Coal engineering construction management method based on BIM +

Through the BIM+-based coal engineering construction management method, digital integrated management of the entire process of coal engineering construction has been realized, and the problems of many hidden dangers, waste of resources, excessive investment and low efficiency have been solved, and management efficiency and quality have been improved.

CN119444505APending Publication Date: 2025-02-14CCTEG BEIJING HUAYU ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411454313.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-17
Publication Date
2025-02-14

AI Technical Summary

Technical Problem

There are problems such as many hidden dangers, waste of resources, excessive investment and low efficiency in coal engineering construction. Due to the large number of participating parties and the chaos of drawings, models and data systems, the inconsistency, mismatch, and inconsistency between the front and back, resulting in waste of process assets. and cost increases.

Method used

The BIM+-based coal engineering construction management method is adopted, and the digital integrated management of the entire process of coal engineering construction is achieved through the construction of basic models, planning management, progress management, resource control, quality and safety management, investment management and other steps.

Benefits of technology

The refined and standardized management of coal engineering construction has been achieved, the construction progress and quality have been ensured, resource waste and costs have been reduced, and management efficiency has been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119444505A_ABST
    Figure CN119444505A_ABST
Patent Text Reader

Abstract

The invention provides a coal engineering construction management method based on BIM +. Comprising the steps of 1, constructing a basic model, and performing sharing management and authority control; step 2, performing plan management to form 4D-BIM resources; step 3, performing respective management according to 4D-BIM resources; and step 4, carrying out electronic processing on various types of data, and associating the data with 4D-BIM resources to realize digital handover in a completion stage. Based on the combination of the BIM technology and other technologies or resources, various drawing and document data, models, data, resources and the like in the capital construction period are classified and integrated through fusion application with the BIM + technology, digital integrated management of plans and progress, resource quantity, quality and safety, investment and the like is achieved, the construction progress and quality are guaranteed, and the construction efficiency is improved. Refining and standardization of coal engineering construction management are promoted, and extended application of BIM + achievements is promoted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of coal mine foundation engineering construction, and in particular to a coal mine engineering construction management method based on BIM+. Background Art

[0002] At present, there are still the following deficiencies in coal engineering construction: (1) Due to the large scale, long cycle, high investment and many hidden projects of coal mine infrastructure projects, some enterprises focus on engineering and neglect construction, and focus on post-management and neglect pre-management, resulting in many hidden dangers, waste of resources, over-investment and low efficiency in the projects. How to conduct comprehensive and timely effective supervision and process traceability of coal mine infrastructure projects is a difficulty in current construction management. (2) There are many parties involved in the coal mine infrastructure construction process, and the drawings, models and data systems at various stages are chaotic, with different standards and complex management. The various stages cannot form a comprehensive and organic integration, which is prone to inconsistency, mismatch and uncoordination. In addition, the basic results of the previous design cannot be used after the construction is turned into operation, resulting in waste of process assets and increased costs.

[0003] Based on the above existing technical problems, a method for solving the above technical problems is urgently needed. Summary of the invention

[0004] The purpose of the present invention is to provide a coal engineering construction management method based on BIM+.

[0005] The present invention is achieved through the following technical solutions:

[0006] The present invention relates to a coal engineering construction management method based on BIM+, comprising the following steps:

[0007] Step 1: Build the basic model: Use the BIM platform to build the briefing model in the construction drawing stage, and combine it with the GIS model to form a BIM+ fusion model. After combining the models, perform lightweight lossless conversion of the model to form a lightweight model, and perform sharing management and authority control;

[0008] Step 2, plan management: prepare a 2D Project plan according to the construction organization, import the 2D plan, associate the planned process with the BIM+ resource object, form a 3D plan with time factors, and form 4D-BIM resources;

[0009] Step 3, according to 4D-BIM resources, respectively carry out planning management, progress management, resource control, quality and safety management, and investment management; specifically: ① Control the visibility of engineering structure objects according to the time schedule, verify the rationality of the engineering plan through progress plan simulation, reasonably arrange the construction process, and improve the construction plan; ② Through progress reporting, reflect the completion status of project tasks (delayed or ahead) in real time, realize the comparison between planned and actual progress and progress optimization; ③ Through material reporting, conduct real-time statistics of engineering resources and realize phased cost management; ④ Through the reporting of quality and safety issues, and realize the link with 4D-BIM resources, carry out instant reminders and dynamic supervision through collaborative mode;

[0010] Step 4: Electronically process all types of drawings and correspondence materials, and associate them with 4D-BIM resources to form standardized digital assets that are consistent with the construction briefing materials, and realize digital handover at the completion stage.

[0011] Preferably, the specific steps of step 3 are:

[0012] The plan management specifically includes:

[0013] Step (1.1): Select the construction process section to be simulated, select the start time and end time, and start the time process;

[0014] Step (1.2): According to the time evolution, the visibility and coloring of the structural objects are controlled by the time factor. The objects linked to the process before the current time are shown in green, the objects linked to the process after the current time are not shown, and the objects linked to the process in the current time process are shown in red;

[0015] Step (1.3): Through this mechanism, potential errors and conflicts in the work order in the process are identified, construction difficulties are discovered, and the process is optimized and the progress is corrected to avoid rework and waste in the later stage;

[0016] The progress management is achieved through progress reporting, specifically:

[0017] Step (2.1): Combined with the three-dimensional progress plan, the actual progress report of the corresponding progress tasks shall be filled in, including the completion progress ratio of the subdivided planned tasks and the image data of the current status of the project construction;

[0018] Step (2.2): Calculate the project phase progress based on the reported content, visualize the simulated progress through the 4D-BIM model, reflect the completion status of the project tasks in real time, and compare and analyze with the planned tasks to show whether the project is lagging behind or ahead of schedule, and provide progress reminders or warnings simultaneously;

[0019] The resource control is realized through material reporting, specifically:

[0020] Step (3.1): Based on the detailed planned tasks, fill in the human, material and machine resources invested in the implementation of the planned tasks according to the actual situation;

[0021] Step (3.2): Associating the reported resource quantity with the BIM object in real time;

[0022] Step (3.3): According to the stages and project objects, the actual resource quantities are classified and counted as a basis for resource management;

[0023] The quality and safety management is specifically:

[0024] Step (4.1): During the on-site review, the relevant personnel of the construction party or the supervisor shall immediately record the quality and safety issues found in images and texts;

[0025] Step (4.2): Fill in the review records in the system in real time, locate the filled items in the 4D-BIM resources, and associate them with the BIM objects;

[0026] Step (4.3): After uploading the problem records to the system, share and circulate them and track the status, and pay real-time attention to the rectification of quality and safety issues;

[0027] The investment management specifically refers to:

[0028] Step (5.1): Enter the total investment, annual investment, monthly investment plan and corresponding contract information according to the project stage, and fill in the investment plan;

[0029] Step (5.2): Based on the contract information created in the investment plan, fill in the corresponding contract payment and completed investment values ​​on a monthly basis, and upload the settlement attachments for each period;

[0030] Step (5.3): Use the configuration tool to visualize the comparison between planned investment and actual investment from the three dimensions of total, year and month.

[0031] The present invention has the following advantages:

[0032] The present invention is based on the combination of BIM technology and other technologies or resources. Through the integrated application of BIM+ technology, various types of drawings, models, data, resources, etc. in the infrastructure period are classified and integrated, and digital integrated management of plans and progress, resource quantity, quality and safety, investment, etc. is realized, so as to ensure the construction progress and quality, promote the refinement and standardization of coal engineering construction management, and promote the extended application of BIM+ results. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1It is a schematic diagram of the coal engineering construction management method based on BIM+ involved in the present invention. DETAILED DESCRIPTION

[0034] The present invention is described in detail below in conjunction with specific embodiments. It should be noted that the following embodiments are only further descriptions of the present invention, but the protection scope of the present invention is not limited to the following embodiments.

[0035] Example

[0036] This embodiment relates to a coal engineering construction management method based on BIM+, see Figure 1 As shown, the following steps are included:

[0037] Step 1: Build a basic model, specifically:

[0038] Step 1.1: Modeling of the entire coal mine scene. The modeling method adopts the integration of real scene and parameterization. The large-scene GIS model adopts real scene construction (oblique photography or laser point cloud), and the micro scene adopts BIM method to build;

[0039] Step 1.2: To facilitate model management, the modeling process adopts unified rules. The coal mine system is divided into four types of projects according to shafts and tunnels, civil engineering, geology, and equipment. Each project is further subdivided according to individual items and unit projects. The classification of systems, projects, and sub-items adopts the EBS (Element Breakdown Structure) coding system. EBS simplifies and filters the refined content in the construction process based on WBS to ensure the unique correspondence between planned tasks and engineering structure objects;

[0040] Step 1.3: Integrate the BIM and GIS models for model merging, and then perform lightweight lossless conversion of the models to meet the compatibility of the information model and multi-scenario application;

[0041] Step 1.4: Share and manage the lightweight model and control permissions to ensure a secure access mechanism for the model;

[0042] Step 2: Plan management, the specific implementation is as follows:

[0043] Step 2.1: Use MicroSoft Project to prepare a 2D plan and import the 2D plan into the system;

[0044] Step 2.2: Link the subdivided planned tasks with the engineering structure objects. The linking method can be directly selecting the model object or selecting the EBS code. If the code is selected, the code is linked to the model object to achieve the association between the engineering structure object and the time factor, and form a three-dimensional plan based on 4D-BIM resources;

[0045] Step 3: Construction process simulation, the specific implementation is as follows:

[0046] Step 3.1: Select the construction process section to be simulated, select the start time and end time, and start the time process;

[0047] Step 3.2: According to the time evolution, the visibility and coloring of the structural objects are controlled by the time factor. The objects linked to the process before the current time are reflected in green, the objects linked to the process after the current time are not reflected, and the objects linked to the process in the current time process are reflected in red;

[0048] Step 3.3: Through this mechanism, potential errors and conflicts in the work order can be identified, construction difficulties can be found, and process optimization and progress correction can be carried out to avoid rework and waste in the later stage;

[0049] Step 4: Progress management is achieved through progress reporting. The specific implementation is as follows:

[0050] Step 4.1: Combined with the three-dimensional progress plan, report the actual progress of the corresponding progress tasks, including the completion rate of the subdivided plan tasks and the image data of the current construction status;

[0051] Step 4.2: Calculate the project phase progress based on the reported content, visualize the simulated progress through the 4D-BIM model, reflect the completion of the project tasks in real time, and compare and analyze with the planned tasks to show whether the project is lagging behind or ahead of schedule, and provide progress reminders or warnings simultaneously;

[0052] Step 5: Resource control is achieved through material reporting, and the specific implementation is as follows:

[0053] Step 5.1: Based on the detailed planned tasks, fill in the resources of people, materials, machines, etc. invested in implementing the planned tasks according to the actual situation;

[0054] Step 5.2: Associate the reported resource quantity with the BIM object in real time;

[0055] Step 5.3: According to the phases and project objects, the actual resource quantities are classified and counted as a basis for resource management;

[0056] Step 6: Quality and safety management, the specific implementation is as follows:

[0057] Step 6.1: During the on-site review, the relevant personnel of the construction party or the supervisor shall immediately record the quality and safety issues found in images and texts;

[0058] Step 6.2: Fill in the review records in the system in real time, locate the filled items in the 4D-BIM resources, and associate them with the BIM objects;

[0059] Step 6.3: After uploading the problem records to the system, share and track the status, and pay attention to the rectification of quality and safety issues in real time;

[0060] Step 7: Investment management, the specific implementation is as follows:

[0061] Step 7.1: Enter the total investment, annual investment, monthly investment plan and corresponding contract information according to the project stage, and fill in the investment plan;

[0062] Step 7.2: Based on the contract information created in the investment plan, fill in the corresponding contract payment and completed investment values ​​on a monthly basis, and upload the settlement attachments for each period;

[0063] Step 7.3: Use the configuration tool to visualize the comparison between planned investment and actual investment from the three dimensions of total, year and month;

[0064] Step 8: Image management, the specific implementation is as follows:

[0065] Step 8.1: Create a folder directory structure, upload drawings, documents and other materials (dwg, pdf, office, etc.), and perform operations such as preview, download, delete and version management on the drawings;

[0066] Step 8.2: Manually link the uploaded drawing data with the corresponding BIM project object. You can instantly view the associated drawing directory and content in the model view state, and you can also view the associated BIM project object in the file view state;

[0067] Step 8.3: 4D-BIM models, drawings, documents and other resources form models, numbers, Figure 1 Complete the completion handover in digital mode.

[0068] The present invention is based on the combination of BIM technology and other technologies or resources. Through the integrated application of BIM+ technology, various types of drawings, models, data, resources, etc. in the infrastructure period are classified and integrated, and digital integrated management of plans and progress, resource quantity, quality and safety, investment, etc. is realized, so as to ensure the construction progress and quality, promote the refinement and standardization of coal engineering construction management, and promote the extended application of BIM+ results.

[0069] The method involved in the present invention is based on the 4D-BIM resources constructed using BIM+ based on the basic foundation. The core modules of the system involved include lightweight model drawing, three-dimensional plan preparation, organizational process simulation, progress reporting, resource quantity control, stage investment management and control, and drawing management, etc., which are used to solve the problems of non-standard system, non-unified standards, and chaotic management in the process of coal mine infrastructure construction.

[0070] The above describes the specific embodiments of the present invention. It should be understood that the present invention is not limited to the above specific embodiments, and those skilled in the art may make various modifications or variations within the scope of the claims, which will not affect the essence of the present invention.

Claims

1. A coal engineering construction management method based on BIM+, characterized in that: The following steps are involved: Step 1: Build the basic model: Use the BIM platform to build the briefing model in the construction drawing stage, and combine it with the GIS model to form a BIM+ fusion model. After combining the models, perform lightweight lossless conversion of the model to form a lightweight model, and perform sharing management and authority control; Step 2, plan management: prepare a 2D Project plan according to the construction organization, import the 2D plan, associate the planned process with the BIM+ resource object, form a 3D plan with time factors, and form 4D-BIM resources; Step 3: Carry out planning management, progress management, resource control, quality and safety management, and investment management based on 4D-BIM resources; Step 4: Electronically process all types of drawings and correspondence materials, and associate them with 4D-BIM resources to form standardized digital assets that are consistent with the construction briefing materials, and realize digital handover at the completion stage.

2. The coal engineering construction management method based on BIM+ according to claim 1, characterized in that: In step 3, the plan management is specifically: Step (1.1): Select the construction process section to be simulated, select the start time and end time, and start the time process; Step (1.2): According to the time evolution, the visibility and coloring of the structural objects are controlled by the time factor. The objects linked to the process before the current time are shown in green, the objects linked to the process after the current time are not shown, and the objects linked to the process in the current time process are shown in red; Step (1.3): Through this mechanism, potential errors and conflicts in the work order in the process are identified, construction difficulties are discovered, and process optimization and progress correction are carried out; The progress management is achieved through progress reporting, specifically: Step (2.1): Combined with the three-dimensional progress plan, the actual progress report of the corresponding progress tasks shall be filled in, including the completion progress ratio of the subdivided planned tasks and the image data of the current status of the project construction; Step (2.2): Calculate the project phase progress based on the reported content, visualize the simulated progress through the 4D-BIM model, reflect the completion status of the project tasks in real time, and compare and analyze with the planned tasks to show whether the project is lagging behind or ahead of schedule, and provide progress reminders or warnings simultaneously; The resource control is realized through material reporting, specifically: Step (3.1): Based on the detailed planned tasks, fill in the human, material and machine resources invested in the implementation of the planned tasks according to the actual situation; Step (3.2): Associating the reported resource quantity with the BIM object in real time; Step (3.3): According to the stages and project objects, the actual resource quantities are classified and counted as a basis for resource management; The quality and safety management is specifically: Step (4.1): During the on-site review, the relevant personnel of the construction party or the supervisor shall immediately record the quality and safety issues found in images and texts; Step (4.2): Fill in the review records in the system in real time, locate the filled items in the 4D-BIM resources, and associate them with the BIM objects; Step (4.3): After uploading the problem records to the system, share and circulate them and track the status, and pay real-time attention to the rectification of quality and safety issues; The investment management specifically refers to: Step (5.1): Enter the total investment, annual investment, monthly investment plan and corresponding contract information according to the project stage, and fill in the investment plan; Step (5.2): Based on the contract information created in the investment plan, fill in the corresponding contract payment and completed investment values ​​on a monthly basis, and upload the settlement attachments for each period; Step (5.3): Use the configuration tool to visualize the comparison between planned investment and actual investment from the three dimensions of total, year and month.