fully consider the specific circumstances of the project and adopt flexible and changeable management methods when managing the project.

[0010] Based on the characteristics of the above enterprise-level projects, the bank head office and branches (or subsidiaries) use a unified commissioning and delivery process, which leads to the following problems:

[0011] 1. The version launch process is difficult to meet the pace of branch version launch. With the diversity of corporate customer needs, branch systems are often faced with urgent or minor changes to the online demand, and the timeliness is often not met according to the head office version launch schedule.

[0012] Second, the production inspection process is relatively long. At present, the integrated version of the branch is reviewed by the head office, and the production inspection (non-functional, functional regression, security testing, installation testing, etc.) contains a lot of content, which further exacerbates the above-mentioned timeliness problem.

[0013] This section is intended to provide a background or context to the embodiments of the invention recited in the claims. No admission is made that the description herein is prior art by inclusion in this section. Summary of the invention

[0014] The embodiment of the present invention provides an enterprise-level project version production delivery process control method, which is applied to a system manager terminal, a target production general control manager terminal, a PIO manager terminal, a project team terminal and a target verification and review terminal; comprising:

[0015] The system manager terminal responds to the creation of a version plan for the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office;

[0016] In response to the production baseline information released by the target production control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier;

[0017] The PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's triggering action of locally executing uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable.

[0018] The target production general control manager terminal includes an enterprise-level production general control manager terminal, and the judgment result identifier includes a first judgment result identifier indicating that the project production involves the cooperation of the head office; accordingly, determining the corresponding target production general control manager terminal according to the judgment result identifier includes:

[0019] If it is determined that the judgment result identifier is the first judgment result identifier, it is determined that the target production general control manager terminal is an enterprise-level production general control manager terminal.

[0020] The target verification and review terminal includes an enterprise-level test center access review terminal; accordingly, the response project team terminal locally executes a triggering action of uploading a target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, including:

[0021] In response to the project team terminal executing a triggering action of uploading a target deliverable locally, the target deliverable is sent to the enterprise-level testing center access review terminal according to the first judgment result identifier.

[0022] Wherein, the target verification and audit terminal also includes an enterprise-level production verification and audit terminal; accordingly, the method also includes:

[0023] In response to the enterprise-level test center access review terminal's processing action of reviewing and approving the target deliverables, the approved target deliverables are sent to the enterprise-level production verification review terminal, so that the enterprise-level production verification review terminal can perform installation test review, functional regression test review and mobile APP review on the approved target deliverables.

[0024] Wherein, after the step of using the enterprise-level production verification and audit terminal to perform installation test audit, functional regression test audit and mobile APP audit on the target deliverables that have passed the audit, the method further includes:

[0025] In response to the enterprise-level production verification review terminal, the installation test review, functional regression test review and mobile APP review are carried out on the target deliverables that have passed the review, and the sub-item review results are fed back to the enterprise-level production general control manager terminal. If the enterprise-level production general control manager terminal determines that all the reviews have passed, the version package of the enterprise-level project version for production delivery will be pushed to the transit machine.

[0026] Wherein, the target production general control manager terminal includes a branch production general control manager terminal, and the judgment result identifier includes a second judgment result identifier indicating that the project production does not involve the cooperation of the head office; accordingly, determining the corresponding target production general control manager terminal according to the judgment result identifier includes:

[0027] If it is determined that the judgment result identifier is the second judgment result identifier, the target production general control manager terminal is determined to be the branch production general control manager terminal.

[0028] The target verification and review terminal includes a branch version verification manager terminal; accordingly, the response project team terminal locally executes a triggering action of uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, including:

[0029] In response to the project team terminal executing a triggering action of uploading a target deliverable locally, the target deliverable is sent to the branch version verification manager terminal according to the second judgment result identifier.

[0030] Wherein, the method further comprises:

[0031] In response to the branch version verification manager terminal, the manager terminal performs non-functional inspection review, security test inspection, installation test review, and functional regression test review on the target deliverable. If it is determined that all the reviews have passed, a first review result indicating that all the reviews have passed is sent to the branch production general control manager terminal, so that the branch production general control manager terminal can make a production decision based on the first review result.

[0032] The embodiment of the present invention further provides an enterprise-level project version production delivery process control device, which is applied to a system manager terminal, a target production general control manager terminal, a PIO manager terminal, a project team terminal, and a target verification and review terminal; comprising:

[0033] The system manager terminal responds to the creation of a version plan for the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office;

[0034] In response to the production baseline information released by the target production control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier;

[0035] The PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's triggering action of locally executing uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable.

[0036] The target production control manager terminal includes an enterprise-level production control manager terminal, and the judgment result identifier includes a first judgment result identifier indicating that the project production involves the cooperation of the head office; accordingly, the system manager terminal is specifically used for:

[0037] If it is determined that the judgment result identifier is the first judgment result identifier, it is determined that the target production general control manager terminal is an enterprise-level production general control manager terminal.

[0038] Wherein, the target verification and audit terminal includes an enterprise-level test center access and audit terminal; accordingly, the project team terminal is specifically used for:

[0039] In response to the project team terminal executing a triggering action of uploading a target deliverable locally, the target deliverable is sent to the enterprise-level testing center access review terminal according to the first judgment result identifier.

[0040] Wherein, the target verification and audit terminal also includes an enterprise-level production verification and audit terminal; accordingly, the device is also used for:

[0041] In response to the enterprise-level test center access review terminal's processing action of reviewing and approving the target deliverables, the approved target deliverables are sent to the enterprise-level production verification review terminal, so that the enterprise-level production verification review terminal can perform installation test review, functional regression test review and mobile APP review on the approved target deliverables.

[0042] An embodiment of the present invention further provides a computer device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the following method when executing the computer program:

[0043] The system manager terminal responds to the creation of a version plan for the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office;

[0044] In response to the production baseline information released by the target production control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier;

[0045] The PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's triggering action of locally executing uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable.

[0046] An embodiment of the present invention further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the following method is implemented:

[0047] The system manager terminal responds to the creation of a version plan for the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office;

[0048] In response to the production baseline information released by the target production control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier;

[0049] The PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's triggering action of locally executing uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable.

[0050] The embodiment of the present invention further provides a computer program product, the computer program product comprising a computer program, and when the computer program is executed by a processor, the following method is implemented:

[0051] The system manager terminal responds to the creation of a version plan for the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office;

[0052] In response to the production baseline information released by the target production control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier;

[0053] The PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's triggering action of locally executing uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable.

[0054] The enterprise-level project version production delivery process control method and device provided by the embodiment of the present invention, the system manager terminal responds to the version plan of the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes the judgment result identifier indicating whether the project production involves the cooperation of the head office; in response to the production baseline information released by the target production general control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier; the PIO manager terminal responds to the action of reviewing the confirmation delivery information, sends the reviewed confirmation delivery information to the project team terminal, responds to the project team terminal locally executing the trigger action of uploading the target deliverable, sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable, and provides different version production delivery processes according to whether the project production involves the cooperation of the head office, which can simultaneously take into account the high-quality delivery and production of the enterprise-level project version and timeliness. BRIEF DESCRIPTION OF THE DRAWINGS

[0055] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the prior art descriptions. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:

[0056] Figure 1 A flow chart of a method for controlling the production and delivery process of an enterprise-level project version provided by an embodiment of the present invention;

[0057] Figure 2 A flowchart of a method for controlling the production and delivery process of an enterprise-level project version provided by another embodiment of the present invention;

[0058] Figure 3 A flowchart of a method for controlling the production and delivery process of an enterprise-level project version provided by another embodiment of the present invention;

[0059] Figure 4 It is a structural diagram of an enterprise-level project version production delivery process control device provided by an embodiment of the present invention.

[0060] Figure 5 A schematic diagram of the physical structure of an electronic device provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0061] To make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the embodiments of the present invention are further described in detail below in conjunction with the accompanying drawings. Here, the exemplary embodiments of the present invention and their descriptions are used to explain the present invention, but are not intended to limit the present invention.

[0062] The information collected in the technical solution of this application is information and data authorized by the user or fully authorized by all parties, and the collection, storage, use, processing, transmission, provision, disclosure and application of relevant data comply with the relevant laws, regulations and standards of relevant countries and regions, take necessary confidentiality measures, do not violate public order and good morals, and provide corresponding operation entrances for users to choose to authorize or refuse.

[0063] The acquisition, transmission, storage, use, and processing of data in the technical solution of this application comply with the relevant provisions of national laws and regulations.

[0064] It should be noted that in the embodiments of the present application, certain software, components, models and other existing solutions in the industry may be mentioned, and they should be regarded as exemplary. Their purpose is only to illustrate the feasibility of implementing the technical solution of the present application, but it does not mean that the applicant has or will necessarily use the solution.

[0065] Explanation of related terms:

[0066] Commissioning management: refers to the process of applying specialized knowledge, skills, tools and methods in project commissioning activities to enable project commissioning to achieve or exceed the set commissioning requirements and expectations under the conditions of limited resources.

[0067] Production system: The physical machine where the requirements of enterprise-level projects are put into production.

[0068] Logical system: Logical division of production systems according to enterprise application architecture specifications.

[0069] Version plan: refers to the production plan for the coordinated production of one or more tasks.

[0070] Baseline plan: refers to the version packages and related information of the version packages that need to be deployed online in the system to be put into production.

[0071] Production baseline: refers to the production scope (including requirements, functions and systems) and the coordinated correspondence.

[0072] Production baseline release: Review of the version plan established for the production of the demand item, including implementation management approval, user test approval, grayscale release plan, OA approval verification, etc. If it meets the requirements of the head office's production management, the baseline release will be approved, otherwise it will be rejected and rectified again.

[0073] Delivery access: The version packages and deliverables delivered by the project team are reviewed for access, including version delivery access review, security access review, and non-functional access review. If the delivery access review is passed, the production inspection review will be carried out.

[0074] Production inspection and review: The version package delivered by the project team is reviewed for production, including non-functional inspection, functional regression inspection, safety test inspection, installation test inspection, etc. If the production inspection and review is passed, the production decision will be made.

[0075] Production decision: Review the decision on whether the demand item will be finally put into production. If the decision is passed, the corresponding version package will be pushed to the production transit machine.

[0076] Project team: refers to the team composed of implementation personnel involved in project commissioning activities. The commissioning of a project usually requires the joint efforts of multiple execution teams.

[0077] Figure 1 FIG. 1 is a flow chart of a method for controlling the production delivery process of an enterprise-level project version provided by an embodiment of the present invention. Figure 1 As shown, an enterprise-level project version production delivery process control method provided by an embodiment of the present invention is applied to a system manager terminal, a target production general control manager terminal, a PIO manager terminal, a project team terminal and a target verification and review terminal, and includes:

[0078] Step S1: The system manager terminal responds to the creation of a version plan for an enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office.

[0079] Step S2: In response to the production baseline information released by the target production general control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier.

[0080] Step S3: The PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's triggering action of locally executing uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable.

[0081] In the above step S1, the device system manager terminal responds to the creation of a version plan for the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office. The device can be a computer device that executes the method.

[0082] The following is an explanation of the version launch:

[0083] Release into production means moving a version of a software or project from the development stage to the production environment, making it available to users.

[0084] Production is a process that involves a version of a software or project entering the production environment after development, testing and verification for user use. This process includes deploying the software or project to the actual production environment to ensure that it functions properly, has stable performance, and can meet user needs. The production process may involve updating both the server and the client to ensure compatibility and stability between the old and new versions. In addition, production also includes verification of the existing production version to ensure that there are no problems with the updated version, ensuring user experience and service quality.

[0085] The purpose of production is to make the functions of the software or project available to the majority of users, and it is also a test of the project development results. Through production, user feedback can be collected to further optimize and improve the product, and improve user experience and satisfaction. Therefore, production is not only a technical operation, but also an important bridge between the product and the user.

[0086] The overall idea of ​​the existing enterprise-level project version commissioning and delivery process is that for all enterprise-level projects, the branch commissioning general control manager needs to operate the branch commissioning general control manager terminal to release the commissioning baseline, and then the enterprise-level commissioning general control manager operates the enterprise-level commissioning general control manager terminal to review the commissioning baseline, and then push it to the next process node. After that, the branch version verification manager operates the branch version verification manager terminal to implement version verification review, and then multi-level reviewers re-review the above-reviewed version, and finally the enterprise-level commissioning general control manager operates the enterprise-level commissioning general control manager terminal to confirm the review results of the multi-level reviewers.

[0087] In the case where the project commissioning involves the cooperation of the head office, the present invention no longer requires the branch commissioning general control manager and the branch version verification manager to perform operations and processing.

[0088] In the case where the project commissioning does not involve the coordination of the head office, the present invention no longer requires an enterprise-level commissioning general control manager and multi-level auditors to perform operations and processing.

[0089] For projects that involve the coordination of the head office, such as Figure 2 As shown, the enterprise-level production control manager operates the enterprise-level production control manager terminal to set the production point, that is, to set the basic content framework information that needs to be put into production, and send the production point to the system manager terminal. The system manager operates the system manager terminal to create a daily version plan and a rapid emergency version plan. The version plan includes a judgment result identifier indicating whether the project production involves the coordination of the head office. The judgment result identifier includes a first judgment result identifier indicating that the project production involves the coordination of the head office, which can be recorded as 1. Whether the project production involves the coordination of the head office can be determined through the production baseline information. The production baseline information is first explained as follows:

[0090] The production baseline information is information about the production baseline created by the user on the IT management platform for the production of the application system.

[0091] The production baseline information may include attribute information on one or more production attributes. The production attributes here may include: physical subsystem name attribute, logical subsystem name attribute, production date attribute, production version type attribute, production-related requirement item attribute (or production-related development task attribute), planned production time attribute, production business impact attribute, production business impact scope attribute, and any one or more of the production collaborative system attributes.

[0092] For example, the production baseline information of an application system may include the name of the physical subsystem, the name of the logical subsystem to which it belongs, the production date, version type, associated development tasks, associated requirements, planned production time, business impact, business impact scope, collaborative system and other information.

[0093] By analyzing the production baseline information, we can get the logical relationship between the physical subsystem and the logical subsystem, and then determine whether the production system and coordination system of the baseline of the demand item production involve the head office system based on the above logical relationship. As long as a demand item production requires the head office system, it means that the current enterprise-level project production involves the head office coordination. If all demand items do not require the head office system, it means that the current enterprise-level project production does not involve the head office coordination.

[0094] In the above step S2, the device responds to the production baseline information released by the target production control manager terminal to the system manager terminal according to the version plan, and the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier. The target production control manager terminal includes an enterprise-level production control manager terminal, and the judgment result identifier includes a first judgment result identifier indicating that the project production involves the cooperation of the head office; accordingly, the determination of the corresponding target production control manager terminal according to the judgment result identifier includes:

[0095] If it is determined that the judgment result identifier is the first judgment result identifier, the target production general control manager terminal is determined to be the enterprise-level production general control manager terminal, and then the version plan is sent to the enterprise-level production general control manager terminal. The enterprise-level production general control manager operates the enterprise-level production general control manager terminal to review the production baseline "involving head office collaboration", including reviewing the implementation management approval and user test results and publishing the baseline.

[0096] PIO managers play an important role in project management. They integrate project management activities and coordinate various aspects of the project to ensure the smooth progress of the project and the achievement of project goals. The main responsibilities of PIO managers include:

[0097] Project Integration Planning: Responsible for developing and managing the overall project plan to ensure consistency and interrelationship in terms of project scope, schedule, cost, quality, risk, etc.

[0098] Project process management: formulate and optimize project management processes to ensure the smooth progress of each stage of the project, coordinate cooperation between departments and teams, and promote the overall progress of the project.

[0099] Project performance management: Establish project performance indicators, manage project performance through monitoring, reporting and evaluation, and regularly report on project progress, including project deviations, problems, risks, etc.

[0100] Project Decision Support: Provide support for project decisions, including decisions on project evaluation, prioritization, resource allocation, etc., and provide opinions and suggestions to project managers and relevant stakeholders.

[0101] Project knowledge management: Responsible for collecting, organizing and disseminating the best practices of project management, establishing a project knowledge base, and ensuring the accumulation and inheritance of project experience and knowledge.

[0102] In addition, the PIO manager needs to be familiar with the business operations of each department of the company and the specific implementation of their business in the project, and provide relevant support and cooperate with other departments to ensure the smooth development of work. This position usually requires rich project management experience and expertise to ensure that the project can be delivered on time and achieve the expected goals.

[0103] The system manager operates the system manager terminal to create baseline plans for the daily version and the rapid emergency version based on the production baseline information, confirms the mechanical plan, generates confirmation delivery information in the form of a version package, and then sends the confirmation delivery information to the PIO manager terminal.

[0104] In the above step S3, the device PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's trigger action of locally executing the upload of the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable. The PIO manager operates the PIO manager terminal to review the confirmed delivery information, and sends the reviewed confirmed delivery information to the project team terminal. The project team leader operates the project team terminal to locally upload the target deliverable, and the target deliverable includes version delivery assets, security delivery assets, and non-functional delivery assets.

[0105] The target verification and review terminal includes an enterprise-level test center access review terminal; accordingly, the response project team terminal locally executes a triggering action of uploading a target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, including:

[0106] In response to the project team terminal executing a triggering action of uploading a target deliverable locally, the target deliverable is sent to the enterprise-level testing center access review terminal according to the first judgment result identifier.

[0107] The target verification and audit terminal also includes an enterprise-level production verification and audit terminal; accordingly, the method also includes:

[0108] In response to the enterprise-level test center access review terminal's processing action of reviewing and approving the target deliverables, the approved target deliverables are sent to the enterprise-level production verification review terminal, so that the enterprise-level production verification review terminal can perform installation test review, functional regression test review and mobile APP review on the approved target deliverables.

[0109] After the step of using the enterprise-level production verification and audit terminal to perform installation test audit, functional regression test audit and mobile APP audit on the target deliverables that have passed the audit, the method further includes:

[0110] In response to the enterprise-level production verification review terminal, the installation test review, functional regression test review and mobile APP review are carried out on the target deliverables that have passed the review, and the sub-item review results are fed back to the enterprise-level production general control manager terminal. If the enterprise-level production general control manager terminal determines that all the reviews have passed, the version package of the enterprise-level project version for production delivery will be pushed to the transit machine.

[0111] The enterprise-level version delivery access reviewer, non-functional access reviewer and security access reviewer shall respectively operate the enterprise-level testing center access review terminal to conduct version delivery access review, non-functional access review and security access review on the target deliverables "involving head office collaboration" respectively.

[0112] After all three access audits are passed, the enterprise-level installation test auditor, functional regression test auditor, and mobile APP auditor will respectively operate the enterprise-level production verification audit terminal to conduct installation test audits, functional regression test audits, and mobile APP audits on the target deliverables that have passed the audit of "involving head office collaboration". Feedback the sub-item audit results, that is, the three audit results, to the enterprise-level production general control manager terminal. If all three production inspection audits are passed, the production decision is automatically reviewed and passed, and the version package is sent to the transfer machine. If all three production inspection audits are not passed, wait for the enterprise-level production general control manager to conduct manual review to make a production decision. If the production decision is to allow production, the version package is sent to the transfer machine; if the production decision is to refuse production, the corresponding reason information and reasons need to be given.

[0113] If all three access audits are not passed, the enterprise-level testing center access audit terminal will feedback the access exception notification message to the project team terminal for the project team terminal to conduct exception impact analysis, re-supplement the above target deliverables, and resubmit new target deliverables to the enterprise-level testing center access audit terminal for the enterprise-level testing center access auditor to re-operate the enterprise-level testing center access audit terminal for review.

[0114] For projects that do not involve the coordination of the head office, such as Figure 3 As shown, the system manager operates the system manager terminal to create daily version plans and rapid emergency version plans. The version plan includes a judgment result identifier indicating whether the project commissioning involves the cooperation of the head office. The judgment result identifier includes a second judgment result identifier indicating that the project commissioning does not involve the cooperation of the head office, which can be recorded as 0. Whether the project commissioning involves the cooperation of the head office can be determined through the commissioning baseline information. The specific implementation can refer to the above description and will not be repeated here.

[0115] The target production control manager terminal includes a branch production control manager terminal, and the judgment result identifier includes a second judgment result identifier indicating that the project production does not involve the cooperation of the head office; accordingly, determining the corresponding target production control manager terminal according to the judgment result identifier includes:

[0116] If it is determined that the judgment result identifier is the second judgment result identifier, the target production general control manager terminal is determined to be the branch production general control manager terminal, and then the version plan is sent to the branch production general control manager terminal. The branch production general control manager operates the branch production general control manager terminal to review the production baseline that "does not involve head office collaboration", including reviewing the implementation management approval and user test results and publishing the baseline.

[0117] The system manager operates the system manager terminal to create baseline plans for the daily version and the rapid emergency version based on the production baseline information, confirms the mechanical plan, generates confirmation delivery information in the form of a version package, and then sends the confirmation delivery information to the PIO manager terminal.

[0118] The PIO manager operates the PIO manager terminal to review the confirmed delivery information and sends the reviewed confirmed delivery information to the project team terminal. The project team leader operates the project team terminal to upload the target deliverables locally, which include version delivery assets, security delivery assets, and non-functional delivery assets.

[0119] The target verification and review terminal includes a branch version verification manager terminal; accordingly, the response project team terminal locally executes a triggering action of uploading a target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, including:

[0120] In response to the project team terminal executing a triggering action of uploading a target deliverable locally, the target deliverable is sent to the branch version verification manager terminal according to the second judgment result identifier.

[0121] The method further comprises:

[0122] In response to the branch version verification manager terminal, the manager terminal performs non-functional inspection review, security test inspection, installation test review, and functional regression test review on the target deliverable. If it is determined that all the reviews have passed, a first review result indicating that all the reviews have passed is sent to the branch production general control manager terminal, so that the branch production general control manager terminal can make a production decision based on the first review result.

[0123] The branch version verification manager operates the branch version verification manager terminal to conduct non-functional inspection and review, security test inspection, installation test review and functional regression test review on the target deliverables that "do not involve head office collaboration". If the four production inspections are reviewed and approved, the first review result will be sent to the branch production general control manager terminal, so that the branch production general control manager terminal can make a production decision based on the first review result. At this time, the production decision is automatically reviewed and approved, and the version package is sent to the transfer machine. If not all of the four production inspections are reviewed and approved, the second review result indicating that not all of the reviews have passed will be sent to the branch production general control manager terminal, so that the branch production general control manager can operate the branch production general control manager terminal to realize manual review.

[0124] The enterprise-level project version production delivery process control method provided by the embodiment of the present invention comprises: a system manager terminal responds to the creation of a version plan of the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes the judgment result identifier indicating whether the project production involves the coordination of the head office; in response to the production baseline information released by the target production general control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier; the PIO manager terminal responds to the action of reviewing the confirmation delivery information, sends the reviewed confirmation delivery information to the project team terminal, responds to the project team terminal executing the trigger action of uploading the target deliverable locally, sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable, and provides different version production delivery processes according to whether the project production involves the coordination of the head office, which can simultaneously take into account the high-quality delivery and production of the enterprise-level project version and timeliness.

[0125] Further, the target production general control manager terminal includes an enterprise-level production general control manager terminal, and the judgment result identifier includes a first judgment result identifier indicating that the project production involves the cooperation of the head office; accordingly, determining the corresponding target production general control manager terminal according to the judgment result identifier includes:

[0126] If it is determined that the judgment result identifier is the first judgment result identifier, the target production general control manager terminal is determined to be an enterprise-level production general control manager terminal.

[0127] The enterprise-level project version production delivery process control method provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version involved in the project production in cooperation with the head office through the enterprise-level production general control manager terminal.

[0128] Further, the target verification and review terminal includes an enterprise-level test center access review terminal; accordingly, the response project team terminal locally executes a triggering action of uploading a target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, including:

[0129] In response to the project team terminal executing a trigger action of uploading the target deliverable locally, the target deliverable is sent to the enterprise-level test center access review terminal according to the first judgment result identifier.

[0130] The enterprise-level project version production delivery process control method provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version involved in the project production in collaboration with the head office through the enterprise-level test center access review terminal.

[0131] Furthermore, the target verification and audit terminal also includes an enterprise-level production verification and audit terminal; accordingly, the method further includes:

[0132] In response to the processing action of the enterprise-level test center access audit terminal for the target deliverable to pass the audit, the target deliverable that has passed the audit is sent to the enterprise-level production verification audit terminal, so that the enterprise-level production verification audit terminal can perform installation test audit, functional regression test audit and mobile APP audit on the target deliverable that has passed the audit. Please refer to the above embodiment for description, and no further details will be given.

[0133] The enterprise-level project version production delivery process control method provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version involved in the project production in collaboration with the head office through the enterprise-level test center access review terminal.

[0134] Furthermore, after the step of using the enterprise-level production verification and audit terminal to perform installation test audit, functional regression test audit and mobile APP audit on the target deliverables that have passed the audit, the method further includes:

[0135] The enterprise-level production verification and audit terminal responds to the target deliverables that have passed the audit by performing installation test audit, functional regression test audit and mobile APP audit, and feedbacks the sub-item audit results to the enterprise-level production general control manager terminal. If the enterprise-level production general control manager terminal determines that all audits have passed, the version package of the enterprise-level project version delivered for production is pushed to the transfer machine. Please refer to the above embodiment for description, and no further details will be given.

[0136] The enterprise-level project version production delivery process control method provided by the embodiment of the present invention processes the project version involved in the project production and the head office collaboration through the enterprise-level production verification and review terminal and the enterprise-level production general control manager terminal, thereby optimizing the production delivery process control.

[0137] Further, the target production general control manager terminal includes a branch production general control manager terminal, and the judgment result identifier includes a second judgment result identifier indicating that the project production does not involve the cooperation of the head office; accordingly, determining the corresponding target production general control manager terminal according to the judgment result identifier includes:

[0138] If it is determined that the judgment result identifier is the second judgment result identifier, the target production control manager terminal is determined to be the branch production control manager terminal.

[0139] The enterprise-level project version production delivery process control method provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version that does not involve the cooperation of the head office through the branch production control manager terminal.

[0140] Further, the target verification and review terminal includes a branch version verification manager terminal; accordingly, the response project team terminal locally executes a triggering action of uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, including:

[0141] In response to the project team terminal executing a trigger action of uploading the target deliverable locally, the target deliverable is sent to the branch version verification manager terminal according to the second judgment result identifier.

[0142] The enterprise-level project version production delivery process control method provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version that does not involve the cooperation of the head office through the branch version verification manager terminal.

[0143] Furthermore, the method further comprises:

[0144] In response to the branch version verification manager terminal, the target deliverable is audited for non-functional inspection, security testing, installation testing, and functional regression testing. If all audits are passed, the first audit result indicating that all audits have passed is sent to the branch production control manager terminal, so that the branch production control manager terminal can make a production decision based on the first audit result. The above-mentioned embodiment can be referred to for explanation and will not be repeated here.

[0145] The enterprise-level project version production delivery process control method provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version that does not involve the cooperation of the head office through the branch production control manager terminal.

[0146] It should be noted that the enterprise-level project version production delivery process control method provided by the embodiment of the present invention can be used in the financial field, and can also be used in any technical field other than the financial field. The embodiment of the present invention does not limit the application field of the enterprise-level project version production delivery process control method.

[0147] The embodiment of the present invention also provides an enterprise-level project version production delivery process control device, as described in the following embodiment. Since the principle of solving the problem by the device is similar to the enterprise-level project version production delivery process control method, the implementation of the device can refer to the implementation of the enterprise-level project version production delivery process control method, and the repeated parts will not be repeated.

[0148] Figure 4is a schematic diagram of the structure of an enterprise-level project version production delivery process control device provided by an embodiment of the present invention, such as Figure 4 As shown, the enterprise-level project version production delivery process control device provided by the embodiment of the present invention includes a system manager terminal 401, a target production general control manager terminal 402, a PIO manager terminal 403, a project team terminal 404 and a target verification and review terminal 405, wherein:

[0149] The system manager terminal 401 responds to the version plan of the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal 402 according to the judgment result identifier, and sends the version plan to the target production general control manager terminal 402; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office;

[0150] In response to the production baseline information released by the target production general control manager terminal 402 to the system manager terminal 401 according to the version plan, the system manager terminal 401 generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal 403; the confirmation delivery information carries the judgment result identifier;

[0151] The PIO manager terminal 403 responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal 404, responds to the project team terminal 404 executing a trigger action of uploading the target deliverable locally, and sends the target deliverable to the target verification and review terminal 405 according to the judgment result identifier, so that the target verification and review terminal 405 verifies and reviews the target deliverable.

[0152] Specifically, the system manager terminal 401 in the device responds to the version plan of the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal 402 according to the judgment result identifier, and sends the version plan to the target production general control manager terminal 402; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office;

[0153] In response to the production baseline information released by the target production general control manager terminal 402 to the system manager terminal 401 according to the version plan, the system manager terminal 401 generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal 403; the confirmation delivery information carries the judgment result identifier;

[0154] The PIO manager terminal 403 responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal 404, responds to the project team terminal 404 executing a trigger action of uploading the target deliverable locally, and sends the target deliverable to the target verification and review terminal 405 according to the judgment result identifier, so that the target verification and review terminal 405 verifies and reviews the target deliverable.

[0155] In the control device for the production and delivery process of enterprise-level project versions provided by the embodiment of the present invention, the system manager terminal responds to the creation of a version plan of the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the coordination of the head office; in response to the production baseline information released by the target production general control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier; the PIO manager terminal responds to the action of reviewing the confirmation delivery information, sends the reviewed confirmation delivery information to the project team terminal, responds to the project team terminal executing the trigger action of uploading the target deliverable locally, sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable, and provides different version production and delivery processes according to whether the project production involves the coordination of the head office, which can simultaneously take into account the high-quality delivery and production of the enterprise-level project version and timeliness.

[0156] Furthermore, the target production control manager terminal 402 includes an enterprise-level production control manager terminal, and the judgment result identifier includes a first judgment result identifier indicating that the project production involves the cooperation of the head office; accordingly, the system manager terminal 401 is specifically used for:

[0157] If it is determined that the judgment result identifier is the first judgment result identifier, it is determined that the target production general control manager terminal 402 is an enterprise-level production general control manager terminal.

[0158] The enterprise-level project version production delivery process control device provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version involved in the project production and the head office collaboration through the enterprise-level production general control manager terminal.

[0159] Furthermore, the target verification and audit terminal 405 includes an enterprise-level test center access and audit terminal; accordingly, the project team terminal 404 is specifically used for:

[0160] In response to the project team terminal 404 executing a triggering action of uploading a target deliverable locally, the target deliverable is sent to the enterprise-level testing center access review terminal according to the first judgment result identifier.

[0161] The enterprise-level project version production delivery process control device provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version involving the head office collaboration in the project production through the enterprise-level test center access review terminal.

[0162] Furthermore, the target verification and audit terminal 405 also includes an enterprise-level production verification and audit terminal; accordingly, the device is also used for:

[0163] In response to the enterprise-level test center access review terminal's processing action of reviewing and approving the target deliverables, the approved target deliverables are sent to the enterprise-level production verification review terminal, so that the enterprise-level production verification review terminal can perform installation test review, functional regression test review and mobile APP review on the approved target deliverables.

[0164] The enterprise-level project version production delivery process control device provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version involving the head office collaboration in the project production through the enterprise-level test center access review terminal.

[0165] Furthermore, after the step of enabling the enterprise-level production verification and audit terminal to perform installation test audit, functional regression test audit and mobile APP audit on the target deliverables that have passed the audit, the device is also used to:

[0166] In response to the enterprise-level production verification review terminal, the installation test review, functional regression test review and mobile APP review are carried out on the target deliverables that have passed the review, and the sub-item review results are fed back to the enterprise-level production general control manager terminal. If the enterprise-level production general control manager terminal determines that all the reviews have passed, the version package of the enterprise-level project version for production delivery will be pushed to the transit machine.

[0167] The enterprise-level project version production delivery process control device provided by the embodiment of the present invention processes the project version involved in the project production and the head office collaboration through the enterprise-level production verification and review terminal and the enterprise-level production general control manager terminal, and can optimize the production delivery process control.

[0168] Furthermore, the target production control manager terminal 402 includes a branch production control manager terminal, and the judgment result identifier includes a second judgment result identifier indicating that the project production does not involve the cooperation of the head office; accordingly, the system manager terminal 401 is specifically used for:

[0169] If it is determined that the judgment result identifier is the second judgment result identifier, the target production general control manager terminal 402 is determined to be the branch production general control manager terminal.

[0170] The enterprise-level project version production delivery process control device provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version that does not involve the cooperation of the head office through the branch production control manager terminal.

[0171] Furthermore, the target verification and audit terminal 405 includes a branch version verification manager terminal; accordingly, the project team terminal 404 is specifically used for:

[0172] In response to the project team terminal 404 executing a triggering action of uploading the target deliverable locally, the target deliverable is sent to the branch version verification manager terminal according to the second judgment result identifier.

[0173] The enterprise-level project version production delivery process control device provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version that does not involve the cooperation of the head office through the branch version verification manager terminal.

[0174] Furthermore, the device is also used for:

[0175] In response to the branch version verification manager terminal, the manager terminal performs non-functional inspection review, security test inspection, installation test review, and functional regression test review on the target deliverable. If it is determined that all the reviews have passed, a first review result indicating that all the reviews have passed is sent to the branch production general control manager terminal, so that the branch production general control manager terminal can make a production decision based on the first review result.

[0176] The enterprise-level project version production delivery process control device provided by the embodiment of the present invention can optimize the production delivery process control by processing the project version that does not involve the cooperation of the head office through the branch production control manager terminal.

[0177] Figure 5 A schematic diagram of the physical structure of an electronic device provided in an embodiment of the present invention, such as Figure 5 As shown, the electronic device includes: a processor (processor) 501, a memory (memory) 502 and a bus 503.

[0178] The processor 501 and the memory 502 communicate with each other via a bus 503 .

[0179] The processor 501 is used to call the program instructions in the memory 502 to execute the methods provided by the above method embodiments, for example, including:

[0180] The system manager terminal responds to the creation of a version plan for the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office;

[0181] In response to the production baseline information released by the target production control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier;

[0182] The PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's triggering action of locally executing uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable.

[0183] The embodiment of the present invention further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the above method is implemented, for example, including:

[0184] The system manager terminal responds to the creation of a version plan for the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office;

[0185] In response to the production baseline information released by the target production control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier;

[0186] The PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's triggering action of locally executing uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable.

[0187] The embodiment of the present invention further provides a computer program product, the computer program product comprising a computer program, and the computer program implements the above method when executed by a processor, for example, comprising:

[0188] The system manager terminal responds to the creation of a version plan for the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office;

[0189] In response to the production baseline information released by the target production control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier;

[0190] The PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's triggering action of locally executing uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable.

[0191] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0192] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0193] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0194] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0195] The specific embodiments described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific embodiment of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A method for controlling the production delivery process of an enterprise-level project version, characterized in that: The method is applied to a system manager terminal, a target production control manager terminal, a PIO manager terminal, a project team terminal and a target verification and audit terminal; and includes: The system manager terminal responds to the creation of a version plan for the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office; In response to the production baseline information released by the target production control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier; The PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's triggering action of locally executing uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable.

2. The method according to claim 1, characterized in that The target production general control manager terminal includes an enterprise-level production general control manager terminal, and the judgment result identifier includes a first judgment result identifier indicating that the project production involves the cooperation of the head office; accordingly, determining the corresponding target production general control manager terminal according to the judgment result identifier includes: If it is determined that the judgment result identifier is the first judgment result identifier, it is determined that the target production general control manager terminal is an enterprise-level production general control manager terminal.

3. The method according to claim 2, characterized in that The target verification and review terminal includes an enterprise-level test center access review terminal; accordingly, the response project team terminal locally executes a triggering action of uploading a target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, including: In response to the project team terminal executing a triggering action of uploading a target deliverable locally, the target deliverable is sent to the enterprise-level testing center access review terminal according to the first judgment result identifier.

4. The method according to claim 3, characterized in that The target verification and audit terminal also includes an enterprise-level production verification and audit terminal; accordingly, the method also includes: In response to the enterprise-level test center access review terminal's processing action of reviewing and approving the target deliverables, the approved target deliverables are sent to the enterprise-level production verification review terminal, so that the enterprise-level production verification review terminal can perform installation test review, functional regression test review and mobile APP review on the approved target deliverables.

5. The method according to claim 4, characterized in that After the step of using the enterprise-level production verification and audit terminal to perform installation test audit, functional regression test audit and mobile APP audit on the target deliverables that have passed the audit, the method further includes: In response to the enterprise-level production verification review terminal, the installation test review, functional regression test review and mobile APP review are carried out on the target deliverables that have passed the review, and the sub-item review results are fed back to the enterprise-level production general control manager terminal. If the enterprise-level production general control manager terminal determines that all the reviews have passed, the version package of the enterprise-level project version for production delivery will be pushed to the transit machine.

6. The method according to any one of claims 1 to 5, characterized in that: The target production control manager terminal includes a branch production control manager terminal, and the judgment result identifier includes a second judgment result identifier indicating that the project production does not involve the cooperation of the head office; accordingly, determining the corresponding target production control manager terminal according to the judgment result identifier includes: If it is determined that the judgment result identifier is the second judgment result identifier, the target production general control manager terminal is determined to be the branch production general control manager terminal.

7. The method according to claim 6, characterized in that The target verification and review terminal includes a branch version verification manager terminal; accordingly, the response project team terminal locally executes a triggering action of uploading a target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, including: In response to the project team terminal executing a triggering action of uploading a target deliverable locally, the target deliverable is sent to the branch version verification manager terminal according to the second judgment result identifier.

8. The method according to claim 7, characterized in that The method further comprises: In response to the branch version verification manager terminal, the manager terminal performs non-functional inspection review, security test inspection, installation test review, and functional regression test review on the target deliverable. If it is determined that all the reviews have passed, a first review result indicating that all the reviews have passed is sent to the branch production general control manager terminal, so that the branch production general control manager terminal can make a production decision based on the first review result.

9. An enterprise-level project version production delivery process control device, characterized in that: The device is applied to a system manager terminal, a target production control manager terminal, a PIO manager terminal, a project team terminal and a target verification and audit terminal; and includes: The system manager terminal responds to the creation of a version plan for the enterprise-level project to be put into production, determines the corresponding target production general control manager terminal according to the judgment result identifier, and sends the version plan to the target production general control manager terminal; the version plan includes a judgment result identifier indicating whether the project production involves the cooperation of the head office; In response to the production baseline information released by the target production control manager terminal to the system manager terminal according to the version plan, the system manager terminal generates confirmation delivery information according to the production baseline information, and sends the confirmation delivery information to the PIO manager terminal; the confirmation delivery information carries the judgment result identifier; The PIO manager terminal responds to the action of reviewing the confirmed delivery information, sends the reviewed confirmed delivery information to the project team terminal, responds to the project team terminal's triggering action of locally executing uploading the target deliverable, and sends the target deliverable to the target verification and review terminal according to the judgment result identifier, so that the target verification and review terminal verifies and reviews the target deliverable.

10. The device according to claim 9, characterized in that The target production control manager terminal includes an enterprise-level production control manager terminal, and the judgment result identifier includes a first judgment result identifier indicating that the project production involves the cooperation of the head office; accordingly, the system manager terminal is specifically used for: If it is determined that the judgment result identifier is the first judgment result identifier, it is determined that the target production general control manager terminal is an enterprise-level production general control manager terminal.

11. The device according to claim 10, characterized in that The target verification and audit terminal includes an enterprise-level test center access and audit terminal; accordingly, the project team terminal is specifically used for: In response to the project team terminal executing a triggering action of uploading a target deliverable locally, the target deliverable is sent to the enterprise-level testing center access review terminal according to the first judgment result identifier.

12. The device according to claim 11, characterized in that The target verification and audit terminal also includes an enterprise-level production verification and audit terminal; accordingly, the device is also used for: In response to the enterprise-level test center access review terminal's processing action of reviewing and approving the target deliverables, the approved target deliverables are sent to the enterprise-level production verification review terminal, so that the enterprise-level production verification review terminal can perform installation test review, functional regression test review and mobile APP review on the approved target deliverables.

13. A computer device comprising a memory, a processor and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the method according to any one of claims 1 to 8 is implemented.

14. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the method according to any one of claims 1 to 8 is implemented.

15. A computer program product, characterized in that The computer program product comprises a computer program, and when the computer program is executed by a processor, the method according to any one of claims 1 to 8 is implemented.