Measurement scheme generation method and system for river control engineering

By generating river prevention and control paths and path measurement tasks, determining complexity with historical environmental information, and dynamically adjusting the measurement plan, the problem of insufficient design accuracy of river prevention and control engineering in the existing technology is solved, and a more efficient and accurate measurement plan design is achieved.

CN119515646AInactive Publication Date: 2025-02-25SHANXI URBAN AGGLOMERATION INVESTMENT & CONSTR GRP CO LTD +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202510089316.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-21
Publication Date
2025-02-25
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The design of existing river prevention and control projects depends on human experience, and it is difficult to ensure the accuracy of measurement plans, especially in complex engineering environments and large amounts of construction data.

Method used

Provide a method and system for measuring scheme generation of river control projects. By generating river control paths and path measurement tasks, combining historical environmental information to determine the path measurement complexity, and dynamically adjust the measurement scheme to improve design accuracy.

Benefits of technology

It improves the accuracy of the measurement solution design, ensures the pertinence and effectiveness of the measurement, reduces the measurement cost, and improves the accuracy and reliability of the measurement data.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119515646A_ABST
    Figure CN119515646A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of river prevention and control, in particular to a measurement scheme generation method and system for river prevention and control engineering. The method comprises the following steps: generating a river prevention and control path and a path measurement task corresponding to the river prevention and control path according to a river area in a target scene; determining the path measurement complexity of the path measurement task according to the environment information of the target scene in the historical time period; the environment information at least comprises weather information, geographic information and traffic information; according to the path measurement complexity and a path measurement task corresponding to the river prevention and control path, generating a measurement scheme for the river prevention and control path in a future time period; wherein the measurement scheme at least comprises a measurement position in the river prevention and control path, a measurement period corresponding to the measurement position, measurement equipment required by the measurement position and a measurement strategy adopted by the measurement equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of river control, and in particular to a method and system for generating a measurement plan for a river control project. Background Art

[0002] River control projects are a general term for a series of engineering and technical measures related to river protection, control and improvement. These projects aim to prevent, reduce and even eliminate pollution in rivers and their basins, improve and maintain water environment quality, and make rational use of water resources.

[0003] Currently, river control projects are usually artificially designed by teams of experts.

[0004] However, faced with complex engineering environments and a large amount of construction data, designs based solely on human experience may lack accuracy. Summary of the invention

[0005] Based on this, it is necessary to provide a method and system for generating a measurement plan for a river control project that can improve the accuracy of measurement plan design in response to the above technical problems.

[0006] In a first aspect, the present application provides a method for generating a measurement plan for a river control project, the method comprising: Generate river control paths and path measurement tasks corresponding to the river control paths according to the river areas in the target scene; Determine the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period; the environmental information includes at least weather information, geographical information and traffic information; According to the path measurement complexity and the path measurement tasks corresponding to the river control path, a measurement plan for the river control path in the future period is generated; The measurement plan includes at least the measurement location in the river control path, the measurement period corresponding to the measurement location, the measurement equipment required for the measurement location, and the measurement strategy adopted by the measurement equipment.

[0007] In one embodiment, generating a river prevention and control path according to a river area in a target scene includes: Determine the key river control locations in the target scene based on the target river characteristics corresponding to the river area in the target scene; the river characteristics include at least the river direction, width, depth and water flow speed; With the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate a river control path covering key locations for river control; Among them, construction feasibility conditions include at least geological stability conditions, hydrological conditions, traffic conditions, equipment and technical conditions, and safety conditions.

[0008] In one embodiment, with the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate a river control path covering key control points, including: With the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate an initial river path covering key locations for river control; In the river record library, query the historical river path corresponding to the historical river characteristics matching the target river characteristics; Based on the path construction records of historical river paths, potential construction failures in the initial river path are analyzed to optimize the initial river path and obtain a river control path covering the key control point locations.

[0009] In one embodiment, with the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate an initial river path covering the key control points, including: Obtain terrain description information of key prevention and control points; terrain description information includes at least topographic maps, hydrological data, geological exploration data, environmental protection requirements and construction specifications; Use Geographic Information System (GIS) tools to perform spatial analysis on terrain description information and obtain digital maps corresponding to key locations for river control; In the digital map, the key locations of river control are used as nodes, and the construction costs are used as edges between nodes to build a graph model; With the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, an initial river path covering the key prevention and control points is generated in the digital map according to the path optimization algorithm corresponding to the graph model.

[0010] In one embodiment, determining the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period includes: Divide the river control path to obtain multiple adjacent sub-sections; According to the path measurement tasks corresponding to the river control path, the section measurement tasks of each sub-section are determined; According to the environmental information of the target scene in the historical period, the measurement complexity of each sub-section is determined; Determine the path measurement complexity of the path measurement task according to the road section measurement complexity corresponding to each sub-road section; Accordingly, according to the path measurement complexity and the path measurement tasks corresponding to the river control path, a measurement plan for the river control path in the future period is generated, including: For each sub-section, according to the section measurement complexity and the section measurement task corresponding to the sub-section, a section measurement plan for the sub-section in the future period is generated; According to the section measurement plan of each sub-section in the future period, a measurement plan for the river control path in the future period is generated.

[0011] In one embodiment, the road section measurement tasks corresponding to the sub-road section include field measurement tasks, office measurement tasks, and control measurement tasks; According to the measurement complexity of the sub-section and the measurement task of the sub-section, a measurement plan for the sub-section in the future period is generated, including: According to the measurement complexity of the sub-section and the measurement task of the sub-section, the position of the main control point is determined, and the position of the main control point is used as the measurement position in the river control path; According to the measurement complexity of the road section corresponding to the sub-road section, the measurement cycle corresponding to the measurement position and the measurement equipment required for the measurement position are determined, and the field measurement plan required for the sub-road section to perform the field measurement work task is obtained; According to the field measurement plan, the measurement office work tasks and the control measurement tasks, a section measurement plan for the sub-section in the future period is generated.

[0012] In one embodiment, a road section measurement plan for a sub-road section in a future period is generated according to the field measurement plan, the measurement office work tasks and the control measurement tasks, including: Based on the surveying internal work tasks, a verification method for verifying the external surveying plan is generated to obtain the internal surveying plan required for the sub-section to perform the surveying internal work tasks; According to the field measurement plan, the indoor measurement plan and the control measurement task, a section measurement plan for the sub-section in the future period is generated.

[0013] In one embodiment, a road section measurement plan for a sub-road section in a future period is generated according to an outdoor measurement plan, an indoor measurement plan, and a control measurement task, including: Generate the plane control measurement and control system and elevation control measurement and control system corresponding to the control measurement task according to the field measurement plan and the indoor measurement plan; Based on the field measurement plan, the indoor measurement plan, the plane control measurement and control system and the elevation control measurement and control system, a section measurement plan for the sub-section in the future period is generated.

[0014] In one embodiment, determining the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period includes: Input the environmental information of the target scene in the historical period into the environmental analysis model, and obtain the path measurement complexity of the path measurement task output by the environmental analysis model; Among them, the environmental analysis model is constructed using an improved multi-factor comprehensive evaluation algorithm.

[0015] In a second aspect, the present application also provides a system for generating a measurement plan for a river control project, the system comprising: A control path generation module is used to generate a river control path and a path measurement task corresponding to the river control path according to the river area in the target scene; A construction complexity calculation module is used to determine the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period; the environmental information includes at least weather information, geographical information and traffic information; A measurement plan generation module is used to generate a measurement plan for the river control path in a future period according to the path measurement complexity and the path measurement tasks corresponding to the river control path; The measurement plan includes at least the measurement location in the river control path, the measurement period corresponding to the measurement location, the measurement equipment required for the measurement location, and the measurement strategy adopted by the measurement equipment.

[0016] In a third aspect, the present application further provides a computer device, including a memory and a processor, wherein the memory stores a computer program, and when the processor executes the computer program, the following steps are implemented: Generate river control paths and path measurement tasks corresponding to the river control paths according to the river areas in the target scene; Determine the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period; the environmental information includes at least weather information, geographical information and traffic information; According to the path measurement complexity and the path measurement tasks corresponding to the river control path, a measurement plan for the river control path in the future period is generated; The measurement plan includes at least the measurement location in the river control path, the measurement period corresponding to the measurement location, the measurement equipment required for the measurement location, and the measurement strategy adopted by the measurement equipment.

[0017] In a fourth aspect, the present application further provides a computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the following steps are implemented: Generate river control paths and path measurement tasks corresponding to the river control paths according to the river areas in the target scene; Determine the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period; the environmental information includes at least weather information, geographical information and traffic information; According to the path measurement complexity and the path measurement tasks corresponding to the river control path, a measurement plan for the river control path in the future period is generated; The measurement plan includes at least the measurement location in the river control path, the measurement period corresponding to the measurement location, the measurement equipment required for the measurement location, and the measurement strategy adopted by the measurement equipment.

[0018] In a fifth aspect, the present application further provides a computer program product, including a computer program, which implements the following steps when executed by a processor: Generate river control paths and path measurement tasks corresponding to the river control paths according to the river areas in the target scene; Determine the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period; the environmental information includes at least weather information, geographical information and traffic information; According to the path measurement complexity and the path measurement tasks corresponding to the river control path, a measurement plan for the river control path in the future period is generated; The measurement plan includes at least the measurement location in the river control path, the measurement period corresponding to the measurement location, the measurement equipment required for the measurement location, and the measurement strategy adopted by the measurement equipment.

[0019] The above-mentioned method and system for generating a measurement plan for a river control project can carry out river management and control work in a more targeted manner by generating a specific river control path, thereby improving the control efficiency. Customized path measurement tasks can ensure the accuracy and effectiveness of measurements based on the actual situation in the target scenario. Considering environmental information (such as weather, geography, and traffic) in historical periods can more accurately assess the complexity of path measurement tasks, and then dynamically adjust measurement plans in future periods to cope with possible changes and challenges. By accurately determining the measurement location, measurement cycle, required measurement equipment, and measurement strategy, unnecessary measurements and equipment use can be avoided, thereby reducing measurement costs. The measurement plan generated by comprehensively considering multiple factors can ensure that the most appropriate measurement equipment is used for measurement at the best time and place, thereby improving the accuracy and reliability of measurement data. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the technical solutions in the embodiments of the present application or related technologies, the drawings required for use in the embodiments of the present application or related technical descriptions will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0021] Figure 1A schematic diagram of a flow chart of a method for generating a measurement plan for a river control project in one embodiment; Figure 2 A schematic diagram of a flow chart of the steps of generating a river prevention and control path in one embodiment; Figure 3 A schematic flow chart of the steps of generating a river control path covering key control point locations in one embodiment; Figure 4 A schematic diagram of a flow chart of steps for generating an initial river path covering key river control locations using a path optimization algorithm in one embodiment; Figure 5 A schematic diagram of a flow chart of a step of determining a path measurement complexity of a path measurement task in an embodiment; Figure 6 A schematic flow chart of steps for generating a road section measurement plan for a sub-road section in a future time period in one embodiment; Figure 7 A structural block diagram of a system for generating a measurement plan for a river control project in one embodiment. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0023] In an exemplary embodiment, Figure 1 As shown, a method for generating a measurement plan for a river control project is provided, comprising: S101, generating a river prevention and control path and a path measurement task corresponding to the river prevention and control path according to a river area in a target scene.

[0024] First, analyze the river area in the target scenario, including: analyzing the topographic and geomorphic features of the river area, including the direction, width, depth, curvature of the river, and the topographic undulations and geomorphic types on both sides of the river. Understand the hydrological conditions of the river, including water flow velocity, water level changes, water quality conditions, etc., as well as the river's flood history and flood control capabilities. Assess the ecological and environmental conditions of the river area, including vegetation coverage, biodiversity, water pollution levels, etc., as well as the impact of the river on the surrounding ecological environment. Clarify the goals of river prevention and control, such as improving flood control capabilities, improving water quality, protecting the ecological environment, etc., as well as the specific requirements and restrictions of prevention and control projects.

[0025] Optionally, when generating a river prevention and control path, the following method can be used: Based on the analysis results of the river area, determine the key areas and key links of prevention and control, such as river sections prone to flooding, areas with serious water pollution, etc. Combined with the prevention and control goals and key areas, plan a reasonable prevention and control path. This usually includes determining the starting point, end point and key nodes of the prevention and control project, as well as the direction and layout of the path. When planning a prevention and control path, it is necessary to consider the feasibility of the project, including construction conditions, material sources, technical difficulty and other factors to ensure the feasibility of the path and the implementation effect.

[0026] Furthermore, after the river control path is generated, the specific requirements of the path measurement task are clarified according to the planning of the control path, including the measurement range, accuracy, time point, etc. According to the measurement requirements, appropriate measurement methods and technologies are selected, such as remote sensing measurement, drone aerial survey, ground measurement, etc. Combined with the measurement methods and requirements, a detailed measurement plan is formulated, including the division of labor of measurement personnel, the configuration of measurement equipment, and the arrangement of measurement time.

[0027] S102: Determine the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period.

[0028] The environmental information includes at least weather information, geographic information and traffic information.

[0029] For example, weather information includes weather data of the target scene in the historical period, such as rainfall, temperature, humidity, wind speed, wind direction, etc. Geographic information includes river width, depth, flow rate, flow direction, river terrain, obstacle location, etc. Traffic information includes river traffic flow, bridge and ferry location, regulatory restrictions, and other traffic-related information.

[0030] Specifically, the path measurement complexity of the path measurement task is determined according to the environmental information of the target scene in the historical period, including: inputting the environmental information of the target scene in the historical period into the environmental analysis model, and obtaining the path measurement complexity of the path measurement task output by the environmental analysis model.

[0031] Among them, the environmental analysis model is constructed using an improved multi-factor comprehensive evaluation algorithm.

[0032] Specifically, the model training process of the environmental analysis model is: First, weather information, geographic information, and traffic information are used as key factors to evaluate the complexity of path measurement. Since the data units and dimensions of different factors may be different, the collected environmental information needs to be standardized to ensure that each factor has equal weight in the evaluation.

[0033] Secondly, assign corresponding weights to each factor according to its importance. This can be determined by expert scoring, analytic hierarchy process (AHP) or entropy weight method. The weight allocation should take into account the possible mutual influence and constraint relationship between different factors.

[0034] Finally, the improved multi-factor comprehensive evaluation algorithm is used to multiply the standardized data by the corresponding weight to obtain the comprehensive evaluation value of each factor. Then, the comprehensive evaluation values ​​of all factors are added together to obtain the overall complexity of the path measurement task.

[0035] S103, generating a measurement plan for the river control path in a future period according to the path measurement complexity and the path measurement task corresponding to the river control path.

[0036] The measurement plan includes at least the measurement location in the river control path, the measurement period corresponding to the measurement location, the measurement equipment required for the measurement location, and the measurement strategy adopted by the measurement equipment.

[0037] It can be understood that key nodes refer to key nodes that need to be measured based on the planning of river control paths and analysis of path measurement complexity, such as river bends, areas with large changes in depth, possible obstacle locations, etc. On the premise of ensuring that the entire control path is covered, the measurement locations are distributed as evenly as possible to obtain a more comprehensive understanding of the river situation.

[0038] Furthermore, the measurement location can be dynamically adjusted based on historical data and real-time monitoring results to cope with changes in river conditions.

[0039] Then, according to the complexity of path measurement and prevention and control needs, set a regular measurement cycle, such as weekly, monthly or quarterly measurement.

[0040] Furthermore, the measuring equipment is selected according to the measuring location, measuring cycle and measuring accuracy requirements; then, the type and quantity of equipment required for each measuring location are determined to ensure the smooth progress of the measuring work.

[0041] In the above-mentioned method for generating a measurement plan for a river control project, by generating a specific river control path, river management and control work can be carried out in a more targeted manner, thereby improving the control efficiency. According to the actual situation in the target scenario, the customized path measurement task can ensure the accuracy and effectiveness of the measurement. Considering the environmental information in the historical period (such as weather, geography, traffic, etc.), the complexity of the path measurement task can be more accurately evaluated, and the measurement plan can be dynamically adjusted in the future period to cope with possible changes and challenges. By accurately determining the measurement location, measurement cycle, required measurement equipment, and measurement strategy, unnecessary measurement and equipment use can be avoided, thereby reducing measurement costs. The measurement plan generated by comprehensively considering multiple factors can ensure that the most appropriate measurement equipment is used for measurement at the best time and place, thereby improving the accuracy and reliability of the measurement data.

[0042] In an exemplary embodiment, Figure 2 As shown in the figure, according to the river area in the target scene, a river control path is generated, including: S201, determining a key position for river control in the target scene according to target river characteristics corresponding to a river area in the target scene.

[0043] Among them, river characteristics include at least river direction, width, depth and water flow speed.

[0044] Optionally, the direction and path of the river can be identified through maps or remote sensing images. The impact of river direction on water flow dynamics, sediment transport and pollutant dispersion can be analyzed.

[0045] Furthermore, the width of the river can be measured at different locations to identify areas with large width changes, which may be the focus of water velocity changes, silt accumulation or scour.

[0046] Furthermore, river depth data can be obtained using bathymetric equipment or remote sensing technology to analyze depth changes, especially the distribution of deep and shallow water areas, which have an important impact on the behavior of water flow, sediment and pollutants.

[0047] Furthermore, water velocity data is obtained through field measurements or numerical simulations. Changes in water velocity are analyzed to identify high-speed and low-speed flow areas, which may involve the concentration and consumption of water flow energy.

[0048] Among them, key locations for river control may include: 1) Bends: The bends of rivers are areas with complex flow dynamics, where sediment deposition and scour are prone to occur. According to the changes in the direction and width of the river, bends should be identified and marked as key locations for prevention and control.

[0049] 2) Wide and shallow sections and deep and narrow sections: Wide and shallow sections may be prone to sedimentation and pollutant retention, while deep and narrow sections may form high-speed flow areas, aggravating riverbed erosion. These key sections are determined by analyzing river width and depth data.

[0050] 3) Areas of water velocity change: Changes in water velocity will affect the movement of sediment and pollutants. Based on water velocity data, identify areas where velocity changes significantly, especially the junction of high-speed and low-speed flow areas.

[0051] 4) Other special areas: such as river confluences, estuaries, unstable sections of embankments, etc. These areas may also become key locations for prevention and control.

[0052] Overlay the key locations identified above to find overlapping or adjacent areas, which may be complex areas where multiple problems coexist. Conduct risk assessment for each key location, considering its impact on river ecosystems, flood control safety, water quality protection, etc. Based on the risk assessment results, determine the prevention and control strategies for each key location, such as strengthening embankments, dredging rivers, and building ecological revetments.

[0053] S202, with the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate a river control path covering key locations for river control.

[0054] Among them, construction feasibility conditions include at least geological stability conditions, hydrological conditions, traffic conditions, equipment and technical conditions, and safety conditions.

[0055] Specifically, the determination of geological stability conditions includes geological exploration reports to identify unstable geological areas. The determination of hydrological conditions includes collecting hydrological data to understand changes in water levels, flow rates, etc. The determination of traffic conditions includes investigating surrounding traffic conditions, including roads, bridges, etc. The determination of equipment and technical conditions includes evaluating existing equipment and technical capabilities and determining construction restrictions. The determination of safety conditions includes analyzing safety risks during construction and formulating safety specifications.

[0056] Optionally, key location data, construction feasibility condition data and cost function are input into the path optimization model. The path optimization algorithm is executed to generate a prevention and control path covering all key locations. Based on the algorithm output, the path with the lowest cost is selected as the optimal solution.

[0057] In an exemplary embodiment, Figure 3 As shown in the figure, with the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate a river control path covering the key control points, including: S301, with the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate an initial river path covering key locations for river control.

[0058] Optionally, collect and organize information on key river control locations, including location coordinates, control requirements, etc. Obtain detailed maps or remote sensing images of the construction area for path planning. Collect relevant data on construction feasibility conditions, such as geological survey reports, hydrological data, traffic conditions, etc. Select an appropriate path optimization algorithm based on the scale and complexity of the problem. Commonly used algorithms include Dijkstra algorithm, A* algorithm, genetic algorithm, etc. These algorithms can generate optimal or near-optimal paths based on different optimization objectives and constraints.

[0059] Using the collected data and the selected algorithm, a path optimization model is constructed. In the model, the construction cost is used as the objective function and the construction feasibility conditions are used as constraints. The path optimization algorithm is executed to generate an initial river path covering all key locations for river control. The algorithm searches and finds the path with the lowest cost based on the objective function and constraints.

[0060] S302, in the river record library, query the historical river path corresponding to the historical river characteristics matching the target river characteristics.

[0061] Specifically, historical river paths that match the characteristics of the target river are searched in the river record library so that past experience can be used to guide current path planning.

[0062] S303, based on the path construction records of the historical river paths, potential construction failures in the initial river path are analyzed to optimize the initial river path to obtain a river control path covering the key control point locations.

[0063] Optionally, based on the construction records of historical river paths, possible construction failures in the initial river path are analyzed and optimized to obtain a more reliable and economical river control path.

[0064] Obtain detailed construction records for the selected historical river path. These records should include problems, failures, solutions, and final construction results during the construction process. Conduct in-depth analysis of the failures in the construction records to find out the causes of the failures, the types of failures, and the impact of the failures on construction costs and time. Based on the analysis results of historical failures, identify potential construction failures that may exist in the initial river path. These failures may include geological instability, water scouring, equipment failure, etc.

[0065] Furthermore, the initial river path is optimized for the identified potential failures. Optimization measures may include adjusting the path direction, adding support structures, switching to more reliable construction equipment, etc. Through simulation or actual construction, it is verified whether the optimized path can effectively avoid or reduce the occurrence of construction failures and ensure that construction costs and time are reasonably controlled.

[0066] In this embodiment, by implementing steps S302 and S303, historical data and experience are fully utilized to guide the generation and optimization of the river control path, so that the final river control path will be more in line with actual construction needs.

[0067] In an exemplary embodiment, Figure 4 As shown in the figure, with the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate an initial river path covering key locations for river control, including: S401, obtaining terrain description information of key prevention and control points.

[0068] The terrain description information includes at least topographic maps, hydrological data, geological exploration data, environmental protection requirements and construction specifications.

[0069] Specifically, collect topographic maps of key prevention and control points to understand information such as terrain undulations and elevations. Collect hydrological data, including water level changes, flow velocity, and flow, to assess the impact of hydrodynamic conditions on construction. Obtain geological exploration data to understand geological structure, soil stability, etc., to ensure geological safety during construction. Check environmental protection requirements to ensure that construction activities meet ecological protection and pollution control standards. Understand construction specifications, including construction methods, material selection, safety standards, etc., to guide the standardization of the construction process.

[0070] S402, using geographic information system (GIS) tools, spatially analyzing the terrain description information to obtain a digital map containing key locations for river control.

[0071] Specifically, GIS tools are used to import topographic maps, hydrological data, geological exploration data, etc. Spatial analysis, such as overlay analysis, terrain analysis, hydrological analysis, etc., is performed to extract key terrain features. A digital map containing key river control locations and their surroundings is generated to provide a basis for subsequent path optimization.

[0072] S403, in the digital map, key river control locations are used as nodes, and construction costs are used as edges between nodes to construct a graph model.

[0073] For example, in a digital map, key river control locations are nodes, representing points that need to be addressed or paid attention to. Construction costs are used as edges between nodes to represent the cost of construction from one key location to another. Construction costs can take into account factors such as material costs, labor costs, and equipment costs. A graph model is constructed, including nodes, edges, and related weights (construction costs), to provide input for subsequent path optimization algorithms.

[0074] S404, with the goal of minimizing the construction cost and the constraints of satisfying the construction feasibility conditions, an initial river path covering the key prevention and control points is generated in the digital map according to the path optimization algorithm corresponding to the graph model.

[0075] Optionally, select a suitable path optimization algorithm, such as Dijkstra algorithm, A* algorithm, genetic algorithm, etc. These algorithms can find the minimum cost path based on the nodes and edges in the graph model. With the goal of minimizing the construction cost, the construction feasibility conditions (such as geological stability, hydrological conditions, traffic conditions, etc.) are input into the path optimization algorithm as constraints. Run the algorithm in the digital map to generate an initial river path covering all key prevention and control points. The path should meet the construction feasibility conditions and minimize the construction cost. Output the initial river path results, including the path direction, length, key locations along the way, etc., to provide guidance for subsequent detailed design and construction.

[0076] In this embodiment, through the implementation of steps S401 to S404, terrain description information is systematically collected and analyzed, a graph model is constructed, and a path optimization algorithm is applied to generate an initial river path. This process ensures that the generation of the path not only takes into account the minimization of construction costs, but also meets the requirements of construction feasibility conditions.

[0077] In an exemplary embodiment, Figure 5 As shown, according to the environmental information of the target scene in the historical period, the path measurement complexity of the path measurement task is determined, including: S501, dividing the river control path to obtain a plurality of adjacent sub-segments.

[0078] Specifically, the river control path is divided into multiple adjacent sub-sections according to its characteristics and measurement requirements, ensuring that each sub-section has a clear starting point and end point, and that the sub-sections are seamlessly connected.

[0079] S502: Determine the section measurement task of each sub-section according to the path measurement task corresponding to the river control path.

[0080] Specifically, according to the path measurement tasks corresponding to the river control path, determine the specific content that needs to be measured in each sub-section, such as water level, flow rate, water quality, etc. Determine the measurement frequency and measurement time of each sub-section to ensure the continuity and accuracy of the data.

[0081] S503: Determine the measurement complexity of each sub-road section according to the environmental information of the target scene in the historical period.

[0082] Specifically, collect environmental information of the target scene in the historical period, including data on climate, hydrology, geology, etc. According to the environmental information and the measurement tasks of the sub-section, evaluate the complexity of each sub-section measurement. The complexity may be affected by many factors, such as terrain complexity, water flow speed, accessibility of measurement equipment, etc.

[0083] S504: Determine the path measurement complexity of the path measurement task according to the road section measurement complexity corresponding to each sub-road section.

[0084] Specifically, the complexity of the route measurement of each sub-segment is summarized and analyzed. According to the complexity of the sub-segments and their proportion in the overall route, the overall complexity of the route measurement task is determined.

[0085] Correspondingly, based on the path measurement complexity and the path measurement tasks corresponding to the river control path, a measurement plan for the river control path in the future time period is generated, including: for each sub-section, based on the section measurement complexity corresponding to the sub-section and the section measurement tasks corresponding to the sub-section, a section measurement plan for the sub-section in the future time period is generated; based on the section measurement plans of each sub-section in the future time period, a measurement plan for the river control path in the future time period is generated.

[0086] Optionally, for each sub-section, a specific section measurement plan is formulated according to the measurement complexity and measurement tasks of the section. The plan should include measurement methods, measurement equipment, measurement personnel, safety measures, etc.

[0087] Integrate and coordinate the road measurement plans of each sub-section to ensure their connection and coordination.

[0088] Generate an overall measurement plan for the river control path in the future period. The plan should clearly define the measurement objectives, measurement cycle, measurement resource requirements, risk management, etc. to ensure the smooth progress of the measurement work.

[0089] In an exemplary embodiment, the road section measurement tasks corresponding to the sub-road sections include field measurement tasks, office measurement tasks, and control measurement tasks.

[0090] 1) Field surveying tasks refer to the operations and related work that need to be performed in the process of conducting surveying operations on the ground. It covers the following aspects: Topographic survey: Investigate the geographical environment, traffic roads, and hydrological landforms of the survey area to provide basic data for subsequent surveying work. Field measurement: Use surveying instruments and equipment, such as total stations and rangefinders, to accurately measure the terrain and objects on the ground, including coordinate control measurement, measurement of buildings, roads, rivers and other objects, and collect other related data such as meteorology, digital images, etc. Data upload and preliminary processing: Upload the collected data to the computer, and perform preliminary sorting and processing to provide basic data support for subsequent internal work.

[0091] 2) Surveying office work tasks refer to the work of further processing and analyzing the data obtained from surveying field work tasks in an office environment. It mainly includes the following aspects: in-depth collation, organization, analysis and management of the data obtained from surveying field work tasks, including map making, geographic database design and maintenance, GIS data update, etc. Remote sensing image processing: Processing and interpreting satellite or aerial photography images obtained using remote sensing technology to extract useful geographic information. Coordinate system conversion: Coordinate conversion is performed according to actual measurement needs and the coordinate system used to ensure the accuracy of the measurement results. Surveying and mapping report and map production: According to surveying and mapping tasks and requirements, surveying reports and maps are prepared to present the geographic information of the survey area. Quality control: Quality inspection and verification of measurement data to ensure the accuracy and consistency of surveying and mapping results.

[0092] 3) Control surveying tasks refer to the surveying work carried out within a certain area to establish a control network for geodetic surveying, photogrammetry, topographic surveying and engineering surveying. It is an important part of surveying and mapping work and provides a basis for the smooth progress of other professional surveying. Control surveying tasks mainly include the following aspects: Establishing a control network: obtaining the coordinates and elevations of control points through precise measurement to form a point coordinate system that forms the skeleton of surveying and mapping results. Management and maintenance of results data: collecting, organizing, preserving and using control survey results data including drawings, tables, calculation results, etc.

[0093] like Figure 6 As shown, according to the segment measurement complexity corresponding to the sub-segment and the segment measurement task corresponding to the sub-segment, a segment measurement plan for the sub-segment in the future period is generated, such as Figure 6 As shown, including: S601, determining the position of the main control point according to the measurement complexity of the sub-section and the measurement task of the sub-section, and using the position of the main control point as the measurement position in the river control path.

[0094] Specifically, according to the measurement complexity and measurement tasks of the corresponding sub-sections, analyze and determine which positions are key control points (i.e., main control points). These main control points should be able to fully reflect the measurement characteristics of the sub-sections and facilitate measurement operations. The determined main control point locations are used as measurement locations in the river control path to provide a benchmark for subsequent measurement work.

[0095] S602, determining the measurement period corresponding to the measurement position and the measurement equipment required for the measurement position according to the measurement complexity of the road section corresponding to the sub-road section, and obtaining the field measurement plan required for executing the field measurement task of the sub-road section.

[0096] For example, the measurement cycle of the measurement location is determined according to the measurement complexity of the road section corresponding to the sub-section. The measurement cycle should take into account factors such as the need to update the measurement data and the availability of measurement resources. Determine the measurement equipment required for the measurement location, including measuring instruments, sensors, data loggers, etc. The equipment selection should be based on the requirements of the measurement task, the conditions of the measurement environment, and the performance and reliability of the equipment. Based on the information of the measurement location, measurement cycle and measurement equipment, formulate the field measurement plan required for the sub-section to perform the measurement field work task. The plan should clearly specify the measurement personnel, measurement time, measurement methods and safety measures.

[0097] S603, generating a road section measurement plan for the sub-road section in a future period according to the field measurement plan, the measurement indoor work tasks and the control measurement tasks.

[0098] Furthermore, according to the field measurement plan, the specific content and steps of the field work are clarified. Combined with the measurement of the internal work tasks and the control measurement tasks, the methods of internal data processing and analysis, the implementation methods of the control measurement, etc. are determined. Taking into account the needs of field and internal work, as well as the requirements of the control measurement, a section measurement plan for the sub-section in the future period is generated. The plan should be comprehensive and detailed, and can guide the smooth progress of the measurement work.

[0099] In an exemplary embodiment, a section measurement plan for a sub-section in a future time period is generated based on a field measurement plan, an indoor measurement task and a control measurement task, including: generating a verification method for verifying the field measurement plan based on the indoor measurement task to obtain the indoor measurement plan required for the sub-section to perform the indoor measurement task; generating a section measurement plan for the sub-section in a future time period based on the field measurement plan, the indoor measurement plan and the control measurement task.

[0100] First, based on the surveying internal work tasks, clarify the goals and requirements of the internal work. Generate verification methods for the field surveying plan, including data inspection, outlier processing, data adjustment, etc. These methods should be able to ensure the accuracy and consistency of the field surveying data. According to the verification methods, formulate the internal surveying plan required for the sub-section to perform the surveying internal work tasks. The plan should clarify the process, methods, tools and time nodes of the internal work to ensure the smooth progress of the internal work.

[0101] Then, integrate the field measurement plan and the office measurement plan to ensure the connection and coordination between the two. This includes determining the handover point between field and office work, data transmission methods, work schedule, etc. Combined with the control measurement task, clarify the implementation method, time and personnel arrangement of the control measurement. Control measurement is an important link to ensure the accuracy and reliability of the entire measurement work, and should be closely coordinated with other measurement tasks.

[0102] Furthermore, based on the field measurement plan, the indoor measurement plan and the control measurement task, a section measurement plan for the sub-section in the future time period is generated, including: based on the field measurement plan and the indoor measurement plan, generating a plane control measurement and control system and an elevation control measurement and control system corresponding to the control measurement task; based on the field measurement plan, the indoor measurement plan, the plane control measurement and control system and the elevation control measurement and control system, generating a section measurement plan for the sub-section in the future time period.

[0103] It can be understood that the control survey task refers to the survey work carried out within a certain area to establish a control network for geodetic surveying, photogrammetry, topographic surveying and engineering surveying. It is an important part of surveying and mapping work and provides a basis for the smooth progress of other professional surveys. The control survey task mainly includes the following aspects: obtaining the coordinates and elevations of the control points through precise measurement, and forming a point coordinate system that forms the skeleton of the surveying and mapping results.

[0104] It should be understood that, although the steps in the flowcharts involved in the above embodiments are displayed in sequence according to the indication of the arrows, these steps are not necessarily executed in sequence according to the order indicated by the arrows. Unless there is a clear explanation in this article, the execution of these steps is not strictly limited in order, and these steps can be executed in other orders. Moreover, at least a part of the steps in the flowcharts involved in the above embodiments may include multiple steps or multiple stages, and these steps or stages are not necessarily executed at the same time, but can be executed at different times, and the execution order of these steps or stages is not necessarily carried out in sequence, but can be executed in turn or alternately with other steps or at least a part of the steps or stages in other steps.

[0105] Based on the same inventive concept, the embodiment of the present application also provides a system for generating a measurement plan for a river control project for implementing the above-mentioned method for generating a measurement plan for a river control project. The implementation scheme for solving the problem provided by the system is similar to the implementation scheme recorded in the above-mentioned method, so the specific limitations in the embodiments of one or more river control project measurement plan generation systems provided below can refer to the limitations of the river control project measurement plan generation method above, and will not be repeated here.

[0106] In an exemplary embodiment, Figure 7 As shown, a system for generating a measurement plan for a river control project is provided, the system comprising: A control path generation module 11 is used to generate a river control path and a path measurement task corresponding to the river control path according to the river area in the target scene; The construction complexity calculation module 12 is used to determine the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period; the environmental information includes at least weather information, geographical information and traffic information; A measurement scheme generating module 13 is used to generate a measurement scheme for the river control path in a future period according to the path measurement complexity and the path measurement task corresponding to the river control path; The measurement plan includes at least the measurement location in the river control path, the measurement period corresponding to the measurement location, the measurement equipment required for the measurement location, and the measurement strategy adopted by the measurement equipment.

[0107] Each module in the above-mentioned river control project measurement scheme generation system can be implemented in whole or in part by software, hardware and their combination. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the corresponding operations of the above-mentioned modules.

[0108] In an exemplary embodiment, a computer device is provided, including a memory and a processor, wherein a computer program is stored in the memory, and when the processor executes the computer program, the following steps are implemented: Generate river control paths and path measurement tasks corresponding to the river control paths according to the river areas in the target scene; Determine the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period; the environmental information includes at least weather information, geographical information and traffic information; According to the path measurement complexity and the path measurement tasks corresponding to the river control path, a measurement plan for the river control path in the future period is generated; The measurement plan includes at least the measurement location in the river control path, the measurement period corresponding to the measurement location, the measurement equipment required for the measurement location, and the measurement strategy adopted by the measurement equipment.

[0109] In one embodiment, a computer readable storage medium is provided, on which a computer program is stored, and when the computer program is executed by a processor, the following steps are implemented: Generate river control paths and path measurement tasks corresponding to the river control paths according to the river areas in the target scene; Determine the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period; the environmental information includes at least weather information, geographical information and traffic information; According to the path measurement complexity and the path measurement tasks corresponding to the river control path, a measurement plan for the river control path in the future period is generated; The measurement plan includes at least the measurement location in the river control path, the measurement period corresponding to the measurement location, the measurement equipment required for the measurement location, and the measurement strategy adopted by the measurement equipment.

[0110] In one embodiment, a computer program product is provided, comprising a computer program, which, when executed by a processor, implements the following steps: Generate river control paths and path measurement tasks corresponding to the river control paths according to the river areas in the target scene; Determine the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period; the environmental information includes at least weather information, geographical information and traffic information; According to the path measurement complexity and the path measurement tasks corresponding to the river control path, a measurement plan for the river control path in the future period is generated; The measurement plan includes at least the measurement location in the river control path, the measurement period corresponding to the measurement location, the measurement equipment required for the measurement location, and the measurement strategy adopted by the measurement equipment.

[0111] A person of ordinary skill in the art can understand that all or part of the processes in the above-mentioned embodiment method can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to the memory, database or other medium used in the embodiments provided in the present application can include at least one of non-volatile memory and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetic random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. As an illustration and not limitation, RAM can be in various forms, such as static random access memory (SRAM) or dynamic random access memory (DRAM). The database involved in each embodiment provided in this application may include at least one of a relational database and a non-relational database. Non-relational databases may include distributed databases based on blockchains, etc., but are not limited to this. The processor involved in each embodiment provided in this application may be a general-purpose processor, a central processing unit, a graphics processor, a digital signal processor, a programmable logic device, a data processing logic device based on quantum computing, an artificial intelligence (AI) processor, etc., but are not limited to this.

[0112] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this application.

[0113] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the attached claims.

Claims

1. A method for generating a measurement plan for a river control project, characterized in that: The method comprises: Generate a river control path and a path measurement task corresponding to the river control path according to the river area in the target scene; Determining the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period; the environmental information includes at least weather information, geographical information and traffic information; generating a measurement plan for the river control path in a future period according to the path measurement complexity and the path measurement task corresponding to the river control path; The measurement scheme includes at least a measurement location in the river control path, a measurement period corresponding to the measurement location, measurement equipment required for the measurement location, and a measurement strategy adopted by the measurement equipment.

2. The method according to claim 1, characterized in that: Generate river control paths based on the river area in the target scenario, including: Determine the key river control position in the target scene according to the target river characteristics corresponding to the river area in the target scene; the river characteristics include at least the river direction, width, depth and water flow speed; With the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate a river control path covering the key locations of the river control; Among them, the construction feasibility conditions include at least geological stability conditions, hydrological conditions, traffic conditions, equipment and technical conditions and safety conditions.

3. The method according to claim 2, characterized in that With the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate a river control path covering the key control points, including: With the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate an initial river path covering key locations for river control; In the river record library, query the historical river path corresponding to the historical river characteristics matching the target river characteristics; Based on the path construction records of the historical river path, potential construction failures in the initial river path are analyzed to optimize the initial river path and obtain a river control path covering key control point locations.

4. The method according to claim 3, characterized in that: With the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, a path optimization algorithm is used to generate an initial river path covering the key control points, including: Obtaining terrain description information of the key prevention and control point; the terrain description information includes at least topographic maps, hydrological data, geological exploration data, environmental protection requirements and construction specifications; Using geographic information system (GIS) tools, spatially analyzing the terrain description information to obtain a digital map containing the key locations for river control; In the digital map, the key locations of river control are used as nodes, and the construction costs are used as edges between the nodes to construct a graph model; With the goal of minimizing construction costs and the constraints of satisfying construction feasibility conditions, an initial river path covering the key prevention and control point locations is generated in the digital map according to the path optimization algorithm corresponding to the graph model.

5. The method according to any one of claims 1 to 4, characterized in that Determining the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period includes: Dividing the river control path to obtain a plurality of adjacent sub-sections; Determining the section measurement task of each sub-section according to the path measurement task corresponding to the river control path; Determine the measurement complexity of each sub-section corresponding to the section according to the environmental information of the target scene in the historical period; Determining the path measurement complexity of the path measurement task according to the road section measurement complexity corresponding to each sub-road section; Accordingly, according to the path measurement complexity and the path measurement task corresponding to the river control path, a measurement plan for the river control path in a future period is generated, including: For each sub-road section, generating a section measurement plan for the sub-road section in a future time period according to the section measurement complexity corresponding to the sub-road section and the section measurement task corresponding to the sub-road section; According to the section measurement plan of each sub-section in the future period, a measurement plan for the river control path in the future period is generated.

6. The method according to claim 5, characterized in that The road section measurement tasks corresponding to the sub-road section include field measurement tasks, office measurement tasks and control measurement tasks; According to the road section measurement complexity corresponding to the sub-road section and the road section measurement task corresponding to the sub-road section, a road section measurement plan for the sub-road section in a future time period is generated, including: Determine the position of the main control point according to the measurement complexity of the section corresponding to the sub-section and the section measurement task corresponding to the sub-section, and use the position of the main control point as the measurement position in the river control path; According to the measurement complexity of the road section corresponding to the sub-road section, determine the measurement period corresponding to the measurement position and the measurement equipment required for the measurement position, and obtain the field measurement plan required for the sub-road section to perform the field measurement task; A section measurement plan for the sub-section in a future time period is generated according to the field measurement plan, the measurement indoor work tasks and the control measurement tasks.

7. The method according to claim 6, characterized in that According to the field measurement plan, the measurement indoor work tasks and the control measurement tasks, a section measurement plan for the sub-section in a future period is generated, including: Based on the measurement internal work task, a verification method for verifying the field measurement plan is generated to obtain the field measurement plan required for the sub-section to perform the measurement internal work task; A section measurement plan for the sub-section in a future time period is generated according to the outdoor measurement plan, the indoor measurement plan and the control measurement task.

8. The method according to claim 7, characterized in that Generating a section measurement plan for the sub-section in a future time period according to the outdoor measurement plan, the indoor measurement plan and the control measurement task, including: Generate a plane control measurement and control system and an elevation control measurement and control system corresponding to the control measurement task according to the field measurement plan and the indoor measurement plan; A section measurement plan for the sub-section in a future time period is generated according to the field measurement plan, the indoor measurement plan, the plane control measurement and control system and the elevation control measurement and control system.

9. The method according to claim 1, characterized in that: Determining the path measurement complexity of the path measurement task according to the environmental information of the target scene in the historical period includes: Inputting the environmental information of the target scene in the historical period into the environmental analysis model, and obtaining the path measurement complexity of the path measurement task output by the environmental analysis model; Wherein, the environmental analysis model is constructed using an improved multi-factor comprehensive evaluation algorithm.

10. A system for generating a measurement plan for a river control project, characterized in that: The system comprises: A control path generation module, used to generate a river control path and a path measurement task corresponding to the river control path according to the river area in the target scene; A construction complexity calculation module, used to determine the path measurement complexity of the path measurement task according to the environmental information of the target scene in a historical period; the environmental information includes at least weather information, geographical information and traffic information; A measurement scheme generating module, used for generating a measurement scheme for the river control path in a future period according to the path measurement complexity and the path measurement task corresponding to the river control path; The measurement scheme includes at least a measurement location in the river control path, a measurement period corresponding to the measurement location, measurement equipment required for the measurement location, and a measurement strategy adopted by the measurement equipment.

Citation Information

Patent Citations

  • High-urbanization river network full-automatic water environment monitoring method and system

    CN117649156A

  • River network water safety detection device path planning method and system

    CN117687416A

  • River integrated management system based on big data analysis

    CN118469157A

  • Sediment sampling system for river regulation of water conservancy project

    CN118758656A

  • Route planning method, system, medium and equipment for riverway walking device

    CN119164405A