Auxiliary device for mounting steel structure building framework
By designing auxiliary devices for steel structure building skeleton installation, the problems of unstable installation of steel frames and inaccurate fixation of lead plates in the prior art are solved, and higher structural stability and safety are achieved, as well as more accurate lead Board installation.
Patent Information
- Application Number
- CN202510044878.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-13
- Publication Date
- 2025-02-14
- Estimated Expiration
- 2045-01-13
AI Technical Summary
When installing the existing lead-protective operating room steel frame, the vertical rod may be deviated due to unstable manual support, and when the wall is uneven, the steel frame is prone to bend, affecting structural stability and safety.
Design an auxiliary device, including support assembly, clamping assembly, adsorption assembly, adjustment assembly and calibration assembly, to achieve clamping and fixing of the steel frame through the slide rail and slide mechanism, and to fix the lead plate with a vacuum suction cup to ensure the vertical structure degree and level.
It effectively avoids the deviation problem caused by artificial mismoving of the steel frame during installation, improves the stability and safety of the structure, and improves the accuracy of the installation position of the lead plate.
Smart Images

Figure CN119434669A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of lead protection operating room construction, in particular to an auxiliary device for installing a steel structure building frame. Background Art
[0002] Lead-protected operating rooms are important facilities in the medical field. They are mainly composed of key parts such as lead walls, lead doors, protective windows and protective screens. These parts are made of lead materials with good protective effects and can effectively block radiation. In medical applications, lead-protected operating rooms play a vital role. They are not only an ideal place for radiotherapy, but can also ensure that patients with malignant tumors are fully protected during treatment. It is also an important place for special operations. The use of lead-protected operating rooms can significantly reduce the risk of radiation exposure for medical staff and patients, thereby effectively protecting the health and safety of both parties. Among them, the construction sequence of the lead wall is to set up a steel structure frame around the radiation-proof operating room - fix the upper and lower floor slabs with expansion bolts - install lead plates on the steel structure frame - cover the nail heads with corresponding lead plates.
[0003] When installing the existing lead wall steel frame, holes are usually drilled on the wall, and the vertical bars of the steel frame are first fixed to the wall by expansion bolts, and then the horizontal bars of the steel frame are welded between the vertical bars. When the vertical bars are fixed, the construction workers need to support them manually. The palms of the workers are easy to move when supporting, causing the vertical bars to shift. In addition, when the wall is uneven, the distance between the steel frame and the wall is different. When the expansion bolts are tightened, the part of the steel frame farther from the wall is easy to bend inward, causing the verticality of the steel frame to shift, which will affect the stability and safety of the overall structure of the steel frame, and it is also easy to cause the aluminum plate to be installed unevenly and with large gaps. Summary of the invention
[0004] The object of the present invention is to provide an auxiliary device for installing a steel structure building frame to solve the problems raised in the above background technology.
[0005] To achieve the above object, the present invention provides the following technical solutions: An auxiliary device for installing a steel structure building frame, comprising: A support assembly, the support assembly comprising a support frame, a slide rail is symmetrically fixedly mounted on one side surface of the support frame, a slider is slidably connected inside the slide rail, and a moving frame is fixedly connected between two sliders; A clamping assembly is fixedly connected to one side of the moving frame, and the clamping assembly includes a plurality of sliding rods fixedly installed on the surface of one side of the moving frame, a No. 1 fixing frame is slidably connected to the outer sides of the plurality of sliding rods, a plurality of extension rods are fixedly installed on one side of the No. 1 fixing frame at equal intervals, and a plurality of No. 1 clamping frames and No. 2 clamping frames are fixedly installed on one end of the plurality of extension rods; Adsorption assembly, movable on one side of the No. 1 fixed frame; Two adjustment components are symmetrically arranged at the lower end of the support frame; The calibration component is movably arranged outside the support frame.
[0006] Furthermore, the outer surfaces of the plurality of No. 1 clamp frames on both sides are fixedly mounted with limit assemblies, and the limit assemblies include: Two connecting rods are symmetrically fixed on the surfaces of both ends of the No. 1 clamp frame; Two baffles are rotatably connected to the outer sides of the two connecting rods respectively; Two elastic arc-shaped sheets are symmetrically and fixedly mounted on one side surface of the first clamp frame, and one end of the elastic arc-shaped sheet is movably fitted with the baffle at the corresponding position.
[0007] Furthermore, a movable pulley is rotatably connected to the upper end of one side surface of the support frame through a bracket, a pull rope is wound around the outer side of the movable pulley, one end of the pull rope is fixedly connected to the movable frame, a clamping ring is symmetrically fixedly installed on the lower end surface of the support frame, a clamping rod is symmetrically fixedly installed on the lower end of the other side surface of the movable frame, the clamping rod is movably engaged with the clamping ring at the corresponding position, and a universal wheel is symmetrically fixedly installed on the lower end of the movable frame.
[0008] Further, a plurality of No. 1 clamping frames located in the middle of the No. 1 fixing frame are screwed together with a No. 1 fastening knob on one side surface, and the No. 1 fastening knob passes through the No. 1 clamping frame; a plurality of sliding grooves are equidistantly provided on a side surface of the No. 1 fixing frame, and the sliding grooves pass through the No. 1 fixing frame.
[0009] Further, the adsorption component comprises: Fixed frame No. 2, movable and arranged on one side of fixed frame No. 1; A plurality of hollow rods are fixedly installed at equal intervals on a surface of one side of the second fixing frame; A plurality of vacuum suction cups are respectively fixedly mounted on one end of a plurality of hollow rods; The two gas chambers are both fixedly mounted on the inner surface of the No. 2 fixing frame.
[0010] Preferably: a multi-way connecting tube is fixedly connected to the lower end of the gas bin, and the multi-way connecting tube is fixedly connected to multiple adjacent hollow rods. A piston plate is slidably connected to the inside of the gas bin, and a threaded groove is opened at the upper end of the gas bin. A pull rod is fixedly installed on one side surface of the piston plate, and the pull rod passes through the threaded groove and is slidably connected to the threaded groove. A thread is fixedly provided at the lower end of the outer surface of the pull rod, and the thread is screwed together with the threaded groove.
[0011] Further, the adjustment component includes: Two mounting grooves are symmetrically arranged at the lower end of the outer surface of the support frame; Two threaded sleeves are symmetrically arranged at the lower end of the outer surface of the support frame; Two No. 2 tightening knobs are respectively screwed and connected to the inside of the two threaded sleeves and penetrate the threaded sleeves; The two pads are respectively fixedly mounted on the lower end surfaces of the two No. 2 fastening knobs.
[0012] Preferably: hollow blocks are fixedly installed on the outer surfaces of the two threaded sleeves, and the two hollow blocks are movably plugged into the installation grooves at corresponding positions respectively, and bolts are symmetrically screwed and connected to the other side surface of the support frame, and the bolts movably penetrate the hollow blocks.
[0013] Further, the calibration component includes: The third clamp frame is movably arranged on the outside of the vertical rod of the steel structure frame; The laser light is detachably connected to the surface of one side of the No. 3 clamp frame through a circular clamp; Two penetration pipes are fixedly installed on one side surface of the support frame; Two vials are symmetrically fixedly installed at the lower end of the outer surface of the support frame.
[0014] Preferably, a No. 3 fastening knob is screwedly connected to a surface of one side of the No. 3 clamp frame, and the No. 3 fastening knob passes through the No. 3 clamp frame.
[0015] Compared with the prior art, the present invention has the following beneficial effects: 1. Place the vertical and horizontal bars of the steel frame on the ground so that they are clamped inside the No. 1 clamp frame and the No. 2 clamp frame respectively. Pull the pull rope to move the mobile frame upward and flip it to a vertical state and make it parallel to the support frame. Place the vertical and horizontal bars of the steel frame on the ground for clamping and fixing. Driven by the mobile frame, the steel frame as a whole is flipped to the side of the support frame. Then press the No. 1 fixing frame to press the steel frame against the wall so that the steel frame as a whole is in the same plane. Then fix it with expansion bolts to ensure the verticality of the steel frame. At the same time, replace the workers' hand-held fixation to avoid the vertical deviation caused by the inward bending of the steel frame part, thereby improving the stability and safety of the overall structure of the steel frame.
[0016] 2. After the steel frame is fixed, lay multiple lead plates flat on the ground, flip the mobile frame downward, press the No. 2 fixing frame downward to press the vacuum suction cup on the surface of the lead plate, and pull the pull rod. At this time, a negative pressure environment is created inside the vacuum suction cup to fix the lead plate. Then flip the mobile frame upward, press the No. 2 fixing frame, and move multiple lead plates to the outside of the steel frame fixed on the wall, thereby replacing the workers' hand-held fixation of a single lead plate, making it easier to fix multiple lead plates at the same time, while avoiding the lead plate from shifting when the workers hold it, thereby improving the accuracy of the installation position.
[0017] 3. According to the floor height of the operating room, remove the bolts and threaded sleeves, replace the No. 2 tightening knobs with different lengths, turn the No. 2 tightening knob, and drive the pad to move down and rotate through the screwing of the No. 2 tightening knob and the threaded sleeve, fix the support frame between the roof and the ground close to the wall, and adjust the verticality of the support frame by observing the level bubble, and clamp the No. 3 clamp frame on the outside of the vertical rod as a reference, and rotate the support frame. When the laser emitted by the laser lamp can pass through the two penetration tubes at the same time, the support frame is flush with the surface of the vertical rod of the reference object, so as to ensure that the steel frame is installed in the same plane when installing the remaining vertical rods, avoid the deviation of the steel frame, ensure the horizontality of the steel frame, and avoid excessive gaps caused by the deviation of the steel frame when the lead plate is installed.
[0018] 4. When clamping the lead plate, there is no obstruction under the baffle. The elastic force of the elastic arc sheet itself pushes the baffle to flip downward, limiting the position of the lead plate from both sides of the lead plate. At the same time, the uppermost lead plate is pressed against the upper end of the movable frame, so that multiple lead plates are neatly stacked under multiple vacuum suction cups. When the vacuum suction cups are adsorbed and fixed, the multiple lead plates are flipped as a whole to the outside of the steel frame. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the overall structure of the present invention; Figure 2 It is a schematic diagram of the structure of the steel skeleton in the grasping state of the present invention; Figure 3 It is a schematic diagram of the structure of the lead plate grabbing state in the present invention; Figure 4 It is a schematic diagram of the overall split structure of the present invention; Figure 5 It is a schematic diagram of the vertical cross-section structure of the adsorption component part in the present invention; Figure 6 It is a schematic diagram of the cross-sectional structure of a clamping assembly in the present invention; Figure 7 It is a schematic diagram of the structure of the support component part in the present invention; Figure 8 It is a schematic diagram of the overall structure of the limit assembly in the present invention; Fig. 9 It is a schematic diagram of the vertical cross-section structure of the gas bin in the present invention; Fig.10 It is a schematic diagram of the split structure of the connection between the adjustment component and the support frame in the present invention.
[0020] In the figure: 1. Support assembly; 101. Support frame; 102. Slide rail; 103. Moving frame; 104. Slider; 105. Moving pulley; 106. Pull rope; 107. Clamp ring; 108. Clamp rod; 109. Universal wheel; 2. Clamp assembly; 201. Slide rod; 202. No. 1 fixing frame; 203. Extension rod; 204. No. 1 clamping frame; 205. No. 1 tightening knob; 206. No. 2 clamping frame; 207. Slide groove; 3. Limit assembly; 301. Connecting rod; 302. Baffle plate; 303. Elastic arc sheet; 4. Adsorption assembly; 401. No. 2 fixing frame; 402. Hollow rod; 403. Vacuum suction cup; 404. Multi-way connecting pipe; 405. Air chamber; 406. Piston plate; 407. Pull rod; 408. Thread; 409. Thread groove; 5. Adjustment assembly; 501. Mounting groove; 502. Threaded sleeve; 503. No. 2 tightening knob; 504. Pad; 505. Bolt; 506. Hollow block; 6. Calibration assembly; 601. No. 3 clamp frame; 602. Laser light; 603. Penetration tube; 604. Level bubble. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] See also Figure 1-10 In an embodiment of the present invention, an auxiliary device for installing a steel structure building skeleton includes a support assembly 1, the support assembly 1 includes a support frame 101, a slide rail 102 is symmetrically fixedly installed on the surface of one side of the support frame 101, a slider 104 is slidably connected inside the slide rail 102, a moving frame 103 is fixedly connected between two sliders 104, a clamping assembly 2 is fixedly connected to one side of the moving frame 103, the clamping assembly 2 includes a plurality of slide bars 201 fixedly installed on the surface of one side of the moving frame 103, a No. 1 fixed frame 202 is slidably connected to the outer sides of the plurality of slide bars 201, a plurality of extension rods 203 are equidistantly fixedly installed on the surface of one side of the No. 1 fixed frame 202, a plurality of No. 1 clamping frames 204 and a No. 2 clamping frames 206 are respectively fixedly installed on one end of the plurality of extension rods 203, an adsorption assembly 4 is movably arranged on one side of the No. 1 fixed frame 202, two adjustment assemblies 5 are symmetrically movably arranged at the lower end of the support frame 101, and a calibration assembly 6 is movably arranged on the outer side of the support frame 101.
[0023] Specifically, first install a vertical rod of a steel frame on the wall, and use the vertical rod as a reference. When the movable frame 103 is in a vertical state, press the No. 1 fixing frame 202 to move it to the maximum distance. Multiple No. 1 clamping frames 204 on one side can be clamped on the outside of the vertical rod to facilitate keeping the distance between the vertical rods of the steel frame the same. Move and adjust the position of the support frame 101, and fix the support frame 101 close to the wall through the adjustment component 5 so that its upper and lower ends are against the roof and the ground. Observe the verticality of the support frame 101 through the calibration component 6, and clamp and fix the vertical pipes and horizontal pipes of the steel frame through the clamping component 2. After the steel frame is installed on the wall, place the lead plate on the ground and fix it through the adsorption component 4, so that multiple lead plates are stacked as a whole on the steel frame for fixation.
[0024] Embodiment 1 like Figure 1-6 As shown, in this embodiment, a movable pulley 105 is rotatably connected to the upper end of one side surface of the support frame 101 through a bracket, a pull rope 106 is wound around the outer side of the movable pulley 105, one end of the pull rope 106 is fixedly connected to the moving frame 103, a snap ring 107 is symmetrically fixedly installed on the lower end surface of the support frame 101, a clamping rod 108 is symmetrically fixedly installed on the lower end of the other side surface of the moving frame 103, the clamping rod 108 is movably engaged with the snap ring 107 at the corresponding position, and a universal wheel 109 is symmetrically fixedly installed on the lower end of the moving frame 103; a plurality of No. 1 clamping frames 204 located in the middle of the No. 1 fixing frame 202 are screwed and connected to a No. 1 tightening knob 205 on one side surface, and the No. 1 tightening knob 205 passes through the No. 1 clamping frame 204, and a plurality of sliding grooves 207 are equidistantly provided on the surface of one side of the No. 1 fixing frame 202, and the sliding grooves 207 pass through the No. 1 fixing frame 202.
[0025] In this embodiment, the vertical rod and the cross rod of the steel frame are placed on the ground, the No. 1 fixing frame 202 is controlled to flip downward and place it on the ground, the vertical rod and the cross rod are moved to be clamped in the No. 1 clamping frame 204 and the No. 2 clamping frame 206 respectively, the upper end of the vertical rod is pressed against the upper end of the moving frame 103 to fix its position, and then the No. 1 tightening knob 205 is turned to press it against the vertical rod to fix the vertical rod, and the cross rod is fixed by the clamping force and friction force with the No. 2 clamping frame 206, and the pull rope 106 is pulled. At this time, the slider 104 slides and rotates inside the slide rail 102, so that the moving frame 103 moves upward and flips to a vertical state and is parallel to the support frame 101. The universal wheel 109 reduces the friction between the moving frame 103 and the ground, and at the same time makes the device as a whole convenient. For movement, when the moving frame 103 is flipped to vertical, the clamping rod 108 is clamped inside the clamping ring 107. At this time, the upper end of the moving frame 103 is restricted by the slide rail 102, and the lower end is restricted by the clamping ring 107 to fix it. Therefore, the vertical rods and horizontal rods of the steel frame are placed on the ground for clamping and fixing, so that the entire part of the steel frame is flipped to the side of the support frame 101 under the drive of the moving frame 103, and then the No. 1 fixing frame 202 is pressed to press the steel frame against the wall so that the entire part of the steel frame is in the same plane, and then fixed with expansion bolts to ensure the verticality of the part of the steel frame. At the same time, it replaces the workers' hand-held fixation to avoid the vertical deviation caused by the inward bending of the steel frame part, thereby improving the stability and safety of the overall structure of the steel frame.
[0026] like Figure 3 , Figure 4 and Fig. 9 As shown, in this embodiment, the adsorption component 4 includes: a No. 2 fixing frame 401 is movably arranged on one side of the No. 1 fixing frame 202, a plurality of hollow rods 402 are equidistantly fixedly installed on the surface of one side of the No. 2 fixing frame 401, a plurality of vacuum suction cups 403 are respectively fixedly installed on one end of the plurality of hollow rods 402, and two air chambers 405 are both fixedly installed on the inner surface of the No. 2 fixing frame 401; a multi-way connecting pipe 404 is fixedly connected to the lower end of the air chamber 405, and the multi-way connecting pipe 404 is fixedly connected to the adjacent plurality of hollow rods 402, a piston plate 406 is slidably connected inside the air chamber 405, a threaded groove 409 is opened at the upper end of the air chamber 405, a pull rod 407 is fixedly installed on the surface of one side of the piston plate 406, the pull rod 407 passes through the threaded groove 409, and is slidably connected to the threaded groove 409, a thread 408 is fixedly provided at the lower end of the outer surface of the pull rod 407, and the thread 408 is screwed together with the threaded groove 409.
[0027] During specific implementation, after the steel frame is fixed, multiple lead plates are laid flat on the ground, the moving frame 103 is flipped downward, and the No. 2 fixing frame 401 is pressed downward to press the vacuum suction cup 403 on the surface of the lead plate, pull the pull rod 407, and rotate the pull rod 407 through the screwing of the thread 408 and the thread groove 409 to move the piston plate 406 upward and fix it inside the air chamber 405. At this time, a negative pressure environment is created inside the vacuum suction cup 403 to fix the lead plate, and then the moving frame 103 is flipped upward, and the No. 2 fixing frame 401 is pressed to move multiple lead plates to the outside of the steel frame fixed to the wall, replacing the workers' hand-held single lead plate for fixing, which is convenient for fixing multiple lead plates at the same time, while avoiding the lead plate from shifting when the workers hold it, thereby improving the accuracy of the installation position.
[0028] like Figure 4 , Figure 7 and Fig.10 As shown, in this embodiment, the adjustment component 5 includes: two installation grooves 501 are symmetrically opened at the lower end of the outer surface of the support frame 101, two threaded sleeves 502 are symmetrically arranged at the lower end of the outer surface of the support frame 101, two No. 2 fastening knobs 503 are respectively screwed together and connected to the inside of the two threaded sleeves 502, and pass through the threaded sleeves 502, and two pads 504 are respectively fixedly installed on the lower end surfaces of the two No. 2 fastening knobs 503; hollow clamping blocks 506 are fixedly installed on the outer surfaces of the two threaded sleeves 502, and the two hollow clamping blocks 506 are respectively movably plugged into the installation grooves 501 at corresponding positions, and the other side surface of the support frame 101 is symmetrically screwed together with bolts 505, and the bolts 505 movably pass through the hollow clamping blocks 506.
[0029] During specific implementation, according to the height of the operating room, the bolt 505 is removed, the threaded sleeve 502 is removed, and the No. 2 fastening knob 503 of different lengths is replaced, so that the support frame 101 can be against the roof and the pad 504 can be against the ground. When fixing the support frame 101, the No. 2 fastening knob 503 is turned, and through the screwing of the No. 2 fastening knob 503 with the threaded sleeve 502, the pad 504 is driven to move down and rotate, and the support frame 101 is fixed between the roof and the ground close to the wall.
[0030] like Figure 1 and Fig.10 As shown, in this embodiment, the calibration component 6 includes: a No. 3 clamp frame 601 is movably arranged on the outside of the vertical rod of the steel structure skeleton, the laser light 602 is detachably connected to the side surface of the No. 3 clamp frame 601 through a circular clamp, two penetration tubes 603 are fixedly installed on the side surface of the support frame 101, and two level bubbles 604 are symmetrically fixedly installed at the lower end of the outer surface of the support frame 101; a No. 3 fastening knob is screwed on the side surface of the No. 3 clamp frame 601, and the No. 3 fastening knob passes through the No. 3 clamp frame 601.
[0031] During specific implementation, the verticality of the support frame 101 is adjusted by observing the level bubbles 604 on both sides, so that the support frame 101 can adjust its position more intuitively, and the No. 3 clamp frame 601 is clamped on the outside of the vertical pole serving as a reference and its height is adjusted to aim the laser light 602 at a penetrating tube 603, and then the support frame 101 is rotated. When the laser emitted by the laser light 602 can pass through two penetrating tubes 603 at the same time, the support frame 101 is flush with the surface of the vertical pole of the reference object, so that when the remaining vertical poles are installed, the steel frame is installed in the same plane to avoid the deviation of the steel frame, to ensure the horizontality of the steel frame, and to avoid excessive gaps caused by the deviation of the steel frame when the lead plate is installed.
[0032] Embodiment 2 On the basis of the first embodiment, in order to make up for the problem that the position of the lead plate in the first embodiment is not convenient for positioning.
[0033] like Figure 6 and Figure 8 As shown, in this embodiment, the outer surfaces of multiple No. 1 clamp frames 204 located on both sides are fixedly installed with limiting components 3, and the limiting components 3 include: two connecting rods 301 symmetrically fixedly installed on the two end surfaces of the No. 1 clamp frame 204, two baffles 302 are rotatably connected to the outside of the two connecting rods 301, and two elastic arc pieces 303 are symmetrically fixedly installed on one side surface of the No. 1 clamp frame 204, and one end of the elastic arc piece 303 is movably fitted with the baffle 302 at the corresponding position.
[0034] During specific implementation, when the vertical rod of the steel frame is stuck inside the No. 1 clamp frame 204, the vertical rod pushes against the baffle 302 to move upward. At this time, the baffle 302 does not play a role. When clamping the lead plate, there is no obstacle under the baffle 302. The elastic force of the elastic arc piece 303 itself pushes the baffle 302 to flip downward, limiting the position of the lead plate from both sides of the lead plate. At the same time, the uppermost lead plate is pressed against the upper end of the movable frame 103, so that multiple lead plates are neatly stacked under multiple vacuum suction cups 403. When the vacuum suction cups 403 are adsorbed and fixed, the multiple lead plates are flipped as a whole to the outside of the steel frame.
[0035] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0036] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. An auxiliary device for installing a steel structure building frame, characterized in that: include: A support assembly (1), the support assembly (1) comprising a support frame (101), a slide rail (102) being symmetrically fixedly mounted on a surface of one side of the support frame (101), a slider (104) being slidably connected inside the slide rail (102), and a moving frame (103) being fixedly connected between two sliders (104); A clamping assembly (2) is fixedly connected to one side of the moving frame (103), the clamping assembly (2) comprising a plurality of sliding rods (201) fixedly mounted on a surface of one side of the moving frame (103), a first fixing frame (202) being slidably connected to the outer sides of the plurality of sliding rods (201), a plurality of extension rods (203) being fixedly mounted at equal intervals on a surface of one side of the first fixing frame (202), and a plurality of first clamping frames (204) and a second clamping frame (206) being fixedly mounted on one end of the plurality of extension rods (203); An adsorption component (4) movably disposed on one side of the first fixing frame (202); Two adjustment components (5) are symmetrically arranged at the lower end of the support frame (101); The calibration component (6) is movably arranged outside the support frame (101).
2. The auxiliary device for installing a steel structure building frame according to claim 1, characterized in that: The outer surfaces of the plurality of No. 1 clamp frames (204) located on both sides are fixedly mounted with limit assemblies (3), the limit assemblies (3) comprising: Two connecting rods (301) are symmetrically fixedly mounted on the surfaces of both ends of the first clamp frame (204); Two baffles (302) are rotatably connected to the outer sides of the two connecting rods (301); Two elastic arc-shaped sheets (303) are symmetrically fixedly mounted on a side surface of the first clamp frame (204), and one end of the elastic arc-shaped sheet (303) is movably fitted with the baffle (302) at a corresponding position.
3. The auxiliary device for installing a steel structure building frame according to claim 1, characterized in that: A movable pulley (105) is rotatably connected to the upper end of the surface of one side of the support frame (101) through a bracket, a pull rope (106) is wound around the outer side of the movable pulley (105), one end of the pull rope (106) is fixedly connected to the moving frame (103), a clamping ring (107) is symmetrically fixedly installed on the lower end surface of the support frame (101), a clamping rod (108) is symmetrically fixedly installed on the lower end of the other side surface of the moving frame (103), the clamping rod (108) is movably engaged with the clamping ring (107) at a corresponding position, and a universal wheel (109) is symmetrically fixedly installed on the lower end of the moving frame (103).
4. The auxiliary device for installing a steel structure building frame according to claim 1, characterized in that: A number one clamping frame (204) located in the middle of the number one fixing frame (202) is screwed together with a number one fastening knob (205) on one side surface, and the number one fastening knob (205) passes through the number one clamping frame (204); a number of slide grooves (207) are equidistantly formed on one side surface of the number one fixing frame (202), and the slide grooves (207) pass through the number one fixing frame (202).
5. The auxiliary device for installing a steel structure building frame according to claim 1, characterized in that: The adsorption component (4) comprises: A second fixing frame (401) is movably arranged on one side of the first fixing frame (202); A plurality of hollow rods (402) are fixedly mounted at equal intervals on a side surface of the second fixing frame (401); A plurality of vacuum suction cups (403) are respectively fixedly mounted on one end of a plurality of hollow rods (402); The two gas chambers (405) are both fixedly mounted on the inner surface of the second fixing frame (401).
6. The auxiliary device for installing a steel structure building frame according to claim 5, characterized in that: The lower end of the gas bin (405) is fixedly connected to a multi-way connecting tube (404), and the multi-way connecting tube (404) is fixedly connected to a plurality of adjacent hollow rods (402). The inside of the gas bin (405) is slidably connected to a piston plate (406), and a threaded groove (409) is provided at the upper end of the gas bin (405). A pull rod (407) is fixedly installed on one side surface of the piston plate (406), and the pull rod (407) passes through the threaded groove (409) and is slidably connected to the threaded groove (409). A thread (408) is fixedly provided at the lower end of the outer surface of the pull rod (407), and the thread (408) is screwed together with the threaded groove (409).
7. The auxiliary device for installing a steel structure building frame according to claim 1, characterized in that: The regulating component (5) comprises: Two mounting grooves (501) are symmetrically arranged at the lower end of the outer surface of the support frame (101); Two threaded sleeves (502) are symmetrically arranged at the lower end of the outer surface of the support frame (101); Two No. 2 tightening knobs (503) are respectively screwed and connected to the inside of the two threaded sleeves (502) and penetrate the threaded sleeves (502); The two pads (504) are respectively fixedly mounted on the lower end surfaces of the two No. 2 fastening knobs (503).
8. The auxiliary device for installing a steel structure building frame according to claim 7, characterized in that: Hollow clamping blocks (506) are fixedly mounted on the outer surfaces of the two threaded sleeves (502), and the two hollow clamping blocks (506) are movably plugged into the mounting grooves (501) at corresponding positions, respectively. Bolts (505) are symmetrically screwed and connected to the other side surface of the support frame (101), and the bolts (505) movably penetrate the hollow clamping blocks (506).
9. The auxiliary device for installing a steel structure building frame according to claim 1, characterized in that: The calibration component (6) comprises: A third clamp frame (601) is movably arranged outside the vertical rod of the steel structure frame; The laser light (602) is detachably connected to a side surface of the third clamp frame (601) via a circular clamping sleeve; Two penetration pipes (603) are fixedly mounted on a side surface of the support frame (101); Two level bubbles (604) are symmetrically fixedly mounted at the lower end of the outer surface of the support frame (101).
10. The auxiliary device for installing a steel structure building frame according to claim 9, characterized in that: A No. 3 fastening knob is screwed together on one side surface of the No. 3 clamping frame (601), and the No. 3 fastening knob passes through the No. 3 clamping frame (601).
Citation Information
Patent Citations
Portable curtain wall construction auxiliary device
CN111894285A
Keel frame fixing and clamping device for steel structure gravel plant
CN112196287A
Auxiliary mounting equipment for fabricated building wallboard
CN112227739A
Auxiliary device for mounting outer frame of glass curtain wall
CN112482785A
Building glass curtain wall hoisting and clamping device
CN116477452A