Construction project visual management method and platform based on BIM simulation and storage medium

Through the visual management method of construction projects based on BIM simulation, a three-dimensional model is built and scene simulation is carried out to obtain the process stage points and cross-domain stage points of project workers, the problem of the inability to effectively analyze the construction situation of project workers in the construction site in the existing technology is solved, and detailed analysis and investigation of construction behavior is realized, safety hazards are reduced and construction efficiency is improved.

CN119808248APending Publication Date: 2025-04-11CCCC THIRD HARBOR ENGINEERING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202510023535.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-07
Publication Date
2025-04-11

AI Technical Summary

Technical Problem

The visual management methods of existing construction projects cannot effectively analyze the construction situation of project workers in the construction site, resulting in the inability to check when construction behavior is abnormal, which poses safety hazards and affects construction efficiency.

Method used

Through the visual management method of construction projects based on BIM simulation, a three-dimensional model is built and scene simulation is carried out, the process stage points and cross-domain stage points of project workers are obtained, the construction progress planning software is integrated, the points to be optimized are obtained, and the data is shared in real time through cloud computing is built.

Benefits of technology

The construction behavior of project workers in construction projects has been carried out in detail, reducing construction safety hazards and improving construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119808248A_ABST
    Figure CN119808248A_ABST
Patent Text Reader

Abstract

The invention discloses a construction project visual management method and platform based on BIM simulation and a storage medium, and relates to the technical field of project management, and the method comprises the steps: building a construction visual model through BIM; scene simulation is carried out, and process stage points and cross-domain stage points are obtained; obtaining a construction progress model and a to-be-optimized point of a project worker; a cooperation platform is constructed, and real-time sharing is carried out; the method is used for solving the problems that in an existing construction project visual management method, the construction conditions of project workers in a construction site cannot be effectively analyzed, so that when the construction behaviors of the project workers are abnormal, the abnormal behaviors cannot be checked based on a visual construction model, potential safety hazards exist in the construction project, and the construction efficiency is improved. And the construction efficiency is influenced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of construction management, and in particular to a construction project visualization management method, platform and storage medium based on BIM simulation. Background Art

[0002] Construction project management refers to the management of the entire process of planning, organizing, arranging, directing, supervising, controlling and coordinating construction projects using systematic viewpoints and theories as well as modern scientific and technological means during the construction process. Its core lies in effectively coordinating resources from all parties to ensure the smooth progress of the project and thus achieve the project's goals. Visual management is a management method that uses visual perception information to organize on-site production activities, aiming to improve labor productivity through intuitive images and colors.

[0003] Existing methods for visual management of construction projects usually use BIM models, topography, and electronic maps to build an electronic sand table of the construction site, and operate the electronic sand table to obtain the construction progress of each construction project for management. Although this improved method can realize the visualization of the construction process of the engineering parts of the construction project, it cannot effectively analyze the construction status of the project workers of the construction project in the construction site. Therefore, when the construction behavior of the project workers is abnormal, such as the unreasonable movement trajectory of the project workers or cross-regional construction, the abnormal behavior cannot be checked based on the visual construction model, which leads to safety hazards in the construction project and affects the construction efficiency. For example, in the patent application with publication number CN112149212A, a visual construction management platform for engineering projects is disclosed. This solution is to use sand to The disk image unit and the roaming unit can preset roaming paths to dynamically display the electronic sand table image of the engineering project, thereby visually managing the construction project. Other methods for visual management of construction projects usually merge multiple subsystems used for construction projects and visualize them through BIM. This improvement method can increase the diversity of management methods, but the management of project workers can only be achieved through monitoring and positioning, and it is still impossible to effectively analyze the construction status of project workers in construction projects within the construction site. Therefore, when the construction behavior of project workers is abnormal, such as unreasonable movement trajectories of project workers or cross-regional construction, it is impossible to check the abnormal behavior based on the visual construction model, which leads to safety hazards in the construction project and affects construction efficiency. In view of this, it is necessary to improve the existing visual management methods for construction projects. Summary of the Invention

[0004] The present invention aims to solve at least one of the technical problems in the prior art to a certain extent. By proposing a construction project visualization management method, platform and storage medium based on BIM simulation, the present invention is used to solve the problem in the existing construction project visualization management method that it is impossible to effectively analyze the construction status of project workers in the construction project within the construction site. As a result, when the construction behavior of the project workers is abnormal, such as the project workers' unreasonable movement trajectory or cross-regional construction, the abnormal behavior cannot be checked based on the visualization construction model, which leads to safety hazards in the construction project and affects the construction efficiency.

[0005] To achieve the above objectives, in a first aspect, the present application provides a construction project visualization management method based on BIM simulation, comprising the following steps:

[0006] Based on the design drawings, engineering parameters, and construction plans, a 3D model is built using BIM and recorded as a construction visualization model. A scenario simulation is performed in the construction visualization model based on the construction sequence, and the process stages and cross-domain stages of project workers in the construction project are obtained based on the results of the scenario simulation.

[0007] Integrate the construction visualization model with the construction schedule software and record the resulting model as the construction schedule model; obtain the points to be optimized for project workers based on the process stage points, cross-domain stage points, and the construction schedule model;

[0008] A collaborative platform is built based on cloud computing, and construction visualization models, construction progress models and points to be optimized are shared in real time.

[0009] Furthermore, based on the construction sequence, scenario simulation is performed in the construction visualization model, and based on the results of the scenario simulation, the process stage points and cross-domain stage points of the project workers in the construction project are obtained, including:

[0010] A three-dimensional model is built in BIM based on the design drawings, engineering parameters and construction plan, and recorded as a construction visualization model. The construction plan includes construction projects and the construction site corresponding to each construction project. All construction projects are obtained based on the construction sequence in the construction plan, and all construction projects are recorded in order from the earliest to the latest construction time as visualization projects KX1 to visualization projects KX n ;

[0011] For any visualization project KX c , c is any one from 1 to n, the visualization project KX c The workers working in the corresponding construction site are recorded as project workers; a plane rectangular coordinate system is established and recorded as the site personnel analysis coordinate system, where the units of the X-axis and Y-axis of the site personnel analysis coordinate system are both m; the visualization project KX cThe corresponding overhead view of the construction site is placed in the first quadrant of the site personnel analysis coordinate system and recorded as the site area; the points corresponding to the maximum and minimum values ​​of the vertical coordinates in the site area are recorded as the upper reference point and the lower reference point respectively, and the points corresponding to the maximum and minimum values ​​of the horizontal coordinates in the site area are recorded as the right reference point and the left reference point respectively.

[0012] Furthermore, performing scene simulation in the construction visualization model based on the construction sequence, and obtaining the process stage points and cross-domain stage points of the project workers in the construction project based on the results of the scene simulation also includes:

[0013] For any project worker, based on the visual project KX c Get the construction area of ​​the project workers; when the construction area is completely within the site area, simulate the movement trajectory of the project workers in the site area based on the scene simulation, and record the point where the project workers are located in the scene simulation as the worker point; [TO, LO, RE, LE] max Recorded as the distance feature value of the worker point, where [TO, LO, RE, LE] max is the value corresponding to the maximum value among TO, LO, RE and LE, TO is the distance between the upper reference point and the worker point, LO is the distance between the lower reference point and the worker point, RE is the distance between the right reference point and the worker point, and LE is the distance between the left reference point and the worker point;

[0014] Establish a plane rectangular coordinate system, recorded as the four-way distance analysis coordinate system, where the unit of the X axis of the four-way distance analysis coordinate system is time and the unit of the Y axis is meter; based on the motion trajectory of the project worker in the simulation, [TO, LO, RE, LE] max The corresponding curve is drawn in the four-way distance analysis coordinate system, recorded as the process analysis curve, and the process stage points in the process analysis curve are marked, where the process stage points are the points where the maximum values ​​of TO, LO, RE and LE change when the process analysis curve is drawn.

[0015] Furthermore, performing scene simulation in the construction visualization model based on the construction sequence, and obtaining the process stage points and cross-domain stage points of the project workers in the construction project based on the results of the scene simulation also includes:

[0016] When part of the construction area is within the site area, the area where the construction area overlaps with the site area is recorded as the inner application area, and the area where the construction area does not overlap with the site area is recorded as the outer application area; based on the scene simulation, the movement trajectory of the project workers in the site area is simulated, and a four-way distance analysis coordinate system is established to obtain the corresponding process analysis curve; the process stage points, outer application line segments and inner application line segments in the process analysis curve are marked, wherein the outer application line segment is the line segment in the process analysis curve corresponding to the project workers in the outer application area, and the inner application line segment is the line segment in the process analysis curve corresponding to the project workers in the inner application area;

[0017] When there is a process stage point in the external application segment, the process stage point in the external application segment is recorded as the cross-domain stage point, and the cross-domain distance is recorded as 0; when there is no process stage point in the external application segment, the point in the internal application segment closest to the external application segment is recorded as the cross-domain stage point, and the cross-domain distance is recorded as the shortest distance between the cross-domain stage point and the external application segment.

[0018] Furthermore, performing scene simulation in the construction visualization model based on the construction sequence, and obtaining the process stage points and cross-domain stage points of the project workers in the construction project based on the results of the scene simulation also includes:

[0019] When the construction area is completely outside the site area, the movement trajectory of the project workers outside the site area is simulated based on the scenario simulation, and [TO, LO, RE, LE] is used to simulate the movement trajectory of the project workers outside the site area. min Record the distance characteristic value of the worker point as the distance characteristic value, and establish a four-way distance analysis coordinate system to obtain the corresponding process analysis curve based on the distance characteristic value; mark the process stage points in the process analysis curve, where the process stage points are the points where the minimum values ​​of TO, LO, RE and LE change when the process analysis curve is drawn;

[0020] Obtain the process phase points corresponding to all project workers in all visualized projects KX and the cross-domain phase points of project workers whose construction areas are partially within the site area.

[0021] Furthermore, based on the process stage points, cross-domain stage points and construction progress model, the points to be optimized for project workers include:

[0022] Integrate the construction visualization model with the construction schedule software and record the resulting model as the construction schedule model;

[0023] Use the construction progress model to simulate all construction projects in sequence; for any visualization project KX during the simulation c Any project worker in: Based on the method for obtaining the process analysis curve of the project worker, obtain the process analysis curve again when simulating the construction progress model, and record the process analysis curve obtained at this time as the contradiction comparison curve;

[0024] Put the process analysis curve and the contradiction comparison curve into the same four-way distance analysis coordinate system, and use the coincidence comparison algorithm to obtain the contradiction threshold corresponding to the project workers. The coincidence comparison algorithm is: Among them, F is the contradiction threshold, f jc is the number of process stage points in the area of ​​the process analysis curve that does not overlap with the contradiction comparison curve, f sum is the number of process stage points in the process analysis curve, f ky It is the number of cross-domain stage points in the area of ​​the process analysis curve that does not overlap with the contradiction comparison curve.

[0025] Furthermore, obtaining the points to be optimized for project workers based on process stage points, cross-domain stage points, and the construction progress model also includes:

[0026] When the contradiction threshold is 0 and f ky When it is 0, no optimization point is set for the project worker;

[0027] When the contradiction threshold is 0 and f ky When it is not 0, all process stage points and cross-domain stage points of the project worker are recorded as the project worker's points to be optimized;

[0028] When the contradiction threshold is less than 0 and greater than -1, the process stage points in the process analysis curve that do not overlap with the contradiction comparison curve and the cross-domain stage points of the project workers are recorded as the project workers' points to be optimized;

[0029] When the contradiction threshold is equal to -1, the cross-domain stage point of the project worker is recorded as the point to be optimized of the project worker;

[0030] When the contradiction threshold is less than -1, the process stage points in the process analysis curve that do not overlap with the contradiction comparison curve and the cross-domain stage points of the project workers are recorded as the project workers' points to be optimized;

[0031] When the contradiction threshold is less than 1 and greater than 0, the process stage points in the area of ​​the process analysis curve that do not overlap with the contradiction comparison curve are recorded as the project worker's points to be optimized;

[0032] When the contradiction threshold is equal to 1, all process stage points of the project worker are recorded as the project worker's points to be optimized;

[0033] Get the points to be optimized corresponding to all project workers.

[0034] Furthermore, a collaborative platform is built based on cloud computing to share construction visualization models, construction progress models, and points to be optimized in real time, including:

[0035] A collaborative platform is built based on cloud computing, and the construction visualization model, construction progress model and the points to be optimized of all project workers are stored in the collaborative platform; when the construction project starts and the real-time progress of the construction project coincides with the point to be optimized of any project worker, the project workers corresponding to the point to be optimized that coincides with the real-time progress are monitored in real time.

[0036] Secondly, this application also provides a construction project visualization management platform based on BIM simulation, including a worker stage analysis module, a construction conflict analysis module, and an optimization sharing module;

[0037] The worker phase analysis module is used to build a 3D model using BIM based on design drawings, engineering parameters, and construction plans, and record it as a construction visualization model. It also performs scenario simulation in the construction visualization model based on the construction sequence, and obtains the process phase points and cross-domain phase points of project workers in the construction project based on the results of the scenario simulation.

[0038] The construction conflict analysis module is used to integrate the construction visualization model with the construction schedule software and record the resulting model as the construction schedule model. It also obtains the points to be optimized for project workers based on process stage points, cross-domain stage points, and the construction schedule model.

[0039] The optimization sharing module is used to build a collaborative platform based on cloud computing, and to share the construction visualization model, construction progress model and points to be optimized in real time.

[0040] In a third aspect, the present application provides a storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the steps in the above method are performed.

[0041] Beneficial effects of the present invention: This application first uses BIM to build a construction visualization model based on design drawings, engineering parameters and construction plans; performs scene simulation in the construction visualization model based on the construction sequence, and obtains the process stage points and cross-domain stage points of project workers in the construction project based on the results of the scene simulation. The advantage of this is that by building a visualization model and performing scene simulation, it is possible to obtain a model that is identical to the actual construction scene to the maximum extent, thereby improving the accuracy of subsequent analysis and making the analysis data more accurate; by obtaining the process stage points and cross-domain stage points of project workers, it is possible to extract the characteristics of the movement trajectory of project workers in the construction area during the implementation of the construction project, so as to ensure that in the subsequent analysis, when the construction behavior of project workers is abnormal, the abnormal behavior can be checked based on the process stage points and cross-domain stage points, and the points that need to be optimized for the construction project can be obtained in time to reduce the safety hazards existing in the construction project and improve construction efficiency;

[0042] This application also integrates the construction visualization model with the construction schedule planning software, and records the obtained model as the construction schedule model; obtains the points to be optimized of the project workers based on the process stage points, cross-domain stage points and the construction schedule model; finally, builds a collaboration platform based on cloud computing, and shares the construction visualization model, the construction schedule model and the points to be optimized in real time. The advantage of this is that by obtaining the points to be optimized and building a collaboration platform for real-time sharing, it is possible to obtain the abnormal positions of the project workers during the construction process, and notify the staff in time through real-time sharing to deal with them, so as to reduce the safety hazards of the construction project and improve construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1 is a functional block diagram of the system of the present invention;

[0044] Figure 2 is a flow chart of the steps of the method of the present invention;

[0045] Figure 3 A schematic diagram of the site personnel analysis coordinate system of the present invention;

[0046] Figure 4 A schematic diagram of obtaining cross-domain stage points of the present invention;

[0047] Figure 5 Schematic diagram of the structure of the electronic device of the present invention. DETAILED DESCRIPTION

[0048] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.

[0049] Example 1, please refer to Figure 1 As shown, this application provides a construction project visualization management platform based on BIM simulation, including a worker stage analysis module, a construction conflict analysis module, and an optimization sharing module;

[0050] The worker phase analysis module is used to build a 3D model using BIM based on design drawings, engineering parameters, and construction plans, and record it as a construction visualization model. It also performs scenario simulation in the construction visualization model based on the construction sequence, and obtains the process phase points and cross-domain phase points of project workers in the construction project based on the results of the scenario simulation.

[0051] The worker phase analysis module includes a construction process analysis unit, which is equipped with a construction process analysis strategy. The construction process analysis strategy includes: building a three-dimensional model in BIM based on design drawings, engineering parameters and construction plans, and recording it as a construction visualization model, wherein the construction plan includes construction projects and the construction site corresponding to each construction project; obtaining all construction projects based on the construction sequence in the construction plan, and recording all construction projects in order from the earliest to the latest based on the construction time as visualization projects KX1 to visualization projects KX n ;

[0052] During the specific implementation process, all construction projects can be marked as visualization projects KX according to the order of all construction projects carried out on the construction site in the actual construction plan. For example, if the construction plan is a civil engineering project, and the construction projects are foundation engineering, earthwork engineering, masonry engineering, concrete engineering, steel engineering, wood structure engineering, wall engineering, floor engineering, roof engineering, staircase engineering and decoration engineering, then the above projects can be recorded in sequence as multiple visualization projects for subsequent analysis.

[0053] For any visualization project KX c , c is any one from 1 to n, the visualization project KX c The workers working in the corresponding construction site are recorded as project workers; a plane rectangular coordinate system is established and recorded as the site personnel analysis coordinate system, where the units of the X-axis and Y-axis of the site personnel analysis coordinate system are both m; the visualization project KX c The top view of the corresponding construction site is placed in the first quadrant of the site personnel analysis coordinate system and recorded as the site area; the points corresponding to the maximum and minimum values ​​of the vertical coordinate in the site area are recorded as the upper reference point and the lower reference point respectively, and the points corresponding to the maximum and minimum values ​​of the horizontal coordinate in the site area are recorded as the right reference point and the left reference point respectively;

[0054] In the specific implementation process, for example, during a data processing, the site personnel analysis coordinate system is obtained as follows Figure 3 As shown in the figure, the area where QY is located is the site area, TO, LO, RE and LE are the upper reference point, lower reference point, right reference point and left reference point in the site area respectively; point RY is the location of the project worker, and the length from LL1 to LL4 is the distance between the upper reference point, lower reference point, right reference point and left reference point and the worker point. By analysis, we can get [TO, LO, RE, LE] max is the distance between point LO and the worker point, that is, the distance between the lower reference point and the worker point;

[0055] For any project worker, based on the visual project KX cGet the construction area of ​​the project workers; when the construction area is completely within the site area, simulate the movement trajectory of the project workers in the site area based on the scene simulation, and record the point where the project workers are located in the scene simulation as the worker point; [TO, LO, RE, LE] max Recorded as the distance feature value of the worker point, where [TO, LO, RE, LE] max is the value corresponding to the maximum value among TO, LO, RE and LE, TO is the distance between the upper reference point and the worker point, LO is the distance between the lower reference point and the worker point, RE is the distance between the right reference point and the worker point, and LE is the distance between the left reference point and the worker point;

[0056] In the specific implementation process, for example, during a data processing, the TO, LO, RE, and LE obtained are 10, 20, 15, and 9 respectively. Then, through analysis, it can be found that when the construction area is completely within the site area, the distance characteristic value can be set to 20; when the construction area is completely outside the site area, the distance characteristic value can be set to 9. By obtaining the distance characteristic value, the position characteristics of the project workers during construction can be obtained, which is conducive to controlling the position of the project workers and thus managing the project workers.

[0057] Establish a plane rectangular coordinate system, recorded as the four-way distance analysis coordinate system, where the unit of the X axis of the four-way distance analysis coordinate system is time and the unit of the Y axis is meter; based on the motion trajectory of the project worker in the simulation, [TO, LO, RE, LE] max The corresponding curve is drawn in the four-way distance analysis coordinate system, recorded as the process analysis curve, and the process stage points in the process analysis curve are marked. The process stage points are the points where the maximum values ​​of TO, LO, RE and LE change when the process analysis curve is drawn;

[0058] When part of the construction area is within the site area, the area where the construction area overlaps with the site area is recorded as the inner application area, and the area where the construction area does not overlap with the site area is recorded as the outer application area; based on the scene simulation, the movement trajectory of the project workers in the site area is simulated, and a four-way distance analysis coordinate system is established to obtain the corresponding process analysis curve; the process stage points, outer application line segments and inner application line segments in the process analysis curve are marked, wherein the outer application line segment is the line segment in the process analysis curve corresponding to the project workers in the outer application area, and the inner application line segment is the line segment in the process analysis curve corresponding to the project workers in the inner application area;

[0059] In the specific implementation process, for example, during a data processing, the construction area and site area are obtained as follows: Figure 4As shown in the figure, the solid line area where QY is located is the site area, and the dotted line area where SG is located is the construction area. By drawing the process analysis curve, it is obtained that points DD1, DD2, and DD3 are all process stage points. Since points DD2 and DD3 are in the external application area, points DD2 and DD3 are recorded as cross-domain stage points to help distinguish the process stage points within the site area and outside the site area.

[0060] When there is a process stage point in the external application segment, the process stage point in the external application segment is recorded as the cross-domain stage point, and the cross-domain distance is recorded as 0; when there is no process stage point in the external application segment, the point in the internal application segment closest to the external application segment is recorded as the cross-domain stage point, and the cross-domain distance is recorded as the shortest distance between the cross-domain stage point and the external application segment;

[0061] When the construction area is completely outside the site area, the movement trajectory of the project workers outside the site area is simulated based on the scenario simulation, and [TO, LO, RE, LE] is used to simulate the movement trajectory of the project workers outside the site area. min Record the distance characteristic value of the worker point as the distance characteristic value, and establish a four-way distance analysis coordinate system to obtain the corresponding process analysis curve based on the distance characteristic value; mark the process stage points in the process analysis curve, where the process stage points are the points where the minimum values ​​of TO, LO, RE and LE change when the process analysis curve is drawn;

[0062] Obtain the process phase points corresponding to all project workers in all visualized projects KX and the cross-domain phase points of project workers whose construction areas are partially within the site area.

[0063] The construction conflict analysis module is used to integrate the construction visualization model with the construction schedule software and record the resulting model as the construction schedule model. It also obtains the points to be optimized for project workers based on process stage points, cross-domain stage points, and the construction schedule model.

[0064] The construction contradiction analysis module includes a unit for obtaining points to be optimized, and the unit is configured with a strategy for obtaining points to be optimized. The strategy for obtaining points to be optimized includes: integrating a construction visualization model with a construction schedule software, and recording the obtained model as a construction schedule model;

[0065] Use the construction progress model to simulate all construction projects in sequence; for any visualization project KX during the simulation c Any project worker in: Based on the method for obtaining the process analysis curve of the project worker, obtain the process analysis curve again when simulating the construction progress model, and record the process analysis curve obtained at this time as the contradiction comparison curve;

[0066] Put the process analysis curve and the contradiction comparison curve into the same four-way distance analysis coordinate system, and use the coincidence comparison algorithm to obtain the contradiction threshold corresponding to the project workers. The coincidence comparison algorithm is: Among them, F is the contradiction threshold, f jc is the number of process stage points in the area of ​​the process analysis curve that does not overlap with the contradiction comparison curve, f sum is the number of process stage points in the process analysis curve, f ky It is the number of cross-domain stage points in the process analysis curve that does not overlap with the contradiction comparison curve;

[0067] In the specific implementation process, for example, during a data processing, f is obtained jc is 1, f sum is 4, and f ky If f is 1, then the contradiction threshold is -0.75. The calculation result shows that since the contradiction threshold is less than 0, the number of cross-domain stage points in the area that does not overlap with the contradiction comparison curve in the process analysis curve is greater than 0, indicating that the project workers have cross-region construction behavior. Therefore, the cross-domain stage points of the project workers should be recorded as the points to be optimized for project workers, so as to manage them. If the threshold is less than 0 and greater than -1, it means that f jc Divide by f sum Less than 1, that is, the number of process stage points in the area of ​​the process analysis curve that does not overlap with the contradiction comparison curve is greater than 0. Therefore, the process stage points in the area of ​​the process analysis curve that does not overlap with the contradiction comparison curve can be recorded as points to be optimized for project workers, thereby managing them;

[0068] When the contradiction threshold is 0 and f ky When it is 0, no optimization point is set for the project worker;

[0069] When the contradiction threshold is 0 and f ky When it is not 0, all process stage points and cross-domain stage points of the project worker are recorded as the project worker's points to be optimized;

[0070] When the contradiction threshold is less than 0 and greater than -1, the process stage points in the process analysis curve that do not overlap with the contradiction comparison curve and the cross-domain stage points of the project workers are recorded as the project workers' points to be optimized;

[0071] When the contradiction threshold is equal to -1, the cross-domain stage point of the project worker is recorded as the point to be optimized of the project worker;

[0072] When the contradiction threshold is less than -1, the process stage points in the process analysis curve that do not overlap with the contradiction comparison curve and the cross-domain stage points of the project workers are recorded as the project workers' points to be optimized;

[0073] When the contradiction threshold is less than 1 and greater than 0, the process stage points in the area of ​​the process analysis curve that do not overlap with the contradiction comparison curve are recorded as the project worker's points to be optimized;

[0074] When the contradiction threshold is equal to 1, all process stage points of the project worker are recorded as the project worker's points to be optimized;

[0075] Get the points to be optimized corresponding to all project workers.

[0076] The optimization sharing module is used to build a collaborative platform based on cloud computing and share the construction visualization model, construction progress model, and points to be optimized in real time. The optimization sharing module includes an optimization sharing unit, which is configured with an optimization sharing strategy. The optimization sharing strategy includes:

[0077] A collaboration platform is built based on cloud computing, and the construction visualization model, construction progress model and the points to be optimized of all project workers are stored in the collaboration platform; when the construction project starts and the real-time progress of the construction project coincides with the point to be optimized of any project worker, the project workers corresponding to the point to be optimized that coincides with the real-time progress are monitored in real time; in the specific implementation process, for example, during a data processing, it is found that the point to be optimized of a project worker in an earthwork project is 10 minutes and 40 seconds after the start of the earthwork project, then the project worker can be monitored in real time 10 minutes and 40 seconds after the start of the earthwork project to prevent construction safety hazards.

[0078] Example 2, please refer to Figure 2 As shown, this application also provides a construction project visualization management method based on BIM simulation, including the following steps:

[0079] Step S1: Based on the design drawings, engineering parameters, and construction plan, a three-dimensional model is built using BIM and recorded as a construction visualization model; scenario simulation is performed in the construction visualization model based on the construction sequence, and the process stage points and cross-domain stage points of the project workers in the construction project are obtained based on the results of the scenario simulation;

[0080] Step S1 includes: Step S101, building a three-dimensional model in BIM based on the design drawings, engineering parameters and construction plan, and recording it as a construction visualization model, wherein the construction plan includes construction projects and the construction site corresponding to each construction project; obtaining all construction projects based on the construction sequence in the construction plan, and recording all construction projects in order from the earliest to the latest based on the construction time as visualization projects KX1 to visualization projects KX n ;

[0081] Step S102: for any visualization project KX c , c is any one from 1 to n, the visualization project KX cThe workers working in the corresponding construction site are recorded as project workers; a plane rectangular coordinate system is established and recorded as the site personnel analysis coordinate system, where the units of the X-axis and Y-axis of the site personnel analysis coordinate system are both m; the visualization project KX c The top view of the corresponding construction site is placed in the first quadrant of the site personnel analysis coordinate system and recorded as the site area; the points corresponding to the maximum and minimum values ​​of the vertical coordinate in the site area are recorded as the upper reference point and the lower reference point respectively, and the points corresponding to the maximum and minimum values ​​of the horizontal coordinate in the site area are recorded as the right reference point and the left reference point respectively;

[0082] Step S103: for any project worker, based on the visualization project KX c Get the construction area of ​​the project workers; when the construction area is completely within the site area, simulate the movement trajectory of the project workers in the site area based on the scene simulation, and record the point where the project workers are located in the scene simulation as the worker point; [TO, LO, RE, LE] max Recorded as the distance feature value of the worker point, where [TO, LO, RE, LE] max is the value corresponding to the maximum value among TO, LO, RE and LE, TO is the distance between the upper reference point and the worker point, LO is the distance between the lower reference point and the worker point, RE is the distance between the right reference point and the worker point, and LE is the distance between the left reference point and the worker point;

[0083] Step S104: establish a plane rectangular coordinate system, which is recorded as the four-way distance analysis coordinate system, wherein the unit of the X axis of the four-way distance analysis coordinate system is time, and the unit of the Y axis is meter; based on the motion trajectory of the project worker in the simulation, [TO, LO, RE, LE] max The corresponding curve is drawn in the four-way distance analysis coordinate system, recorded as the process analysis curve, and the process stage points in the process analysis curve are marked. The process stage points are the points where the maximum values ​​of TO, LO, RE and LE change when the process analysis curve is drawn;

[0084] Step S105: When the construction area is partially within the site area, the area where the construction area overlaps with the site area is recorded as the inner application area, and the area where the construction area does not overlap with the site area is recorded as the outer application area; based on the scenario simulation, the movement trajectory of the project workers in the site area is simulated, and a four-way distance analysis coordinate system is established to obtain the corresponding process analysis curve; the process stage points, outer application line segments, and inner application line segments in the process analysis curve are marked, wherein the outer application line segments are the line segments in the process analysis curve corresponding to the project workers in the outer application area, and the inner application line segments are the line segments in the process analysis curve corresponding to the project workers in the inner application area;

[0085] Step S106: When there is a process stage point in the external application segment, the process stage point in the external application segment is recorded as the cross-domain stage point, and the cross-domain distance is recorded as 0; when there is no process stage point in the external application segment, the point in the internal application segment closest to the external application segment is recorded as the cross-domain stage point, and the cross-domain distance is recorded as the shortest distance between the cross-domain stage point and the external application segment;

[0086] Step S107: When the construction area is completely outside the site area, the movement trajectory of the project workers outside the site area is simulated based on the scene simulation, and [TO, LO, RE, LE] is converted to min Record the distance characteristic value of the worker point as the distance characteristic value, and establish a four-way distance analysis coordinate system to obtain the corresponding process analysis curve based on the distance characteristic value; mark the process stage points in the process analysis curve, where the process stage points are the points where the minimum values ​​of TO, LO, RE and LE change when the process analysis curve is drawn;

[0087] Step S108 , obtaining the process phase points corresponding to all project workers in all visualized projects KX and the cross-domain phase points of project workers whose construction areas are partially within the site area.

[0088] Step S2: Integrate the construction visualization model with the construction schedule software, and record the resulting model as the construction schedule model; obtain the points to be optimized for project workers based on the process stage points, cross-domain stage points, and the construction schedule model;

[0089] Step S2 includes: step S201, integrating the construction visualization model with the construction progress planning software, and recording the obtained model as the construction progress model;

[0090] Step S202: Simulate all construction projects in sequence using the construction progress model; for any visualization project KX during the simulation c Any project worker in: Based on the method for obtaining the process analysis curve of the project worker, obtain the process analysis curve again when simulating the construction progress model, and record the process analysis curve obtained at this time as the contradiction comparison curve;

[0091] Step S203: Place the process analysis curve and the contradiction comparison curve into the same four-way distance analysis coordinate system, and use the coincidence comparison algorithm to obtain the contradiction threshold corresponding to the project worker. The coincidence comparison algorithm is: Among them, F is the contradiction threshold, f jc is the number of process stage points in the area of ​​the process analysis curve that does not overlap with the contradiction comparison curve, f sum is the number of process stage points in the process analysis curve, f ky It is the number of cross-domain stage points in the process analysis curve that does not overlap with the contradiction comparison curve;

[0092] Step S203: When the contradiction threshold is 0 and f ky When it is 0, no optimization point is set for the project worker;

[0093] Step S204: When the contradiction threshold is 0 and f ky When it is not 0, all process stage points and cross-domain stage points of the project worker are recorded as the project worker's points to be optimized;

[0094] Step S205: When the contradiction threshold is less than 0 and greater than -1, the process stage points in the area of ​​the process analysis curve that does not overlap with the contradiction comparison curve and the cross-domain stage points of the project worker are recorded as points to be optimized for the project worker;

[0095] Step S206: When the contradiction threshold is equal to -1, the cross-domain stage point of the project worker is recorded as the point to be optimized of the project worker;

[0096] Step S207: When the contradiction threshold is less than -1, the process stage points in the area of ​​the process analysis curve that do not overlap with the contradiction comparison curve and the cross-domain stage points of the project worker are recorded as points to be optimized for the project worker;

[0097] Step S208 , when the contradiction threshold is less than 1 and greater than 0, the process stage points in the area of ​​the process analysis curve that do not overlap with the contradiction comparison curve are recorded as points to be optimized for the project worker;

[0098] Step S209 , when the contradiction threshold is equal to 1, all process stage points of the project worker are recorded as points to be optimized for the project worker;

[0099] Get the points to be optimized corresponding to all project workers.

[0100] Step S3, building a collaboration platform based on cloud computing, and sharing the construction visualization model, construction progress model and points to be optimized in real time; Step S3 includes: building a collaboration platform based on cloud computing, and storing the construction visualization model, construction progress model and points to be optimized of all project workers in the collaboration platform; when the construction project starts and the real-time progress of the construction project coincides with the point to be optimized of any project worker, real-time monitoring of the project workers corresponding to the point to be optimized that coincides with the real-time progress is carried out.

[0101] Example 3, please refer to Figure 5 As shown, Figure 5The present invention provides a structural schematic diagram of an electronic device, which may include a processor, a communication interface, a memory, and a communication bus, wherein the processor, the communication interface, and the memory communicate with each other via the communication bus. The memory stores computer-readable instructions, and the processor can call the instructions in the memory. When the computer-readable instructions are executed by the processor, the steps of a construction project visualization management method based on BIM simulation are executed to achieve the following functions: first, a construction visualization model is built using BIM based on design drawings, engineering parameters, and construction plans; a scene simulation is performed in the construction visualization model based on the construction sequence, and the process stage points and cross-domain stage points of project workers in the construction project are obtained based on the results of the scene simulation; then, the construction visualization model is integrated with construction schedule software, and the resulting model is recorded as a construction schedule model; based on the process stage points, cross-domain stage points, and the construction schedule model, points to be optimized for project workers are obtained; finally, a collaboration platform is built based on cloud computing, and the construction visualization model, construction schedule model, and points to be optimized are shared in real time.

[0102] In addition, the logical instructions in the above-mentioned memory can be implemented in the form of a software functional unit and can be stored in a computer-readable storage medium when sold or used as an independent product. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art, or the part of the technical solution, can be embodied in the form of a software product, which is stored in a storage medium and includes several instructions for enabling a computer device (which can be a personal computer, a server, or a network device, etc.) to execute all or part of the steps of the method described in each embodiment of the present application. The aforementioned storage medium includes: various media that can store program codes, such as a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk.

[0103] Example 4. The present application also provides a computer-readable storage medium. The present application provides a storage medium on which a computer program is stored. When the computer program is executed by a processor, the steps in the construction project visualization management method based on BIM simulation are executed to achieve the following functions: first, based on the design drawings, engineering parameters and construction plans, a construction visualization model is built using BIM; based on the construction sequence, a scene simulation is performed in the construction visualization model, and based on the results of the scene simulation, the process stage points and cross-domain stage points of the project workers in the construction project are obtained; then, the construction visualization model is integrated with the construction schedule software, and the obtained model is recorded as a construction schedule model; based on the process stage points, cross-domain stage points and the construction schedule model, the points to be optimized of the project workers are obtained; finally, a collaboration platform is built based on cloud computing, and the construction visualization model, the construction schedule model and the points to be optimized are shared in real time.

[0104] Through the description of the above embodiments, the embodiments of the present invention can be provided as methods, systems or computer program products. Based on this understanding, the above technical solutions, in essence or in other words, the part that contributes to the prior art, can be embodied in the form of a software product, which can be stored in a computer-readable storage medium, such as ROM / RAM, a magnetic disk, an optical disk, etc., and includes a number of instructions for enabling a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in each embodiment or certain parts of the embodiment.

[0105] In the embodiments provided in this application, it should be understood that the disclosed system or method can be implemented in other ways. The embodiments described above are merely illustrative. For example, the division of modules or units is only a logical function division. There may be other division methods in actual implementation. For example, multiple modules or units can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some communication interfaces, and the indirect coupling or communication connection of systems, modules and units can be electrical, mechanical or other forms.

[0106] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.

Claims

1. A construction project visualization management method based on BIM simulation, characterized in that: The steps include: Based on the design drawings, engineering parameters and construction plans, a three-dimensional model is built using BIM and recorded as a construction visualization model; scene simulation is performed in the construction visualization model based on the construction sequence, and the process stage points and cross-domain stage points of project workers in the construction project are obtained based on the results of the scene simulation; Integrate the construction visualization model with the construction schedule software, and record the obtained model as the construction schedule model; obtain the points to be optimized for project workers based on the process stage points, cross-domain stage points and the construction schedule model; A collaborative platform is built based on cloud computing, and construction visualization models, construction progress models and points to be optimized are shared in real time.

2. The method for visual management of construction projects based on BIM simulation according to claim 1, characterized in that: Based on the construction sequence, scenario simulation is performed in the construction visualization model, and based on the results of scenario simulation, the process stage points and cross-domain stage points of project workers in the construction project are obtained, including: A three-dimensional model is built in BIM based on design drawings, engineering parameters and construction plans, and recorded as a construction visualization model, where the construction plan includes construction projects and the construction site corresponding to each construction project; all construction projects are obtained based on the construction sequence in the construction plan, and all construction projects are recorded in order from visualization project KX1 to visualization project KX based on the construction time. n ; For any visualization project KX c , c is any one from 1 to n, the visualization project KX c The workers working in the corresponding construction site are recorded as project workers; a plane rectangular coordinate system is established, recorded as the site personnel analysis coordinate system, where the units of the X-axis and Y-axis of the site personnel analysis coordinate system are both m; the visualization project KX c The corresponding top view of the construction site is placed in the first quadrant of the site personnel analysis coordinate system and recorded as the site area; the points corresponding to the maximum and minimum values ​​of the vertical coordinates in the site area are recorded as upper reference points and lower reference points, respectively, and the points corresponding to the maximum and minimum values ​​of the horizontal coordinates in the site area are recorded as right reference points and left reference points, respectively.

3. The method for visual management of construction projects based on BIM simulation according to claim 2 is characterized in that: Based on the construction sequence, scenario simulation is performed in the construction visualization model, and based on the results of the scenario simulation, the process stage points and cross-domain stage points of the project workers in the construction project are obtained, which also include: For any project worker, based on the visual project KX c Get the construction area of ​​the project workers; when the construction area is completely within the site area, simulate the movement trajectory of the project workers in the site area based on the scene simulation, and record the point where the project workers are located in the scene simulation as the worker point; [TO, LO, RE, LE] max Recorded as the distance feature value of the worker point, where [TO, LO, RE, LE] max is the value corresponding to the maximum value among TO, LO, RE and LE, TO is the distance between the upper reference point and the worker point, LO is the distance between the lower reference point and the worker point, RE is the distance between the right reference point and the worker point, and LE is the distance between the left reference point and the worker point; A plane rectangular coordinate system is established, recorded as the four-way distance analysis coordinate system, where the unit of the X-axis of the four-way distance analysis coordinate system is time, and the unit of the Y-axis is m; based on the motion trajectory of the project worker in the simulation, [TO, LO, RE, LE] max The corresponding curve is drawn in the four-way distance analysis coordinate system, recorded as the process analysis curve, and the process stage points in the process analysis curve are marked, where the process stage points are the points where the maximum values ​​of TO, LO, RE and LE change when the process analysis curve is drawn.

4. The method for visual management of construction projects based on BIM simulation according to claim 3 is characterized in that: Based on the construction sequence, scenario simulation is performed in the construction visualization model, and based on the results of the scenario simulation, the process stage points and cross-domain stage points of the project workers in the construction project are obtained, which also include: When part of the construction area is within the site area, the area where the construction area overlaps with the site area is recorded as the inner application area, and the area where the construction area does not overlap with the site area is recorded as the outer application area; based on the scene simulation, the movement trajectory of the project workers in the site area is simulated, and a four-way distance analysis coordinate system is established to obtain the corresponding process analysis curve; the process stage points, outer application line segments and inner application line segments in the process analysis curve are marked, wherein the outer application line segments are the line segments corresponding to the project workers in the outer application area in the process analysis curve, and the inner application line segments are the line segments corresponding to the project workers in the inner application area in the process analysis curve; When there is a process stage point in the external application segment, the process stage point in the external application segment is recorded as the cross-domain stage point, and the cross-domain distance is recorded as 0; when there is no process stage point in the external application segment, the point in the internal application segment closest to the external application segment is recorded as the cross-domain stage point, and the cross-domain distance is recorded as the shortest distance between the cross-domain stage point and the external application segment.

5. The method for visual management of construction projects based on BIM simulation according to claim 4 is characterized in that: Based on the construction sequence, scenario simulation is performed in the construction visualization model, and based on the results of the scenario simulation, the process stage points and cross-domain stage points of the project workers in the construction project are obtained, which also include: When the construction area is completely outside the site area, the movement trajectory of the project workers outside the site area is simulated based on the scenario simulation, and [TO, LO, RE, LE] is converted into min Record as the distance characteristic value of the worker point, and establish a four-way distance analysis coordinate system to obtain the corresponding process analysis curve based on the distance characteristic value; mark the process stage points in the process analysis curve, where the process stage points are the points where the minimum values ​​of TO, LO, RE and LE are transformed when the process analysis curve is drawn; Obtain the process phase points corresponding to all project workers in all visualized projects KX and the cross-domain phase points of project workers whose construction areas are partially within the site area.

6. The method for visual management of construction projects based on BIM simulation according to claim 5 is characterized in that: The optimization points for project workers based on process phase points, cross-domain phase points and construction progress model include: Integrate the construction visualization model with the construction schedule software and record the resulting model as the construction schedule model; Use the construction progress model to simulate all construction projects in sequence; for any visualization project KX during the simulation c Any project worker in: Based on the method of obtaining the process analysis curve of the project worker, the process analysis curve is obtained again when the construction progress model is simulated, and the process analysis curve obtained at this time is recorded as a contradiction comparison curve; The process analysis curve and the contradiction comparison curve are placed in the same four-way distance analysis coordinate system, and the coincidence comparison algorithm is used to obtain the contradiction threshold corresponding to the project workers. The coincidence comparison algorithm is: Among them, F is the contradiction threshold, f jc is the number of process stage points in the area of ​​the process analysis curve that does not overlap with the contradiction comparison curve, f sum is the number of process stage points in the process analysis curve, f ky It is the number of cross-domain stage points in the area of ​​the process analysis curve that does not overlap with the contradiction comparison curve.

7. The method for visual management of construction projects based on BIM simulation according to claim 6 is characterized in that: The optimization points for obtaining project workers based on process phase points, cross-domain phase points and construction progress models also include: When the contradiction threshold is 0 and f ky When it is 0, no optimization point is set for the project worker; When the contradiction threshold is 0 and f ky When it is not 0, all process stage points and cross-domain stage points of the project worker are recorded as the points to be optimized of the project worker; When the contradiction threshold is less than 0 and greater than -1, the process stage points in the process analysis curve that do not overlap with the contradiction comparison curve and the cross-domain stage points of the project workers are recorded as the points to be optimized of the project workers; When the contradiction threshold is equal to -1, the cross-domain stage point of the project worker is recorded as the point to be optimized of the project worker; When the contradiction threshold is less than -1, the process stage points in the process analysis curve that are not overlapped with the contradiction comparison curve and the cross-domain stage points of the project workers are recorded as the points to be optimized of the project workers; When the contradiction threshold is less than 1 and greater than 0, the process stage points in the process analysis curve that do not overlap with the contradiction comparison curve are recorded as the points to be optimized for the project workers; When the contradiction threshold is equal to 1, all process stage points of the project worker are recorded as the project worker's points to be optimized; Get the points to be optimized corresponding to all project workers.

8. The method for visual management of construction projects based on BIM simulation according to claim 7 is characterized in that: Building a collaborative platform based on cloud computing and sharing the construction visualization model, construction progress model and points to be optimized in real time include: A collaboration platform is built based on cloud computing, and the construction visualization model, construction progress model and the points to be optimized of all project workers are stored in the collaboration platform; when the construction project starts and the real-time progress of the construction project coincides with the point to be optimized of any project worker, the project workers corresponding to the point to be optimized that coincides with the real-time progress are monitored in real time.

9. A construction project visualization management platform based on BIM simulation, used to implement the construction project visualization management method based on BIM simulation according to any one of claims 1 to 8, characterized in that: It includes worker phase analysis module, construction conflict analysis module and optimization sharing module; The worker phase analysis module is used to build a three-dimensional model based on design drawings, engineering parameters and construction plans using BIM, and record it as a construction visualization model; perform scene simulation in the construction visualization model based on the construction sequence, and obtain the process phase points and cross-domain phase points of project workers in the construction project based on the results of the scene simulation; The construction conflict analysis module is used to integrate the construction visualization model with the construction schedule software, and record the obtained model as the construction schedule model; based on the process stage points, cross-domain stage points and the construction schedule model, the points to be optimized for the project workers are obtained; The optimization sharing module is used to build a collaborative platform based on cloud computing, and to share the construction visualization model, construction progress model and points to be optimized in real time.

10. A storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 8 are executed.