The invention discloses a
tower crane foundation and
basement foundation combined construction structure and method. The
tower crane foundation and
basement foundation combined construction structure comprises a
basement foundation and a
tower crane foundation. The foundation pit is divided into upper and lower
layers; the
tower crane foundation is located in the lower-layer foundation pit, and the top of the
tower crane foundation extends to the upper-layer foundation pit; the basement foundation is located in the upper-layer foundation pit, and the upper surface of the basement foundation is flush with the upper surface of the
tower crane foundation; the tower crane foundation and the surrounding basement foundations are integrally poured and formed; a plurality of
pile foundations are arranged in the foundation of the lower-layer foundation pit at intervals, and the top ends of the
pile foundations extend into the tower crane foundation; the bottom ends of the tower crane embedded supporting legs are embedded in the tower crane foundation, and the top ends of the tower crane embedded supporting legs protrude out of the upper surface of the lifting foundation and are connected with an external tower crane. The
cushion layer is laid at the bottoms of the lower-layer foundation pit and the upper-layer foundation pit, and the
brick blank film is built on the side wall of the lower-layer foundation pit; the waterproof structure is laid on the surface of the
cushion layer and the
brick blank film, located among the foundation pit, the basement foundation and the tower crane foundation and integrated. The concrete consumption is greatly reduced, and the overall waterproof quality is improved; in addition, the tower crane foundation and the basement are high in
structural integrity, and the tower crane is safe, reliable and high in applicability after being installed.