A large steel structure weld processing equipment

By installing guide components in the clamping sleeve of the weld treatment equipment of the steel structural parts, multi-stage support of the steel column is realized, the stress concentration problem caused by single point support is solved, and the stability and efficiency of weld treatment are improved.

CN119772696AInactive Publication Date: 2025-04-08ZHONGGOU (SUZHOU) CONSTR ENG CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202510272028.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-10
Publication Date
2025-04-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During the weld treatment process, steel columns are stress-concentrated due to single point support, which is prone to cracks or fractures, which increases the difficulty and risk of weld treatment.

Method used

A large-scale weld processing equipment for steel structural parts is designed. By setting a guide assembly in the clamping sleeve, multi-stage support of steel columns is realized, weight and stress are dispersed, and stress concentration is reduced.

Benefits of technology

Effectively disperse the weight and stress of steel columns, reduce the risk of cracks or fracture, improve the stability and processing accuracy of the entire structure, and improve the efficiency and safety of weld processing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119772696A_ABST
    Figure CN119772696A_ABST
Patent Text Reader

Abstract

The present invention discloses a large-scale steel structure weld processing equipment, which specifically relates to the technical field of steel structure weld processing, comprising: a frame and a steel column, wherein two symmetrical clamping sleeves are installed at the top of the frame, and the two clamping sleeves are used to stably connect the steel column to the frame, and a slidable grinding head is installed at the top of the frame; two groups of guide bearing assemblies are used to guide and support the steel column, and each group of the guide bearing assemblies comprises a guide bearing box fixed to the top of the frame, a guide bearing seat sleeved on the outside of the steel column, and a threaded column rotatably installed in the guide bearing box, and a guide bearing frame is installed at the bottom end of the guide bearing seat; the present invention can realize multi-section support of the steel column in the clamping sleeve through the arrangement of the guide bearing assembly, which can effectively disperse the weight and stress of the steel column, avoid stress concentration that may be caused by single-point support, and reduce the risk of cracks or fractures caused by stress concentration, thereby improving the stability and processing accuracy of the entire structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of steel structure weld processing, and in particular to a large steel structure weld processing device. Background Art

[0002] Steel structure is a structure made of steel materials and is one of the main types of building structures. The structure is mainly composed of steel beams, steel columns, steel trusses and other components made of steel sections and steel plates. When the welds of steel columns are processed, the welds on the outside of the steel columns are generally polished using weld processing equipment to ensure the smoothness of the surface of the steel columns. Since the surface of the steel columns is relatively smooth, clamping assemblies are required to clamp both ends of the steel columns to ensure the stability of the steel columns during polishing. When the steel columns are being polished, the clamping parts of the steel columns are subjected to greater support force because the clamping assemblies clamp both ends of the steel columns. However, the steel columns are in a hollow state in the clamping assemblies, so that there is a single-point support between the steel columns and the clamping assemblies, resulting in a relatively concentrated stress on the steel columns in the clamping assemblies, which causes cracks or fractures in the steel columns due to stress concentration, increasing the difficulty of steel column weld processing and reducing weld processing efficiency. Summary of the invention

[0003] The purpose of the present invention is to provide a large-scale steel structure weld processing equipment. Through the setting of the guide assembly, it is possible to support the steel column in multiple sections within the clamping sleeve, which can effectively disperse the weight and stress of the steel column, avoid the stress concentration that may be caused by single-point support, and reduce the risk of cracks or fractures caused by stress concentration, thereby improving the stability and processing accuracy of the entire structure to solve the above-mentioned deficiencies in the technology.

[0004] In order to achieve the above object, the present invention provides the following technical solution: a large steel structure weld processing equipment, comprising: A frame and a steel column, wherein two symmetrical clamping sleeves are installed on the top of the frame, and the two clamping sleeves are used to stably connect the steel column to the frame, and a slidable grinding head is installed on the top of the frame; Two groups of guide bearing components are used to guide and support the steel column. Each group of guide bearing components includes a guide bearing box fixed to the top of the frame, a guide bearing seat sleeved on the outside of the steel column, and a threaded column rotatably installed in the guide bearing box. A guide bearing frame is installed at the bottom end of the guide bearing seat, and the guide bearing frame is slidably sleeved on the outside of the guide bearing box. A movable ring is sleeved on the outside of the threaded column. A guide component for connecting the guide bearing frame is provided on the movable ring. A cleaning component is provided on the guide bearing seat, and the cleaning component is used to clean the iron filings after grinding on the surface of the steel column in time. The guide bearing box is provided with a driving clamping sleeve A detection component that rotates with the threaded column, wherein the detection component is provided with a control component that disconnects or connects it with the threaded column; and the two clamping sleeves and the guide seat are combined to form a support structure for realizing multi-section support of the steel column, and the multi-section support can effectively disperse the weight and stress of the steel column, reduce the deformation or tilt that may be caused by single-point support, thereby improving the stability and processing accuracy of the entire structure, and reducing the risk of cracks or fractures caused by stress concentration. Since the internal thread of the moving ring is screwed together with the thread on the surface of the threaded column, the moving ring is moved back and forth along the threaded column.

[0005] Preferably, the guide assembly includes a guide rod fixed to one side of the guide support frame, a guide column fixed in the guide support box, and a guide ring installed on the outside of the movable ring, and the guide ring is slidably sleeved on the outside of the guide column, and one side of the guide support box is provided with a guide groove communicated with the interior thereof for sliding the guide rod, and one end of the guide rod extends into the guide support box and is fixed on the guide ring; through the setting of the guide assembly, when no steel column is placed on the guide support seat, the guide support frame can be driven to slide synchronously along the guide support box when the rotating column rotates, and the position of the guide support seat can be adjusted to adapt to steel columns of different lengths and weights. This flexibility enables the equipment to be handled It can handle more kinds of steel structures, improve the versatility and utilization rate of the equipment. At the same time, it can also flexibly adjust the position of the cleaning component and the weld on the outside of the steel column, so that the cleaning component can accurately clean the iron filings generated by the steel column. When one end of the steel column passes through one of the clamping sleeves and is placed on one of the guide seats, it can temporarily connect the steel column between the two clamping sleeves, making it easier to guide the steel column into another clamping sleeve. The position and posture of the steel column can be adjusted more conveniently to meet the requirements of weld processing, which reduces the adjustment time, improves work efficiency, and also reduces the labor intensity of operators.

[0006] Preferably, the detection components include a gear ring fixedly sleeved on the outside of the clamping sleeve, a first support frame fixed on the top of the frame, and a rotating column rotatably installed at one end of the threaded column, and the rotating column is located in the first support frame, and the outside of the rotating column is fixedly sleeved with a gear matching the gear ring, a servo motor is installed on one side of the first support frame, and the servo motor is used to drive the rotating column to rotate; and the gear and the gear ring are engaged, and the gear is driven to rotate in the first support frame under the drive of the rotating column, and then the gear and the gear ring are engaged and transmitted to rotate the clamping sleeve on the first support frame, so that the weld connection of the steel column can be polished, and the polishing range of the weld of the steel column is improved. At the same time, the rotating column drives the threaded column to rotate, thereby increasing the flexibility of the device.

[0007] Preferably, a connecting ring is fixed to the outside of the clamping sleeve, a second support frame is fixed to the side of the frame adjacent to the first support frame, and the second support frame is sleeved on the outside of the rotating column, and an auxiliary wheel matching the connecting ring is installed in the second support frame; and the auxiliary wheel is rotatably installed in the second support frame, and the outside of the auxiliary wheel is rotatably connected to the outside of the connecting ring, which is used to keep the clamping sleeve in stable rotation on the first support frame to avoid the first support frame from tilting during rotation and causing damage to the steel column.

[0008] Preferably, the control component includes a control ring slidably sleeved on the outside of the rotating column and a connecting ring fixed on one end of the threaded column, and one end of the connecting ring passes through the guide bearing box and is fixed with a second gear disc, a first gear disc matching the second gear disc is fixed to the outside of the control ring, and the guide bearing box is provided with a push rod assembly that pushes the control ring to move and is fixed thereto; and the first gear disc and the second gear disc are plugged and fixed together, so that the first gear disc and the second gear disc are pluggable and removable, and when the first gear disc and the second gear disc are plugged together, a short connection is maintained between the rotating column and the connecting ring, so that the rotation of the rotating column drives the connecting ring to rotate, and when the first gear disc and the second gear disc are disconnected, the rotation of the rotating column cannot drive the connecting ring to rotate.

[0009] Preferably, the push rod assembly includes a receiving ring mounted on the control ring and a connecting rod slidably mounted on the top of the guide bearing box, and the bottom end of the connecting rod is fixedly connected to the outside of the receiving ring, the top of the connecting rod is provided with a first screw hole, the top of the guide bearing box is provided with a plurality of second screw holes, a control threaded rod is screwed on the connecting rod, and the control threaded rod is screwed into a second screw hole corresponding to the first screw hole through the first screw hole; and the receiving ring is rotatably and slidably sleeved on the outside of the control ring, which can ensure that the control ring rotates along the receiving ring, and at the same time, the receiving ring can push the control ring to move forward and backward along the rotating column.

[0010] Preferably, the cleaning assembly includes a mounting frame installed on the top of the guide seat, a cleaning scraper installed on the mounting frame and fit to the outside of the steel column, and a scraper rod fixed to one side of the cleaning scraper, and a through groove for inserting the scraper rod is provided at one end of the mounting frame, a first connecting plate is fixed at one end of the scraper rod, a mounting groove for sliding the first connecting plate is provided in the through groove, and a spring is installed between the mounting groove and the first connecting plate; and under the action of the spring, the spring can make the contact force between the cleaning scraper and the steel column more uniform and stable, thereby effectively improving the cleaning effect.

[0011] Preferably, the cleaning assembly also includes a second connecting plate installed in the mounting groove, a connecting rod fixed in the mounting groove and a threaded hole provided in the through groove, and the second connecting plate is sleeved on the outside of the connecting rod, an adjusting bolt is threaded in the threaded hole, and one end of the adjusting bolt extends into the mounting groove and is rotatably installed at one end of the second connecting plate; and one end of the second connecting plate is fixedly connected to one end of the spring, so that the spring is installed between the second connecting plate and the first connecting plate, so as to facilitate the adjustment of the tension of the spring. At the same time, the pressure of the cleaning scraper on the surface of the steel structure can be adjusted, so that the cleaning scraper contacts the surface of the steel structure without being too tight, thereby reducing possible scratches or other surface damage.

[0012] In the above technical solution, the technical effects and advantages provided by the present invention are: 1. Through the setting of the guide assembly, the steel column can be supported in multiple sections in the clamping sleeve, which can effectively disperse the weight and stress of the steel column, avoid the stress concentration that may be caused by single-point support, and reduce the risk of cracks or fractures caused by stress concentration, thereby improving the stability and processing accuracy of the entire structure.

[0013] 2. Through the setting of the cleaning component, not only can the iron filings generated by the grinding of the weld between the cleaning scraper and the steel column surface be cleaned, but also the iron filings adsorbed near the weld can be reduced. In addition, the pressure between the cleaning scraper and the steel column can be adjusted so that the contact between the cleaning scraper and the steel column surface is not too tight, thereby reducing possible scratches or other surface damage and improving the quality of steel column weld processing.

[0014] 3. Through the setting of the detection component, the steel column can be rotated on the guide assembly, which is convenient for visual inspection of the outside of the steel column, helps to find weld defects, cracks or other problems, and take repair measures in time to ensure the quality of the weld and the safety of the structure.

[0015] 4. Through the setting of the guide assembly, the guide assembly and the detection assembly can be connected or disconnected, so that the guide assembly and the detection assembly have high versatility, which facilitates the flexible use of the guide assembly and the detection assembly according to actual on-site needs, thereby increasing overall convenience. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the present invention. For ordinary technicians in this field, other drawings can also be obtained based on these drawings.

[0017] Figure 1 It is a schematic diagram of the overall structure of the present invention; Figure 2 It is a structural schematic diagram of the guide box of the present invention; Figure 3 For the present invention Figure 2 A partial enlarged view of the middle part; Figure 4 It is a schematic structural diagram of the gear ring of the present invention; Figure 5 It is a schematic diagram of the structure of the rotating column of the present invention; Figure 6 For the present invention Figure 2 A partial enlarged view of point B in the middle; Figure 7 It is a structural schematic diagram of the first toothed disc of the present invention; Figure 8 It is a structural schematic diagram of the scraper rod of the present invention; Fig. 9 It is a schematic structural diagram of the spring of the present invention.

[0018] Description of reference numerals: 1. Frame; 11. Steel column; 12. Clamping sleeve; 13. Grinding head; 2. Detection assembly; 21. First support frame; 22. Gear ring; 23. Gear; 24. Connecting ring; 25. Rotating column; 26. Servo motor; 27. Second support frame; 28. Auxiliary wheel; 3. Guide bearing assembly; 31. Guide bearing box; 32. Guide bearing frame; 33. Guide bearing seat; 34. Threaded column; 35. Guide column; 36. Guide groove; 37. Guide rod; 38. Moving ring; 39. Guide ring; 4. Control assembly; 41. Connecting ring; 42. Control ring; 43. First toothed disc; 44. Second toothed disc; 45. Adapter ring; 46. Connecting rod; 47. Control threaded rod; 48. First screw hole; 49. Second screw hole; 5. Cleaning assembly; 51. Mounting frame; 52. Cleaning scraper; 53. Scraper rod; 54. Mounting groove; 55. First connecting plate; 56. Spring; 57. Second connecting plate; 58. Connecting rod; 59. Adjusting bolt. DETAILED DESCRIPTION

[0019] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings.

[0020] The present invention provides Figure 1-Figure 9 A large steel structure weld processing device is shown, comprising: a frame 1 and a steel column 11, two symmetrical clamping sleeves 12 are installed on the top of the frame 1, and the two clamping sleeves 12 are used to stably connect the steel column 11 to the frame 1, and a slidable grinding head 13 is installed on the top of the frame 1; Two sets of guide bearing components 3 are used to guide and support the steel column 11. Each set of guide bearing components 3 includes a guide bearing box 31 fixed to the top of the frame 1, a guide bearing seat 33 sleeved on the outside of the steel column 11, and a threaded column 34 rotatably installed in the guide bearing box 31. A guide bearing frame 32 is installed at the bottom end of the guide bearing seat 33, and the guide bearing frame 32 is slidably sleeved on the outside of the guide bearing box 31. The outer sleeve of the threaded column 34 is provided with a moving ring 38, and the moving ring 38 is provided with a guide component for connecting the guide bearing frame 32. A cleaning component 5 is provided on the guide bearing seat 33, and the cleaning component 5 is used to clean the iron filings after grinding on the surface of the steel column 11 in time. A detection component 2 is provided on the guide bearing box 31 to drive the clamping sleeve 12 and the threaded column 34 to rotate, and a detection component 2 is provided in the detection component 2 to disconnect or engage it with the threaded column 34. The control component 4 connected; the detection component 2 includes a gear ring 22 fixedly sleeved on the outside of the clamping sleeve 12, a first support frame 21 fixed on the top of the frame 1 and a rotating column 25 rotatably installed at one end of the threaded column 34, and the rotating column 25 is located in the first support frame 21, and the outside of the rotating column 25 is fixedly sleeved with a gear 23 that matches the gear ring 22, a servo motor 26 is installed on one side of the first support frame 21, and the servo motor 26 is used to drive the rotating column 25 to rotate; the outside of the clamping sleeve 12 is also fixedly sleeved with a connecting ring 24, and a second support frame 27 is fixed on one side of the frame 1 adjacent to the first support frame 21, and the second support frame 27 is sleeved on the outside of the rotating column 25, and an auxiliary wheel 28 that matches the connecting ring 24 is installed in the second support frame 27.

[0021] The guide assembly includes a guide rod 37 fixed to one side of the guide frame 32, a guide column 35 fixed in the guide box 31, and a guide ring 39 installed on the outside of the movable ring 38, and the guide ring 39 is slidably sleeved on the outside of the guide column 35. A guide groove 36 is opened on one side of the guide box 31 and communicated with the interior of the guide box for the guide rod 37 to slide, and one end of the guide rod 37 extends into the guide box 31 and is fixed on the guide ring 39.

[0022] When the steel column 11 needs to be supported, the clamping sleeve 12 first pre-restricts the steel column 11 so that the steel column 11 fits the guide seat 33 but is not too tight. The servo motor 26 drives the rotating column 25 to rotate, and then the rotating column 25 rotates to drive the gear 23 to rotate. At this time, the gear 23 rotates and engages with the gear ring 22 to drive the clamping sleeve 12 to rotate along the first support frame 21, and the connecting ring 24 rotates along the outside of the auxiliary wheel 28 to rotate the steel column 11 along the guide seat 33, which is convenient for observing the surface of the steel column 11. The rotation of the rotating column 25 drives the control component 4 and the screw The threaded column 34 rotates, so that the threaded column 34 and the movable ring 38 are meshed and transmitted, and the movable ring 38 slides back and forth in the guide box 31. However, the movable ring 38 moves forward and pushes the guide ring 39 to slide forward along the outside of the guide column 35. As the guide ring 39 moves, it pushes the guide rod 37 to slide along the guide groove 36, and then the guide frame 32 slides forward along the outside of the guide box 31. Then, the position between the guide seat 33 and the steel column 11 is adjusted, so that the clamping sleeve 12 is adjusted to make the steel column 11 contact with the guide seat 33, and the steel column 11 is supported in multiple sections on the clamping sleeve 12 and the guide seat 33.

[0023] refer to Figure 1 , Figure 8 and Fig. 9 As shown, the cleaning component 5 includes a mounting frame 51 mounted on the top of the guide seat 33, a cleaning scraper 52 mounted on the mounting frame 51 and fitted to the outside of the steel column 11, and a scraper rod 53 fixed on one side of the cleaning scraper 52, and a through groove for the scraper rod 53 to be inserted is provided at one end of the mounting frame 51, a first connecting plate 55 is fixed at one end of the scraper rod 53, a mounting groove 54 for the first connecting plate 55 to slide is provided in the through groove, and a spring 56 is installed between the mounting groove 54 and the first connecting plate 55; the cleaning component 5 also includes a second connecting plate 57 mounted in the mounting groove 54, a connecting rod 58 fixed in the mounting groove 54 and a threaded hole provided in the through groove, and the second connecting plate 57 is sleeved on the outside of the connecting rod 58, an adjusting bolt 59 is threaded in the threaded hole, and one end of the adjusting bolt 59 extends into the mounting groove 54 and is rotatably mounted on one end of the second connecting plate 57.

[0024] Through the above technical solution: When the pressure between the cleaning scraper 52 and the steel column 11 is adjusted, the adjusting bolt 59 is rotated along the threaded hole, and then the adjusting bolt 59 is rotated along one side of the second connecting plate 57 and pushes the second connecting plate 57 to move forward along the mounting groove 54. At this time, the second connecting plate 57 moves in the mounting groove 54 to push the spring 56 to move, and the spring 56 moves to push the first connecting plate 55 to move, so that the scraper rod 53 slides along the mounting groove 54 and the through groove, and the cleaning scraper 52 is brought closer to the surface of the steel column 11, and the tension of the spring 56 between the second connecting plate 57 and the first connecting plate 55 is adjusted. At the same time, the mutual squeezing pressure between the cleaning scraper 52 and the steel column 11 is adjusted to facilitate the stable fitting of the cleaning scraper 52 to the surface of the steel column 11.

[0025] refer to Figure 1 , Figure 2 , Figure 5 , Figure 6 and Figure 7 As shown, the control assembly 4 includes a control ring 42 slidably sleeved on the outside of the rotating column 25 and a connecting ring 41 fixed to one end of the threaded column 34, and one end of the connecting ring 41 passes through the guide bearing box 31 and is fixed with a second gear disc 44, and the outside of the control ring 42 is fixed with a first gear disc 43 that matches the second gear disc 44, and the guide bearing box 31 is provided with a push rod assembly that pushes the control ring 42 to move and is fixed; the push rod assembly includes a receiving ring 45 installed on the control ring 42 and a connecting rod 46 slidably installed on the top of the guide bearing box 31, and the bottom end of the connecting rod 46 is fixedly connected to the outside of the receiving ring 45, a first screw hole 48 is opened at the top of the connecting rod 46, and a plurality of second screw holes 49 are opened at the top of the guide bearing box 31, a control threaded rod 47 is screwed on the connecting rod 46, and the control threaded rod 47 passes through the first screw hole 48 and is screwed into the second screw hole 49 corresponding to the first screw hole 48.

[0026] Through the above technical solution: When the distance between the guide assembly 3 and the steel column 11 is adjusted appropriately, and the detection assembly 2 needs to rotate continuously, first stop the drive of the servo motor 26, and rotate the control threaded rod 47 to remove it from the first screw hole 48 and one of the second screw holes 49, so that the restriction between the connecting rod 46 and the guide bearing box 31 is lost. At this time, the connecting rod 46 is pushed to move along the guide bearing box 31 to drive the receiving ring 45 to move synchronously, and the receiving ring 45 moves to drive the control ring 42 to slide along the outside of the rotating column 25, so that the control ring 42 moves to drive the first toothed disc 43 to approach the end of the rotating column 25, and the first toothed disc 43 moves during the movement process. The connecting rod 46 moves slowly outward from the second toothed disc 44, thereby losing the connection between the first toothed disc 43 and the second toothed disc 44. As the connecting rod 46 moves, the first screw hole 48 overlaps with the other second screw hole 49, and then the control threaded rod 47 is screwed into the first screw hole 48 and the other second screw hole 49 again, and the connecting rod 46 and the guide bearing box 31 are screwed together. Subsequently, the servo motor 26 drives the rotating column 25 to rotate, and then the rotating column 25 rotates to drive the control ring 42 to rotate along the receiving ring 45, so that the rotation of the first toothed disc 43 cannot drive the second toothed disc 44 to rotate, and the guide bearing component 3 and the detection component 2 are disconnected.

[0027] The above description is only by way of illustration of certain exemplary embodiments of the present invention. It is undoubted that those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of the present invention. Therefore, the above drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.

Claims

1. A large steel structure weld processing equipment, characterized in that: include: A frame (1) and a steel column (11), wherein two symmetrical clamping sleeves (12) are installed at the top of the frame (1), and the two clamping sleeves (12) are used to stably connect the steel column (11) to the frame (1), and a slidable grinding head (13) is installed at the top of the frame (1); Two sets of guide bearing assemblies (3) are used to guide and support the steel column (11), each set of the guide bearing assemblies (3) comprises a guide bearing box (31) fixed to the top of the frame (1), a guide bearing seat (33) sleeved on the outside of the steel column (11), and a threaded column (34) rotatably installed in the guide bearing box (31), a guide bearing frame (32) is installed at the bottom end of the guide bearing seat (33), and the guide bearing frame (32) is slidably sleeved on the outside of the guide bearing box (31), and the outside of the threaded column (34) is sleeved A movable ring (38) is provided on the movable ring (38), and a guide component for connecting the guide support frame (32) is provided on the guide support seat (33). A cleaning component (5) is provided on the guide support seat (33), and the cleaning component (5) is used to timely clean iron filings after grinding on the surface of the steel column (11). The guide support box (31) is provided with a detection component (2) for driving the clamping sleeve (12) and the threaded column (34) to rotate, and a control component (4) is provided in the detection component (2) for disconnecting or connecting it with the threaded column (34).

2. A large steel structure weld processing equipment according to claim 1, characterized in that: The guide assembly comprises a guide rod (37) fixed to one side of a guide frame (32), a guide column (35) fixed in a guide bearing box (31), and a guide ring (39) mounted on the outside of a movable ring (38), wherein the guide ring (39) is slidably sleeved on the outside of the guide column (35), a guide groove (36) communicating with the inside of the guide bearing box (31) is provided on one side of the guide bearing box (31) for the guide rod (37) to slide, and one end of the guide rod (37) extends into the guide bearing box (31) and is fixed on the guide ring (39).

3. A large steel structure weld processing equipment according to claim 1, characterized in that: The detection components (2) each comprise a toothed ring (22) fixedly sleeved on the outside of a clamping sleeve (12), a first support frame (21) fixed on the top of a frame (1), and a rotating column (25) rotatably mounted on one end of a threaded column (34), wherein the rotating column (25) is located inside the first support frame (21), a gear (23) matching with the toothed ring (22) is fixedly sleeved on the outside of the rotating column (25), a servo motor (26) is mounted on one side of the first support frame (21), and the servo motor (26) is used to drive the rotating column (25) to rotate.

4. The large steel structure weld processing equipment according to claim 1, characterized in that: A connecting ring (24) is also fixed to the outside of the clamping sleeve (12); a second supporting frame (27) is fixed to one side of the frame (1) adjacent to the first supporting frame (21); the second supporting frame (27) is sleeved on the outside of the rotating column (25); an auxiliary wheel (28) matching the connecting ring (24) is installed in the second supporting frame (27).

5. The large steel structure weld processing equipment according to claim 3 is characterized by: The control assembly (4) comprises a control ring (42) slidably sleeved on the outside of the rotating column (25) and a connecting ring (41) fixed to one end of the threaded column (34), and one end of the connecting ring (41) passes through the guide bearing box (31) and is fixed with a second toothed disc (44), and a first toothed disc (43) matching with the second toothed disc (44) is fixed on the outside of the control ring (42), and a push rod assembly is provided on the guide bearing box (31) to push the control ring (42) to move and is fixed with the push rod assembly.

6. A large steel structure weld processing equipment according to claim 5, characterized in that: The push rod assembly comprises a receiving ring (45) mounted on the control ring (42) and a connecting rod (46) slidably mounted on the top of the guide bearing box (31), and the bottom end of the connecting rod (46) is fixedly connected to the outside of the receiving ring (45), the top end of the connecting rod (46) is provided with a first screw hole (48), the top end of the guide bearing box (31) is provided with a plurality of second screw holes (49), a control threaded rod (47) is screwed on the connecting rod (46), and the control threaded rod (47) passes through the first screw hole (48) and is screwed into a second screw hole (49) corresponding to the first screw hole (48).

7. The large steel structure weld processing equipment according to claim 1, characterized in that: The cleaning assembly (5) comprises a mounting frame (51) mounted on the top of the guide seat (33), a cleaning scraper (52) mounted on the mounting frame (51) and in contact with the outside of the steel column (11), and a scraper rod (53) fixed to one side of the cleaning scraper (52), and a through groove for inserting the scraper rod (53) is formed at one end of the mounting frame (51), a first connecting plate (55) is fixed at one end of the scraper rod (53), a mounting groove (54) for sliding the first connecting plate (55) is formed in the through groove, and a spring (56) is installed between the mounting groove (54) and the first connecting plate (55).

8. The large steel structure weld processing equipment according to claim 7, characterized in that: The cleaning assembly (5) further comprises a second connecting plate (57) mounted in the mounting groove (54), a connecting rod (58) fixed in the mounting groove (54), and a threaded hole provided in the through groove, wherein the second connecting plate (57) is sleeved on the outside of the connecting rod (58), an adjusting bolt (59) is threadedly connected in the threaded hole, and one end of the adjusting bolt (59) extends into the mounting groove (54) and is rotatably mounted on one end of the second connecting plate (57).

Citation Information

Patent Citations

  • Automatic welding equipment for structural pipe

    CN115401379A

  • Metal product butt welding device

    CN118456241A

  • Efficient grinding device with dust removal function for automobile transmission shaft machining

    CN215239728U

  • Pipe outer surface polishing device

    CN217071725U

  • Aluminum pipe on-line feeding pretreatment device

    CN217255367U