SMT (Surface Mount Technology) tray transfer method

By introducing an automated system in SMT production, the automatic shearing of material trays, feeding of materials and automatic loading of new materials trays is solved, and the problems of high error rates and increased production costs caused by manual operations in the prior art are improved, and the degree of automation and work efficiency are improved.

CN119789407AActive Publication Date: 2025-04-08昆山迈征自动化科技有限公司
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202311288671.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-10-08
Publication Date
2025-04-08
Estimated Expiration
2043-10-08

AI Technical Summary

Technical Problem

During the production and processing of existing SMTs, the replacement of material trays and jointing of material belts at the feed stations rely on manual operations, resulting in high error rates, low working efficiency and increased production costs.

Method used

Through an automated system, the automatic shearing, feeding and automatic loading of new material trays when the tape is about to be exhausted, including the use of a transfer robot, feeding mechanism and tail shearing mechanism.

Benefits of technology

It improves the automation and accuracy of material tray transfer, reduces production costs, and improves work efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119789407A_ABST
    Figure CN119789407A_ABST
Patent Text Reader

Abstract

The invention provides an SMT (Surface Mount Technology) tray transfer method, which is characterized in that after a material belt of a tray is about to be used up, material belt supplementation is completed through automatic material cutting, material receiving and automatic feeding of a new tray, the automation degree is high, the accuracy rate is high, and the production cost is reduced. The chip mounter comprises a chip mounter trolley and a material receiving machine, the chip mounter trolley and the material receiving machine are independently arranged, the material receiving machine is integrally arranged to be mobile equipment, and a transfer manipulator, a feeding platform, an empty tray placing mechanism, a lifting mechanism, a temporary storage bin, a material receiving mechanism and a material tail shearing mechanism are arranged on the material receiving machine; material boxes are arranged on the feeding platform, a material disc is placed in each material box, a material belt driving mechanism is arranged on each material box, the initial end of each new material disc is opposite to the material belt driving mechanism, a material disc clamp is arranged at the output end of the transferring mechanical arm, a winding motor is further arranged on each material disc clamp, and the winding motors are used for winding the material discs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of material tray transfer, and in particular to a SMT material tray transfer method. Background Art

[0002] SMT patch refers to the abbreviation of a series of process flows for processing on PCB boards. PCB (Printed Circuit Board) is a printed circuit board. SMT is surface mounting technology, which is the most popular technology and process in the electronic assembly industry.

[0003] In the existing SMT production and processing process, the material tray of the feeding station conveys the material tape to the placement machine, and the placement machine completes the placement work. When the material tape in the old material tray of the feeding station is about to run out, the operator needs to remove the old material tray from the feeding station, take out the new material tray, and connect the material tape head of the new material tray and the material tape tail of the old material tray through the material receiving machine, and then place the new material tray at the feeding station to continue the material feeding of the old material tray. At the same time, before joining, the blank part of the tail end of the old material tray needs to be cut off and then joined. Manual operation of blank cutting and joining relies on manual judgment, has a high error rate, and is cumbersome to operate, which not only has low work efficiency, but also increases production costs. Summary of the invention

[0004] In view of the above problems, the present invention provides an SMT material tray transfer method, which enables the material tray to be replenished by automatic cutting, splicing and automatic loading of new material trays when the material tape is about to be exhausted. It has a high degree of automation and high accuracy, thereby reducing production costs.

[0005] A SMT tray transfer method, comprising a placement machine trolley and a material receiving machine, wherein the placement machine trolley and the material receiving machine are independently arranged, and characterized in that: the material receiving machine is arranged as a mobile device as a whole, and a transfer manipulator, a feeding platform, an empty tray placement mechanism, a lifting mechanism, a buffer bin, a material receiving mechanism and a tail shearing mechanism are arranged on the material receiving machine; material boxes are arranged on the feeding platform, and a material tray is placed in each material box, and a material belt driving mechanism is arranged on the material box, and the initial end of each new material tray is aligned with the material belt driving mechanism, and a material tray clamp is arranged at the output end of the transfer manipulator, and a winding motor is also arranged on the material tray clamp, and the winding motor is used to wind up the material tray;

[0006] After the old material tray on the SMT trolley that needs to be replenished is pushed out, the old material tray is taken away from the SMT trolley by the transfer robot, and the old material belt is brought into the material receiving flow channel of the material receiving mechanism, and the excess part of the old material belt is brought into the buffer bin, so that the material belt can ensure the normal operation of the SMT trolley during the transfer process. At the same time, the CCD of the tail shearing mechanism detects the empty tail belt, the tail cutting mechanism cuts off the empty tail belt, and the old material tray is transferred to the empty tray placement mechanism;

[0007] The new material tray is lifted by the lifting mechanism, and then the new material tray enters the feeding channel through the material belt driving mechanism, and stops after the CCD detects the empty material belt position at the head. The tail end of the old material belt and the head end of the new material belt are sent to the material receiving mechanism at the same time, and the head and tail material belts are bonded together;

[0008] The transfer robot then takes out the new material tray, and the receiving motor starts receiving the material, placing the new material tray at the corresponding loading position on the SMT trolley that needs to be replenished.

[0009] It is further characterized in that it comprises the following specific steps:

[0010] S1. Prepare the material tray for the placement machine in the material basket and place the material basket at the buffer station;

[0011] S2, automatically moves the material basket to the loading platform of the material receiving machine;

[0012] S3. Move the material receiving machine to the corresponding material receiving position according to the requirements of the SMT production line;

[0013] S4, the loading platform will also move to the corresponding material position, and the lifting mechanism will lift the material box corresponding to the new material tray;

[0014] S5, the transfer robot moves to the position where the new material tray is on the line, the scanner scans the confirmation information, the lifting mechanism lowers the new material tray to make way, and at the same time the push-pull module of the placement machine trolley pushes out the material box to be refilled;

[0015] S6, the transfer robot moves to the position of the placement machine trolley, scans and confirms the old material tray information, and takes a photo again to confirm the position of the old material tray;

[0016] S7, the buffer bin is rotated and aligned, the robot takes out the old material tray from the bin of the placement machine trolley, and puts the old material belt into the material receiving channel;

[0017] S8, the buffer pressing mechanism acts to limit the flow direction of the old material tape, and the winding motor on the transfer robot feeds in the reverse direction, so that the old material tape is buffered into the buffer bin without affecting the feeding of the placement machine trolley. After the CCD on the tail material buffer module detects the tail empty material tape position, the winding motor stops, and the transfer robot places the empty material tray to a fixed position;

[0018] S9, the tail material cutting mechanism cuts off the tail empty material strip;

[0019] S10, the lifting mechanism lifts the new material tray and docks it with the feeding channel, and feeds the material through the material belt driving mechanism until the corresponding CCD detects the material belt position of the head and stops the driving operation of the material belt driving mechanism;

[0020] S11, the first and last material strips are simultaneously fed into the material receiving mechanism to bond the first and last material strips together;

[0021] S12, the transfer robot takes out the new material tray, and the receiving motor starts receiving the material;

[0022] S13, when the manipulator moves to the top of the cache bin, the cache module presses down, lifts the module and rotates back to its original position;

[0023] S14, the robot puts the new material tray back into the material box at the corresponding position of the placement machine trolley;

[0024] S15, the push-pull module of the placement machine trolley automatically pulls the material box back into the trolley;

[0025] S16, all modules of the receiving machine return to their original positions

[0026] S17, the robot returns to the safe position.

[0027] It is further characterized by:

[0028] There are several groups of material boxes arranged along a straight line in the material basket. Each material box is driven up by the lifting mechanism, and then the material tray is separated from the material box by the material tray clamp. Then the material box is lowered to the corresponding position of the material basket by the lifting mechanism. The entire material basket moves in a straight line driven by the linear drive mechanism until all the material trays in the material boxes are transferred. Then, the empty material basket is transferred out by the external transfer mechanism and transported into a new material basket.

[0029] After the empty trays of the empty tray placing mechanism are filled, the external transfer mechanism simultaneously takes away the empty trays on the empty tray placing mechanism.

[0030] After adopting the above technical scheme, after the material tray on the SMT trolley has operated for the set time and the system senses that the material on the material tray is about to run out, the SMT trolley will push out the corresponding material tray, and through the movement of the transfer robot and the action of its material tray clamp, the old material tray will be transferred to the transfer bin, and the old material belt will be placed on the material receiving channel, and the old material tray will be transferred to the empty material tray placement mechanism, and then the new material tray will be replenished, and the new material belt will be connected to the material receiving channel. After cutting off the empty material belt at the tail, the material belt is connected through the material receiving mechanism, and then the new material tray is placed on the corresponding material tray position of the SMT trolley through the transfer robot, and the system continues to operate reliably. It enables the material tray to be replenished through automatic cutting, connecting and automatic loading of the new material tray after the material belt is about to run out. It has a high degree of automation and high accuracy, which reduces production costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 A top view of the equipment arrangement corresponding to the method of the present invention;

[0032] Figure 2 A three-dimensional diagram of the equipment corresponding to the method of the present invention;

[0033] The names of the corresponding serial numbers in the figure are as follows:

[0034] SMT trolley 100, material receiving machine 200, AGV trolley 300

[0035] Transfer robot 1, loading platform 2, empty tray placing mechanism 3, lifting mechanism 4, buffer bin 5, material receiving mechanism 6, material tail shearing mechanism 7, material basket 8, material box 9, material belt driving mechanism 91, material tray 10, material tray clamp 11, winding motor 12, driving motor 13. DETAILED DESCRIPTION

[0036] A method for transferring SMT trays, see Figure 1-Figure 2 , which includes a SMT trolley 100 and a material receiving machine 200. The SMT trolley 100 and the material receiving machine 200 are independently arranged, and the material receiving machine 200 is arranged as a mobile device as a whole. In specific implementation, an AGV vehicle 300 is arranged at the bottom of the material receiving machine 200, and the material receiving machine 200 is provided with a transfer manipulator 1, a feeding platform 2, an empty material tray placement mechanism 3, a lifting mechanism 4, a buffer bin 5, a material receiving mechanism 6 and a material tail shearing mechanism 7; a material basket 8 is arranged on the feeding platform 2, and a plurality of groups of material boxes 9 are arranged along a straight line in the material basket 8. , a material tray 10 is placed in each material box 9, and a material belt driving mechanism 91 is provided on the material box 9. The initial end of each new material tray is aligned with the material belt driving mechanism 91. In specific implementation, the material belt driving mechanism 91 is provided with an insertion hole, and the lifting mechanism 4 rises to a position, and the output end of the driving motor 13 is installed in the insertion hole to drive the material belt driving mechanism 91 to drive the material belt input, and a material tray clamp 11 is provided at the output end of the transfer robot 1, and a winding motor 12 is also provided on the material tray clamp 11, and the winding motor 12 is used to wind up the material tray 10;

[0037] After the old material tray on the SMT trolley 100 that needs to be replenished is pushed out, the old material tray is taken away from the SMT trolley 100 by the transfer robot 1, and at the same time, the old material belt is brought into the material receiving channel of the material receiving mechanism 6, and the excess part of the old material belt is brought into the buffer bin 5, so that the material belt can ensure the normal operation of the SMT trolley 100 during the transportation process, and at the same time, the CCD of the tail shearing mechanism 7 detects the empty tail material belt, the tail material cutting mechanism of the tail shearing mechanism 7 cuts off the empty tail material belt, and the old material tray is transported to the empty tray placement mechanism 3;

[0038] The new material tray is lifted by the lifting mechanism 4, and then the new material tray enters the feeding channel through the material belt driving mechanism 91, and stops after the CCD detects the empty material belt position at the head.

[0039] The tail end of the old material strip and the head end of the new material strip are simultaneously fed into the material receiving mechanism 6 to bond the head and tail material strips together;

[0040] Then the transfer robot 1 takes out the new material tray, and the winding motor 12 starts to rewind the material, placing the new material tray at the corresponding loading position on the SMT machine trolley 100 that needs to be replenished.

[0041] It includes the following specific steps:

[0042] S1. Prepare the material tray for the placement machine in the material basket and place the material basket at the buffer station;

[0043] S2, automatically moves the material basket to the loading platform of the material receiving machine;

[0044] S3. Move the material receiving machine to the corresponding material receiving position according to the requirements of the SMT production line;

[0045] S4, the loading platform will also move to the corresponding material position, and the lifting mechanism will lift the material box corresponding to the new material tray;

[0046] S5, the transfer robot moves to the position where the new material tray is on the line, the scanner scans the confirmation information, the lifting mechanism lowers the new material tray to make way, and at the same time the push-pull module of the placement machine trolley pushes out the material box to be refilled;

[0047] S6, the transfer robot moves to the position of the placement machine trolley, scans and confirms the old material tray information, and takes a photo again to confirm the position of the old material tray;

[0048] S7, the buffer bin is rotated and aligned, the robot takes out the old material tray from the bin of the placement machine trolley, and puts the old material belt into the material receiving channel;

[0049] S8, the buffer pressing mechanism acts to limit the flow direction of the old material tape, and the winding motor on the transfer robot feeds in the reverse direction, so that the old material tape is buffered into the buffer bin without affecting the feeding of the placement machine trolley. After the CCD on the tail material buffer module detects the tail empty material tape position, the winding motor stops, and the transfer robot places the empty material tray to a fixed position;

[0050] S9, the tail material cutting mechanism cuts off the tail empty material strip;

[0051] S10, the lifting mechanism lifts the new material tray and docks it with the feeding channel, and feeds the material through the material belt driving mechanism until the corresponding CCD detects the material belt position of the head and stops the driving operation of the material belt driving mechanism;

[0052] S11, the first and last material strips are simultaneously fed into the material receiving mechanism to bond the first and last material strips together;

[0053] S12, the transfer robot takes out the new material tray, and the receiving motor starts receiving the material;

[0054] S13, when the manipulator moves to the top of the cache bin, the cache module presses down, lifts the module and rotates back to its original position;

[0055] S14, the robot puts the new material tray back into the material box at the corresponding position of the placement machine trolley;

[0056] S15, the push-pull module of the placement machine trolley automatically pulls the material box back into the trolley;

[0057] S16, all modules of the receiving machine return to their original positions

[0058] S17, the robot returns to the safe position.

[0059] During the specific implementation: a plurality of material boxes are arranged along a straight line in the material basket, each material box is driven up by the lifting mechanism, and then the material tray is separated from the material box by the material tray clamp, and then the material box is lowered to the corresponding position of the material basket by the lifting mechanism, and the entire material basket moves in a straight line driven by the linear drive mechanism until all the material trays in the material boxes are transferred, and then the empty material basket is transferred out by the external transfer mechanism and transported into a new material basket;

[0060] After the empty trays of the empty tray placing mechanism are filled, the external transfer mechanism simultaneously takes away the empty trays on the empty tray placing mechanism.

[0061] Its working principle is as follows: after the set time has passed and the system senses that the material on the tray is about to run out, the SMT trolley will push out the corresponding tray, and the old tray will be transferred to the transfer bin through the movement of the transfer robot and the action of its tray clamp, and the old material belt will be placed on the material receiving channel, and the old tray will be transferred to the empty tray placement mechanism, and then the new tray will be replenished, and the new material belt will be connected to the material receiving channel. After cutting off the empty material belt at the tail, the material belt is connected through the material receiving mechanism, and then the new tray is placed on the corresponding tray position of the SMT trolley through the transfer robot, and the system continues to operate reliably. When the material belt is about to run out, the tray can be replenished through automatic cutting, connecting and automatic loading of the new tray. It has a high degree of automation and high accuracy, which reduces production costs.

[0062] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

[0063] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A SMT tray transfer method, comprising a placement machine trolley and a material receiving machine, wherein the placement machine trolley and the material receiving machine are independently arranged, and characterized in that: The whole material receiving machine is set as a mobile device, and a transfer manipulator, a feeding platform, an empty material tray placement mechanism, a lifting mechanism, a buffer bin, a material receiving mechanism and a material tail shearing mechanism are arranged on the material receiving machine; material boxes are arranged on the feeding platform, and a material tray is placed in each material box. A material belt driving mechanism is arranged on the material box, and the initial end of each new material tray is aligned with the material belt driving mechanism. A material tray clamp is arranged at the output end of the transfer manipulator, and a winding motor is also arranged on the material tray clamp, and the winding motor is used to wind up the material tray; After the old material tray on the SMT trolley that needs to be replenished is pushed out, the old material tray is taken away from the SMT trolley by the transfer robot, and the old material belt is brought into the material receiving flow channel of the material receiving mechanism, and the excess part of the old material belt is brought into the buffer bin, so that the material belt can ensure the normal operation of the SMT trolley during the transfer process. At the same time, the CCD of the tail shearing mechanism detects the empty tail belt, the tail cutting mechanism cuts off the empty tail belt, and the old material tray is transferred to the empty tray placement mechanism; The new material tray is lifted by the lifting mechanism, and then the new material tray enters the feeding channel through the material belt driving mechanism, and stops after the CCD detects the empty material belt position at the head. The tail end of the old material belt and the head end of the new material belt are sent to the material receiving mechanism at the same time, and the head and tail material belts are bonded together; The transfer robot then takes out the new material tray, and the receiving motor starts receiving the material, placing the new material tray at the corresponding loading position on the SMT trolley that needs to be replenished.

2. A SMT tray transfer method as claimed in claim 1, characterized in that: It includes the following specific steps: S1. Prepare the material tray for the placement machine in the material basket and place the material basket at the buffer station; S2, automatically moves the material basket to the loading platform of the material receiving machine; S3. Move the material receiving machine to the corresponding material receiving position according to the requirements of the SMT production line; S4, the loading platform will also move to the corresponding material position, and the lifting mechanism will lift the material box corresponding to the new material tray; S5, the transfer robot moves to the position where the new material tray is on the line, the scanner scans the confirmation information, the lifting mechanism lowers the new material tray to make way, and at the same time the push-pull module of the placement machine trolley pushes out the material box to be refilled; S6, the transfer robot moves to the position of the placement machine trolley, scans and confirms the old material tray information, and takes a photo again to confirm the position of the old material tray; S7, the buffer bin is rotated and aligned, the robot takes out the old material tray from the bin of the placement machine trolley, and puts the old material belt into the material receiving channel; S8, the buffer pressing mechanism acts to limit the flow direction of the old material tape, and the winding motor on the transfer robot feeds in the reverse direction, so that the old material tape is buffered into the buffer bin without affecting the feeding of the placement machine trolley. After the CCD on the tail material buffer module detects the tail empty material tape position, the winding motor stops, and the transfer robot places the empty material tray to a fixed position; S9, the tail material cutting mechanism cuts off the tail empty material strip; S10, the lifting mechanism lifts the new material tray and docks it with the feeding channel, and feeds the material through the material belt driving mechanism until the corresponding CCD detects the material belt position of the head and stops the driving operation of the material belt driving mechanism; S11, the first and last material strips are simultaneously fed into the material receiving mechanism to bond the first and last material strips together; S12, the transfer robot takes out the new material tray, and the receiving motor starts receiving the material; S13, when the manipulator moves to the top of the cache bin, the cache module presses down, lifts the module and rotates back to its original position; S14, the robot puts the new material tray back into the material box at the corresponding position of the placement machine trolley; S15, the push-pull module of the placement machine trolley automatically pulls the material box back into the trolley; S16, all modules of the receiving machine return to their original positions S17, the robot returns to the safe position.

3. A SMT tray transfer method as claimed in claim 2, characterized in that: There are several groups of material boxes arranged along a straight line in the material basket. Each material box is driven up by the lifting mechanism, and then the material tray is separated from the material box through the material tray clamp. After that, the material box is lowered to the corresponding positioning position of the material basket through the lifting mechanism. The entire material basket moves in a straight line driven by the linear drive mechanism until all the material trays in the material boxes are transferred. After that, the empty material basket is transferred out by the external transfer mechanism and transported into a new material basket.

4. A SMT tray transfer method as claimed in claim 2, characterized in that: After the empty trays of the empty tray placing mechanism are filled, the external transfer mechanism simultaneously takes away the empty trays on the empty tray placing mechanism.

Citation Information

Patent Citations

  • Automatic feeding method of chip mounter

    CN116367453A

  • Automatic product feeding and discharging equipment

    CN219408278U

  • Component mounting method and component mounting device

    JP2017045791A

  • Maintenance Method and Component Mounter

    US20080147232A1

  • Tape splicing device

    WO2018011984A1