Shield tunnel construction period muck transfer facility and using method thereof
By setting up height-adjustable baffles and stable structures in the slag transfer facilities for shield tunnel construction, the problem of slag falling under complex terrain conditions is solved, transportation safety and stability are improved, and construction efficiency and safety are ensured.
Patent Information
- Application Number
- CN202411936882.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-26
- Publication Date
- 2025-04-04
AI Technical Summary
During the construction of the shield tunnel, when the slag transfer facilities go through complex terrain such as sharp turns and ground slope, the slag can easily slide off the truck bucket, affecting loading capacity and construction safety.
A slag transport facility including a height-adjustable baffle is designed to prevent the slag from sliding off through adjustment and fixation of the baffle, and ensure the stability and safety of the facilities through stable structures such as bases, feet, skateboards and foot pads.
Effectively prevent the slag from falling under complex terrain conditions, improve transportation safety and stability, and ensure efficient and safe construction.
Smart Images

Figure CN119749661A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of shield tunnel construction, and in particular to a slag transfer facility during shield tunnel construction and a use method thereof. Background Art
[0002] As a method of underground excavation construction, the shield method is not restricted by terrain, landform, river water conditions, etc. It has the advantages of high safety, fast construction speed, less impact on the environment, and flexible line selection. It has been widely used in the construction of subway tunnel projects passing through urban core areas or sensitive areas.
[0003] During the shield tunnel construction process, the excavated soil and debris cut by the shield machine cutter head needs to be transported to the outside of the tunnel using transfer facilities. During the soil transfer process, when the transfer facilities pass through complex terrain such as sharp turns and inclined ground, the soil and debris in the truck bed can easily slip off the truck bed, affecting the loading capacity of the transfer facilities and threatening the safety of on-site construction personnel and equipment. Summary of the invention
[0004] The purpose of the present invention is to overcome the defects and shortcomings of existing slag transfer facilities during shield tunnel construction, and to provide a slag transfer facility during shield tunnel construction. The transfer facility effectively prevents the slag from sliding off the truck bed during transportation in complex terrain in the tunnel by setting a height-adjustable baffle, thereby ensuring the stability and safety of the slag during transportation. The transfer facility is particularly suitable for slag transfer under complex terrain conditions in the tunnel during shield tunnel construction.
[0005] Another object of the present invention is to provide a method for using a slag transfer facility during shield tunnel construction. The method is applied to the slag transfer facility during shield tunnel construction provided by the present invention to ensure efficient, safe and stable operation of the facility under complex terrain conditions.
[0006] The purpose of the present invention can be achieved through the following technical solutions: A slag transfer facility during shield tunnel construction, comprising a bottom plate structure; the bottom plate structure comprises a bottom plate, a universal wheel is arranged at the bottom of the bottom plate, a bucket is fixedly connected to the top of the bottom plate; a baffle structure is arranged on the outside of the bucket; The baffle structure includes a baffle with a limiting hole, and the outer side of the truck bed is threadedly connected to a first screw; the baffle is slidably connected to the first screw through the limiting hole, and the cooperation between the first screw and the limiting hole enables the baffle to be adjusted and fixed at different positions on the truck bed.
[0007] As a preferred embodiment, the baffle adopts a U-shaped structure and is wrapped along three sides of the periphery of the truck box.
[0008] As a preferred embodiment, a sliding bar is provided on the inner side of the baffle, and the sliding bar forms a sliding connection with the outer side of the truck bed; a limiting bar is provided on the outer side of the truck bed, and the limiting bar abuts against the edge of the baffle to prevent the baffle from shifting when it is raised or lowered on the truck bed.
[0009] As a preferred embodiment, it further includes a gasket, and the end of the first screw rod passes through the gasket and the limiting holes on the baffle in sequence to be connected to the outside of the truck bucket.
[0010] As a preference, a handle is provided on the outer side of the baffle.
[0011] As a preferred embodiment, it also includes a stabilizing structure; the stabilizing structure includes a base, a tripod and a foot pad fixedly connected to the bottom plate, the base is rotatably connected to the tripod, and a slide plate is provided at the end of the tripod; one end of the slide plate is slidably connected to the tripod, and the other end is movably connected to the foot pad, and a limiting nail is provided on the foot pad.
[0012] As a preferred embodiment, the stabilizing structure also includes a third screw for limiting the relative sliding of the skateboard and the tripod. The skateboard and the tripod are provided with corresponding screw holes. The third screw is arranged on the skateboard and the tripod and cooperates with the screw holes, so that the skateboard can be adjusted and fixed at different positions on the tripod.
[0013] Preferably, a fourth screw is installed at the connecting end of the skateboard and the foot pad through a threaded hole, and the bottom end of the fourth screw is fixedly connected to the foot pad.
[0014] As a preference, a plug is provided at the top end of the fourth screw rod, and a spring is sleeved outside the fourth screw rod, and the spring is located between the bottom of the plug rod and the top of the slide plate.
[0015] A method for using a slag transfer facility during shield tunnel construction, which is applied to the slag transfer facility during shield tunnel construction as described above, comprises the following steps: Step 1: Before loading the excavated soil from the shield machine, move the bucket to the predetermined position, rotate the tripod to a suitable angle, stretch the length of the slide, and then fix the length of the slide. Rotate the fourth screw to lower the foot pad to a height that fully fits the ground, drive the limit nail into the ground in the tunnel, stabilize the position of the device, and load the soil into the bucket; Step 2: After the slag is loaded, pull up the limit pin to a height clear of the ground, loosen the fourth screw, retract the slide plate and rotate the slide plate and the tripod to the position where one side of the tripod fits the bottom plate, fix the angle of the tripod, loosen the first screw, move the baffle plate up to the required height, block the slag in the truck bed, tighten the first screw to fix the baffle plate, and pull the truck bed for transportation.
[0016] Compared with the prior art, the present invention has the following advantages and beneficial effects: 1. Improve transportation safety: A baffle is set on the outside of the bucket of the slag transfer facility to provide effective lateral protection for the bucket. Especially when passing through complex terrains such as turns and inclined ground, the baffle can effectively prevent the slag from sliding, ensuring the safety and efficiency of slag transportation; through the cooperation of the limit hole and the first screw, the baffle can be adjusted and fixed at different heights to adapt to different loading requirements and terrain conditions, further improving the safety of slag transportation.
[0017] 2. Enhance the stability of the transfer facility: By setting up a series of stable structures such as a base, a tripod, a slide plate and a foot pad, the stability of the transfer facility is increased. The limit nails on the foot pad are nailed into the ground to achieve a fixed connection between the slag transfer facility and the ground; in addition, the spring located between the bottom of the plug and the top of the slide plate provides additional buffering effect, effectively reducing the impact of vibration caused by external loads during slag loading and transportation on the transfer facility, thereby enhancing the overall stability of the transfer facility.
[0018] 3. Improve operational convenience: The slide bar and the slide groove cooperate to ensure that the baffle does not shift laterally when it is lifted or lowered, and simplify the installation process; the foot pad is rotatably connected to the bottom plate through the base, the tripod, and the slide plate, and the limit pin is movably connected to the foot pad, so that the slag transfer facility during the shield tunnel construction period can be detachably connected to the ground, ensuring the flexible movement of the slag transfer facility during the shield tunnel construction period, while improving the stability of the transfer facility during the slag loading process; the third screw is used to limit the relative sliding of the slide plate and the tripod, ensuring that the slide plate can be firmly fixed at different positions; the handle is set on the outside of the baffle, which is convenient for manual adjustment of the position of the baffle and simplifies the operation process; the rotary handle is installed on the plug, so that the operator can directly rotate the fourth screw through the rotary handle to quickly adjust the height of the foot pad and improve work efficiency.
[0019] 4. Extend service life: The application of gaskets effectively reduces the looseness caused during long-term use and extends the service life of the baffle. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a schematic structural diagram of the slag transfer facility during the shield tunnel construction period of the present invention; Figure 2 for Figure 1 The enlarged schematic diagram of point A in the middle; Figure 3 for Figure 1 The enlarged schematic diagram of point B in the middle; Figure 4 It is a schematic structural diagram of the slag transfer facility during the shield tunnel construction period of the present invention when it is in use; Figure 5 A top view of the slag transfer facility during the shield tunnel construction period of the present invention; Figure 6It is a front view of the slag transfer facility during the shield tunnel construction period of the present invention; Figure 7 It is a side view of one side of the slag transfer facility during the shield tunnel construction period of the present invention; Figure 8 It is a side view of the other side of the slag transfer facility during the shield tunnel construction period of the present invention; Fig. 9 for Figure 8 The enlarged schematic diagram of the center C; Among them: bottom plate structure-1, bottom plate-101, handrail-102, push rod-103, first screw-104, universal wheel-105, baffle structure-2, baffle-201, limiting hole-202, slide bar-203, cart-204, stabilizing structure-3, base-301, second screw-302, tripod-303, third screw-304, screw hole-305, slide plate-306, fourth screw-307, plug-308, foot pad-309, anti-slip pad-4, cross bar-5, limiting strip-6, limiting nail-7, spring-8, rotary handle-9, handle-10, gasket-11. DETAILED DESCRIPTION
[0021] The present invention is further described in detail below in conjunction with embodiments and drawings, but the embodiments of the present invention are not limited thereto.
[0022] like Figures 1 to 9 As shown, a slag transfer facility during shield tunnel construction period includes a bottom plate structure 1; the bottom plate structure 1 includes a bottom plate 101, a universal wheel 105 is arranged at the bottom of the bottom plate 101, and a truck box 204 is fixedly connected to the top of the bottom plate 101; a baffle structure 2 is arranged on the outer side of the truck box 204.
[0023] like Figure 1 As shown in FIG. 1 , the bottom plate structure 1 is the foundation part of the slag transfer facility during the shield tunnel construction period. Figure 1 As shown. It includes an L-shaped bottom plate 101, and the bottom plate 101 includes a horizontal plate and a vertical plate vertically arranged on the horizontal plate. The bottom of the horizontal plate is fixedly connected to a number of symmetrically distributed universal wheels 105, so that the entire device can be flexibly moved in the tunnel. Two symmetrically arranged handrails 102 are fixedly connected to the vertical plate, and a push rod 103 is fixedly connected between the handrails 102, which is convenient for the operator to push or pull the device. A bucket 204 is fixedly connected to the top of the bottom plate 101, which is used to load the debris excavated during the shield tunnel construction process. A cross bar 5 is also arranged below the push rod 103, and both ends of the cross bar 5 are fixedly connected to the handrail 102 to increase the stability of the overall structure.
[0024] Preferably, a non-slip pad 4 made of flexible material is fixedly connected to the outside of the push rod 103, and a plurality of grooves are symmetrically arranged on the outer surface of the push rod 103, thereby improving the comfort and safety of holding.
[0025] The baffle structure 2 includes a baffle 201 with a limiting hole 202, and the outer side of the truck bucket 204 is threadedly connected to a first screw rod 104; the baffle 201 forms a sliding connection with the first screw rod 104 through the limiting hole 202, and the cooperation between the first screw rod 104 and the limiting hole 202 enables the baffle 201 to be adjusted and fixed at different positions on the truck bucket 204.
[0026] The baffle structure 2 is intended to prevent the dirt from sliding off the bucket 204 when transporting on complex terrain. Figure 2 , 3 As shown. The baffle 201 adopts a U-shaped structure, which surrounds and fits the three sides of the bucket 204, providing effective lateral protection. Two limiting holes 202 are provided on the three outer sides of the baffle 201. These limiting holes 202 are U-shaped structures, which form a sliding connection with the first screw rods 104 set on the bucket 204. The six first screw rods 104 are respectively fixed on the three outer sides of the bucket 204 through threaded connection, allowing the baffle 201 to adjust its height as needed. Three slide bars 203 are also provided on the inner side of the baffle 201. The three slide bars 203 surround the three outer sides of the bucket 204 respectively. Three slide grooves are correspondingly provided on the three outer sides of the bucket 204. The slide bars 203 form a sliding fit with the slide grooves to ensure that the baffle 201 does not deviate laterally during lifting and lowering. In addition, two limiting bars 6 are provided on the outer side of the bucket 204. The limiting bars 6 abut against the edge of the baffle 201 to further prevent the baffle 201 from moving laterally during lifting and lowering.
[0027] Preferably, if Figure 3 As shown, one end of the first screw rod 104 passes through the gasket 11 and the limiting hole 202 on the baffle 201 in sequence and is connected to the outer side of the bucket 204, which effectively reduces the looseness generated during long-term use.
[0028] Preferably, two handles 10 are fixedly connected to the front and rear sides of the baffle 201 , respectively, to facilitate operators to manually adjust the position of the baffle 201 .
[0029] like Figure 2 As shown, the slag transfer facility during the shield tunnel construction period also includes a stabilizing structure 3; the stabilizing structure 3 includes a base 301 fixedly connected to the bottom plate 101, a tripod 303 and a foot pad 309, the base 301 is rotatably connected to the tripod 303, and a slide plate 306 is arranged at the end of the tripod 303; one end of the slide plate 306 is slidably connected to the tripod 303, and the other end is movably connected to the foot pad 309, and a limiting pin 7 is arranged on the foot pad 309.
[0030] The stabilizing structure 3 is to ensure that the device is in good contact with the ground in a static state and improve stability, and includes two symmetrically arranged bases 301, one side of each base 301 is fixedly connected to the bottom plate 101. The base 301 is rotatably connected to the tripod 303 through a second screw 302, and the tripod 303 can rotate relative to the base 301.
[0031] The tripod 303 is sleeved on the outside of the skateboard 306 and is fastened to the skateboard 306 by a third screw 304. Specifically, the stabilizing structure 3 also includes a third screw 304 for limiting the relative sliding of the skateboard 306 and the tripod 303. The skateboard 306 and the tripod 303 are provided with corresponding screw holes 305. The third screw 304 is provided on the skateboard 306 and the tripod 303 and cooperates with the screw hole 305, so that the skateboard 306 can be adjusted and fixed at different positions on the tripod 303.
[0032] The connecting end of the slide plate 306 and the foot pad 309 is installed with a fourth screw rod 307 through a threaded hole, and the bottom end of the fourth screw rod 307 is fixedly connected to the foot pad 309. The foot pad 309 is internally movably connected with a limit pin 7 for being nailed into the ground to enhance the stability of the device.
[0033] The fourth screw rod 307 is provided with a spring 8 on its outer sleeve, and the spring 8 is located between the bottom of the plug 308 and the top of the slide plate 306, so as to provide additional buffering effect and reduce the impact of vibration on the device. The plug 308 is also fixedly connected with a rotary handle 9, so that the facility operator can directly rotate the fourth screw rod 307 through the rotary handle 9 to adjust the height of the foot pad 309.
[0034] A method for using a slag transfer facility during shield tunnel construction, which is applied to the slag transfer facility during shield tunnel construction as described above, comprises the following steps: Step 1: before loading the excavated soil from the shield machine, move the bucket 204 to a predetermined position, rotate the footrest 303 to a suitable angle, stretch the length of the slide plate 306, and then fix the length of the slide plate 306, rotate the fourth screw 307 to lower the foot pad 309 to a height that fully fits the ground, nail the limit nail 7 into the ground in the tunnel, stabilize the position of the device, and load the soil into the bucket 204; Specifically, the operator holds the anti-skid pad 4 on the outside of the push rod 103 and moves the bucket 204 to a predetermined position through the universal wheel 105 at the bottom of the bottom plate 101. Then, the second screw rod 302 is rotated counterclockwise to loosen the tripod 303, rotate it to a suitable angle, stretch the length of the slide plate 306, and fix the position of the slide plate 306 through the third screw rod 304. Then, the fourth screw rod 307 is rotated clockwise to lower the foot pad 309 to a height that fully fits the ground, and finally the limit nail 7 is nailed into the ground to stabilize the position of the device.
[0035] Step 2: After the slag is loaded, pull up the limit pin 7 to a height clear of the ground, loosen the fourth screw 307, retract the slide 306 and rotate the slide 306 and the tripod 303 to a position where one side of the tripod 303 is in contact with the bottom plate 101, fix the angle of the tripod 303, loosen the first screw 104, move the baffle 201 up to the required height, block the slag in the truck bed 204, tighten the first screw 104 to fix the baffle 201, and pull the truck bed 204 for transportation.
[0036] Specifically, after the slag is loaded in the truck bed 204, the limiting nail 7 is pulled up, the slide plate 306 is retracted, and the slide plate 306 and the tripod 303 are rotated to be close to the bottom plate 101. After fixing the angle of the tripod 303, the first screw 104 is rotated counterclockwise to move the baffle 201 up to the required height for blocking, and then the first screw is rotated clockwise to fix the position of the baffle 201. After that, the device is pulled by the universal wheel 105 for safe transportation. When encountering complex terrain, the baffle 201 can effectively prevent the slag loaded in the truck bed 204 from sliding down, ensuring the safety and efficiency of slag transportation.
[0037] In general, through the above-mentioned specific implementation methods, the present invention provides an efficient and safe solution for the transportation of slag during the construction period of a shield tunnel, which is particularly suitable for the transportation of slag under complex terrain conditions in the tunnel during the construction period of a shield tunnel.
[0038] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.
Claims
1. A slag transfer facility during shield tunnel construction, characterized in that: The vehicle comprises a bottom plate structure (1); the bottom plate structure (1) comprises a bottom plate (101); a universal wheel (105) is arranged at the bottom of the bottom plate (101); a vehicle bucket (204) is fixedly connected to the top of the bottom plate (101); a baffle structure (2) is arranged on the outside of the vehicle bucket (204); The baffle structure (2) comprises a baffle (201) having a limiting hole (202), and the outer side of the truck bucket (204) is connected to a first screw rod (104) via a thread; the baffle (201) is slidably connected to the first screw rod (104) via the limiting hole (202), and the cooperation between the first screw rod (104) and the limiting hole (202) enables the baffle (201) to be adjusted and fixed at different positions on the truck bucket (204).
2. The slag transfer facility during shield tunnel construction according to claim 1, characterized in that: The baffle (201) adopts a U-shaped structure and wraps around three sides of the vehicle bucket (204).
3. The slag transfer facility during shield tunnel construction according to claim 2, characterized in that: A sliding bar (203) is provided on the inner side of the baffle (201), and the sliding bar (203) is slidably connected to the outer side of the bucket (204); a limiting bar (6) is provided on the outer side of the bucket (204), and the limiting bar (6) abuts against the edge of the baffle (201) to prevent the baffle (201) from deflecting when it is raised or lowered on the bucket (204).
4. The slag transfer facility during shield tunnel construction according to claim 1, characterized in that: It also includes a gasket (11), and the end of the first screw rod (104) passes through the gasket (11) and the limiting hole (202) on the baffle (201) in sequence to be connected to the outside of the bucket (204).
5. The slag transfer facility during shield tunnel construction according to claim 1, characterized in that: A handle (10) is provided on the outer side of the baffle (201).
6. The slag transfer facility during shield tunnel construction according to claim 1, characterized in that: The invention also comprises a stabilizing structure (3); the stabilizing structure (3) comprises a base (301) fixedly connected to the bottom plate (101), a tripod (303) and a foot pad (309); the base (301) is rotatably connected to the tripod (303); a slide plate (306) is arranged at the end of the tripod (303); one end of the slide plate (306) is slidably connected to the tripod (303), and the other end is movably connected to the foot pad (309); a limiting pin (7) is arranged on the foot pad (309).
7. The slag transfer facility during shield tunnel construction according to claim 6, characterized in that: The stabilizing structure (3) further comprises a third screw rod (304) for limiting the relative sliding of the slide plate (306) and the tripod (303); the slide plate (306) and the tripod (303) are provided with screw holes (305) corresponding to each other; the third screw rod (304) is provided on the slide plate (306) and the tripod (303) and cooperates with the screw holes (305), so that the slide plate (306) can be adjusted and fixed at different positions on the tripod (303).
8. The slag transfer facility during shield tunnel construction according to claim 6, characterized in that: A fourth screw rod (307) is installed at the connection end between the slide plate (306) and the foot pad (309) through a threaded hole, and the bottom end of the fourth screw rod (307) is fixedly connected to the foot pad (309).
9. A facility for transferring slag during construction of a shield tunnel according to claim 7: a plug (308) is arranged at the top of the fourth screw (307), a spring (8) is sleeved on the outside of the fourth screw (307), and the spring (8) is located between the bottom of the plug (308) and the top of the slide plate (306).
10. A method for using a slag transfer facility during shield tunnel construction, characterized in that: The method is applied to the slag transfer facility during the construction period of a shield tunnel as claimed in any one of claims 6 to 9, comprising the following steps: Step 1: before loading the excavated soil from the shield machine, after moving the bucket (204) to a predetermined position, the footrest (303) is rotated to a suitable angle, the length of the slide plate (306) is stretched, and then the length of the slide plate (306) is fixed, the fourth screw rod (307) is rotated to lower the foot pad (309) to a height that fully fits the ground, the limit nail (7) is nailed into the ground in the tunnel, the position of the device is stabilized, and the soil is loaded into the bucket (204); Step 2: After the loading of the slag is completed, the limit pin (7) is pulled up to a height clear of the ground, the fourth screw rod (307) is loosened, the slide plate (306) is retracted, and the slide plate (306) and the tripod (303) are rotated to a position where one side of the tripod (303) is in contact with the bottom plate (101), the angle of the tripod (303) is fixed, the first screw rod (104) is loosened, the baffle plate (201) is moved up to a desired height, the slag in the bucket (204) is blocked, the first screw rod (104) is tightened to fix the baffle plate (201), and the bucket (204) is pulled for transportation.