Power grid infrastructure project entry progress and site construction progress coupling degree evaluation method and system based on PSQ settlement mode
Through the PSQ settlement model method, the accounting progress and on-site progress deviation of power grid infrastructure projects are evaluated, and the problem of lack of coupling assessment in the existing technology is solved, and more accurate investment completion and settlement is achieved.
Patent Information
- Application Number
- CN202411578370.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-07
- Publication Date
- 2025-02-14
AI Technical Summary
The existing technology lacks a coupling assessment plan for the accounting progress of power grid infrastructure projects and on-site construction progress, resulting in insufficient investment completion and settlement.
Using a PSQ settlement model method, the monthly accounting progress and on-site progress of the power grid infrastructure project are evaluated, and the deviation between the monthly accounting progress and on-site progress is predicted, thereby calculating the coupling degree between the accounting progress and the project progress.
It has achieved an accurate assessment of the accounting progress of power grid infrastructure projects and on-site construction progress, and improved the accuracy of investment completion and settlement.
Smart Images

Figure CN119444508A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical fields of power grid investment management, power grid big data processing, power grid system prediction and evaluation, and in particular to a method and system for evaluating the coupling degree between the accounting progress and on-site construction progress of a power grid infrastructure project based on a PSQ settlement model. Background Art
[0002] According to relevant laws and regulations and the development plan of the State Grid Corporation, it is required that newly started projects be counted using the financial expenditure method, while continued projects continue to be counted using the visual progress method. After the reform, investment completion and settlement are "serial relationships" and are directly related. The financial expenditure method is used for investment completion statistics, and the statistical basis is cost accounting. The amount of project investment completed is obtained by adding up the amount of cost accounting, which is closely related to the settlement of project progress payments. The settlement of project progress payments needs to be coupled with the visual progress of the project site. At present, the existing technology lacks a coupling evaluation scheme for the accounting progress and on-site construction progress of power grid infrastructure projects. Summary of the invention
[0003] To address the gaps and deficiencies in the prior art, based on the PSQ settlement model, the present invention proposes a method and system for evaluating the coupling degree between the accounting progress and the on-site construction progress of power grid infrastructure projects, which can accurately predict the coupling degree between the accounting progress and the on-site construction progress and has strong universality and stability.
[0004] The present invention specifically adopts the following technical solutions: A coupling evaluation method for power grid infrastructure project accounting progress and on-site construction progress based on PSQ settlement model: Based on the PSQ settlement model, by evaluating the monthly accounting progress and monthly on-site progress of power grid infrastructure projects, predicting the deviation between the monthly accounting progress and the monthly on-site progress, the coupling degree of power grid infrastructure project accounting progress and engineering progress is calculated.
[0005] Furthermore, the PSQ settlement model is adopted to set the power grid infrastructure project costs to include only progress payments, completion settlement payments and warranty deposits; and the warranty period is 12 months; Among them, the progress payment settlement standard is: progress payment is paid twice, and when the on-site progress is 80% completed, the first progress payment is settled, with a maximum of 50%; when the on-site progress is 80% completed, the second progress payment can be settled, with a maximum of 80%; The settlement standard for the quality guarantee deposit is: if there are no governance issues within one year after the completion of the project, the quality guarantee deposit will be settled at 3%; The settlement standard for the final settlement payment is: after the project is completed, the contract amount minus the progress payment already paid and the retained warranty deposit is the final settlement payment, which is 17%.
[0006] Furthermore, the monthly progress of the assessed power grid infrastructure project is as follows: The progress of depositing funds is divided into 5 stages: Phase A: From the start of construction to 80% completion of the on-site progress; Phase B: From 80% to 100% completion of the on-site progress Stage C is when the on-site progress is 100% completed until the project is finalized and settled; The period from project completion settlement to payment of warranty deposit is the D stage; Pay the security deposit, which is the E stage; This will evaluate the monthly progress of each stage: Phase A: Monthly deposit progress = 0; Phase B: Monthly deposit progress = 50%; Phase C: Monthly deposit progress = 70%; Phase D: Monthly deposit progress = 97%; Phase E: Monthly deposit progress = 100%.
[0007] Furthermore, the monthly progress of the assessed power grid infrastructure project is as follows: The on-site progress is divided into two stages: the first stage is from the start of construction to 80% completion of the on-site progress; the second stage is from 80% completion of the on-site progress to 100% completion of the on-site progress; The monthly on-site progress of each phase is evaluated as follows: Phase I: Monthly on-site progress = 80% / Phase I construction period in months Phase II: Monthly on-site progress = 80% + 20% / number of months for Phase II.
[0008] Furthermore, the deviation between the predicted monthly account progress and the monthly on-site progress is specifically: Statistical construction period: Construction period = number of months of construction period in Phase I + number of months of construction period in Phase II Evaluate monthly deviation: Monthly deviation = Monthly on-site progress - Monthly account progress Evaluate coupling deviation: Coupling deviation = Evaluate coupling: Coupling = .
[0009] And, a coupling evaluation system for the accounting progress and on-site construction progress of power grid infrastructure projects based on the PSQ settlement model, based on a computer system: Includes: PSQ settlement module, account entry progress assessment module, on-site progress assessment module and coupling degree assessment module; The PSQ settlement module is used to calculate the settlement costs of power grid infrastructure project costs using the PSQ settlement model; The account entry progress evaluation module is used to evaluate the monthly account entry progress of power grid infrastructure project expenses; The on-site progress assessment module is used to assess the monthly on-site progress of power grid infrastructure projects; The coupling degree evaluation module is used to evaluate the coupling degree between the accounting progress and the engineering progress of the power grid infrastructure project.
[0010] 1. According to claim 6, a system for evaluating the coupling degree between the accounting progress and the on-site construction progress of power grid infrastructure projects based on the PSQ settlement mode, characterized in that: The PSQ settlement model stipulates that the costs of power grid infrastructure projects only include progress payments, completion settlement payments and warranty deposits; and the warranty period is 12 months; Among them, the progress payment settlement standard is: progress payment is paid twice, and when the on-site progress is 80% completed, the first progress payment is settled, with a maximum of 50%; when the on-site progress is 80% completed, the second progress payment can be settled, with a maximum of 80%; The settlement standard for the quality guarantee deposit is: if there are no governance issues within one year after the completion of the project, the quality guarantee deposit will be settled at 3%; The settlement standard for the final settlement payment is: after the project is completed, the contract amount minus the progress payment already paid and the retained warranty deposit is the final settlement payment, which is 17%.
[0011] Furthermore, the account entry progress evaluation module divides the account entry progress into five stages: Phase A: From the start of construction to 80% completion of the on-site progress; Phase B: From 80% to 100% completion of the on-site progress Stage C is when the on-site progress is 100% completed until the project is finalized and settled; The period from project completion settlement to payment of warranty deposit is the D stage; Pay the security deposit, which is the E stage; This will evaluate the monthly progress of each stage: Phase A: Monthly deposit progress = 0; Phase B: Monthly deposit progress = 50%; Phase C: Monthly deposit progress = 70%; Phase D: Monthly deposit progress = 97%; Phase E: Monthly deposit progress = 100%.
[0012] Furthermore, the on-site progress assessment module divides the on-site progress into two stages: from the start of construction to 80% completion of the on-site progress, which is stage I; from 80% completion of the on-site progress to 100% completion of the on-site progress, which is stage II; The monthly on-site progress of each phase is evaluated as follows: Phase I: Monthly on-site progress = 80% / Phase I construction period in months Phase II: Monthly on-site progress = 80% + 20% / number of months for Phase II.
[0013] Furthermore, the coupling evaluation module includes the following calculations: Statistical construction period: Construction period = number of months of construction period in Phase I + number of months of construction period in Phase II Evaluate monthly deviation: Monthly deviation = Monthly on-site progress - Monthly account progress Evaluate coupling deviation: Coupling deviation = Evaluate coupling: Coupling = .
[0014] An electronic device comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the steps of a method for evaluating the coupling degree between the accounting progress and the on-site construction progress of a power grid infrastructure project based on the PSQ settlement mode are implemented as described above.
[0015] A non-transitory computer-readable storage medium stores a computer program, which, when executed by a processor, implements the steps of a method for evaluating the coupling degree between the accounting progress and on-site construction progress of a power grid infrastructure project based on the PSQ settlement model as described above.
[0016] Compared with the prior art, the present invention and its preferred solution can evaluate the monthly accounting progress and monthly on-site progress of power grid infrastructure projects, predict the deviation between the monthly accounting progress and the monthly on-site progress, and thus calculate the coupling degree between the accounting progress and the engineering progress of power grid infrastructure projects, providing support for improving the investment completion rate of power grid infrastructure projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments: Figure 1 It is a schematic diagram of the construction process of the embodiment of the present invention. DETAILED DESCRIPTION
[0018] Hereinafter, the specific embodiments of the present application will be described in detail with reference to the accompanying drawings. According to these detailed descriptions, those skilled in the art can clearly understand the present application and can implement the present application. Without violating the principles of the present application, the features in the various embodiments can be combined to obtain new implementations, or certain features in certain embodiments can be replaced to obtain other preferred implementations.
[0019] In order to make the features and advantages of the present invention more clearly understood, the following embodiments are specifically described in detail with reference to the accompanying drawings: like Figure 1The overall construction process of a method and system for evaluating the coupling degree between the accounting progress and the on-site construction progress of a power grid infrastructure project based on the PSQ settlement mode provided by the present invention includes the following steps: S1: Determine the settlement standards for the PSQ settlement model: PSQ settlement model definition: The costs of power grid infrastructure projects only include progress payments, completion settlement payments and warranty deposits.
[0020] Progress payment settlement standard: Progress payment is paid twice. When the on-site progress is 80% completed, the first progress payment can be settled, with a maximum of 50%; when the on-site progress is 80% completed, the second progress payment can be settled, with a maximum of 80%; Guarantee deposit settlement standard: if there are no governance issues within one year after the completion of the project, the guarantee deposit will be settled at 3%; Completion settlement payment settlement standard: After the project is completed, the contract amount minus the progress payment already paid and the retained warranty deposit is the completion settlement payment, which is 17%; Warranty period = 12 months; Thus, a PSQ settlement module is constructed to realize the calculation of settlement costs for power grid infrastructure project costs using the PSQ settlement model.
[0021] S2: Evaluate the monthly progress of power grid infrastructure projects: Account entry progress division: Phase A: From the start of construction to 80% completion of the on-site progress; Phase B: From 80% to 100% completion of the on-site progress Stage C is when the on-site progress is 100% completed until the project is finalized and settled; The period from project completion settlement to payment of warranty deposit is the D stage; Pay the security deposit, which is the E stage; Evaluate monthly deposit progress: Phase A: Monthly deposit progress = 0; Phase B: Monthly deposit progress = 50%; Phase C: Monthly deposit progress = 70%; Phase D: Monthly deposit progress = 97%; Phase E: Monthly deposit progress = 100%; Thus, a payment progress assessment module is constructed to evaluate the monthly payment progress of power grid infrastructure project expenses.
[0022] S3: Evaluate the monthly on-site progress of power grid infrastructure projects: On-site progress division: The period from the start of construction to 80% completion of the on-site progress is the first stage; The second stage is when the on-site progress is 80% to 100% completed; Monthly on-site progress: Phase I: Monthly on-site progress = 80% / Phase I construction period in months Phase II: Monthly on-site progress = 80% + 20% / Phase II construction period in months; Thus, a field progress assessment module is constructed to assess the monthly field progress of power grid infrastructure projects; Among them, we can first define the construction period = the number of months of the first stage + the number of months of the second stage.
[0023] S4: Evaluate the coupling degree between the accounting progress and engineering progress of power grid infrastructure projects: Evaluate monthly deviation = monthly on-site progress - monthly account progress Evaluate coupling deviation: Coupling deviation = Evaluate coupling: Coupling = The coupling evaluation module thus constructed can evaluate the monthly accounting progress and monthly on-site progress of power grid infrastructure projects as a whole, predict the deviation between the monthly accounting progress and the monthly on-site progress, and thus calculate the coupling degree between the accounting progress and the engineering progress of power grid infrastructure projects.
[0024] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present application may adopt the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program codes.
[0025] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0026] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0027] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 A step that specifies a function in one or more boxes.
[0028] It should be noted that, unless otherwise defined, the technical terms or scientific terms used in the present invention should be understood by people with ordinary skills in the field to which the present invention belongs. The "first", "second" and similar words used in the present invention do not indicate any order, quantity or importance, but are only used to distinguish different components. "Include" or "comprise" and similar words mean that the elements or objects appearing before the word include the elements or objects listed after the word and their equivalents, without excluding other elements or objects. "Connect" or "connected" and similar words are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect. "Up", "down", "left", "right" and the like are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.
[0029] The above is only a preferred embodiment of the present invention, and does not limit the present invention in other forms. Any technician familiar with the profession may use the above disclosed technical content to change or modify it into an equivalent embodiment with equivalent changes. However, any simple modification, equivalent change and modification made to the above embodiment according to the technical essence of the present invention without departing from the technical solution of the present invention still belongs to the protection scope of the technical solution of the present invention.
[0030] The present invention is not limited to the above-mentioned optimal implementation mode. Anyone can derive various other forms of a method and system for evaluating the coupling degree between the accounting progress and the on-site construction progress of a power grid infrastructure project based on the PSQ settlement model under the inspiration of the present invention. All equivalent changes and modifications made within the scope of the patent application of the present invention shall fall within the scope of the present invention.
Claims
1. A method for evaluating the coupling degree between the accounting progress and on-site construction progress of power grid infrastructure projects based on the PSQ settlement model, characterized by: Based on the PSQ settlement model, by evaluating the monthly accounting progress and monthly on-site progress of power grid infrastructure projects, the deviation between the monthly accounting progress and the monthly on-site progress is predicted, thereby calculating the coupling degree between the accounting progress and the engineering progress of power grid infrastructure projects.
2. According to claim 1, a method for evaluating the coupling degree between the accounting progress and the on-site construction progress of a power grid infrastructure project based on the PSQ settlement mode, characterized in that: The PSQ settlement model is used to set the power grid infrastructure project costs to include only progress payments, completion settlement payments and warranty deposits; and the warranty period is 12 months; Among them, the progress payment settlement standard is: progress payment is paid twice, and when the on-site progress is 80% completed, the first progress payment is settled, with a maximum of 50%; when the on-site progress is 80% completed, the second progress payment can be settled, with a maximum of 80%; The settlement standard for the quality guarantee deposit is: if there are no governance issues within one year after the completion of the project, the quality guarantee deposit will be settled at 3%; The settlement standard for the final settlement payment is: after the project is completed, the contract amount minus the progress payment already paid and the retained warranty deposit is the final settlement payment, which is 17%.
3. According to claim 1, a method for evaluating the coupling degree between the accounting progress and the on-site construction progress of a power grid infrastructure project based on the PSQ settlement mode, characterized in that: The monthly progress of the assessed power grid infrastructure project is as follows: The progress of depositing funds is divided into 5 stages: Phase A: From the start of construction to 80% completion of the on-site progress; Phase B: From 80% to 100% completion of the on-site progress Stage C is when the on-site progress is 100% completed until the project is finalized and settled; The period from project completion settlement to payment of warranty deposit is the D stage; Pay the security deposit, which is the E stage; This will evaluate the monthly progress of each stage: Phase A: Monthly deposit progress = 0; Phase B: Monthly deposit progress = 50%; Phase C: Monthly deposit progress = 70%; Phase D: Monthly deposit progress = 97%; Phase E: Monthly deposit progress = 100%.
4. According to claim 1, a method for evaluating the coupling degree between the accounting progress and the on-site construction progress of a power grid infrastructure project based on the PSQ settlement mode is characterized by: The monthly progress of the assessed power grid infrastructure project is as follows: The on-site progress is divided into two stages: the first stage is from the start of construction to 80% completion of the on-site progress; the second stage is from 80% completion of the on-site progress to 100% completion of the on-site progress; This is how the monthly on-site progress of each phase is assessed: Phase I: Monthly on-site progress = 80% / Phase I construction period in months Phase II: Monthly on-site progress = 80% + 20% / number of months for Phase II.
5. According to claim 1, a method for evaluating the coupling degree between the accounting progress and the on-site construction progress of a power grid infrastructure project based on the PSQ settlement mode, characterized in that: The deviation between the predicted monthly payment progress and the monthly on-site progress is as follows: Statistical construction period: Construction period = number of months of construction period in Phase I + number of months of construction period in Phase II Evaluate monthly deviation: Monthly deviation = Monthly on-site progress - Monthly account progress Evaluate coupling deviation: Coupling deviation = Evaluate coupling: Coupling = .
6. A coupling evaluation system for the accounting progress and on-site construction progress of power grid infrastructure projects based on the PSQ settlement model, based on a computer system, characterized by: include: PSQ settlement module, account entry progress assessment module, on-site progress assessment module and coupling degree assessment module; The PSQ settlement module is used to calculate the settlement costs of power grid infrastructure project costs using the PSQ settlement model; The account entry progress evaluation module is used to evaluate the monthly account entry progress of power grid infrastructure project expenses; The on-site progress assessment module is used to assess the monthly on-site progress of power grid infrastructure projects; The coupling degree evaluation module is used to evaluate the coupling degree between the accounting progress and the engineering progress of the power grid infrastructure project.
7. According to claim 6, a system for evaluating the coupling degree between the accounting progress and the on-site construction progress of power grid infrastructure projects based on the PSQ settlement mode, characterized in that: The PSQ settlement model stipulates that the costs of power grid infrastructure projects only include progress payments, completion settlement payments and warranty deposits; and the warranty period is 12 months; Among them, the progress payment settlement standard is: progress payment is paid twice, and when the on-site progress is 80% completed, the first progress payment is settled, with a maximum of 50%; when the on-site progress is 80% completed, the second progress payment can be settled, with a maximum of 80%; The settlement standard for the quality guarantee deposit is: if there are no governance issues within one year after the completion of the project, the quality guarantee deposit will be settled at 3%; The settlement standard for the final settlement payment is: after the project is completed, the contract amount minus the progress payment already paid and the retained warranty deposit is the final settlement payment, which is 17%.
8. The system for evaluating the coupling degree between the accounting progress and the on-site construction progress of power grid infrastructure projects based on the PSQ settlement mode according to claim 6 is characterized by: The account entry progress evaluation module divides the account entry progress into five stages: Phase A: From the start of construction to 80% completion of the on-site progress; Phase B: From 80% to 100% completion of the on-site progress Stage C is when the on-site progress is 100% completed until the project is finalized and settled; The period from project completion settlement to payment of warranty deposit is the D stage; Pay the security deposit, which is the E stage; This will evaluate the monthly progress of each stage: Phase A: Monthly deposit progress = 0; Phase B: Monthly deposit progress = 50%; Phase C: Monthly deposit progress = 70%; Phase D: Monthly deposit progress = 97%; Phase E: Monthly deposit progress = 100%.
9. The system for evaluating the coupling degree between the accounting progress and the on-site construction progress of power grid infrastructure projects based on the PSQ settlement mode according to claim 6 is characterized by: The on-site progress assessment module divides the on-site progress into two stages: the first stage is from the start of construction to 80% completion of the on-site progress; the second stage is from 80% completion of the on-site progress to 100% completion of the on-site progress; This is how the monthly on-site progress of each phase is assessed: Phase I: Monthly on-site progress = 80% / Phase I construction period in months Phase II: Monthly on-site progress = 80% + 20% / number of months for Phase II.
10. The system for evaluating the coupling degree between the accounting progress and the on-site construction progress of power grid infrastructure projects based on the PSQ settlement mode according to claim 6, characterized in that: The coupling evaluation module includes the following calculations: Statistical construction period: Construction period = number of months of construction period in Phase I + number of months of construction period in Phase II Evaluate monthly deviation: Monthly deviation = Monthly on-site progress - Monthly account progress Evaluate coupling deviation: Coupling deviation = Evaluate coupling: Coupling = .