Long-distance construction method and device under slightly acidic geological condition

Through the construction methods of using drilling rigs and jet pipes under slightly acidic geological conditions, the problems of rock corrosion and landslides during long-distance construction are solved, an efficient and stable construction process is achieved, and construction efficiency and safety are improved through circulating water.

CN119712140APending Publication Date: 2025-03-28POWERCHINA WATER ENVIRONMENT GOVERANCE
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411803116.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-10
Publication Date
2025-03-28

AI Technical Summary

Technical Problem

Under slightly acidic geological conditions, long-distance construction faces problems such as strong rock corrosion, abundant groundwater, and easy landslide, which seriously affects the construction progress and safety.

Method used

A construction device including a drilling rig, sealing partition, cutter plate, support column, collection tube, conveyor belt and jet pipe is adopted to break rocks through the drilling rig, use sealing partition plate and cutting plate to form a mud and water chamber, input pressurized mud to stabilize the excavation surface, and spray concrete through the jet pipe to fill the surface depression to form a protective layer.

Benefits of technology

This method effectively reduces dependence on external water sources, inhibits dust pollution, improves construction efficiency, enhances overall structural stability, and achieves a win-win situation of economic and social benefits through circulating water.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119712140A_ABST
    Figure CN119712140A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of engineering construction, and discloses a long-distance construction method and device under the meta-acid geological condition. The long-distance construction device comprises an excavation mechanism, and a conveying mechanism is arranged at the bottom of the excavation mechanism; the excavation mechanism comprises a drilling machine, a sealing partition plate is fixedly connected to the left side of the drilling machine, a cutter head is fixedly connected to the left side of the sealing partition plate, a plurality of supporting columns are fixedly connected to the bottom of the drilling machine and arranged in a rectangular array, a mounting hole is formed in the right side of the drilling machine, and a collecting pipe is mounted in the mounting hole. According to the long-distance construction method and device under the meta-acid geological condition, concrete is injected into cracks opened in a sprayed face through the injection pipe, surface pits are filled, stress concentration of a sprayed structure is avoided or relieved, the surface of the structure is pasted, a protection layer is formed, a gear is rotated through a motor, and a lantern ring is driven to rotate on the surface of a collecting pipe through meshing tooth blades; the working angle of the injection pipe is adjusted, and the working coverage and flexibility are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of engineering construction, and in particular to a long-distance construction method and device under acidic geological conditions. Background Art

[0002] In the current engineering construction field, especially in areas with acidic geological conditions, the research and application of long-distance construction technology is particularly important. The soil and groundwater in these areas often contain high acid components, which puts higher requirements on the corrosion resistance of construction materials and equipment. In order to ensure the construction quality and long-term stability of the project, engineers and technicians must take a series of effective measures and methods.

[0003] Traditionally, long-distance construction under acidic geological conditions faces many challenges, such as strong rock corrosion, abundant groundwater, and easy landslides. These problems seriously affect the construction progress and safety. At present, in order to cope with the long-distance construction difficulties under acidic geological conditions, the industry usually takes the following measures: First, use anti-corrosion materials to extend the service life of the structure by improving the corrosion resistance of the materials; second, strengthen support and use more stable support structures to prevent surrounding rock collapse; third, optimize the drainage system and remove groundwater in time to reduce the impact on construction. Although these methods have alleviated the construction difficulty to a certain extent, the large-scale use of anti-corrosion materials and strengthened support will result in higher purchase and installation costs, longer maintenance time and other shortcomings.

[0004] The above methods do not fundamentally solve the problem, especially for long-term operations, it is still difficult to avoid frequent engineering accidents caused by soil erosion. Therefore, it is particularly urgent to develop a set of long-distance construction methods with strong adaptability and high reliability under acidic geological conditions. Summary of the invention

[0005] The purpose of the present invention is to provide a long-distance construction method and device under acidic geological conditions to solve the problems raised in the above-mentioned background technology.

[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: a long-distance construction device under acidic geological conditions, comprising an excavation mechanism, wherein a conveying mechanism is provided at the bottom of the excavation mechanism; The excavation mechanism includes a drilling rig, a sealing baffle is fixedly connected to the left side of the drilling rig, a cutter head is fixedly connected to the left side of the sealing baffle, a plurality of support columns are fixedly connected to the bottom of the drilling rig, the plurality of support columns are arranged in a rectangular array, a mounting hole is opened on the right side of the drilling rig, and a collecting pipe is installed in the mounting hole; The conveying mechanism includes a conveying pipe, the front and rear sides of the conveying pipe are respectively fixedly connected to the support columns, the left side of the conveying pipe is fixedly connected to a collecting frame, the front and rear sides of the top of the collecting frame are respectively fixedly connected to inclined plates, a conveying belt is arranged inside the conveying pipe, and a plurality of sieve holes are opened on the surface of the conveying belt.

[0007] Depending on the specific conditions of the construction site, different types of cutter heads can be selected for the front-end excavation mechanism to adapt to rocks of different hardness.

[0008] Preferably, a baffle is fixedly connected to the interior of the collecting pipe, a feed pipe is arranged on the top of the baffle, the output port of the feed pipe is fixedly connected to the drilling rig, a discharge pipe is arranged on the bottom of the baffle, and the input port of the discharge pipe is fixedly connected to the drilling rig.

[0009] Preferably, a ring is provided on the surface of the collecting pipe, a fixed block is fixedly connected to the top of the ring, an injection pipe is fixedly connected to the top of the fixed block, a channel is opened in the fixed block, a concrete pipe is fixedly connected to the right side of the channel, and a plurality of teeth are fixedly connected to the surface of the ring, and the plurality of teeth are arranged in a circular array with the ring as the center.

[0010] Preferably, a motor is fixedly connected to the bottom of the collecting pipe, an output shaft of the motor is fixedly connected to a rotating shaft, an output end of the rotating shaft is fixedly connected to a gear, and the gear is meshed with a toothed blade.

[0011] Preferably, a water purifier is fixedly connected to the front of the delivery pipe, a water pumping pipe is fixedly connected to the left side of the water purifier, and an input port of the water pumping pipe passes through the interior of the delivery pipe and extends to the bottom of the inner wall thereof.

[0012] Preferably, a taking port is provided on the top of the water purifier, a cover plate is attached to the top of the taking port, and a sewage pipe is fixedly connected to the right side of the water purifier.

[0013] Preferably, the back of the transmission pipe is fixedly connected to a water tank, the right side of the water tank is fixedly connected to a clean water pipe, the left side of the water tank is fixedly connected to an electric pump, and the output port of the electric pump is fixedly connected to a water outlet pipe.

[0014] Preferably, an installation groove is opened at the top of the inner wall of the delivery pipe, a water outlet plate is installed in the installation groove, a plurality of nozzles are installed in the water outlet plate, the top of the water outlet plate is fixedly connected to the water outlet pipe, and the output port of the water outlet pipe passes through the interior of the delivery pipe and extends to the top of its inner wall.

[0015] On the other hand, a long-distance construction method under acidic geological conditions is also provided, and the steps are as follows: S1: Determine the construction route and clean up the debris on site; S2: moving the device to the starting point and aligning it with the predetermined path; S3: Start the front excavation mechanism to perform initial rock breaking; S4: Adjust the speed of the intermediate conveyor belt to match the actual output; S5: Gradually implement rear reinforcement measures as the pace of progress increases; S6: Regularly check the working status of each component and perform repairs and maintenance in a timely manner; S7: After the construction is completed, the site should be completely cleared and restored to its original state. During the operation, special attention should be paid to the changes in hydrological monitoring data. Once an abnormality is found, the operation should be suspended immediately to find out the cause.

[0016] Compared with the prior art, the beneficial effects achieved by the present invention are: First, the present invention breaks rocks by drilling rigs, forms a mud and water chamber between the sealing partition and the cutter disc of the excavation face, inputs pressurized mud through the feed pipe separated by the baffle in the collecting pipe to stabilize the excavation face, and the excavated soil is mixed with the mud through the discharge pipe and re-transported to the outside world. The mud can be reused after separation, which not only reduces the dependence on external water sources but also effectively suppresses dust pollution. The injection pipe on the collar is used to inject into the cracks opened on the sprayed surface, fill the surface pits, avoid or alleviate the stress concentration of the sprayed structure, and stick to the surface of the structure to form a protective layer. Among them, the thickness of the sprayed concrete is recommended to be controlled between 10-15cm to enhance the overall structural stability. The gear is rotated by the motor, and the collar is driven to rotate on the surface of the collecting pipe through the meshing teeth. The working angle of the injection pipe is adjusted to improve the working coverage and flexibility.

[0017] Secondly, the present invention uses an inclined plate to assist the collection frame to collect the broken rocks and sewage during operation into a conveying pipe, and transports them through a conveyor belt. The sewage will fall to the bottom of the conveying pipe through the sieve holes on the conveyor belt, and be collected through a pumping pipe for rough purification using a water purifier. The silt and impurities in the water are screened and adsorbed, and finally transported out through a sewage conveying pipe for re-purification and use. The clean water is input into a water storage tank through a clean water pipe, injected into a water outlet plate through an electric pump through a water outlet pipe, and sprayed out through a nozzle for cleaning the inside of the conveying pipe. While reusing the sewage, the conveyor belt can be ensured to operate efficiently for a long time, and the construction efficiency is improved while recycling water, achieving a win-win situation of economic and social benefits.

[0018] Third, the present invention, the safety control complies with the standards "Safety Production Law of the People's Republic of China", "Construction Project Safety Production Management Regulations", "Technical Specifications for Temporary Electricity Safety at Construction Sites". In step S1, before construction, the temperature is determined to be above 0°C. Construction cannot be carried out below 0°C. During construction, rain protection measures must be taken and construction should be stopped when it rains. In step S3, according to the specific conditions of the construction site, the cutter head model of the front excavation mechanism can be selected into different types to adapt to rocks of different hardness. In step S4, after each material is transported from the conveyor belt, the electric pump is started to clean the conveyor belt to reduce the waste of water resources and the production of sewage. In step S5, the anchor rod is used to Reinforcement is carried out, with the diameter of the anchor rod not less than 25mm and the length not less than 3m. In combination with modern chemical protective coating technology, high-performance anti-corrosion coatings are used on the surfaces of key parts during the reinforcement process, which greatly improves the ability of the entire system to resist external acidic geological soil erosion. Due to the use of advanced mechanical automation technology, the construction speed is significantly improved, and the possibility of manual intervention is reduced, thereby effectively shortening the entire project cycle. Through accurate prediction of geological conditions and reasonable engineering layout planning, coupled with high-quality building materials and professional construction teams, the safety level of the construction site is greatly guaranteed and potential risk factors are reduced. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a three-dimensional schematic diagram of the overall structure of the present invention; Figure 2 It is a three-dimensional schematic diagram of the structural excavation mechanism of the present invention; Figure 3 This is a schematic diagram of the disassembly of the excavation mechanism of the structure of the present invention; Figure 4 It is a rear view schematic diagram of the excavation mechanism of the structure of the present invention; Figure 5 It is a three-dimensional schematic diagram of the structural conveying mechanism of the present invention; Figure 6 It is a rear view schematic diagram of the conveying mechanism of the structure of the present invention; Figure 7 This is a schematic diagram of the disassembly of the structural conveying mechanism of the present invention.

[0020] Legend: 1. Excavation mechanism; 101. Drilling machine; 102. Sealing baffle; 103. Cutter head; 104. Support column; 105. Manifold; 106. Waterproof plate; 107. Feed pipe; 108. Discharge pipe; 109. Ring; 110. Fixed block; 111. Jet pipe; 112. Concrete pipe; 113. Tooth blade; 114. Motor; 115. Rotating shaft; 116. Gear; 2. Conveying mechanism; 201. Conveying pipe; 202. Collecting frame; 203. Inclined plate; 204. Conveyor belt; 205. Water outlet plate; 206. Nozzle; 207. Suction pipe; 208. Water purifier; 209. Cover plate; 210. Sewage pipe; 211. Clean water pipe; 212. Water storage tank; 213. Electric pump; 214. Water outlet pipe. DETAILED DESCRIPTION

[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Example

[0022] like Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 and Figure 7 As shown, the present invention provides a technical solution: a long-distance construction device under acidic geological conditions, comprising an excavation mechanism 1, and a conveying mechanism 2 is arranged at the bottom of the excavation mechanism 1; The excavation mechanism 1 includes a drilling rig 101, a sealing baffle 102 is fixedly connected to the left side of the drilling rig 101, a cutter head 103 is fixedly connected to the left side of the sealing baffle 102, a plurality of support columns 104 are fixedly connected to the bottom of the drilling rig 101, and the plurality of support columns 104 are arranged in a rectangular array. An installation hole is opened on the right side of the drilling rig 101, and a collecting pipe 105 is installed in the installation hole.

[0023] A water-blocking plate 106 is fixedly connected to the interior of the collecting pipe 105 , a feed pipe 107 is arranged on the top of the water-blocking plate 106 , the output port of the feed pipe 107 is fixedly connected to the drilling rig 101 , a discharge pipe 108 is arranged on the bottom of the water-blocking plate 106 , the input port of the discharge pipe 108 is fixedly connected to the drilling rig 101 .

[0024] A collar 109 is sleeved on the surface of the collecting pipe 105, a fixing block 110 is fixedly connected to the top of the collar 109, an injection pipe 111 is fixedly connected to the top of the fixing block 110, a channel is opened in the fixing block 110, a concrete pipe 112 is fixedly connected to the right side of the channel, a plurality of teeth 113 are fixedly connected to the surface of the collar 109, and the plurality of teeth 113 are arranged in a circular array with the collar 109 as the center.

[0025] A motor 114 is fixedly connected to the bottom of the collecting tube 105 . The output shaft of the motor 114 is fixedly connected to a rotating shaft 115 . The output end of the rotating shaft 115 is fixedly connected to a gear 116 . The gear 116 is meshed with the tooth blades 113 .

[0026] Through the above technical scheme, the rock is broken by the drilling rig 101, and a mud and water chamber is formed between the sealing partition 102 and the excavation face cutter disc 103. The pressurized mud is input through the feed pipe 107 separated by the baffle 106 in the manifold 105 to stabilize the excavation face. The excavated soil is mixed with the mud through the discharge pipe 108 and re-transported to the outside. The mud can be reused after separation, which not only reduces the dependence on external water sources but also effectively suppresses dust pollution. The injection pipe 111 on the ring 109 is used to inject into the cracks opened on the sprayed surface, fill the surface pits, avoid or alleviate the stress concentration of the sprayed structure, and stick to the surface of the structure to form a protective layer. Among them, the thickness of the sprayed concrete is recommended to be controlled between 10-15cm to enhance the overall structural stability. The gear 116 is rotated by the motor 114, and the ring 109 is driven to rotate on the surface of the manifold 105 through the meshing teeth 113. The working angle of the injection pipe 111 is adjusted to improve the working coverage and flexibility.

[0027] like Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 and Figure 7 As shown, the present invention provides a technical solution: the conveying mechanism 2 includes a conveying pipe 201, the front and rear sides of the conveying pipe 201 are respectively fixedly connected to the support column 104, the left side of the conveying pipe 201 is fixedly connected with a collecting frame 202, the front and rear sides of the top of the collecting frame 202 are respectively fixedly connected with an inclined plate 203, a conveying belt 204 is arranged inside the conveying pipe 201, and a plurality of sieve holes are opened on the surface of the conveying belt 204.

[0028] A water purifier 208 is fixedly connected to the front of the delivery pipe 201, and a water pumping pipe 207 is fixedly connected to the left side of the water purifier 208. The input port of the water pumping pipe 207 passes through the interior of the delivery pipe 201 and extends to the bottom of the inner wall thereof.

[0029] A take-out opening is provided on the top of the water purifier 208 , a cover plate 209 is attached to the top of the take-out opening, and a sewage pipe 210 is fixedly connected to the right side of the water purifier 208 .

[0030] A water tank 212 is fixedly connected to the back of the transmission pipe 201 , a clean water pipe 211 is fixedly connected to the right side of the water tank 212 , an electric pump 213 is fixedly connected to the left side of the water tank 212 , and a water outlet pipe 214 is fixedly connected to the output port of the electric pump 213 .

[0031] An installation groove is provided at the top of the inner wall of the delivery pipe 201, in which a water outlet plate 205 is installed, and a plurality of nozzles 206 are installed in the water outlet plate 205. The top of the water outlet plate 205 is fixedly connected to the water outlet pipe 214, and the output port of the water outlet pipe 214 passes through the interior of the delivery pipe 201 and extends to the top of its inner wall.

[0032] Through the above technical scheme, the rock blocks and sewage broken during operation are collected into the conveying pipe 201 with the assistance of the collecting frame 202 through the inclined plate 203, and transported through the conveyor belt 204. The sewage will fall to the bottom of the conveying pipe 201 through the sieve holes on the conveyor belt 204, and be collected through the pumping pipe 207. It is roughly purified by the water purifier 208, and the silt and impurities in the water are screened and adsorbed. Finally, it is transported out through the sewage conveying pipe 210 for re-purification and use. The clean water is input into the water storage tank 212 through the clean water pipe 211, and is injected into the water outlet plate 205 through the outlet pipe 214 through the electric pump 213, and is sprayed out through the nozzle 206 for cleaning the inside of the conveying pipe 201. While reusing the sewage, the conveyor belt 204 can be guaranteed to operate efficiently for a long time, and the construction efficiency is improved while recycling water, achieving a win-win situation of economic and social benefits.

[0033] like Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 and Figure 7 As shown, the present invention provides a technical solution: a long-distance construction method under acidic geological conditions, the steps are as follows: S1: Determine the construction route and clean up the debris on site; S2: moving the device to the starting point and aligning it with the predetermined path; S3: starting the front excavation mechanism 1 to perform initial rock breaking; S4: adjusting the speed of the intermediate conveyor belt 204 to match the actual output; S5: Gradually implement rear reinforcement measures as the pace of progress increases; S6: Regularly check the working status of each component and perform repairs and maintenance in a timely manner; S7: After the construction is completed, the site should be completely cleared and restored to its original state. During the operation, special attention should be paid to the changes in hydrological monitoring data. Once an abnormality is found, the operation should be suspended immediately to find out the cause.

[0034] Through the above technical scheme, the safety control complies with the specifications of the "Safety Production Law of the People's Republic of China" 978-7-5216-1908-9, the "Construction Project Safety Production Management Regulations" 1511211635, and the "Technical Specifications for Temporary Electricity Safety at Construction Sites" JGJ46-2005. In step S1, before construction, it is determined that the temperature is above 0°C. Construction cannot be carried out below 0°C. During construction, rain protection measures must be taken and construction should be stopped when it rains. In step S3, according to the specific conditions of the construction site, the cutter head model of the front excavation mechanism 1 can be selected from different types, such as single-blade or multi-blade, to adapt to rocks of different hardness. In step S4, after each material is transported from the conveyor belt 204, the electric pump 213 is started to excavate the conveyor belt 204. Cleaning, reduce the waste of water resources and the production of sewage. In step S5, anchor rods are used for reinforcement, where the diameter of the anchor rods is not less than 25mm and the length is not less than 3m. In combination with modern chemical protective coating technology, high-performance anti-corrosion coatings are used to coat the surfaces of key parts in the reinforcement process, which greatly improves the ability of the entire system to resist external acidic geological soil erosion. Due to the use of advanced mechanical automation technology, the construction speed is significantly improved, and the possibility of human intervention is reduced, thereby effectively shortening the entire project cycle. Through accurate prediction of geological conditions and reasonable engineering layout planning, coupled with high-quality building materials and professional construction teams, the safety level of the construction site is greatly guaranteed and potential risk factors are reduced.

[0035] When in use, the rock is broken by the drilling rig 101, and a mud and water chamber is formed between the sealing partition 102 and the excavation face cutter disc 103. The pressurized mud is input through the feed pipe 107 separated by the baffle 106 in the manifold 105 to stabilize the excavation face. The excavated soil is mixed with the mud through the discharge pipe 108 and re-transported to the outside. The mud can be reused after separation, which not only reduces the dependence on external water sources but also effectively suppresses dust pollution. The injection pipe 111 on the ring 109 is used to inject into the cracks opened on the sprayed surface, fill the surface pits, avoid or alleviate the stress concentration of the sprayed structure, and adhere to the surface of the structure to form a protective layer. Among them, the thickness of the sprayed concrete is recommended to be controlled between 10-15cm to enhance the overall structural stability. The gear 116 is rotated by the motor 114, and the ring 109 is driven to rotate on the surface of the manifold 105 through the meshing teeth 113. The working angle of the injection pipe 111 is adjusted to improve the working coverage and flexibility. The rock blocks and sewage broken during operation are collected into the conveying pipe 201 with the assistance of the inclined plate 203 and the collecting frame 202, and transported through the conveying belt 204. The sewage will fall to the bottom of the conveying pipe 201 through the sieve holes on the conveying belt 204, and be collected through the pumping pipe 207. It is roughly purified by the water purifier 208, and the silt and impurities in the water are screened and adsorbed, and finally transported out through the sewage conveying pipe 210 for re-purification and use. The clean water is input into the water storage tank 212 through the clean water pipe 211, and is injected into the water outlet plate 205 through the outlet pipe 214 through the electric pump 213, and is sprayed out through the nozzle 206 for cleaning the inside of the conveying pipe 201. While reusing the sewage, the conveying belt 204 can be guaranteed to operate efficiently for a long time, and the construction efficiency is improved while recycling water, achieving a win-win situation of economic and social benefits.Safety control complies with the standards "Safety Production Law of the People's Republic of China" 978-7-5216-1908-9, "Construction Project Safety Production Management Regulations" 1511211635, "Technical Specifications for Temporary Electricity Safety at Construction Sites" JGJ46-2005. In step S1, before construction, the temperature must be above 0°C. Construction cannot be carried out below 0°C. During construction, rain protection measures must be taken and construction should be stopped when it rains. In step S3, according to the specific conditions of the construction site, the cutter head model of the front excavation mechanism 1 can be selected from different types, such as single-blade or multi-blade, to adapt to rocks of different hardness. In step S4, after each material is transported from the conveyor belt 204, the electric pump 213 is started to clean the conveyor belt 204 to reduce In order to reduce the waste of water resources and the production of sewage, in step S5, anchor rods are used for reinforcement, where the diameter of the anchor rods is not less than 25 mm and the length is not less than 3 m. In combination with modern chemical protective coating technology, high-performance anti-corrosion coatings are used to coat the surfaces of key parts during the reinforcement process, which greatly improves the ability of the entire system to resist external acidic geological soil erosion. Due to the use of advanced mechanical automation technology, the construction speed is significantly improved, and the possibility of human intervention is reduced, thereby effectively shortening the entire project cycle. Through accurate prediction of geological conditions and reasonable engineering layout planning, coupled with high-quality building materials and professional construction teams, the safety level of the construction site is greatly guaranteed and potential risk factors are reduced.

[0036] While embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and alterations may be made to the embodiments without departing from the principles and spirit thereof, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A long-distance construction device under acidic geological conditions, comprising an excavation mechanism (1), characterized in that: A conveying mechanism (2) is provided at the bottom of the excavation mechanism (1); The excavation mechanism (1) comprises a drilling rig (101), a sealing baffle (102) being fixedly connected to the left side of the drilling rig (101), a cutter head (103) being fixedly connected to the left side of the sealing baffle (102), a plurality of support columns (104) being fixedly connected to the bottom of the drilling rig (101), the plurality of support columns (104) being arranged in a rectangular array, a mounting hole being provided on the right side of the drilling rig (101), a collecting pipe (105) being installed in the mounting hole; The conveying mechanism (2) comprises a conveying pipe (201), the front and rear sides of the conveying pipe (201) are respectively fixedly connected to the support column (104), the left side of the conveying pipe (201) is fixedly connected to a collecting frame (202), the front and rear sides of the top of the collecting frame (202) are respectively fixedly connected to inclined plates (203), and a conveying belt (204) is arranged inside the conveying pipe (201), and a plurality of sieve holes are provided on the surface of the conveying belt (204).

2. The long-distance construction device under acidic geological conditions according to claim 1, characterized in that: A water-blocking plate (106) is fixedly connected to the interior of the collecting pipe (105), a material delivery pipe (107) is arranged on the top of the water-blocking plate (106), and the output port of the material delivery pipe (107) is fixedly connected to the drilling rig (101); a material discharge pipe (108) is arranged at the bottom of the water-blocking plate (106), and the input port of the material discharge pipe (108) is fixedly connected to the drilling rig (101).

3. The long-distance construction device under acidic geological conditions according to claim 1 is characterized in that: The surface of the collecting pipe (105) is sleeved with a collar (109), the top of the collar (109) is fixedly connected to a fixing block (110), the top of the fixing block (110) is fixedly connected to an injection pipe (111), the fixing block (110) is provided with a channel, the right side of the channel is fixedly connected to a concrete pipe (112), and the surface of the collar (109) is fixedly connected to a plurality of tooth blades (113), the plurality of tooth blades (113) are arranged in a ring array with the collar (109) as the center.

4. The long-distance construction device under acidic geological conditions according to claim 1, characterized in that: The bottom of the collecting tube (105) is fixedly connected to a motor (114), the output shaft of the motor (114) is fixedly connected to a rotating shaft (115), the output end of the rotating shaft (115) is fixedly connected to a gear (116), and the gear (116) is meshed with the tooth blade (113).

5. The long-distance construction device under acidic geological conditions according to claim 1, characterized in that: A water purifier (208) is fixedly connected to the front of the delivery pipe (201), and a water pumping pipe (207) is fixedly connected to the left side of the water purifier (208). The input port of the water pumping pipe (207) penetrates the interior of the delivery pipe (201) and extends to the bottom of the inner wall thereof.

6. The long-distance construction device under acidic geological conditions according to claim 5, characterized in that: The top of the water purifier (208) is provided with a taking-out opening, the top of which is affixed with a cover plate (209), and the right side of the water purifier (208) is fixedly connected with a sewage pipe (210).

7. The long-distance construction device under acidic geological conditions according to claim 1, characterized in that: The back of the transmission pipe (201) is fixedly connected to a water tank (212), the right side of the water tank (212) is fixedly connected to a clean water pipe (211), the left side of the water tank (212) is fixedly connected to an electric pump (213), and the output port of the electric pump (213) is fixedly connected to a water outlet pipe (214).

8. The long-distance construction device under acidic geological conditions according to claim 1, characterized in that: The top of the inner wall of the delivery pipe (201) is provided with an installation groove, a water outlet plate (205) is installed in the installation groove, a plurality of nozzles (206) are installed in the water outlet plate (205), the top of the water outlet plate (205) is fixedly connected to the water outlet pipe (214), and the outlet of the water outlet pipe (214) passes through the interior of the delivery pipe (201) and extends to the top of the inner wall thereof.

9. A long-distance construction method under acidic geological conditions, applied to a long-distance construction device under acidic geological conditions as described in any one of claims 1 to 8, characterized in that: Here are the steps: S1: Determine the construction route and clean up the debris on site; S2: moving the device to the starting point and aligning it with the predetermined path; S3: starting the front excavation mechanism (1) to perform initial rock breaking; S4: adjusting the speed of the intermediate conveyor belt (204) to match the actual output; S5: Gradually implement rear reinforcement measures as the pace of progress increases; S6: Regularly check the working status of each component and perform repairs and maintenance in a timely manner; S7: After the construction is completed, the site should be completely cleared and restored to its original state. During the operation, attention should be paid to the changes in hydrological monitoring data. Once an abnormality is found, the operation should be suspended immediately to find out the cause.

Citation Information

Patent Citations

  • Muddy water balance push bench

    CN103398214A

  • Integrated equipment for prospecting, mining and ore transportation

    CN107143341A

  • Originating method in cave for earth pressing balanced shield in small space

    CN109505613A

  • Intelligent equipment for rapid rock breaking, excavation and supporting of tunnel

    CN113847052A

  • Residue soil conveying device suitable for small-curve earth pressure balance shield tunneling machine

    CN114893200A