Large equipment foundation bolt anchor box positioning and mounting device and method

By using positioning frames and positioning ribs to weld and fix them during the installation of bolt anchor boxes, the problems of cumbersome construction and difficult to control accuracy are solved, and the high accuracy and stable installation of bolt anchor boxes are achieved, which improves construction efficiency and reduces costs.

CN119801272APending Publication Date: 2025-04-11CHINA MCC22 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510051835.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-14
Publication Date
2025-04-11

AI Technical Summary

Technical Problem

The prior art is cumbersome to construct during the installation of bolt anchor boxes, and the elevation control accuracy is difficult to accurately control, and it is easy to cause the anchor box to move.

Method used

The positioning frame is used as the overall support and positioning structure of the bolt anchor box. The positioning frame is welded and fixed with the positioning ribs to achieve convenient adjustment and stable fixation of the bolt anchor box.

Benefits of technology

It significantly improves the installation accuracy and stability of the bolt anchor box, improves construction efficiency, avoids rework, and reduces labor and production costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119801272A_ABST
    Figure CN119801272A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of equipment installation and construction, in particular to a large-scale equipment foundation bolt anchor box positioning and installing device and method.The positioning and installing method comprises the following steps of S1, positioning and paying off and installing positioning ribs, S2, welding and fixing a bolt anchor box and anchor box supporting legs, S3, welding and fixing a positioning frame and the positioning ribs, and S4, welding and fixing the positioning frame and the positioning ribs. S4, the bolt anchor box and the positioning frame are welded and fixed, S5, the steel bar round cage is installed, S6, concrete pouring and vibrating are conducted, and S7, overall inspection is conducted. The positioning frame serves as an overall supporting and positioning structure of the bolt anchor box, the elevation and the horizontal position of the bolt anchor box can be conveniently adjusted and positioned on the positioning frame, controllability is remarkably improved, meanwhile, the positioning frame and the positioning rib are welded and fixed, the stability of the positioning frame is guaranteed, and then the stability of the bolt anchor box is guaranteed. The installation precision of the bolt anchor box is improved, the construction efficiency is improved, the situation of reworking due to the precision problem is avoided, and meanwhile the labor cost and the production cost are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of equipment installation construction technology, and in particular to a large-scale equipment foundation bolt anchor box positioning and installation device and method. Background Art

[0002] With the continuous development of the equipment installation industry, the pursuit of construction speed and quality is getting higher and higher. At present, the basic method for bolt anchor box installation in China is: first locate and lay out on the cushion layer, install the positioning steel bars, then locate the individual anchor box legs one by one and weld them with the positioning steel bars, and finally hoist the anchor box and weld it with the anchor box legs, and adjust the welding position while measuring during the welding process.

[0003] This method has a complicated construction process, the elevation control accuracy is difficult to accurately control, and it is easy to cause horizontal and vertical displacement of the anchor box during the concrete pouring process. Summary of the invention

[0004] In order to improve the positioning accuracy and installation stability of foundation bolts of large equipment, the present invention provides a positioning and installation device and method for a foundation bolt anchor box of large equipment.

[0005] In the first aspect, the present invention provides a large equipment foundation bolt anchor box positioning and installation device, which adopts the following technical solution: The large equipment foundation bolt anchor box positioning and installation device includes a positioning frame for fixing the bolt anchor box. The positioning frames are arranged in pairs. The bolt anchor box is welded and fixed between the two positioning frames. The bottom end of the positioning frame is welded and fixed to the positioning reinforcement embedded in the cushion layer. The cushion layer is also vertically embedded with a steel bar cage for pouring and vibrating concrete.

[0006] By adopting the above technical solution, the positioning frame serves as the overall support and positioning structure of the bolt anchor box. The elevation and horizontal position of the bolt anchor box can be conveniently adjusted and positioned on the positioning frame, and the controllability is significantly improved. At the same time, the positioning frame and the positioning ribs are welded and fixed to ensure the stability of the positioning frame, and thus the stability of the bolt anchor box is also ensured; this not only improves the installation accuracy of the bolt anchor box, but also improves the construction efficiency, avoids rework due to installation accuracy problems, and is also conducive to reducing labor costs and production costs.

[0007] Optionally, the positioning ribs include a transversely arranged support rod, a bolt anchor box is welded and fixed between two adjacent support rods, a leg is obliquely fixed to the bottom of each end of the support rod, two adjacent obliquely arranged legs at the same end are arranged in an eight-shape, a leg is vertically fixed to the middle bottom of the support rod, and the leg is welded and fixed to the positioning ribs.

[0008] By adopting the above technical solution, the positioning frame can maintain an upright state by cooperating with the obliquely arranged frame legs and the vertically arranged frame legs, which is convenient for the placement and positioning of the positioning frame. The positioning ribs are easy to assemble and manufacture to improve construction efficiency.

[0009] Optionally, the positioning frame is made of square steel pipes, and the frame legs are inserted into or clamped into the positioning ribs and welded to the positioning ribs.

[0010] By adopting the above technical solution, square steel pipes are easy to obtain and manufacture, which can reduce production costs and improve construction efficiency.

[0011] Optionally, a measure rib is welded and fixed between two adjacent support rods.

[0012] By adopting the above technical solution, the overall structural strength and stability of the positioning frame are effectively improved.

[0013] In a second aspect, the present invention provides a method for positioning and installing a bolt anchor box for a large equipment foundation, which adopts the following technical solution: S1. Positioning and laying out the lines and installing the positioning bars, specifically including: positioning and laying out the lines on the equipment foundation cushion and implanting the positioning bars; S2. Welding and fixing the bolt anchor box and the anchor box legs, specifically including: first inspecting the bolt anchor box and the anchor box legs, and welding the bolt anchor box and the anchor box legs after confirming that they are correct; S3, welding and fixing the positioning frame to the positioning rib, specifically including: placing the positioning frame on the cushion layer, inserting or clamping the frame legs onto the positioning rib and welding and fixing them to the positioning rib; S4. The bolt anchor box is welded and fixed to the positioning frame, specifically including: marking the position on the support rod, hoisting each bolt anchor box as a whole to the corresponding position, and welding and fixing the bolt anchor box to the support rod after determining the elevation and horizontal position; S5. Install steel bar cages, including: pre-embedding several steel bar cages on the cushion layer, and avoid the steel bar dense area and the location of the bolt anchor box; S6. concrete pouring and vibrating, specifically comprising: pumping concrete into a steel cage, and spreading the concrete to the surroundings through the gaps on the steel cage according to a layered pouring mode, and inserting a vibrating rod into the steel cage to vibrate the concrete; S7. Overall inspection, including: inspection of the initial axis, diagonal, elevation and reinforcement conditions, and reporting for inspection after passing the self-inspection.

[0014] Optionally, the horizontal deviation of the positioning frame in S3 is ≤2mm, and the elevation deviation is ≤1mm.

[0015] In summary, the present invention includes at least one of the following beneficial technical effects: The positioning frame serves as the overall support and positioning structure of the bolt anchor box. The elevation and horizontal position of the bolt anchor box can be easily adjusted and positioned on the positioning frame, which significantly improves controllability. The positioning frame is welded and fixed to the positioning rib, which ensures the stability of the positioning frame and thus the stability of the bolt anchor box; It not only improves the installation accuracy of the bolt anchor box, but also improves the construction efficiency, avoids rework due to installation accuracy problems, and is also beneficial to reducing labor costs and production costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a structural schematic diagram of a large equipment foundation bolt anchor box positioning and installation device according to an embodiment of the present invention.

[0017] Figure 2 It is a schematic diagram of assembling a positioning frame and a bolt anchor box according to an embodiment of the present invention.

[0018] Figure 3 It is a flow chart of a method for positioning and installing a bolt anchor box for a large equipment foundation according to an embodiment of the present invention.

[0019] Explanation of the reference numerals: 1. bolt anchor box; 10. anchor box leg; 2. positioning frame; 20. support rod; 21. frame leg; 3. steel bar cage. DETAILED DESCRIPTION

[0020] The following is combined with Figure 1 -Attached Figure 3 The present invention is described in further detail.

[0021] The embodiment of the present invention discloses a device and method for positioning and installing a bolt anchor box for a large equipment foundation. Figure 1 and Figure 2 The large equipment foundation bolt anchor box positioning installation device is used to fix multiple bolt anchor boxes 1, and the bottom of the bolt anchor box 1 is fixed with an anchor box leg 10. The installation device includes a positioning frame 2 used in pairs. In this embodiment, two pairs of parallel positioning frames 2 are taken as an example. The positioning frame 2 is made of 100mm*100mm square steel pipe.

[0022] Reference Figure 1 and Figure 2 The positioning frame 2 includes a horizontally arranged support rod 20, and a frame leg 21 is fixedly connected to the bottom of each end of the support rod 20 in an oblique manner, and two frame legs 21 are fixedly connected to the bottom of the middle of the support rod 20 in a vertical manner. The bottom end of the frame leg 21 is welded and fixed to the positioning rib embedded in the cushion layer, and the adjacent two obliquely arranged frames 21 at the same end are arranged in an eight-shaped shape. The adjacent two support rods 20 can be welded and fixed by means of a rib to enhance the overall structural strength. The positioning frame 2 is maintained in an upright state by the obliquely arranged frames 21 and the vertically arranged frames 21 cooperating with each other.

[0023] Reference Figure 1 and Figure 2 A plurality of steel bar cages 3 arranged in a straight line are vertically pre-embedded on the cushion layer. The steel bar cages 3 are located in the middle of the two pairs of positioning frames 2 to avoid the steel bar dense area and the bolt anchor box 1. The steel bar cages 3 serve as the concrete pouring entrance and the vibrating rod insertion point to reduce the impact on the installation accuracy of the bolt anchor box 1 during concrete pouring and vibrating.

[0024] Reference Figure 3 The method for positioning and installing a bolt anchor box for a large equipment foundation according to an embodiment of the present invention comprises the following steps: S1. Positioning and laying out the lines and installing the positioning ribs, specifically including: positioning and laying out the lines on the equipment foundation cushion layer by means of instruments, followed by drilling holes and implanting the positioning ribs to ensure accurate positioning when the positioning frame 2 is installed later.

[0025] S2. The bolt anchor box 1 is welded and fixed to the anchor box leg 10, specifically including: first inspecting the bolt anchor box 1 and the anchor box leg 10, checking their material certification documents, test reports and appearance quality, welding the bolt anchor box 1 and the anchor box leg 10 after confirmation, and checking the overall height and levelness after welding.

[0026] S3, the positioning frame 2 is welded and fixed to the positioning reinforcement, specifically including: while the reinforcement is tied, the positioning frame 2 is placed on the cushion layer, the frame legs 21 are inserted or clamped onto the positioning reinforcement and welded and fixed to the positioning reinforcement, ensuring that the horizontal deviation of the positioning frame 2 is ≤2mm and the elevation deviation is ≤1mm.

[0027] S4, the bolt anchor box 1 is welded and fixed to the positioning frame 2, specifically including: positioning and marking on the support rod 20 of the positioning frame 2, hoisting each bolt anchor box 1 as a whole to the corresponding position, and welding and fixing the bolt anchor box 1 to the support rod 20 after determining the elevation and horizontal position of the bolt anchor box 1, and subsequently welding reinforcement bars to enhance the overall structural strength.

[0028] S5, installing the steel bar round cage 3, specifically including: pre-embedding a number of steel bar round cages 3 on the cushion layer, paying attention to avoiding the steel bar dense area and the position of the bolt anchor box 1.

[0029] S6, concrete pouring and vibrating, specifically including: pumping concrete into the steel cage 3, according to the layered pouring mode, the concrete diffuses to the surroundings through the gaps on the steel cage 3, thereby reducing the influence of the concrete pouring process on the installation accuracy of the bolt anchor box 1; inserting a vibrating rod into the steel cage 3 to vibrate the concrete, so as to avoid the influence of the concrete vibration process on the installation accuracy of the bolt anchor box 1.

[0030] S7. Overall inspection, including: inspection of the initial axis, diagonal, elevation and reinforcement conditions, and reporting for inspection after passing the self-inspection.

[0031] Compared with the positioning and installation process of the traditional bolt anchor box 1, the present invention adopts a positioning frame 2 as the overall support and positioning structure of the bolt anchor box 1. The elevation and horizontal position of the bolt anchor box 1 can be conveniently adjusted and positioned on the positioning frame 2, and the controllability is significantly improved. At the same time, the positioning frame 2 is welded and fixed to the positioning ribs, which ensures the stability of the positioning frame 2, and thus also ensures the stability of the bolt anchor box 1.

[0032] The anchor box legs 10 can be cast in concrete as anchors, improving the overall pull-out resistance of the bolt anchor box 1. The elevation adjustment of the bolt anchor box 1 no longer relies on the anchor box legs 10. Even if the cushion layer is laid unevenly, causing the bottom end of the anchor box legs 10 to be suspended, it will not affect the accurate positioning and position fixation of the bolt anchor box 1. The positioning and installation device and method not only improve the installation accuracy of the bolt anchor box 1, but also improve the construction efficiency, avoid rework due to installation accuracy problems, and also help reduce labor costs and production costs.

[0033] The above are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A large equipment foundation bolt anchor box positioning and installation device, characterized in that: The invention comprises a positioning frame (2) for fixing a bolt anchor box (1), the positioning frames (2) are arranged in pairs, the bolt anchor box (1) is welded and fixed between two positioning frames (2), the bottom end of the positioning frame (2) is welded and fixed to a positioning rib pre-buried on the cushion layer, and a steel bar round cage (3) for pouring and vibrating concrete is also vertically pre-buried on the cushion layer.

2. The large equipment foundation bolt anchor box positioning and installation device according to claim 1 is characterized by: The positioning ribs include a laterally arranged support rod (20), a bolt anchor box (1) is welded and fixed between two adjacent support rods (20), a frame leg (21) is respectively fixedly connected obliquely to the bottom of both ends of the support rod (20), two adjacent obliquely arranged frames legs (21) at the same end are arranged in an eight-shaped shape, a frame leg (21) is vertically fixedly connected to the middle bottom of the support rod (20), and the frames legs (21) are welded and fixed to the positioning ribs.

3. The large equipment foundation bolt anchor box positioning and installation device according to claim 2 is characterized in that: The positioning frame (2) is made of a square steel pipe, and the frame legs (21) are inserted into or clamped on the positioning ribs and are welded and fixed to the positioning ribs.

4. The large equipment foundation bolt anchor box positioning and installation device according to claim 2 is characterized in that: A measure rib is welded and fixed between two adjacent support rods (20).

5. A method for installing a large equipment foundation bolt anchor box positioning and installation device according to any one of claims 1 to 4, characterized in that: The following steps are involved: S1. Positioning and laying out the lines and installing the positioning bars, specifically including: positioning and laying out the lines on the equipment foundation cushion and implanting the positioning bars; S2, welding and fixing the bolt anchor box (1) and the anchor box leg (10), specifically comprising: first inspecting the bolt anchor box (1) and the anchor box leg (10), and after confirming that they are correct, welding the bolt anchor box (1) and the anchor box leg (10); S3, the positioning frame (2) is welded and fixed to the positioning rib, specifically comprising: placing the positioning frame (2) on the cushion layer, inserting or clamping the frame legs (21) onto the positioning rib and welding and fixing them to the positioning rib; S4, welding and fixing the bolt anchor box (1) and the positioning frame (2), specifically comprising: marking the position on the support rod (20), hoisting each bolt anchor box (1) as a whole to the corresponding position, and welding and fixing the bolt anchor box (1) to the support rod (20) after determining the elevation and horizontal position of the bolt anchor box (1); S5, installing the steel bar cage (3), specifically comprising: pre-embedding a number of steel bar cages (3) on the cushion layer, taking care to avoid the steel bar dense area and the position of the bolt anchor box (1); S6, concrete pouring and vibrating, specifically comprising: pumping concrete into the steel cage (3), according to a layered pouring mode, the concrete diffuses to the surroundings through the gaps on the steel cage (3), and inserting a vibrating rod into the steel cage (3) to vibrate the concrete; S7. Overall inspection, including: inspection of the initial axis, diagonal, elevation and reinforcement conditions, and reporting for inspection after passing the self-inspection.

6. The method for positioning and installing a bolt anchor box for a large equipment foundation according to claim 5 is characterized in that: The horizontal deviation of the positioning frame (2) in S3 is ≤2mm, and the elevation deviation is ≤1mm.