Building construction safety monitoring system
By designing a building construction safety monitoring system in construction and using mobile slide rods to control the opening and closing of the protective plate, the safety hazards and equipment vulnerability problems during the construction raw materials are solved, and efficient and safe monitoring effects are achieved.
Patent Information
- Application Number
- CN202510165147.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-14
- Publication Date
- 2025-03-18
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the existing construction, there is a lack of effective monitoring and detection methods during the shaping of building raw materials, which leads to safety hazards in manual inspections, and the lens of the monitoring equipment is vulnerable to damage, making it difficult to ensure the monitoring effect.
A construction safety monitoring system is designed. By installing a monitoring table on a hybrid mold and setting a mobile slide chute and limit slot on the monitoring table, the opening and closing of the protective plate is controlled by using the mobile slide rod to ensure that the monitoring probe is effectively protected before and after monitoring.
It realizes safe and efficient monitoring of the construction raw material shaping process, reduces the safety hazards brought by manual inspection, and effectively protects the monitoring probe, ensuring the monitoring effect.
Smart Images

Figure CN119635825A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a building construction safety monitoring system. Background Art
[0002] In construction, the production of construction materials is often an indispensable process. After mixing and stirring, the construction materials often need to be molded and shaped. Monitoring and testing during the shaping process is one of the indispensable processes.
[0003] In the prior art, the detection of the finalization of building materials is generally carried out through manual inspections to achieve the corresponding monitoring effects. Although this method will not affect the final detection effect, in a construction environment, manual inspections may be accompanied by uncertain safety hazards. At the same time, since the lens of the monitoring equipment is a fragile device after all, if it is only inspected by manual handling without corresponding protection of the lens, it is very likely that corresponding damage will occur during the detection process, thereby affecting the subsequent monitoring and detection effects of the finalization of building materials.
[0004] Therefore, the existing needs are not met, and we propose a construction safety monitoring system. Summary of the invention
[0005] The present invention provides a construction safety monitoring system. On the one hand, before monitoring, the protective plate can be controlled to open accordingly by moving the first movable slide bar inside the first limit groove, so that the monitoring probe can complete the monitoring effect of the construction materials inside the mixing mold during the movement. On the other hand, after the monitoring is completed, the protective plate can be controlled to close again by sliding the first movable slide bar inside the first limit groove, so that the protective plate can complete the protection effect of the monitoring probe again, thereby solving the problems mentioned in the above-mentioned background technology.
[0006] The present invention provides the following technical solutions: a construction safety monitoring system, comprising a mixed mold, a monitoring platform installed on the mixed mold, two movable slides arranged on the monitoring platform, a movable screw rod installed inside each movable slide, a monitoring component installed on each movable screw rod, the monitoring component is used to monitor the construction materials injected into the mixed mold, the monitoring component is composed of a movable block, a protective sleeve and a monitoring probe, the movable block is fixedly installed on the protective sleeve, the movable block is threadedly sleeved on the movable screw rod, and the monitoring probe is installed inside the protective sleeve; A movable slider is installed inside the protective sleeve, a rotating sleeve is rotatably installed on the bottom surface of the movable slider, a second movable slide rod is symmetrically installed on the surface of the movable slider, and a second limiting groove is opened on the inner wall of each movable slide groove; An extrusion bottom plate is slidably installed inside the protective sleeve, a corrugated airbag is provided on the top surface of the movable slider, a plurality of cleaning nozzles for cleaning the bottom lens of the monitoring probe are installed on the inner wall of the rotating sleeve, and a connecting hose for air supply is installed between the cleaning nozzle and the corrugated airbag.
[0007] As an optional solution of a construction safety monitoring system described in the present invention, the protective sleeve surface is provided with a movable side groove, each movable slide groove inner wall is provided with a first limiting groove, each second movable slide rod is slidably provided with an embedded slide rod, and the second movable slide rod and the embedded slide rod are slidably provided inside the second limiting groove.
[0008] As an optional solution of a construction safety monitoring system described in the present invention, a first limiting groove is opened on the inner wall of the movable slide groove, one end of a first movable slide rod is slidably arranged inside the first limiting groove, the first movable slide rod is slidably arranged on the protective sleeve through a slider, the other end of the first movable slide rod is fixedly connected with the first movable rack, and the first movable rack is meshed with the first rotating gear.
[0009] As an optional solution of a construction safety monitoring system described in the present invention, several groups of connecting teeth are installed on the inner wall of the bottom of the rotating sleeve, a connecting base is fixedly installed on the bottom of the protective sleeve, a connecting base is provided with a connecting groove, and several special-shaped gears are rotatably installed on the top surface of the connecting base.
[0010] As an optional solution of a construction safety monitoring system described in the present invention, each of the special-shaped gears is meshed with the corresponding connecting tooth mouth, and each of the special-shaped gears is connected to a protective plate, and the protective plate is used to seal the connecting groove.
[0011] As an optional solution of a construction safety monitoring system described in the present invention, the extruded bottom plate is installed above the moving slider.
[0012] As an optional solution of a construction safety monitoring system described in the present invention, the cleaning nozzle and the rotating sleeve are rotatably connected via a rotating rod, and a second rotating gear is sleeved on the rotating rod.
[0013] As an optional solution of a construction safety monitoring system described in the present invention, wherein: a rotating slider is arranged on the outer surface of the bottom of the rotating sleeve, a rotating slide groove is opened on the inner wall of the protective sleeve, the rotating slider is slidably arranged inside the rotating slide groove, a movable spiral groove is opened on the inner wall of the protective sleeve, and a movable straight groove for connecting the rotating slide groove and the movable spiral groove is opened on the inner wall of the protective sleeve.
[0014] As an optional solution of a construction safety monitoring system described in the present invention, a connecting spring is installed between the second movable sliding rod and the embedded sliding rod, one end of a fixed connecting rod is connected to the embedded sliding rod, and the other end of the fixed connecting rod is installed on the second movable push plate.
[0015] As an optional solution of a construction safety monitoring system described in the present invention, the second movable push plate is slidably arranged inside the rotating sleeve, a plurality of first movable push plates are arranged inside the rotating sleeve, each of the first movable push plates is installed with a second movable rack, and the second movable rack and the second rotating gear are meshed with each other.
[0016] The present invention has the following beneficial effects: The construction safety monitoring system is configured by arranging a monitoring platform on the mixed mold and providing a first limit slot on the monitoring platform. This allows the user to control the monitoring component to move on the monitoring platform. On the one hand, before monitoring, the first movable slide bar is moved in the first limit slot to control the protective plate to open accordingly, so that the monitoring probe can complete the monitoring effect of the construction materials inside the mixed mold during the movement. On the other hand, after the monitoring is completed, the protective plate can be controlled to close again by sliding the first movable slide bar in the first limit slot, so that the protective plate can complete the protection effect of the monitoring probe again.
[0017] 2. The construction safety monitoring system has a second limit groove inside the monitoring platform, so that when the moving block moves, the moving slider can slide in the second limit groove through the second moving slide bar and the embedded slide bar, so that the moving slider and the rotating sleeve can complete the corresponding upward movement, and the rotating sleeve can rotate accordingly during the upward movement. Through this arrangement, not only the cleaning nozzle arranged on the rotating sleeve can spray jets to complete the rotation cleaning of the bottom lens of the monitoring probe, but also the cleaning nozzle can perform corresponding angle adjustment during the rotation cleaning process, so that the monitoring probe can complete a certain cleaning before monitoring, thereby better completing the monitoring effect of the building materials inside the mixed mold. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the overall structure of the present invention.
[0019] Figure 2 It is a schematic diagram of the structure of the monitoring component of the present invention when viewed from above.
[0020] Figure 3 It is a schematic diagram of the side structure of the monitoring component of the present invention.
[0021] Figure 4 It is a schematic diagram of the cross-sectional structure of the local monitoring component of the present invention.
[0022] Figure 5 It is a schematic diagram of the cross-sectional structure of the local protective sleeve of the present invention.
[0023] Figure 6 It is a schematic diagram of the connecting base structure of the present invention.
[0024] Figure 7 It is a bottom view structural schematic diagram of the movable slider of the present invention.
[0025] Figure 8 It is a schematic diagram of the cross-sectional structure of a local rotating sleeve of the present invention.
[0026] Fig. 9 It is a schematic diagram of the structure of the local movable chute of the present invention.
[0027] Fig.10 For the present invention Figure 8 Enlarged structural diagram at A in the middle.
[0028] In the figure: 1. Mixing mold; 2. Monitoring component; 101, monitoring station; 102, moving slide; 103, moving screw rod; 104, first limiting groove; 1041, first track; 1042, second track; 1043, third track; 1044, first limiting block; 105, second limiting groove; 1051, fourth track; 1052, fifth track; 1053, sixth track; 1054, second limiting block; 201, moving block; 202, protective sleeve; 203, moving slider; 204, special-shaped gear; 205, second moving slide bar; 206, embedded slide bar; 207, first moving rack; 208, moving side groove; 209, first moving slide bar; 210, connecting base; 211, connecting groove; 212, protective plate; 213, connecting tooth mouth; 214, monitoring probe; 215, first rotating gear; 216, rotating sleeve; 217, rotating slider; 218, rotating slide groove; 219, moving straight groove; 220, moving spiral groove; 221, cleaning nozzle; 222, first moving push plate; 223, second moving push plate; 224, fixed connecting rod; 225, connecting hose; 226, second moving rack; 227, second rotating gear; 228, corrugated airbag; 229, extrusion bottom plate; 230, connecting spring. DETAILED DESCRIPTION
[0029] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0030] For example, see Figure 1-Figure 10 A construction safety monitoring system includes a mixing mold 1. It should be noted that the mixing mold 1 is a mold component commonly used by people in the field to shape the mixed building materials. The user can adjust the mixing mold 1 according to the actual situation and their own needs. It will not be repeated here. When the user injects the mixed building materials into the mixing mold 1, refer to Figure 1 It can be seen that a monitoring platform 101 is installed on the mixed mold 1, and two movable chutes 102 are provided on the monitoring platform 101. A movable screw rod 103 is installed inside each movable chutes 102, and a monitoring component 2 is installed on each movable screw rod 103. It should be noted that each movable screw rod 103 is fixedly connected to the output end of the corresponding drive motor, and the drive motor is installed on the monitoring platform 101. Therefore, when the user needs to monitor the shape of the building materials injected into the mixed mold 1, the user only needs to start the drive motor to rotate the movable screw rod 103, thereby driving the monitoring component 2 to perform Figure 1 The monitoring component 2 moves in the left and right directions so that the monitoring component 2 can complete the monitoring effect of the construction materials.
[0031] See also Figure 2 and Figure 3 It can be seen that the monitoring component 2 is composed of a moving block 201, a protective sleeve 202 and a monitoring probe 214. The moving block 201 is fixedly mounted on the protective sleeve 202. The moving block 201 is sleeved on the moving screw rod 103. The moving block 201 and the moving screw rod 103 form a transmission connection. The monitoring probe 214 is installed inside the protective sleeve 202. Therefore, when the moving screw rod 103 rotates, the moving block 201 will synchronously rotate on the moving screw rod 103. Figure 1 The entire monitoring component 2 moves leftward. Figure 1 Shift left in .
[0032] See also Figure 2-Figure 4It can be seen that a movable side groove 208 is opened on the surface of the protective sleeve 202. By opening the movable side groove 208, after the subsequent first movable slide bar 209 moves, the first movable rack 207 can complete the engagement with the first rotating gear 215 set inside the protective sleeve 202, thereby driving the first rotating gear 215 to rotate. A movable slider 203 is installed inside the protective sleeve 202, and a rotating sleeve 216 is installed below the movable slider 203. The rotating sleeve 216 is rotatably installed on the bottom surface of the movable slider 203, and the first rotating gear 215 is fixedly installed on the surface of the rotating sleeve 216.
[0033] See also Fig. 9 It can be seen that, since one end of the first movable slide bar 209 is slidably arranged inside the first limiting groove 104, and the first limiting groove 104 is divided into a first track 1041, a second track 1042 and a third track 1043, the first track 1041 and the second track 1042 are arranged in two groups, and the two groups of the first track 1041 and the second track 1042 are symmetrically arranged with the third track 1043 as the center, when the moving block 201 moves, the first movable slide bar 209 will also move from Fig. 9 The first track 1041 on the right side slides toward the second track 1042 on the left side. Since a first stop block 1044 is provided inside the first track 1041, when the first movable slide bar 209 slides, it is restricted by the first stop block 1044 and moves closer to the protective sleeve 202. In other words, the first movable slide bar 209 moves Figure 2 When the first moving slide bar 209 moves to the left, the first moving rack 207 connected to the first moving slide bar 209 will also move synchronously. Since the first moving rack 207 and the first rotating gear 215 are meshed with each other, when the first moving rack 207 moves, the first rotating gear 215 will rotate accordingly, thereby driving the rotating sleeve 216 to rotate synchronously.
[0034] It should be noted that the first movable slide bar 209 is also slidably set on the protective sleeve 202 through the slider, and the first movable slide bar 209 is slidably set on the slider, which makes the first movable slide bar 209 synchronously slide inside the first limiting groove 104 after the protective sleeve 202 moves following the moving block 201, and when the first movable slide bar 209 moves left and right subsequently, the first movable slide bar 209 will only move on the slider and will not separate from the protective sleeve 202.
[0035] See also Figure 7 It can be seen that a plurality of connecting teeth 213 are installed on the inner wall of the bottom of the rotating sleeve 216. Figure 4It can be seen that a connecting base 210 is fixedly installed at the bottom of the protective sleeve 202, and a connecting groove 211 is opened on the connecting base 210. A plurality of special-shaped gears 204 are rotatably installed on the top surface of the connecting base 210, and each special-shaped gear 204 is meshed with the corresponding connecting tooth opening 213, and each special-shaped gear 204 is connected to a protective plate 212. This means that when the rotating sleeve 216 rotates, the plurality of connecting tooth openings 213 arranged at the bottom of the rotating sleeve 216 will also drive the corresponding special-shaped gears 204 to rotate, and then drive the protective plate 212 to complete the corresponding rotation, so as to release the blocking effect of the connecting groove 211. When the blocking of the connecting groove 211 is released, the monitoring probe 214 arranged inside the protective sleeve 202 can complete the monitoring effect of injecting the building materials inside the mixing mold 1.
[0036] On the one hand, see Fig. 9 It can be seen that since the first limiting block 1044 is arranged inside the first limiting groove 104, and the first limiting blocks 1044 arranged inside the two first tracks 1041 are symmetrically provided with limiting inclined surfaces, when the subsequent first moving slide bar 209 moves to Fig. 9 After entering the first track 1041 on the left side, the first movable slide bar 209 is squeezed by the limiting inclined surface of the first limiting block 1044 here, and the first movable slide bar 209 is reset to the initial position, and drives the rotating sleeve 216 to rotate in the opposite direction during the reset process, thereby driving the plurality of special-shaped gears 204 to rotate in the opposite direction, so that the plurality of protective plates 212 can complete the blocking effect of the connecting groove 211 again; On the other hand, see Fig. 9 It can be seen that the opening direction of the second track 1042 is inclined downward, so when the first moving slide bar 209 slides into the second track 1042, the first moving slide bar 209 will drive the first moving rack 207 to move downward accordingly, and this setting is also to allow the first moving rack 207 to release the engagement with the first rotating gear 215 in advance when the rotating sleeve 216 moves subsequently, so as to avoid the rotating sleeve 216 from getting stuck when moving. At the same time, when the first moving slide bar 209 moves to Fig. 9 When the first moving slide bar 209 is inside the second track 1042 on the left side, the first moving slide bar 209 will gradually return to the initial position because the second track 1042 is inclined upward. Fig. 9 Before reaching the position of the first trajectory 1041, the rotating sleeve 216 has also been reset, so that the first movable rack 207 and the first rotating gear 215 are engaged again, so that during subsequent movement, the first movable rack 207 can still perform the above-mentioned movement effect, thereby completing the protection of the monitoring probe 214.
[0037] Through the above-mentioned arrangement, not only can the user control the protective plate 212 to open accordingly by moving the first movable slide bar 209 inside the first limit groove 104 before monitoring, so that the monitoring probe 214 can complete the monitoring effect of the building materials inside the mixing mold 1 during the movement, but also after the monitoring is completed, the protective plate 212 can be controlled to close again by sliding the first movable slide bar 209 inside the first limit groove 104, so that the protective plate 212 can complete the protection effect of the monitoring probe 214 again.
[0038] Embodiment 2: This embodiment is intended to solve the problem that during the movement of the monitoring probe 214, some dust and impurities may adhere to the lens of the monitoring probe 214 due to the opening of the protective plate 212, thereby affecting the real-time monitoring effect of the monitoring probe 214. This embodiment is an improvement made on the basis of embodiment 1. For details, please refer to Figure 1-Figure 10 , the surface of the moving slider 203 is symmetrically installed with a second moving slide bar 205, each of the second moving slide bars 205 is slidably provided with an embedded slide bar 206, and the other end of the embedded slide bar 206 is slidably provided in the second limiting groove 105. It should be noted that the second limiting groove 105 is composed of a fourth track 1051, a fifth track 1052 and a sixth track 1053, and the fourth track 1051 and the fifth track 1052 are provided with two groups, and the two groups of the fourth track 1051 and the fifth track 1052 are symmetrically provided with the sixth track 1053 as the center. Therefore, when the moving block 201 moves, the second moving slide bar 205 and the embedded slide bar 206 will move from Fig. 9 The fourth track 1051 on the right side slides in the direction of the fifth track 1052 .
[0039] On the one hand, since the fifth track 1052 is opened obliquely upward, when the second moving slide bar 205 and the embedded slide bar 206 slide into the fifth track 1052, the second moving slide bar 205 will move obliquely upward due to the restriction of the fifth track 1052, thereby driving the moving slider 203 to move upward synchronously. Figure 4It can be seen that an extrusion bottom plate 229 is arranged above the movable slider 203, and a corrugated airbag 228 is installed on the extrusion bottom plate 229. Therefore, when the movable slider 203 moves upward, the extrusion bottom plate 229 will be squeezed. Since the extrusion bottom plate 229 is slidably arranged inside the protective sleeve 202, after the extrusion bottom plate 229 is squeezed, the corrugated airbag 228 above it will be squeezed. At the same time, since the corrugated airbag 228 is connected to the corresponding cleaning nozzle 221 through a plurality of connecting hoses 225, that is to say, after the corrugated airbag 228 is squeezed, the gas inside it will be transported to the inside of the corresponding cleaning nozzle 221 through the connecting hose 225, and sprayed to the bottom lens of the monitoring probe 214 through the cleaning nozzle 221, thereby completing the cleaning effect of the bottom lens of the monitoring probe 214 to a certain extent.
[0040] On the other hand, see Figure 7 It can be seen that the outer surface of the rotating sleeve 216 is also connected to a rotating slider 217, see Figure 5 It can be seen that a rotating groove 218 is provided on the inner wall of the protective sleeve 202. Through this arrangement, when the first moving rack 207 drives the rotating sleeve 216 to rotate in the early stage, the rotating sleeve 216 will slide inside the rotating groove 218 through the rotating slider 217, and finally slide to the intersection of the rotating groove 218 and the moving straight groove 219. It should be noted that the contact friction between the moving slider 203 and the rotating sleeve 216 is much greater than the friction between the rotating slider 217 and the rotating groove 218, and then the moving slider 203 and the rotating sleeve 216 will be kept stationary first, and the rotating slider 217 on the rotating sleeve 216 will slide in the rotating groove 218; Also, see Figure 5It can be seen that the protective sleeve 202 is further provided with a moving straight groove 219 and a moving spiral groove 220, and the moving straight groove 219 is respectively connected with the rotating groove 218 and the moving spiral groove 220, so that when the second moving slide bar 205 slides into the fifth track 1052 and drives the moving slider 203 to move upward, the rotating slider 217 arranged on the rotating sleeve 216 can slide from the bottom end of the moving straight groove 219 to the top end of the moving straight groove 219, and the rotating slider 217 will eventually enter the moving spiral groove 220. Since the moving slider 203 is still moving upward at this time, the rotating slider 217 will slide inside the movable spiral groove 220, and when the rotating slider 217 enters the movable spiral groove 220, it is restricted by the movable spiral groove 220, so the rotating slider 217 will rotate accordingly, thereby driving the rotating sleeve 216 to rotate synchronously. This arrangement is also to allow the several cleaning nozzles 221 arranged on the rotating sleeve 216 to utilize the rotation of the rotating sleeve 216 during the upward movement of the movable slider 203, thereby increasing the cleaning range of the cleaning nozzle 221, so that the cleaning nozzle 221 can better complete the cleaning effect of the bottom lens of the monitoring probe 214.
[0041] Embodiment 3: This embodiment is intended to promote the solution of the problem that the cleaning nozzle 221 cannot clean part of the monitoring probe 214 during the upward movement of the rotating sleeve 216 because the spray cleaning angle of the cleaning nozzle 221 remains unchanged during the early cleaning. This embodiment is an improvement made on the basis of embodiment 2. For details, please refer to Figure 1-Figure 10 , see Figure 4 It can be seen that the embedded slide bar 206 is slidably arranged inside the second movable slide bar 205, and a connecting spring 230 is also arranged between the two. Therefore, when the embedded slide bar 206 slides into the fifth track 1052, the embedded slide bar 206 will be squeezed by the limiting inclined surface of the second limit block 1054 here, and then move closer to the center position of the protective sleeve 202, see Figure 4 It can be seen that the portion of the embedded sliding rod 206 disposed inside the protective sleeve 202 is also connected to the fixed connecting rod 224 , so when the embedded sliding rod 206 moves closer to the center position of the protective sleeve 202 , the fixed connecting rod 224 will also move synchronously.
[0042] See also Figure 8It can be seen that the other end of the fixed link 224 is fixedly connected to the second movable push plate 223, and the second movable push plate 223 is an arc-shaped plate, and the second movable push plate 223 is arranged inside the rotating sleeve 216. Therefore, when the fixed link 224 moves following the embedded slide bar 206, the second movable push plate 223 will move synchronously close to the center position of the rotating sleeve 216. Since the first movable push plate 222 is also fitted on the inner wall of the second movable push plate 223, the first movable push plate 222 is also an arc-shaped plate, and the first movable push plate 222 can only slide toward the center position of the rotating sleeve 216, and refer to Figure 8 It can be seen that a spring for resetting is arranged between the first movable push plate 222 and the rotating sleeve 216. Therefore, when the second movable push plate 223 moves, several first movable push plates 222 will be squeezed by the second movable push plate 223, so that several first movable push plates 222 move synchronously close to the center position of the rotating sleeve 216.
[0043] It should be noted that even if the rotating sleeve 216 rotates, the second movable push plate 223 will not move because it is connected to the embedded slide bar 206 through the fixed connecting rod 224. However, since the arc surface of the second movable push plate 223 is relatively large, even if the first movable push plate 222 set on the rotating sleeve 216 rotates with the rotating sleeve 216, the second movable push plate 223 can maintain contact with at least two first movable push plates 222, so that when the second movable push plate 223 moves, it can synchronously drive several first movable push plates 222 to perform corresponding movement effects.
[0044] See also Fig.10 It can be seen that each first movable push plate 222 is connected to a second movable rack 226, and each second movable rack 226 is meshed with the corresponding second rotating gear 227, and the second rotating gear 227 is fixedly sleeved on the rotating rod connected to the cleaning nozzle 221. Therefore, when the first movable push plate 222 moves, the second movable rack 226 will also move synchronously, thereby allowing the second rotating gear 227 to rotate accordingly. When the second rotating gear 227 rotates, through the above connection, the cleaning nozzle 221 will also have a certain degree of angular deviation. This setting is also to allow the rotating sleeve 216 to follow the moving slider 203 to rise, by changing the cleaning angle of the cleaning nozzle 221, so that the cleaning nozzle 221 can complete the cleaning effect of the lens surface at different positions at the bottom of the monitoring probe 214 to a certain extent.
[0045] On the one hand, due to Fig. 9 The opening of the fifth track 1052 on the left side is inclined downward, so when the second moving slide bar 205 moves to Fig. 9After the second moving slide bar 205 is inside the fifth track 1052 on the left side, the second moving slide bar 205 can drive the moving slide block 203 to complete the corresponding reset, and during the reset process of the moving slide block 203, the rotating sleeve 216 will also move downward synchronously and perform corresponding reset rotation during the downward movement. This setting is also to facilitate the subsequent movement of the moving slide block 203, and the rotating sleeve 216 can still use its internal parts to complete the mobile cleaning effect of the monitoring probe 214; On the other hand, since the second limit blocks 1054 are arranged inside the fifth track 1052 and the sixth track 1053, but the second limit blocks 1054 arranged inside the two fifth tracks 1052 are arranged symmetrically, and the limiting slopes of the second limit blocks 1054 arranged inside the two fifth tracks 1052 are in opposite directions, when the embedded sliding rod 206 moves to the Fig. 9 After entering the fifth track 1052 on the left, the embedded slide bar 206 is squeezed by the limiting inclined surface here, and can complete the corresponding reset through the connecting spring 230, and drive the rotating sleeve 216 to rotate in the opposite direction during the reset process, so that the cleaning nozzle 221 set on the rotating sleeve 216 is reset to the corresponding position, so that when the moving block 201 is reset subsequently, the above-mentioned movement effect can still be performed, and then the monitoring probe 214 is cleaned again.
[0046] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0047] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A construction safety monitoring system, comprising a hybrid mold (1), characterized in that: A monitoring platform (101) is installed on the mixing mold (1), and two movable chutes (102) are provided on the monitoring platform (101). A movable screw rod (103) is installed inside each movable chutes (102), and a monitoring component (2) is installed on each movable screw rod (103). The monitoring component (2) is used to monitor the building materials injected into the mixing mold (1). The monitoring component (2) is composed of a moving block (201), a protective sleeve (202), and a monitoring probe (214). The moving block (201) is fixedly installed on the protective sleeve (202), the moving block (201) is threadedly sleeved on the moving screw rod (103), and the monitoring probe (214) is installed inside the protective sleeve (202); A movable slider (203) is installed inside the protective sleeve (202), a rotating sleeve (216) is rotatably installed on the bottom surface of the movable slider (203), a second movable slide rod (205) is symmetrically installed on the surface of the movable slider (203), and a second limiting groove (105) is opened on the inner wall of each movable slide groove (102); An extrusion bottom plate (229) is slidably mounted inside the protective sleeve (202), a corrugated airbag (228) is disposed on the top surface of the movable slider (203), a plurality of cleaning nozzles (221) for cleaning the bottom lens of the monitoring probe (214) are mounted on the inner wall of the rotating sleeve (216), and a connecting hose (225) for air supply is mounted between the cleaning nozzle (221) and the corrugated airbag (228).
2. A construction safety monitoring system according to claim 1, characterized in that: A movable side groove (208) is provided on the surface of the protective sleeve (202), a first limiting groove (104) is provided on the inner wall of each movable slide groove (102), an embedded slide rod (206) is slidably arranged inside each second movable slide rod (205), and the second movable slide rod (205) and the embedded slide rod (206) are slidably arranged inside the second limiting groove (105).
3. A construction safety monitoring system according to claim 2, characterized in that: A first limiting groove (104) is provided on the inner wall of the movable slide groove (102), one end of a first movable slide rod (209) is slidably arranged inside the first limiting groove (104), the first movable slide rod (209) is slidably arranged on the protective sleeve (202) through a slider, the other end of the first movable slide rod (209) is fixedly connected to the first movable rack (207), and the first movable rack (207) is meshed with the first rotating gear (215).
4. A construction safety monitoring system according to claim 3, characterized in that: A plurality of groups of connecting teeth (213) are installed on the inner wall of the bottom of the rotating sleeve (216), a connecting base (210) is fixedly installed on the bottom of the protective sleeve (202), a connecting groove (211) is provided on the connecting base (210), and a plurality of special-shaped gears (204) are rotatably installed on the top surface of the connecting base (210).
5. A construction safety monitoring system according to claim 4, characterized in that: Each of the special-shaped gears (204) is meshed with a corresponding connecting tooth opening (213), and each of the special-shaped gears (204) is connected to a protective plate (212), and the protective plate (212) is used to block the connecting groove (211).
6. A construction safety monitoring system according to claim 1, characterized in that: The extrusion bottom plate (229) is installed above the moving slider (203).
7. A construction safety monitoring system according to claim 1, characterized in that: The cleaning nozzle (221) and the rotating sleeve (216) are rotatably connected via a rotating rod, and a second rotating gear (227) is sleeved on the rotating rod.
8. A construction safety monitoring system according to claim 7, characterized in that: A rotating slider (217) is provided on the outer surface of the bottom of the rotating sleeve (216); a rotating slide groove (218) is provided on the inner wall of the protective sleeve (202); the rotating slider (217) is slidably arranged inside the rotating slide groove (218); a movable spiral groove (220) is provided on the inner wall of the protective sleeve (202); and a movable straight groove (219) for connecting the rotating slide groove (218) and the movable spiral groove (220) is provided on the inner wall of the protective sleeve (202).
9. A construction safety monitoring system according to claim 2, characterized in that: A connecting spring (230) is installed between the second movable slide bar (205) and the embedded slide bar (206), one end of a fixed connecting rod (224) is connected to the embedded slide bar (206), and the other end of the fixed connecting rod (224) is installed on the second movable push plate (223).
10. A construction safety monitoring system according to claim 9, characterized in that: The second movable push plate (223) is slidably arranged inside the rotating sleeve (216), and a plurality of first movable push plates (222) are arranged inside the rotating sleeve (216). A second movable rack (226) is mounted on each of the first movable push plates (222), and the second movable rack (226) and the second rotating gear (227) are meshed with each other.