A furnace top hoisting system for continuous casting tunnel furnace
By designing a furnace ceiling hoisting system for continuous cast tunnel furnaces, the problem of furnace ceiling hoisting in the prior art is solved due to space limitations, and stable and safe hoisting operations in complex environments are achieved, and efficiency and safety are improved.
Patent Information
- Application Number
- CN202510008255.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-03
- Publication Date
- 2025-04-08
AI Technical Summary
The furnace ceiling hoisting operation of the existing continuous cast tunnel furnace is limited by space limitations and cannot be carried out directly, resulting in inconvenient production, maintenance and maintenance, affecting lifting safety.
A furnace ceiling hoisting system is designed, including main body parts, adjusting parts, counterweight parts and hoisting parts. By measuring the lifting space and furnace top structure size, optimizing the T-shaped structure and hanging point distribution, setting up a telescopic adjustment locking mechanism and special spreader to ensure the force balance of the lifting point and maintaining the balance and stability of the lifting object.
It realizes the stability and safety of lifting operations in complex operating environments, improves labor efficiency, reduces labor intensity, flexibly arranges the operating positions of lifting equipment, and avoids interference positions for reliable operations.
Smart Images

Figure CN119774417A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of continuous casting tunnel furnaces, and in particular to a furnace top hoisting system for a continuous casting tunnel furnace. Background Art
[0002] The information provided in this section is for the purpose of generally presenting the background of the present disclosure. To the extent described in this section, the work of the presently named inventors and aspects of the description that may not constitute prior art at the time of filing are neither explicitly nor implicitly admitted to be prior art to the present disclosure.
[0003] In the existing continuous casting and rolling tunnel furnace environment, due to the space limitation of the workshop structure, part of the furnace roof is installed directly below the pillars of the factory building. Since the lifting crane cannot directly move above the tunnel furnace roof, it is impossible to directly carry out the lifting operation, which brings certain inconveniences to production, inspection and maintenance, and affects the safety of lifting. The present invention is based on the structural characteristics of the tunnel furnace roof, combined with the workshop crane space structure, by measuring the lifting space and the size of the furnace roof structure. Reasonable calculation and optimization of the T-shaped structure of the lifting auxiliary equipment, calculation and distribution of lifting points, balanced counterweight device, retractable and adjustable unlocking mechanism, special lifting equipment, reasonable distribution and balance of the load on each lifting point, keep the suspended object balanced and stable, avoid damage to the suspended object, improve labor efficiency, reduce labor intensity, and ensure the safety of lifting operations. Summary of the invention
[0004] In view of the defects existing in the prior art, the present application provides a furnace top hoisting system for a continuous casting tunnel furnace to solve the problem in the prior art that the furnace top hoisting operation of the continuous casting tunnel furnace cannot be carried out due to space limitations.
[0005] The above-mentioned purpose of the present application is mainly achieved through the following technical solutions:
[0006] A furnace top hoisting system for a continuous casting tunnel furnace, the furnace top hoisting system comprising:
[0007] A main body, wherein a connecting portion for connecting a lifting device is provided in the middle of the main body, the main body having a first working end and a second working end, and a plurality of connecting positions are provided at intervals on the first working end;
[0008] An adjusting member, the adjusting member is fixedly connected to the main member, and the adjusting member is detachably arranged on one of the connecting positions to change the distance between the adjusting member and the second working section;
[0009] A counterweight, the counterweight being detachably connected to the adjusting member;
[0010] A hoisting piece is fixedly arranged on the second working end and is used for connecting to the working furnace top.
[0011] In an optional embodiment, the adjusting member is sleeved on the first working end of the main member, and the adjusting member is provided with a plurality of positioning holes corresponding to the connection, and a locking member fixedly connected to the main member is passed through the positioning hole.
[0012] In an optional embodiment, the locking member includes a plurality of bolts, and the plurality of bolts are passed through the plurality of positioning holes and fixedly connected to the plurality of connecting positions.
[0013] In an optional embodiment, a fixed platform is provided between the adjusting member and the counterweight member, the fixed platform is fixedly connected to the adjusting member, at least two mounting rods are provided on the fixed platform, and the counterweight member is detachably provided on the mounting rods.
[0014] In an optional embodiment, the counterweight member includes a plurality of counterweight units, and the counterweight units are provided with accommodating holes for the mounting rod to pass through.
[0015] In an optional embodiment, a supporting block supported under the counterweight unit and a pressing block pressed on the counterweight unit are threadedly connected to the mounting rod.
[0016] In an optional embodiment, the hoisting member includes a transverse portion fixed to the upper portion of the second working end and arranged perpendicular to the main body, and the transverse portion is provided with a plurality of flexible hoisting portions for connecting to the working furnace top.
[0017] In an optional embodiment, at least four flexible hoisting parts are provided, and ends of the flexible hoisting parts are provided with hoisting bolts that can be fixed to the working furnace roof.
[0018] In an optional embodiment, support blocks fixedly connected to the lateral portion are respectively provided on both sides of the main body.
[0019] In an optional embodiment, the adjusting member and / or the main body is configured as a square tube.
[0020] Compared with the prior art, the advantages of this application are:
[0021] The furnace top hoisting system in the present application is used for auxiliary hoisting operations of a continuous casting tunnel furnace. The furnace top hoisting system includes a main body and an adjusting member. A connecting portion for connecting a hoisting device is provided in the middle of the main body. The main body has a first working end and a second working end. A plurality of connecting positions are provided at intervals on the first working end. The adjusting member is fixedly connected to the main body. The adjusting member is detachably arranged on one of the connecting positions to change the distance between the adjusting member and the second working section. A counterweight is detachably connected to the adjusting member. A hoisting member is fixedly provided on the second working end. , and is used to connect the working furnace top. During actual operations, the connecting part on the main part is used as the lifting connection point through the lifting equipment in the working environment, and is installed and fixed on the working furnace top of the continuous casting tunnel furnace through the lifting parts on the main part. The counterweight provides counterweight at the first working end and achieves lifting balance. After the lifting operation of the lifting equipment, the lifting operation of the working furnace top is completed. In a complex working environment, the stability of the lifting operation is maintained, and the working position of the lifting equipment can be flexibly arranged. Under the working conditions of limited workshop structure space, it can flexibly avoid interference positions for reliable operation, ensure operation safety, and improve efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0023] Figure 1 A side view of a furnace top hoisting system is provided for an embodiment of the present application;
[0024] Figure 2 A top view of a furnace top hoisting system is provided for an embodiment of the present application;
[0025] Figure 3 A partial schematic diagram of a lateral portion is provided for an embodiment of the present application;
[0026] In the figure: 100, main body; 101, connecting part; 102, connecting position; 200, adjusting part; 201, positioning hole; 202, locking part; 204, fixing platform; 205, mounting rod; 206, supporting block; 207, pressing block; 300, counterweight; 401, transverse part; 402, flexible lifting part; 403, lifting bolt; 404, supporting block; 500, working furnace top. DETAILED DESCRIPTION
[0027] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the description of these embodiments is used to help understand the present invention, but does not constitute a limitation of the present invention. The specific structures and functional details disclosed herein are only used to describe the exemplary embodiments of the present invention. However, the present invention can be embodied in many alternative forms, and it should not be understood that the present invention is limited to the embodiments set forth herein.
[0028] like Figure 1 , Figure 2 As shown, Figure 1 A side view of a furnace top hoisting system is provided for an embodiment of the present application. Figure 2 A top view of a furnace top hoisting system is provided for an embodiment of the present application. A furnace top hoisting system for a continuous casting tunnel furnace includes a main body 100, an adjustment member 200, a counterweight member 300 and a hoisting member, wherein:
[0029] like Figure 1 , Figure 2 As shown, a connecting portion 101 for connecting to a lifting device is provided in the middle of the main body 100 , and the main body 100 has a first working end and a second working end, and a plurality of connecting positions 102 are provided at intervals on the first working end.
[0030] The main body 100 serves as the intermediate foundation of the entire furnace roof hoisting system, ensuring stability and reliability under high temperature and heavy load conditions. A connecting portion 101 is provided in the middle of the main body 100, and the connecting portion 101 is used to connect with a hoisting device such as a crane or a hook to realize the hoisting operation of the furnace roof.
[0031] like Figure 1 , Figure 2 As shown, the main body 100 is provided with a first working end and a second working end, and the two working ends respectively assume different functions. The first working end is close to the installed counterweight 300, and the second working end is close to the working furnace top 500.
[0032] A plurality of spaced connection positions 102 are provided on the first operation end. The connection positions 102 are used to install the adjustment member 200. The spacing and number of the connection positions 102 can be adjusted according to actual needs to adapt to different operation requirements.
[0033] The adjusting member 200 is fixedly connected to the main member 100 , and the adjusting member 200 is detachably disposed on one of the connecting positions 102 to change the distance between the adjusting member 200 and the second working section.
[0034] like Figure 1 , Figure 2As shown, the adjusting member 200 is fixedly connected to the main member 100, but can be detachably arranged on the connecting position 102 at different positions. The main function of the adjusting member 200 is to adjust the distance between the adjusting member 200 and the second working end, so that the relative position of the adjusting member 200 can be flexibly changed according to different furnace roof sizes, shapes and weights, so that the adjusting member 200 and the second working end have different distance states compared with the connecting portion 101 on the main member 100, ensuring that the two sides of the connecting portion 101 of the main member 100 obtain different lengths of force arms, so that the working furnace roof 500 can be correctly and safely hoisted.
[0035] like Figure 1 , Figure 2 As shown, the counterweight 300 is detachably connected to the adjusting member 200, and the counterweight 300 is detachably connected to the adjusting member 200. The counterweight 300 provides necessary balance during the hoisting process to prevent the main member 100 from tilting or flipping due to uneven weight distribution. The position of the counterweight 300 can be adjusted relative to the adjusting member 200 according to actual hoisting requirements to ensure the stability and safety of the hoisting operation.
[0036] like Figure 1 As shown, the hoisting member is fixedly arranged on the second working end and is used to connect the working furnace roof 500. The hoisting member is fixedly installed on the second working end of the main body 100 and is directly connected to the working furnace roof 500. The hoisting member ensures that the working furnace roof 500 can be firmly connected during the hoisting process to prevent sliding or falling off. In the hoisting operation of the furnace roof of the continuous casting tunnel furnace, the various variables in the actual operation can be flexibly adjusted to ensure the efficiency and safety of the hoisting operation.
[0037] like Figure 1As shown, in an optional embodiment, the furnace top hoisting system in the present application is used for auxiliary hoisting operations of a continuous casting tunnel furnace, and the furnace top hoisting system includes a main body 100 and an adjusting member 200, wherein a connecting portion 101 for connecting a hoisting device is provided in the middle of the main body 100, and the main body 100 has a first working end and a second working end, and a plurality of connecting positions 102 are provided on the first working end at intervals, and the adjusting member 200 is fixedly connected to the main body 100, and the adjusting member 200 is detachably arranged on one of the connecting positions 102 to change the distance between the adjusting member 200 and the second working section, and a counterweight 30 is detachably connected to the adjusting member 200. 0, a hoisting part is fixedly provided on the second working end, and is used to connect the working furnace roof 500. When actually working, the connecting part 101 on the main part 100 is used as the hoisting connection point through the hoisting equipment in the working environment, and is installed and fixed on the working furnace roof 500 of the continuous casting tunnel furnace through the hoisting part on the main part 100. The counterweight 300 provides counterweight at the first working end and achieves hoisting balance. After the hoisting operation of the hoisting equipment, the hoisting operation of the working furnace roof 500 is completed. In a complex working environment, the hoisting operation stability is maintained, and the working position of the hoisting equipment can be flexibly arranged. Under the working condition of limited workshop structure space, the interference position can be flexibly avoided to perform reliable operation, thereby ensuring operation safety and improving efficiency.
[0038] like Figure 1 As shown, in an optional embodiment, the adjusting member 200 is sleeved on the first working end of the main member 100, and the adjusting member 200 is provided with a plurality of positioning holes 201 corresponding to the connection, and a locking member 202 fixedly connected to the main member 100 is passed through the positioning hole 201.
[0039] The adjusting member 200 is sleeved on the first working end of the main member 100 to allow the adjusting member 200 to be flexibly moved on the main member 100 to meet different working requirements. The displacement direction of the adjusting member 200 is based on the common center line with the main member 100 to adjust the relative position and posture of the furnace top hoisting system as a whole, thereby ensuring the stability and safety of the working furnace top 500 during the hoisting process.
[0040] The adjusting member 200 is provided with a plurality of positioning holes 201 corresponding to the connection position 102. The number and distribution of the positioning holes 201 can be determined according to the actual configuration specifications. Each positioning hole 201 corresponds to the connection position 102 on the main member 100, so that the adjusting member 200 can be quickly and accurately positioned on the main member 100. This not only improves the flexibility of the hoisting system, but also ensures that accurate hoisting operations can be achieved under different working conditions.
[0041] like Figure 1 , Figure 2 As shown, a locking piece 202 fixedly connected to the main body 100 is provided in the positioning hole 201. The function of the locking piece 202 is to ensure that the adjusting piece 200 can be firmly fixed after being adjusted to a suitable position, so as to prevent the adjusting piece 200 from shifting due to vibration or load changes during the hoisting process. The locking piece 202 can be configured to be made of high-strength material to ensure that the stability and reliability of its structure can be maintained in a high-temperature and heavy-loaded operating environment. The use of the locking piece 202 in conjunction with the positioning hole 201 provides a reliable locking mechanism, so that the operator can easily adjust the relative position of the adjusting piece 200 and ensure that the adjusted setting remains unchanged during the operation, especially in a high-temperature and heavy-loaded industrial environment such as a continuous casting tunnel furnace, which improves the efficiency of the hoisting operation and enhances the safety of the operation.
[0042] like Figure 1 , Figure 2 As shown, in an optional embodiment, the locking member 202 includes a plurality of bolts, and the plurality of bolts are passed through the plurality of positioning holes 201 and fixedly connected to the plurality of connecting positions 102 .
[0043] The locking members 202 are configured as a plurality of bolts to ensure that they can withstand various forces that may be encountered during the lifting process, such as tension, compression and shearing forces. A plurality of bolts are inserted into the plurality of positioning holes 201 to provide a strong fixing force and also allow the adjusting member 200 to be flexibly adjusted on the main member 100. Each connection position 102 is a preset fixing point on the main member 100, which, when used in conjunction with the bolts, can ensure that the adjusting member 200 is securely locked after being adjusted to a suitable position. It can remain stable even under heavy loads and vibrations, thereby improving the safety and reliability of the operation, as well as the flexibility and efficiency of the operation.
[0044] like Figure 1 , Figure 2 As shown, in an optional embodiment, a fixed platform 204 is provided between the adjusting member 200 and the counterweight member 300 , the fixed platform 204 is fixedly connected to the adjusting member 200 , at least two mounting rods 205 are provided on the fixed platform 204 , and the counterweight member 300 is detachably provided on the mounting rods 205 .
[0045] The fixed platform 204 between the adjusting member 200 and the counterweight 300 provides a stable support base for the counterweight 300. At least two mounting rods 205 are provided on the fixed platform 204. The mounting rods 205 not only provide physical connection points for mounting the counterweight 300, but also ensure the correct positioning and reliable fixation of the counterweight 300. The structural strength configuration of the mounting rods 205 is embodied in the bearing capacity to ensure that the weight of the counterweight 300 can be safely supported, and it is also convenient for the installation and removal of the counterweight 300.
[0046] like Figure 1 , Figure 2 As shown, in an optional embodiment, the counterweight member 300 includes a plurality of counterweight units, each of which is provided with a receiving hole for the mounting rod 205 to pass through, and the counterweight unit is mounted on the mounting rod 205 through the receiving hole.
[0047] Multiple counterweight units are detachably mounted on the mounting rod 205, allowing the operator to quickly change the weight of the overall counterweight 300 by the number of counterweight units according to specific lifting requirements. The detachability of the counterweight unit greatly improves flexibility and adaptability, allowing the system to adapt to different operating conditions and load requirements. The installation and removal process of the counterweight unit is simple and quick, and does not require complex tools or equipment, thereby saving time and labor.
[0048] like Figure 1 , Figure 2 As shown, in an optional embodiment, the mounting rod 205 is threadedly connected with a supporting block 206 supported under the counterweight unit, and a pressing block 207 pressed on the counterweight unit.
[0049] The mounting rod 205 is threadedly connected with a support block 206 supported under the counterweight unit and a pressure block 207 pressed on the counterweight unit. The support block 206 and the pressure block 207 are connected to the mounting rod 205 by threads. This threaded connection method not only provides a strong fastening force, but also allows the positions of the support block 206 and the pressure block 207 to be quickly adjusted when necessary, so as to facilitate the increase or decrease of the number of counterweight units. The self-locking characteristics of the threaded connection ensure that the counterweight unit will not loosen due to vibration during the lifting process.
[0050] The support block 206 bears the vertical pressure of the counterweight unit to prevent the counterweight unit from being displaced or falling off during the lifting process. The pressure block 207 is located above the counterweight unit and is connected to the mounting rod 205 by threads. During the lifting process, the pressure block 207 applies a certain pressure to the counterweight unit to ensure close contact between the counterweight unit and the support block 206 to prevent the movement of the counterweight unit due to vibration or impact.
[0051] like Figure 1 , Figure 3As shown, Figure 3 A local schematic diagram of the transverse portion 401 is provided for an embodiment of the present application. In an optional embodiment, the hanging member includes a transverse portion 401 fixed to the upper portion of the second working end and arranged vertically with the main body 100, and the transverse portion 401 is provided with a plurality of flexible hanging portions 402 for connecting to the working furnace top 500.
[0052] The transverse portion 401 is fixed on the main body 100, providing a space for the flexible lifting portion 402 to be arranged in the length direction of the transverse portion 401, so that after the flexible lifting portion 402 is connected to the working furnace roof 500, it can maintain the stability of the working furnace roof 500 during the lifting process. The transverse portion 401 is perpendicular to the main body 100, so as to fully utilize the space in this direction through the transverse portion 401 and maintain the lightweight layout of the main body 100.
[0053] like Figure 1 , Figure 2 As shown, in an optional embodiment, at least four flexible lifting parts 402 are provided, and the ends of the flexible lifting parts 402 are provided with lifting bolts 403 that can be fixed to the working furnace top 500 to maintain the connection stability of the flexible lifting parts 402, and when connecting, the working furnace top 500 is connected through the lifting screws at one end of the flexible lifting parts 402.
[0054] like Figure 1 , Figure 3 As shown, in an optional embodiment, support blocks 404 fixedly connected to the transverse portion 401 are respectively provided on both sides of the main body 100 to improve the connection stability between the main body 100 and the transverse portion 401, and the support blocks 404 can be respectively connected to the main body 100 and the transverse portion 401 by welding.
[0055] In an optional embodiment, the adjusting member 200 and / or the main member 100 are configured as square tubes to improve the bending resistance of the adjusting member 200 and the main member 100 .
[0056] It should be understood that the terms first, second, etc. are only used to distinguish descriptions and should not be understood as indicating or suggesting relative importance. Although the terms first, second, etc. may be used herein to describe various units, these units should not be limited by these terms. These terms are only used to distinguish one unit from another unit. For example, the first unit may be referred to as the second unit, and similarly, the second unit may be referred to as the first unit without departing from the scope of the exemplary embodiments of the present invention.
[0057] It should be understood that the term "and / or" in this article is merely a description of the association relationship of associated objects, indicating that three relationships may exist. For example, A and / or B can represent three situations: A exists alone, B exists alone, and A and B exist at the same time. The term " / and" in this article describes another relationship between associated objects, indicating that two relationships may exist. For example, A / and B can represent two situations: A exists alone, and A and B exist alone. In addition, the character " / " in this article generally indicates that the previous and next associated objects are in an "or" relationship.
[0058] It should be understood that in the description of the present invention, the terms "upper", "vertical", "inside", "outside" and the like indicate orientations or positional relationships that are customarily placed when the disclosed product is used, or are orientations or positional relationships that are customarily understood by those skilled in the art. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0059] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "setting", "installation" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be a communication between the two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0060] The terms used herein are only used to describe specific embodiments and are not intended to limit the exemplary embodiments of the present invention. As used herein, the singular forms "a", "an", and "the" are intended to include the plural forms unless the context clearly indicates the opposite meaning. It should also be understood that the terms "include", "comprising", "including", and / or "comprising" when used herein specify the existence of the claimed features, integers, steps, operations, units, and / or components, and do not exclude the existence or increase of one or more other features, quantities, steps, operations, units, components, and / or their combinations.
[0061] Specific details are provided in the following description to facilitate a complete understanding of the exemplary embodiments. However, it should be understood by those of ordinary skill in the art that the exemplary embodiments may be implemented without these specific details. In other embodiments, well-known processes, structures, and techniques may not be shown in unnecessary detail to avoid making the exemplary embodiments unclear.
[0062] The above is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest range consistent with the principles and novel features applied for herein.
[0063] It should be noted that the information disclosed in the above background technology section is only used to enhance the understanding of the background of the present disclosure, and therefore may include information that does not constitute the prior art known to ordinary technicians in the field.
Claims
1. A furnace top hoisting system for a continuous casting tunnel furnace, characterized in that: The furnace top hoisting system comprises: A main body, wherein a connecting portion for connecting a lifting device is provided in the middle of the main body, the main body having a first working end and a second working end, and a plurality of connecting positions are provided at intervals on the first working end; An adjusting member, the adjusting member is fixedly connected to the main member, and the adjusting member is detachably arranged on one of the connecting positions to change the distance between the adjusting member and the second working section; A counterweight, the counterweight being detachably connected to the adjusting member; A hoisting piece is fixedly arranged on the second working end and is used for connecting to the working furnace top.
2. The furnace top hoisting system for a continuous casting tunnel furnace according to claim 1, characterized in that: The adjusting member is sleeved on the first working end of the main member, and a plurality of positioning holes corresponding to the connection are provided on the adjusting member, and a locking member fixedly connected to the main member is passed through the positioning hole.
3. The furnace top hoisting system for a continuous casting tunnel furnace as claimed in claim 2, characterized in that: The locking member comprises a plurality of bolts, and the plurality of bolts are passed through the plurality of positioning holes and fixedly connected to the plurality of connecting positions.
4. The furnace top hoisting system for a continuous casting tunnel furnace according to claim 1, characterized in that: A fixed platform is provided between the adjusting member and the counterweight member, the fixed platform is fixedly connected to the adjusting member, at least two mounting rods are provided on the fixed platform, and the counterweight member is detachably provided on the mounting rods.
5. The furnace top hoisting system for a continuous casting tunnel furnace according to claim 4, characterized in that: The counterweight component includes a plurality of counterweight units, and the counterweight units are provided with accommodating holes for the installation rods to pass through.
6. The furnace top hoisting system for a continuous casting tunnel furnace as claimed in claim 5, characterized in that: The mounting rod is threadedly connected with a supporting block supported under the counterweight unit and a pressing block pressed on the counterweight unit.
7. The furnace top hoisting system for a continuous casting tunnel furnace according to claim 1, characterized in that: The hanging member comprises a transverse part fixed on the upper part of the second working end and arranged perpendicularly to the main body member, and the transverse part is provided with a plurality of flexible hanging parts for connecting to the working furnace top.
8. The furnace top hoisting system for a continuous casting tunnel furnace according to claim 7, characterized in that: At least four flexible hoisting parts are provided, and hoisting bolts which can be fixed to the working furnace top are provided at the ends of the flexible hoisting parts.
9. The furnace top hoisting system for a continuous casting tunnel furnace according to claim 7, characterized in that: Support blocks fixedly connected to the lateral parts are respectively provided on both sides of the main body.
10. The furnace top hoisting system for a continuous casting tunnel furnace according to claim 1, characterized in that: The adjusting member and / or the main body member are configured as square tube members.