Substation monitoring information automatic acceptance system and method

By designing an automatic acceptance system for monitoring information in the substation and using automation technology to automatically check and accept monitoring information, the problem of low manual acceptance efficiency in the existing technology is solved, and the rapid automatic acceptance of monitoring information in the substation is realized, and the acceptance efficiency is improved.

CN119628199AInactive Publication Date: 2025-03-14SHANGQIU POWER SUPPLY CO OF STATE GRID HANAN ELECTRIC POWER CO
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202311443704.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-11-02
Publication Date
2025-03-14
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the prior art, the acceptance of substation monitoring information requires manual participation throughout the process, which is inefficient, especially when multiple main stations are checked, the same work needs to be repeated.

Method used

Design a substation monitoring information automatic acceptance system, including a monitoring host, a remote device and an automatic acceptance system, connect the monitoring host and a remote device through a communication module, and use the main station-side acceptance module and the factory station-side acceptance module for automatic acceptance, realizing automatic verification and acceptance of remote signal, telemetry and remote control information.

Benefits of technology

Through the automatic acceptance system, the closed-loop automatic test of remote device forwarding configuration, the synchronous acceptance of remote device configuration and monitoring backend information points, the main station information acceptance and the joint inspection and acceptance of factory and main station information are carried out to realize the rapid automatic acceptance of substation monitoring information and improve acceptance efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119628199A_ABST
    Figure CN119628199A_ABST
Patent Text Reader

Abstract

The invention discloses a transformer station monitoring information automatic acceptance system and method, the system comprises a monitoring host, a telecontrol device and an automatic acceptance system, the automatic acceptance system comprises a master station end acceptance module, a plant station end acceptance module and a communication module, and the automatic acceptance system is connected with the monitoring host and the telecontrol device through the communication module; the master station end acceptance module comprises a master station data checking module and a master station data acceptance module; the plant station end acceptance module comprises a telecontrol information checking module, a telecontrol information triggering module, a telecontrol acceptance module and a telecontrol information closed-loop checking module; the communication module comprises an IEC104 communication module and an MMS communication module; rapid and automatic acceptance of the substation monitoring information can be realized, and the acceptance efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of power system automation, and in particular relates to a substation monitoring information automatic acceptance system and method. Background Art

[0002] At present, most substations are managed in unattended mode, and a large amount of substation monitoring information needs to be connected to the dispatching master station. Since the monitoring information reflects the operating status of the substation equipment, accurate monitoring information is the guarantee for the safe operation of the power grid. Therefore, during the substation acceptance process, monitoring information acceptance is an important part of the substation acceptance.

[0003] Traditional monitoring information acceptance is done manually one by one. First, the monitoring information acceptance is completed within the station. The primary and secondary equipment debugging personnel then trigger the information upload. Then the monitoring acceptance personnel on the master station side and the on-site debugging personnel conduct information verification and acceptance. In this mode, all work requires full manual participation, especially when verifying with multiple master stations. The same work needs to be repeated several times, and the acceptance efficiency is low.

[0004] Therefore, in order to solve the above problems, it is necessary to develop an automatic acceptance system and method for substation monitoring information. Summary of the invention

[0005] The purpose of the present invention is to overcome the deficiencies of the prior art and to provide a substation monitoring information automatic acceptance system and method, which can automatically accept the substation monitoring information and improve work efficiency.

[0006] The object of the present invention is achieved as follows: a substation monitoring information automatic acceptance system, including a monitoring host, a telecontrol device and an automatic acceptance system, the automatic acceptance system including a master station acceptance module, a plant station acceptance module and a communication module, the automatic acceptance system is connected to the monitoring host and the telecontrol device respectively through the communication module; the master station acceptance module includes a master station data verification module and a master station data acceptance module, the data master station data verification module is used to verify the telesignaling, telemetering and remote control tables based on the monitoring information setting list, the master station data acceptance module is used for automatic acceptance of monitoring information, including telesignaling, telemetering and remote control; the plant station acceptance module includes a telecontrol information verification module, a telecontrol information trigger module, a telecontrol acceptance module and a telecontrol information closed-loop verification module, the telecontrol information verification The module is used to check the remote control configuration description file, i.e., the RCD file, based on the monitoring information setting sheet, and generate the verification result; the remote control information trigger module is used to simulate the information interaction behavior of the station control layer of the protection and measurement and control device based on the SCD file, and send the substation side information to the main station in the order of the monitoring information table; the remote control acceptance module is used to receive and display the monitoring information, and compare it with the trigger information for consistency, and complete the loop verification from the trigger device to the remote control device; the remote control information closed-loop verification module can connect another remote control channel to the remote control acceptance module while automatically triggering the information with the main station, and the remote control acceptance module automatically verifies the received telesignaling and telemetry information according to the verification strategy of the main station; the communication module includes an IEC104 communication module and an MMS communication module.

[0007] Furthermore, the automatic acceptance system also includes a monitoring system configuration verification module, which is used to verify the validity of the monitoring information setting value sheet, RCD file, and SCD file, and import the monitoring information setting value sheet, RCD file, and SCD file into the automatic acceptance system, and configure the remote control channel information according to the automation configuration list.

[0008] Furthermore, when the master station data verification module verifies the three tables of telesignaling, telemetering and remote control at the master station, the telesignaling information table mainly verifies the point number, information description, voltage level, alarm type and whether it is an optical sign, while the telemetering information table and the remote control information table only verify the point number and information description.

[0009] Furthermore, the master station data verification module generates a verification result report after verifying and comparing the master station data, and prompts abnormal information; the telecontrol information verification module generates a verification result report after verifying the RCD file, and prompts abnormal information.

[0010] A method for automatic acceptance of substation monitoring information, comprising the following steps: (1) Closed-loop automatic test of telecontrol device forwarding configuration; the plant-side acceptance module simulates the station-wide bay-layer equipment sending MMS messages to the telecontrol device, and at the same time retrieves the IEC104 messages sent by the telecontrol device, automatically checking and accepting the telesignaling and telemetering information of the telecontrol device's entire station monitoring information point table; simulates the master station sending IEC104 messages to the telecontrol device, receiving the MMS messages sent by the telecontrol device, and realizing the verification of the telecontrol and teleadjustment information of the telecontrol device.

[0011] (2) Synchronous acceptance of telecontrol device configuration and monitoring background information points; the plant-side acceptance module simulates the dispatching master station receiving the IEC104 message sent by the telecontrol device, verifies the correctness of the information through on-site actions, alarm information and actual on-site IED device action points, and completes the information verification of the MMS to IEC104 in the station; at the same time, it simulates the dispatching master station sending IEC104 messages to realize the acceptance of the master station remote control information points.

[0012] (3) Master station information acceptance: Import the correct results of the closed-loop test of the telecontrol device. The plant-side acceptance module simulates the sending of MMS messages by the IED devices at the bay level of the entire station. Manually verify the correctness of the relationship between the IEC104 monitoring information of the dispatching master station and the MMS message, and complete the point-to-point acceptance of the telesignaling and telemetering of the remote dispatching master station.

[0013] (4) Joint commissioning and acceptance of plant and master station information: Import the correct point list after station verification, and the plant and station acceptance module simulates the IED of the entire station according to the established rules, and cooperates with the remote master station acceptance module to perform programmed automatic point and screen association verification to achieve joint automatic acceptance of the master station and plant.

[0014] Due to the adoption of the above technical scheme, the beneficial effects of the present invention are: through the automatic acceptance system, closed-loop automatic testing of the telecontrol device forwarding configuration, synchronous acceptance of the telecontrol device configuration and monitoring background information points, master station information acceptance and joint acceptance of plant and master station information can be carried out, thereby realizing rapid and automatic acceptance of substation monitoring information and improving acceptance efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a structural schematic diagram of the automatic acceptance system of the present invention.

[0016] In the figure: A, master station end B, plant station end C, dispatching data network D, MMS network 1, monitoring host 2, remote control device 3, plant station end acceptance module 4, master station end acceptance module. Implementation

[0017] The technical solution of the present invention is further specifically described below through embodiments and in conjunction with the accompanying drawings.

[0018] like Figure 1As shown, a substation monitoring information automatic acceptance system includes a monitoring host, a remote control device and an automatic acceptance system. The automatic acceptance system includes a master station acceptance module, a plant station acceptance module and a communication module. The automatic acceptance system is connected to the monitoring host and the remote control device respectively through the communication module.

[0019] Among them, the master station acceptance module includes a master station data verification module and a master station data acceptance module. The data master station data verification module is used to calibrate the telesignaling, telemetering and remote control tables based on the monitoring information setting sheet. The master station data acceptance module is used for automatic acceptance of monitoring information, including telesignaling, telemetering and remote control.

[0020] Among them, the plant-side acceptance module includes a telecontrol information verification module, a telecontrol information trigger module, a telecontrol acceptance module and a telecontrol information closed-loop verification module. The telecontrol information verification module is used to verify the telecontrol configuration description file, i.e., the RCD file, based on the monitoring information setting sheet, and generate a verification result; the telecontrol information trigger module is used to simulate the information interaction behavior of the station control layer of the protection and measurement and control device based on the SCD file, and send the substation side information to the main station in the order of the monitoring information table; the telecontrol acceptance module is used to receive and display the monitoring information, and compare it with the trigger information for consistency, and complete the loop verification from the trigger device to the telecontrol device; the telecontrol information closed-loop verification module can connect another telecontrol channel to the telecontrol acceptance module while automatically triggering the information with the main station for joint debugging, and the telecontrol acceptance module automatically verifies the received telesignaling and telemetry information according to the verification strategy of the main station.

[0021] Wherein, the communication module includes an IEC104 communication module and an MMS communication module.

[0022] Among them, the automatic acceptance system also includes a monitoring system configuration verification module, which is used to verify the validity of the monitoring information setting sheet, RCD file, and SCD file, and import the monitoring information setting sheet, RCD file and SCD file into the automatic acceptance system, and configure the remote control channel information according to the automation configuration list.

[0023] Among them, when the master station data verification module verifies the three tables of telesignaling, telemetering and remote control at the master station, the telesignaling information table mainly verifies the point number, information description, voltage level, alarm type, and whether it is an optical sign, while the telemetering information table and the remote control information table only verify the point number and information description.

[0024] Among them, the master station data verification module generates a verification result report after verifying and comparing the master station data, and prompts abnormal information; the remote control information verification module generates a verification result report after verifying the RCD file, and prompts abnormal information.

[0025] A method for automatic acceptance of substation monitoring information, comprising the following steps: (1) Closed-loop automatic test of telecontrol device forwarding configuration; the plant-side acceptance module simulates the station-wide bay-layer equipment sending MMS messages to the telecontrol device, and at the same time retrieves the IEC104 messages sent by the telecontrol device, automatically checking and accepting the telesignaling and telemetering information of the telecontrol device's entire station monitoring information point table; simulates the master station sending IEC104 messages to the telecontrol device, receiving the MMS messages sent by the telecontrol device, and realizing the verification of the telecontrol and teleadjustment information of the telecontrol device.

[0026] (2) Synchronous acceptance of telecontrol device configuration and monitoring background information points; the plant-side acceptance module simulates the dispatching master station receiving the IEC104 message sent by the telecontrol device, verifies the correctness of the information through on-site actions, alarm information and actual on-site IED device action points, and completes the information verification of the MMS to IEC104 in the station; at the same time, it simulates the dispatching master station sending IEC104 messages to realize the acceptance of the master station remote control information points.

[0027] (3) Master station information acceptance: Import the correct results of the closed-loop test of the telecontrol device. The plant-side acceptance module simulates the sending of MMS messages by the IED devices at the bay level of the entire station. Manually verify the correctness of the relationship between the IEC104 monitoring information of the dispatching master station and the MMS message, and complete the point-to-point acceptance of the telesignaling and telemetering of the remote dispatching master station.

[0028] (4) Joint commissioning and acceptance of plant and master station information: Import the correct point list after station verification, and the plant and station acceptance module simulates the IED of the entire station according to the established rules, and cooperates with the remote master station acceptance module to perform programmed automatic point and screen association verification to achieve joint automatic acceptance of the master station and plant.

[0029] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that the specific implementation modes of the present invention can still be modified or replaced by equivalents, and any modification or equivalent replacement that does not depart from the spirit and scope of the present invention should be included in the scope of the claims of the present invention.

Claims

1. A substation monitoring information automatic acceptance system, characterized by: It includes a monitoring host, a telecontrol device and an automatic acceptance system. The automatic acceptance system includes a master station acceptance module, a plant station acceptance module and a communication module. The automatic acceptance system is connected to the monitoring host and the telecontrol device respectively through the communication module; the master station acceptance module includes a master station data verification module and a master station data acceptance module. The data master station data verification module is used to verify the telesignaling, telemetering and remote control tables based on the monitoring information setting list. The master station data acceptance module is used for automatic acceptance of monitoring information, including telesignaling, telemetering and remote control; the plant station acceptance module includes a telecontrol information verification module, a telecontrol information trigger module, a telecontrol acceptance module and a telecontrol information closed-loop verification module. The telecontrol information verification module is used to verify the telecontrol configuration description file, i.e., the RCD file, based on the monitoring information setting list, and generate a verification result; the telecontrol information trigger module is used to simulate the information interaction behavior of the station control layer of the protection and measurement and control device based on the SCD file, and send the substation side information to the master station in the order of the monitoring information table; The remote control acceptance module is used to receive and display monitoring information, and compare it with the trigger information for consistency, completing the loop verification from the trigger device to the remote control device; the remote control information closed-loop verification module can connect another remote control channel to the remote control acceptance module while automatically triggering information with the main station. The remote control acceptance module automatically verifies the received telesignaling and telemetry information according to the main station verification strategy; the communication module includes an IEC104 communication module and an MMS communication module.

2. The automatic acceptance system for substation monitoring information according to claim 1 is characterized in that: The automatic acceptance system also includes a monitoring system configuration verification module, which is used to verify the validity of the monitoring information setting value sheet, RCD file, and SCD file, and import the monitoring information setting value sheet, RCD file, and SCD file into the automatic acceptance system, and configure the remote control channel information according to the automation configuration list.

3. The automatic acceptance system for substation monitoring information according to claim 1 is characterized in that: When the master station data verification module verifies the three tables of telesignaling, telemetering and remote control at the master station, the telesignaling information table mainly verifies the point number, information description, voltage level, alarm type and whether it is an optical sign, while the telemetering information table and the remote control information table only verify the point number and information description.

4. The automatic acceptance system for substation monitoring information according to claim 1 is characterized in that: The master station data verification module generates a verification result report after verifying and comparing the master station data, and prompts abnormal information; the telecontrol information verification module generates a verification result report after verifying the RCD file, and prompts abnormal information.

5. A method for automatic acceptance of substation monitoring information, characterized in that: The following steps are involved: (1) Closed-loop automatic test of telecontrol device forwarding configuration; the plant-side acceptance module simulates the station-wide bay-layer equipment sending MMS messages to the telecontrol device, and at the same time retrieves the IEC104 messages sent by the telecontrol device, automatically checking and accepting the telecontrol device's station-wide monitoring information point table telesignaling and telemetering information; simulates the master station sending IEC104 messages to the telecontrol device, receives the MMS messages sent by the telecontrol device, and realizes the verification of the telecontrol device's remote control and remote adjustment information; (2) Synchronous acceptance of telecontrol device configuration and monitoring background information points; the plant-side acceptance module simulates the dispatching master station receiving the IEC104 message sent by the telecontrol device, verifies the correctness of the information through on-site actions, alarm information and actual on-site IED device action points, and completes the information verification of the MMS to IEC104 in the station; at the same time, it simulates the dispatching master station sending IEC104 messages to realize the acceptance of the master station remote control information points; (3) Master station information acceptance: import the correct results of the closed-loop test of the telecontrol device, and the plant-side acceptance module simulates the sending of MMS messages by the IED devices at the bay level of the entire station, manually verifies the correctness of the relationship between the IEC104 monitoring information of the dispatching master station and the MMS message, and completes the remote signaling and telemetry point-to-point acceptance of the remote dispatching master station; (4) Joint commissioning and acceptance of plant and master station information: Import the correct point list after station verification, and the plant and station acceptance module simulates the IED of the entire station according to the established rules, and cooperates with the remote master station acceptance module to perform programmed automatic point and screen association verification to achieve joint automatic acceptance of the master station and plant.

Citation Information

Cited By

  • Urban rail transit comprehensive monitoring full-automatic verification system

    CN120792924A