Waste dump planning method and device, storage medium and electronic equipment
By obtaining village and community boundary data, determining the target village and community and dividing areas, and connecting the areas with the predetermined distance threshold, the problem of the external soil discharge yard occupying multiple villages and community and the internal soil discharge yard is solved, and a more reasonable soil discharge yard planning is achieved, ensuring slope stability.
Patent Information
- Application Number
- CN202411696665.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-25
- Publication Date
- 2025-03-18
AI Technical Summary
In the prior art, foreign soil discharge yards occupy multiple villages and communities, and each village only accounts for part of the land. The internal soil discharge yard accounts for a small proportion, and the distance between the external soil discharge yard and the mining site is large, resulting in an increase in the drainage distance and may form artificial gullies, which is not conducive to slope stability.
By obtaining the boundary data of multiple villages and communities and the target boundary data of the soil discharge site to be planned, the target villages and communities are determined and divided, and the target areas of the inner and outer soil discharge sites are obtained. These areas are connected according to a predetermined distance threshold to form a planned target soil discharge field.
The land use of the outer drainage site is optimized, the distance between the inner and outer drainage site is reduced, the formation of artificial gullies is avoided, and the stability of the slope is ensured.
Smart Images

Figure CN119647849A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of data processing technology, and in particular to a method, device, storage medium and electronic equipment for planning a spoil dump. Background Art
[0002] The ecological types of the mining area of Weijiamao open-pit mine include grassland landscape, forest (including shrubbery) landscape, farmland landscape, sandy land landscape, dry valley landscape and artificial landscape, with grassland landscape accounting for the largest proportion, about 68.34%, followed by cultivated land. The consequence of soil occupation by the dumping site has caused the original surface vegetation to disappear, which is easy to cause dust and soil erosion, causing the deterioration of the ecological environment.
[0003] At present, the external dump occupies multiple villages and each village only occupies part of the land. The capacity of the internal dump is small and the distance between the external dump and the mining site is large, which increases the distance for dumping soil. It will also eventually form an artificial ditch between the external dump and the mining site, which is not conducive to slope stability. Summary of the invention
[0004] In view of this, the present application provides a planning method, device, storage medium and electronic equipment for a spoil dump, the main purpose of which is to improve the current existing technology in which the external spoil dump occupies multiple villages and each village only occupies part of the land, the capacity of the internal spoil dump is small, and the distance between the external spoil dump and the mining site is large, resulting in an increase in the spoil transportation distance, and also causing the external spoil dump and the mining site to eventually form an artificial ditch, which is not conducive to the stability of the slope. Technical problems.
[0005] In a first aspect, the present application provides a method for planning a spoil dump, comprising:
[0006] Obtain boundary data of multiple villages and communities and target boundary data corresponding to the planned spoil dump;
[0007] Based on the boundary data and the target boundary data, determining a target village corresponding to the spoil dump to be planned from the multiple villages, the target village being the village to be occupied by the spoil dump to be planned;
[0008] Dividing the target villages and communities to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned and a second target area corresponding to the outer spoil dump in the spoil dump to be planned;
[0009] The first target area and the second target area are connected according to a predetermined distance threshold to obtain a planned target spoil dump.
[0010] Optionally, determining the target village corresponding to the spoil dump to be planned from the plurality of villages based on the boundary data and the target boundary data includes:
[0011] Determining the area data of the plurality of villages based on the boundary data, and determining the target area data corresponding to the target spoil dump based on the target boundary data;
[0012] Based on the boundary data, the area data, the target area data, and the target boundary data, the target village and community corresponding to the spoil dump to be planned is determined from the multiple villages and communities.
[0013] Optionally, determining a target village or community corresponding to the spoil dump to be planned from the plurality of villages or communities based on the boundary data, the area data, the target area data, and the target boundary data includes:
[0014] Analyzing the plurality of villages based on the boundary data, the area data, the target area data, and the target boundary data;
[0015] The target village or community corresponding to the spoil dump to be planned is determined from the multiple villages or communities according to the analysis result.
[0016] Optionally, the dividing of the target villages and communities to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned and a second target area corresponding to the outer spoil dump in the spoil dump to be planned includes:
[0017] Determine, in the target area data, first target area data corresponding to the inner dump and second target area data corresponding to the outer dump; and,
[0018] Determine the first target boundary data corresponding to the inner dump and the second target boundary data corresponding to the outer dump in the target boundary data.
[0019] Optionally, the dividing of the target villages and communities to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned and a second target area corresponding to the outer spoil dump in the spoil dump to be planned further includes:
[0020] Dividing the target village based on the first target area data and the first target boundary data to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned; and
[0021] Based on the second target area data and the second target boundary data, the target village is divided to obtain a second target area corresponding to the inner spoil dump in the spoil dump to be planned.
[0022] Optionally, the connecting the first target area and the second target area according to a predetermined distance threshold to obtain a planned target dumping ground includes:
[0023] Determining connection data between the first target area and the second target area according to the predetermined distance threshold;
[0024] Based on the connection data, the first target area and the second target area are connected to obtain a planned target spoil dump.
[0025] In a second aspect, the present application provides a planning device for a spoil dump, comprising:
[0026] An acquisition module is configured to acquire boundary data of multiple villages and target boundary data corresponding to the spoil dump to be planned;
[0027] A determination module is configured to determine a target village corresponding to the to-be-planned spoil dump from the plurality of villages based on the boundary data and the target boundary data, wherein the target village is the village to be occupied by the to-be-planned spoil dump;
[0028] A division module is configured to divide the target village community to obtain a first target area corresponding to the inner dumping ground in the dumping ground to be planned and a second target area corresponding to the outer dumping ground in the dumping ground to be planned;
[0029] The connection module is configured to connect the first target area and the second target area according to a predetermined distance threshold to obtain a planned target spoil dump.
[0030] In a third aspect, the present application provides a computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the method for planning a spoil dump described in the first aspect is implemented.
[0031] In a fourth aspect, the present application provides an electronic device, comprising a storage medium, a processor, and a computer program stored on the storage medium and executable on the processor, wherein when the processor executes the computer program, the method for planning a spoil dump described in the first aspect is implemented.
[0032] In a fifth aspect, the present application provides a computer program product, which includes a computer program, and is characterized in that when the computer program is executed by a processor, it implements the planning method of the spoil dump described in the first aspect.
[0033] By means of the above technical scheme, the present application provides a method, device, storage medium and electronic device for planning a spoil dump. Compared with the current existing technology, the present application obtains boundary data of multiple villages and target boundary data corresponding to the spoil dump to be planned; based on the boundary data and the target boundary data, determines the target village corresponding to the spoil dump to be planned from multiple villages, the target village being the village that needs to be occupied by the spoil dump to be planned; divides the target village to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned and a second target area corresponding to the outer spoil dump in the spoil dump to be planned; connects the first target area and the second target area according to a predetermined distance threshold to obtain the planned target spoil dump, which can optimize the situation where the outer spoil dump occupies multiple villages and each village only occupies part of the land, and can also reduce the distance between the inner and outer spoil dumps to avoid the formation of artificial gullies and ensure the stability of the slope. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.
[0035] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.
[0036] Figure 1 A schematic diagram of a process flow of a method for planning a spoil dump provided in an embodiment of the present application is shown;
[0037] Figure 2 A schematic diagram of a process flow of a method for planning a spoil dump provided in an embodiment of the present application is shown;
[0038] Figure 3 A schematic diagram showing an example provided by an embodiment of the present application;
[0039] Figure 4 A schematic diagram showing an example provided by an embodiment of the present application;
[0040] Figure 5 A schematic structural diagram of a spoil dump planning device provided in an embodiment of the present application is shown;
[0041] Figure 6 A schematic structural diagram of an electronic device provided in an embodiment of the present application is shown. DETAILED DESCRIPTION
[0042] The embodiments of the present application will be described in more detail below with reference to the accompanying drawings. It should be noted that the embodiments and features in the embodiments of the present application can be combined with each other without conflict.
[0043] In order to improve the existing technology, the external dump occupies multiple villages and each village only occupies part of the land, the internal dump capacity is small, the distance between the external dump and the mining site is large, resulting in increased dump transportation distance, and the external dump and the mining site eventually form artificial trenches, which is not conducive to slope stability. This embodiment provides a method for planning a dump, such as Figure 1 As shown, the method includes:
[0044] Step 101: Obtain boundary data of multiple villages and communities and target boundary data corresponding to the spoil dump to be planned.
[0045] In the embodiment of the present application, the spoil dump may be an external spoil dump of an open-pit coal mine. Specifically, the spoil dump is a site for stacking stripping materials and waste rocks in places such as mines and construction sites. Reasonable spoil dump planning and management are of great significance for ensuring safe production, environmental protection and resource utilization. The target spoil dump in the embodiment of the present application may be a spoil dump that needs to be planned.
[0046] In some examples, planning the boundaries of the spoil dump is a key step to ensure its safety, environmental protection and sustainable development. Reasonable boundary planning can not only reduce the impact on the surrounding environment and community, but also improve the efficiency of the use of the spoil dump. Specifically, it is necessary to ensure that the boundaries of the spoil dump are away from sensitive areas such as residential areas, schools, hospitals, etc., to reduce potential threats to people and property; avoid occupying important ecological areas such as nature reserves, water sources, and farmland; choose a location with convenient transportation to facilitate transportation and management; and make full use of underutilized land such as abandoned land and wasteland to reduce the occupation of existing land resources.
[0047] Step 102: Based on the boundary data and the target boundary data, determine the target village corresponding to the spoil dump to be planned from multiple villages.
[0048] Among them, the target villages and communities are those that need to be occupied by the planned spoil dump.
[0049] In the embodiment of the present application, the target village is a village selected from multiple villages and needs to be occupied.
[0050] Step 103, dividing the target villages and communities to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned and a second target area corresponding to the outer spoil dump in the spoil dump to be planned.
[0051] For this embodiment, the external dump and the internal dump are two common ways of dumping earth in mining projects, and they differ in terms of site selection, function, environmental impact, etc.
[0052] Specifically, an external dump refers to a place where waste rock, tailings and other wastes generated during mining are transported to a designated location outside the mining area for storage. The external dump is located outside the mining area, usually away from sensitive areas such as residential areas and water sources; it occupies a large area and can be expanded as needed; it requires additional transportation costs, but can better control the impact on the internal environment of the mining area; it has a small impact on the environment inside the mining area, but it needs to consider the impact on the surrounding environment, such as soil erosion, dust, etc.; it requires strict environmental supervision and management measures, such as setting up environmental buffer zones and monitoring points.
[0053] For example, external dumping sites are suitable for large mines, especially those that produce large amounts of waste rock and tailings; when the internal environment of the mining area is sensitive and not suitable for dumping waste, it is more appropriate to choose an external dumping site; there are many unused land resources around the mining area, which can be used for the construction of external dumping sites.
[0054] In some examples, an internal dump refers to the direct storage of waste rock, tailings and other waste generated during mining at a designated location within the mining area. The internal dump is located inside the mining area, usually in goafs, abandoned tunnels and other areas; it occupies a relatively small area and is limited by the internal space of the mining area; the transportation cost is low because the waste can be directly stored inside the mining area; it has a greater impact on the internal environment of the mining area, which may affect the production and safety of the mining area; it requires strict internal management and monitoring to ensure that it will not have a negative impact on the production and environment of the mining area.
[0055] For example, internal dumping grounds are suitable for small mines, especially those that produce less waste rock and tailings; when there are not enough unused land resources around the mining area, it is more appropriate to choose an internal dumping ground; when the internal environmental impact of the mining area can be controlled by effective measures, an internal dumping ground can be selected.
[0056] Step 104: Connect the first target area and the second target area according to a predetermined distance threshold to obtain a planned target dump.
[0057] In the embodiment of the present application, the connection between the inner dump and the outer dump is an important link to ensure the balance between mine production and environmental protection. This connection not only involves logistics and transportation, but also involves environmental protection, safety management and other aspects.
[0058] Compared with the current existing technology, this embodiment obtains boundary data of multiple villages and target boundary data corresponding to the spoil dump to be planned; based on the boundary data and the target boundary data, determines the target village corresponding to the spoil dump to be planned from multiple villages, the target village being the village that needs to be occupied by the spoil dump to be planned; divides the target village to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned and a second target area corresponding to the outer spoil dump in the spoil dump to be planned; connects the first target area and the second target area according to a predetermined distance threshold to obtain the planned target spoil dump, which can optimize the situation where the outer spoil dump occupies multiple villages and each village only occupies part of the land, and can also reduce the distance between the inner and outer spoil dumps to avoid the formation of artificial gullies and ensure the stability of the slope.
[0059] As a refinement and extension of the above embodiment, when determining the target village corresponding to the spoil dump to be planned from multiple villages based on the boundary data and the target boundary data, the following method may be used but is not limited to: Figure 2 As shown, the method includes:
[0060] Step 201: determine the area data of multiple villages based on the boundary data, and determine the target area data corresponding to the target spoil dump based on the target boundary data.
[0061] In some examples, determining the area of a village is one of the basic tasks for land management and planning. Accordingly, determining the target area data corresponding to the target spoil dump based on the target boundary data can specifically include: accurately marking the boundary line of the spoil dump on the topographic map to ensure that the boundary line is clearly visible for subsequent measurement; using measuring tools (such as GIS software, AutoCAD, etc.) to measure the total length of the boundary line; using the area calculation function of the measuring tool to calculate the area of the spoil dump. If the boundary line is more complex, it can be decomposed into multiple simple geometric shapes (such as triangles, rectangles, etc.), and the areas are calculated separately and then added together; verifying the calculation results to ensure accuracy, and if necessary, conducting on-site review to ensure the accuracy of the measurement data.
[0062] Step 202: Based on the boundary data, area data, target area data and target boundary data, determine the target village corresponding to the spoil dump to be planned from multiple villages.
[0063] Optionally, when executing step 202, the following method may be used but is not limited to the following method, which includes:
[0064] Step 11: Analyze multiple villages and communities based on boundary data, area data, target area data, and target boundary data.
[0065] Step 12: Determine the target village or community corresponding to the spoil dump to be planned from multiple villages or communities based on the analysis results.
[0066] In the embodiment of the present application, the target village and community can be the village and community that need to be occupied determined based on the area and boundary. Exemplarily, if N villages and N original villages respectively represent the number of villages and communities occupied after the re - planning of the external spoil ground and the originally designed plan, then N villages < N original villages. Correspondingly, if S row and S original row respectively represent the areas occupied by the external spoil ground after re - planning and the originally designed plan, and S village and S original village respectively represent the sum of the areas of the villages and communities occupied by the external spoil ground after re - planning and the originally designed plan, then S 排 / S 村 >S 原排 / S 原村 。
[0067] Further, when dividing the target village and community to obtain the first target area corresponding to the internal spoil ground in the spoil ground to be planned and the second target area corresponding to the external spoil ground in the spoil ground to be planned, the following method can be adopted but is not limited to it. This method includes:
[0068] Step 21a: Determine the first target area data corresponding to the internal spoil ground in the target area data and the second target area data corresponding to the external spoil ground.
[0069] In the embodiment of the present application, the first target area data can be the area data of the internal spoil ground in the spoil ground. Correspondingly, the second target area data can be the area data of the external spoil ground in the spoil ground.
[0070] Step 21b: Determine the first target boundary data corresponding to the internal spoil ground in the target boundary data and the second target boundary data corresponding to the external spoil ground.
[0071] In the embodiment of the present application, the first target boundary data can be the boundary data of the internal spoil ground in the spoil ground. Correspondingly, the second target boundary data can be the boundary data of the external spoil ground in the spoil ground.
[0072] Step 22a: Divide the target village and community based on the first target area data and the first target boundary data to obtain the first target area corresponding to the internal spoil ground in the spoil ground to be planned.
[0073] Step 22b: Divide the target village and community based on the second target area data and the second target boundary data to obtain the second target area corresponding to the external spoil ground in the spoil ground to be planned.
[0074] In some examples, if V inner, V west, and V east respectively represent the volumes of the internal spoil ground, the southwest and the east - second external spoil grounds after the re - planning of the external spoil ground, and V original inner, V original west, and V original east respectively represent the volumes of the internal spoil ground, the southwest and the east - second external spoil grounds in the original design plan of the external spoil ground, then V 内 +V 西 +V 东 >V 原内 +V原西 +V 原东 .
[0075] Further, when the first target area and the second target area are connected according to the predetermined distance threshold to obtain the planned target dumping ground, the following method may be used but is not limited to the following method, which includes:
[0076] Step 31: Determine connection data between the first target area and the second target area according to a predetermined distance threshold.
[0077] In the embodiment of the present application, the predetermined distance threshold may be the distance between the inner dump and the outer dump.
[0078] Step 32: Based on the connection data, the first target area and the second target area are connected to obtain a planned target spoil dump.
[0079] Exemplarily, if Hinner and Horiginalinner respectively represent the final elevations of the inner dump after re-planning and the original design plan, then inner>Horiginalinner; correspondingly, if Ltoinner represents the distance from the inner dump after re-planning; Ltoouter and Ltooriginalouter respectively represent the distance from the outer dump after re-planning and the original design plan; then Ltoinner<Ltooriginalouter; Ltoouter<Ltooriginalouter.
[0080] For example, if Fbeforepressure represents the stability coefficient of the slope of the inner dumping yard before the inner and outer dumping yards are pressed against each other; and Ffinal represents the stability coefficient of the slope connected to the inner and outer dumping yards after the inner and outer dumping yards are pressed against each other, then Fbeforepressure>1.0 and Ffinal>1.2.
[0081] For example, Figure 3 Replan the external dumping site for the Weijiamao open-pit coal mine. Figure 4 This is a schematic diagram of reducing the transport distance for internal transportation. Figure 3 and Figure 4 , N village = 4, N original village = 7, the Southwest and East Second External Spoil Dumping Sites reduced the land acquisition work of three villages and communities, saving approximately RMB 721 million in land acquisition costs.
[0082] Specifically, S. 排 / S 村 =93.30%, S 原排 / S 原村 =50.59%, which improved the land utilization rate of the external dumping site and reduced the area of invalid land acquisition.
[0083] Vinner = 578 million cubic meters, Vwest = 101.57 million cubic meters, Veast = 130.15 million cubic meters, Voriginal inner = 398.44 million cubic meters, Voriginal west = 200.20 million cubic meters, Voriginal east = 203.78 million cubic meters, the overall height of the inner dump is increased by 32 meters, the capacity of the dump in the first mining area is increased by 110 million cubic meters, and the dump in the first mining area and the southwest and east second outer dumps help each other to increase the dump capacity by 70 million cubic meters. The total capacity of the re-planned dump meets the requirements and conforms to the time-space deduction relationship.
[0084] Hinner = 1208 meters, Hyuaninner = 1176 meters, the height of the inner dumping site increased by 32 meters. L to inner < L to original outer, the capacity of the outer dumping site decreased, the capacity of the inner dumping site increased, the waste originally sent to the outer dumping site was discharged to the inner dumping site, taking 2022 as an example, saving 771 meters of transportation distance. L to outer < L to original outer, after the inner and outer dumping sites are connected, the transportation distance to the planned outer dumping site is reduced by 100-200 meters.
[0085] Fbefore compression>1.0, before the inner and outer dumps collide with each other, the exposure time of the inner dump slope is short, about 1 year, and the temporary slope stability coefficient is greater than 1. Ffinal>1.2, the inner and outer dumps collide with each other to form the final slope, the exposure time is greater than 20 years, and the slope stability coefficient must be greater than 1.2.
[0086] Taking Weijiamao open-pit coal mine as the research object, the existing soil dumping planning problems were studied, and effective countermeasures were proposed and implemented, thereby achieving the goal of less land acquisition, short transportation distance and stable slope. Specifically, the number of villages occupied by the Southwest and East Second Outer Dumping Sites was reduced from 7 to 4, saving about 721 million yuan in land acquisition costs, including 199 million yuan for Hongshuliang Community, 195 million yuan for Miaoliang Community, and 327 million yuan for Xingshumao Community. The Southwest and East Second Outer Dumping Sites served the first mining area for 19 years, which saved about 37.9 million yuan in land acquisition costs. Furthermore, the overall height of the inner dumping site was increased, and the boundary of the outer dumping site overlapped with the mining boundary. The dual effect reduced the distance of soil dumping. The inner dumping volume was about 15 million cubic meters, and the transportation distance was reduced by 771 meters. The transportation distance adjustment cost of each cubic meter of soil and rock was 0.001 yuan / cubic meter, and 11.56 million yuan was saved due to the reduction of transportation distance. The change requires that the inner and outer dumps support each other, and the change clearly stipulates that a 100-meter dump safety boundary should be reserved during the operation process, so that the inner and outer dumps can be connected in time and support each other more easily. After the change, the slope stability coefficient of the East Second Outer Dump is 1.31, the slope stability coefficient of the Southwest Outer Dump is 1.26, and the slope stability coefficient of the Inner Dump is 1.36.
[0087] Compared with the current existing technology, this embodiment obtains boundary data of multiple villages and target boundary data corresponding to the spoil dump to be planned; based on the boundary data and the target boundary data, determines the target village corresponding to the spoil dump to be planned from multiple villages, the target village being the village that needs to be occupied by the spoil dump to be planned; divides the target village to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned and a second target area corresponding to the outer spoil dump in the spoil dump to be planned; connects the first target area and the second target area according to a predetermined distance threshold to obtain the planned target spoil dump, which can optimize the situation where the outer spoil dump occupies multiple villages and each village only occupies part of the land, and can also reduce the distance between the inner and outer spoil dumps to avoid the formation of artificial gullies and ensure the stability of the slope.
[0088] Further, as Figure 1 and Figure 2 The specific implementation of the method shown in the embodiment provides a planning device for a spoil dump, such as Figure 5 As shown, the device includes: an acquisition module 31, a determination module 32, a division module 33, and a connection module 34.
[0089] An acquisition module 31 is configured to acquire boundary data of multiple villages and target boundary data corresponding to the spoil dump to be planned;
[0090] A determination module 32 is configured to determine a target village corresponding to the to-be-planned spoil dump from the plurality of villages based on the boundary data and the target boundary data, wherein the target village is the village to be occupied by the to-be-planned spoil dump;
[0091] The division module 33 is configured to divide the target village community to obtain a first target area corresponding to the inner dumping ground in the dumping ground to be planned and a second target area corresponding to the outer dumping ground in the dumping ground to be planned;
[0092] The connection module 34 is configured to connect the first target area and the second target area according to a predetermined distance threshold to obtain a planned target dump.
[0093] In some examples of this embodiment, the determination module 32 is specifically configured to determine the area data of the multiple villages based on the boundary data, and to determine the target area data corresponding to the target spoil dump based on the target boundary data; based on the boundary data, the area data, the target area data and the target boundary data, determine the target village corresponding to the spoil dump to be planned from the multiple villages.
[0094] In some examples of this embodiment, the determination module 32 is specifically configured to analyze the multiple villages based on the boundary data, the area data, the target area data and the target boundary data; and determine the target village corresponding to the spoil dump to be planned from the multiple villages according to the analysis results.
[0095] In some examples of this embodiment, the division module 33 is specifically configured to determine the first target area data corresponding to the inner spoil dump and the second target area data corresponding to the outer spoil dump in the target area data; and to determine the first target boundary data corresponding to the inner spoil dump and the second target boundary data corresponding to the outer spoil dump in the target boundary data.
[0096] In some examples of this embodiment, the division module 33 is further configured to divide the target village based on the first target area data and the first target boundary data to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned; and to divide the target village based on the second target area data and the second target boundary data to obtain a second target area corresponding to the inner spoil dump in the spoil dump to be planned.
[0097] In some examples of this embodiment, the connection module 34 is specifically configured to determine the connection data of the first target area and the second target area according to the predetermined distance threshold; based on the connection data, the first target area and the second target area are connected to obtain the planned target spoil dump.
[0098] It should be noted that for other corresponding descriptions of the functional units involved in the planning device for a spoil dump provided in this embodiment, reference can be made to Figure 1 and Figure 2 The corresponding description in will not be repeated here.
[0099] Based on the above Figure 1 and Figure 2 The method shown in the embodiment also provides a computer-readable storage medium on which a computer program is stored. When the computer program is executed by a processor, the above-mentioned Figure 1 and Figure 2 The method shown.
[0100] Based on this understanding, the technical solution of the present application can be embodied in the form of a software product, which can be stored in a non-volatile storage medium (which can be a CD-ROM, USB flash drive, mobile hard disk, etc.), including a number of instructions for enabling a computer device (which can be a personal computer, server, or network device, etc.) to execute the methods of various implementation scenarios of the present application.
[0101] like Figure 6 The figure shows a hardware structure diagram of an electronic device of the present invention, including:
[0102] at least one processor 401; and,
[0103] A memory 402 is communicatively connected to at least one of the processors 401; wherein,
[0104] The memory 402 stores instructions that can be executed by at least one of the processors. The instructions are executed by at least one of the processors so that the at least one processor can execute the method for planning a spoil dump as described above.
[0105] Figure 6 A processor 401 is taken as an example.
[0106] The electronic device may further include: an input device 403 and a display device 404 .
[0107] The processor 401, the memory 402, the input device 403 and the display device 404 may be connected via a bus or other means. Figure 6 The example of connecting through bus is taken in the following.
[0108] The memory 402 is a non-volatile computer-readable storage medium that can be used to store non-volatile software programs, non-volatile computer executable programs and modules, such as program instructions / modules corresponding to the method for planning a spoil dump in the embodiment of the present application, for example, Figure 1 and Figure 2 The processor 401 executes various functional applications and data processing by running the non-volatile software programs, instructions and modules stored in the memory 402, that is, the method for planning the spoil dump in the above embodiment is implemented.
[0109] The memory 402 may include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required by at least one function; the data storage area may store data created according to the use of the method for planning a soil dump, etc. In addition, the memory 402 may include a high-speed random access memory, and may also include a non-volatile memory, such as at least one disk storage device, a flash memory device, or other non-volatile solid-state storage devices. In some embodiments, the memory 402 may optionally include a memory remotely arranged relative to the processor 401, and these remote memories may be connected to a device for executing the method for planning a soil dump via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0110] The input device 403 can receive user clicks and generate signal inputs related to user settings and function controls of the spoil dump planning method. The display device 404 can include display devices such as a display screen.
[0111] The one or more modules are stored in the memory 402, and when executed by the one or more processors 401, the method for planning a spoil dump in any of the above method embodiments is executed.
[0112] Optionally, the above-mentioned physical device may also include a user interface, a network interface, a camera, a radio frequency (RF) circuit, a sensor, an audio circuit, a WI-FI module, etc. The user interface may include a display, an input unit such as a keyboard, etc., and the optional user interface may also include a USB interface, a card reader interface, etc. The network interface may optionally include a standard wired interface, a wireless interface (such as a WI-FI interface), etc.
[0113] Those skilled in the art will appreciate that the above-mentioned physical device structure provided in this embodiment does not constitute a limitation on the physical device, and may include more or fewer components, or a combination of certain components, or different arrangements of components.
[0114] The storage medium may also include an operating system and a network communication module. The operating system is a program that manages the hardware and software resources of the above-mentioned physical device, and supports the operation of the information processing program and other software and / or programs. The network communication module is used to realize the communication between the components inside the storage medium, and the communication with other hardware and software in the information processing physical device.
[0115] Through the description of the above implementation methods, the technical personnel in this field can clearly understand that the present application can be implemented by means of software plus the necessary general hardware platform, or by hardware. By applying the scheme of this embodiment, compared with the current existing technology, this embodiment obtains the boundary data of multiple villages and the target boundary data corresponding to the planned spoil dump; based on the boundary data and the target boundary data, the target village corresponding to the planned spoil dump is determined from multiple villages, and the target village is the village that needs to be occupied by the planned spoil dump; the target village is divided to obtain the first target area corresponding to the inner spoil dump in the planned spoil dump and the second target area corresponding to the outer spoil dump in the planned spoil dump; the first target area and the second target area are connected according to the predetermined distance threshold to obtain the planned target spoil dump, which can optimize the situation where the outer spoil dump occupies multiple villages and each village only occupies part of the land, and can also reduce the distance between the inner and outer spoil dumps to avoid the formation of artificial gullies and ensure the stability of the slope.
[0116] It should be noted that, in this article, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0117] The above is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments described herein, but will conform to the widest scope consistent with the principles and novel features applied for herein.
Claims
1. A method for planning a spoil dump, characterized in that: include: Obtain boundary data of multiple villages and communities and target boundary data corresponding to the planned spoil dump; Based on the boundary data and the target boundary data, determining a target village corresponding to the to-be-planned spoil dump from the plurality of villages, the target village being the village to be occupied by the to-be-planned spoil dump; Dividing the target villages and communities to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned and a second target area corresponding to the outer spoil dump in the spoil dump to be planned; The first target area and the second target area are connected according to a predetermined distance threshold to obtain a planned target spoil dump.
2. The method according to claim 1, characterized in that The step of determining the target village corresponding to the spoil dump to be planned from the plurality of villages based on the boundary data and the target boundary data includes: Determining the area data of the plurality of villages based on the boundary data, and determining the target area data corresponding to the target spoil dump based on the target boundary data; Based on the boundary data, the area data, the target area data and the target boundary data, the target village corresponding to the spoil dump to be planned is determined from the multiple villages.
3. The method according to claim 2, characterized in that The step of determining a target village corresponding to the spoil dump to be planned from the plurality of villages based on the boundary data, the area data, the target area data and the target boundary data comprises: Analyzing the plurality of villages based on the boundary data, the area data, the target area data, and the target boundary data; The target village or community corresponding to the spoil dump to be planned is determined from the multiple villages or communities according to the analysis result.
4. The method according to claim 3, characterized in that The target villages and communities are divided to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned and a second target area corresponding to the outer spoil dump in the spoil dump to be planned, including: Determine first target area data corresponding to the inner dump and second target area data corresponding to the outer dump in the target area data; and, Determine the first target boundary data corresponding to the inner dump and the second target boundary data corresponding to the outer dump in the target boundary data.
5. The method according to claim 4, characterized in that The dividing of the target villages and communities to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned and a second target area corresponding to the outer spoil dump in the spoil dump to be planned also includes: Dividing the target village based on the first target area data and the first target boundary data to obtain a first target area corresponding to the inner spoil dump in the spoil dump to be planned; and Based on the second target area data and the second target boundary data, the target village is divided to obtain a second target area corresponding to the inner spoil dump in the spoil dump to be planned.
6. The method according to claim 5, characterized in that The step of connecting the first target area and the second target area according to a predetermined distance threshold to obtain a planned target dumping ground includes: Determining connection data between the first target area and the second target area according to the predetermined distance threshold; Based on the connection data, the first target area and the second target area are connected to obtain a planned target spoil dump.
7. A planning device for a spoil dump, characterized in that: include: An acquisition module is configured to acquire boundary data of multiple villages and target boundary data corresponding to the spoil dump to be planned; A determination module is configured to determine a target village corresponding to the to-be-planned spoil dump from the plurality of villages based on the boundary data and the target boundary data, wherein the target village is the village to be occupied by the to-be-planned spoil dump; A division module is configured to divide the target village community to obtain a first target area corresponding to the inner dumping ground in the dumping ground to be planned and a second target area corresponding to the outer dumping ground in the dumping ground to be planned; The connection module is configured to connect the first target area and the second target area according to a predetermined distance threshold to obtain a planned target spoil dump.
8. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 6 is implemented.
9. An electronic device comprising a storage medium, a processor, and a computer program stored in the storage medium and executable on the processor, characterized in that: When the processor executes the computer program, the method according to any one of claims 1 to 6 is implemented.
10. A computer program product, comprising a computer program, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 6 is implemented.