Construction stage structure safety assessment method and equipment

By applying BIM and artificial intelligence technology in the construction stage, dynamically assessing the safety of the structure in the construction stage, the problem of missing structural safety analysis in the construction stage is solved, real-time prediction of the probability of structural failure is achieved, and construction safety and structural stability are ensured.

CN119830419APending Publication Date: 2025-04-15SHANGHAI CONSTRUCTION FOURTH CONSTRUCTION GROUP CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202510012692.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-06
Publication Date
2025-04-15

AI Technical Summary

Technical Problem

During the construction process, the safety analysis of the structure in the construction stage is missing, which makes it difficult to predict and respond to natural disasters, increasing the risk of safety accidents.

Method used

A construction stage structure safety evaluation method based on BIM and artificial intelligence technology is adopted. Through the construction status acquisition system, natural disaster information acquisition system and construction progress acquisition system, the construction stage structural model is dynamically predicted, and the limited unit software is used for safety analysis.

Benefits of technology

Real-time prediction of the structural failure probability of the construction stage is achieved, ensuring the safety of the construction process and the stability of the structure, preventing safety accidents caused by natural disasters, and ensuring the safety of personnel and property on the construction site.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119830419A_ABST
    Figure CN119830419A_ABST
Patent Text Reader

Abstract

The invention provides a construction stage structure safety assessment method and equipment, and aims to solve the problem of lack of construction stage structure safety analysis. The method comprises the following steps: obtaining a site construction state through a construction state acquisition system, and predicting the occurrence time of a natural disaster through a natural disaster information acquisition system; and predicting a corresponding construction progress when the natural disaster occurs through a construction progress acquisition system, calling the structure design model, outputting a corresponding construction stage structure model when the natural disaster occurs, and performing safety assessment on the structure at the moment. Based on the BIM and artificial intelligence technology, the structure failure probability in the construction stage is predicted in real time, so that the safety of the construction process and the stability of the structure are ensured, safety accidents possibly caused by force majeure factors are prevented, and the safety of construction site personnel and property is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a method and equipment for evaluating structural safety in a construction phase. Background Art

[0002] During the construction process, especially during the structural construction stage, since the integrity of the building structure has not yet been fully formed, its ability to resist external disturbances is relatively weak. During this period, if it encounters natural disasters such as strong winds, heavy rains, earthquakes, etc., the building structure may face safety risks, which can easily lead to safety accidents. However, the structure is always changing dynamically during the construction stage, and designers often only perform earthquake and wind resistance calculations on the final state of the building structure, and there is almost no safety analysis of the structure at each stage of construction in the above-mentioned natural disasters. Summary of the invention

[0003] The purpose of the present invention is to provide a method and device for evaluating the safety of a structure during construction.

[0004] In order to solve the above problems, the present invention provides a method for evaluating the safety of a structure during construction, comprising:

[0005] The construction status acquisition system identifies the image and video data of the on-site construction site and exports the on-site construction status information to the construction progress acquisition system;

[0006] The natural disaster information collection system collects real-time warning information issued by the Meteorological Bureau and the Earthquake Bureau, and combines it with map information to predict the time and extent of impact of extreme weather or natural disasters on the construction site;

[0007] The construction progress collection system dynamically predicts the construction progress on site when extreme weather or natural disasters occur based on the project department's construction progress plan, site conditions, emergency factors and construction status information;

[0008] The BIM model synchronization module converts the structural design model into a construction phase structural model corresponding to the time of impact of natural disasters on the construction site based on the information transmitted by the natural disaster information collection system and the construction progress collection system and in combination with the structural design model;

[0009] The safety assessment module uses finite element software to perform safety analysis on the structural model of the construction phase.

[0010] Furthermore, in the above method, the construction status acquisition system identifies the image and video data of the on-site construction site and derives the on-site construction status information, including:

[0011] The construction status acquisition system is based on CNN or RNN machine learning technology to identify the image and video data of the on-site construction site and export the on-site construction status information to the construction progress acquisition system.

[0012] Furthermore, in the above method, before the construction status acquisition system recognizes the image and video data of the on-site construction site, it also includes:

[0013] Visual monitoring equipment using high-definition cameras, drones and laser scanners are installed at the construction site to capture images and video data of the construction site in real time.

[0014] Furthermore, in the above method, the on-site construction status information includes: the number of planar components installed on each floor and the connection status of the components.

[0015] Furthermore, in the above method, the site conditions include: the current status of construction personnel, machinery and materials.

[0016] Furthermore, in the above method, the emergencies include: design changes, material supply delays, bad weather and safety and quality accidents.

[0017] Furthermore, in the above method, the safety assessment module uses finite element software to perform safety analysis on the structural model in the construction phase, including:

[0018] The safety assessment module uses finite element software to perform safety analysis on the structural model of the construction phase.

[0019] Furthermore, in the above method, the safety assessment module uses finite element software to perform safety analysis on the structural model in the construction phase, including:

[0020] When the natural disasters are typhoons and rainstorms, the safety assessment module conducts wind resistance analysis on the structural model during the construction phase;

[0021] When the natural disaster is an earthquake, the safety assessment module performs seismic analysis on the structural model during the construction phase;

[0022] When the natural disasters occur in the form of extremely high temperatures or severe cold, the safety assessment module conducts temperature response analysis on the structural model during the construction phase.

[0023] According to another aspect of the present invention, there is further provided a computer-readable storage medium having computer-executable instructions stored thereon, wherein when the computer-executable instructions are executed by a processor, the processor is caused to: adopt any of the methods described above.

[0024] According to another aspect of the present invention, there is also provided a computer device, comprising:

[0025] Processor; and

[0026] A memory arranged to store computer executable instructions which, when executed, cause the processor to: employ a method as described in any one of the above.

[0027] In summary, in order to solve the problem of lack of structural safety analysis in the construction phase, the present invention proposes a new method for evaluating the structural safety in the construction phase based on BIM and artificial intelligence technology. The on-site construction status is acquired through a construction status acquisition system, and the time of occurrence of natural disasters is predicted through a natural disaster information acquisition system. The construction progress corresponding to the occurrence of natural disasters is predicted through a construction progress acquisition system. At the same time, the structural design model is retrieved, and the construction phase structural model corresponding to the occurrence of natural disasters is output to perform a safety assessment on the structure at this time.

[0028] The present invention is based on BIM and artificial intelligence technology to achieve real-time prediction of the probability of structural failure during the construction phase, so as to ensure the safety of the construction process and the stability of the structure, prevent safety accidents that may be caused by force majeure factors, and protect the safety of personnel and property at the construction site.

[0029] Compared with the current structural safety analysis in the construction stage, the beneficial effects of the present invention are mainly as follows:

[0030] (1) Strong real-time performance. The present invention provides a construction phase structural safety assessment method based on BIM and artificial intelligence technology, which can automatically collect on-site progress and dynamically adjust the construction phase model based on the collected progress plan, extreme weather, natural disasters and other information;

[0031] (2) Targeting strong. The construction phase lasts for a long time. If modeling and calculation are performed for each phase, a lot of manpower and material resources will be required. This method only analyzes the construction phase model when extreme weather and natural disasters may occur, which greatly saves computing resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 It is a flow chart of a method for evaluating structural safety during construction phase according to an embodiment of the present invention. DETAILED DESCRIPTION

[0033] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0034] like Figure 1 As shown, the present invention provides a method for evaluating the safety of a structure in a construction phase, comprising:

[0035] Step S1, the construction status acquisition system identifies the image and video data of the on-site construction site and exports the on-site construction status information to the construction progress acquisition system;

[0036] Preferably, the construction status acquisition system recognizes the image and video data of the on-site construction site based on machine learning technologies such as CNN and RNN, and exports the on-site construction status information to the construction progress acquisition system;

[0037] Preferably, visual monitoring equipment such as high-definition cameras, drones, laser scanners, etc. can be installed at the construction site to capture images and video data of the construction site in real time;

[0038] More preferably, the on-site construction status information includes: the number of plane components installed on each floor and the connection status of the components;

[0039] Step S2, the natural disaster information collection system collects real-time warning information issued by the Meteorological Bureau and the Earthquake Bureau, and combines it with map information to predict the time and extent of impact of extreme weather or natural disasters on the construction site;

[0040] Step S3, the construction progress collection system dynamically predicts the construction progress on site when extreme weather or natural disasters occur based on the project department's construction progress plan, site conditions, factors of emergencies, and construction status information;

[0041] Preferably, the site conditions include: the current status of construction personnel, machinery and materials;

[0042] The emergencies include but are not limited to: design changes, material supply delays, bad weather and safety and quality accidents;

[0043] Step S4, the BIM model synchronization module converts the structural design model into a construction phase structural model corresponding to the time of impact of natural disasters on the construction site based on the information transmitted by the natural disaster information collection system and the construction progress collection system, in combination with the structural design model, so as to establish a construction phase structural model corresponding to the occurrence of extreme weather or natural disasters;

[0044] Step S5, the safety assessment module uses finite element software to perform safety analysis on the structural model in the construction phase;

[0045] Preferably, the safety assessment module uses finite element software to perform safety analysis on the construction stage structural model, including:

[0046] The safety assessment module performs load analysis based on the impact degree predicted by the natural disaster information collection system;

[0047] When the natural disasters are typhoons and rainstorms, the safety assessment module conducts wind resistance analysis on the structural model during the construction phase;

[0048] When the natural disaster is an earthquake, the safety assessment module performs seismic analysis on the structural model during the construction phase;

[0049] When the natural disasters occur in the form of extremely high temperatures or severe cold, the safety assessment module conducts temperature response analysis on the structural model during the construction phase.

[0050] According to another aspect of the present invention, there is further provided a computer-readable storage medium having computer-executable instructions stored thereon, wherein when the computer-executable instructions are executed by a processor, the processor is caused to: adopt any of the methods described above.

[0051] According to another aspect of the present invention, there is also provided a computer device, comprising:

[0052] Processor; and

[0053] A memory arranged to store computer executable instructions which, when executed, cause the processor to: employ a method as described in any one of the above.

[0054] In summary, in order to solve the problem of lack of structural safety analysis in the construction phase mentioned above, the present invention proposes a new method for evaluating the structural safety in the construction phase based on BIM and artificial intelligence technology. The on-site construction status is acquired through a construction status acquisition system, and the time of occurrence of natural disasters is predicted through a natural disaster information acquisition system. The construction progress corresponding to the occurrence of natural disasters is predicted through a construction progress acquisition system. At the same time, the structural design model is retrieved, and the construction phase structural model corresponding to the occurrence of natural disasters is output to perform a safety assessment on the structure at this time.

[0055] The present invention is based on BIM and artificial intelligence technology to achieve real-time prediction of the probability of structural failure during the construction phase, so as to ensure the safety of the construction process and the stability of the structure, prevent safety accidents that may be caused by force majeure factors, and protect the safety of personnel and property at the construction site.

[0056] Compared with the current structural safety analysis in the construction stage, the beneficial effects of the present invention are mainly as follows:

[0057] (1) Strong real-time performance. The present invention provides a construction phase structural safety assessment method based on BIM and artificial intelligence technology, which can automatically collect on-site progress and dynamically adjust the construction phase model based on the collected progress plan, extreme weather, natural disasters and other information;

[0058] (2) Targeting strong. The construction phase lasts for a long time. If modeling and calculation are performed for each phase, a lot of manpower and material resources will be required. This method only analyzes the construction phase model when extreme weather and natural disasters may occur, which greatly saves computing resources.

[0059] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0060] Professionals may further appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, computer software, or a combination of the two. In order to clearly illustrate the interchangeability of hardware and software, the composition and steps of each example have been generally described in the above description according to function. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professionals and technicians may use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.

[0061] Obviously, those skilled in the art can make various changes and modifications to the invention without departing from the spirit and scope of the invention. Thus, if these modifications and variations of the invention fall within the scope of the claims of the invention and their equivalents, the invention is also intended to include these modifications and variations.

Claims

1. A method for evaluating the safety of a structure during construction, characterized in that: include: The construction status acquisition system identifies the image and video data of the on-site construction site and exports the on-site construction status information to the construction progress acquisition system; The natural disaster information collection system collects real-time warning information issued by the Meteorological Bureau and the Earthquake Bureau, and combines it with map information to predict the time and extent of impact of extreme weather or natural disasters on the construction site; The construction progress collection system dynamically predicts the construction progress on site when extreme weather or natural disasters occur based on the project department's construction progress plan, site conditions, emergency factors and construction status information; The BIM model synchronization module converts the structural design model into a construction phase structural model corresponding to the time of impact of natural disasters on the construction site based on the information transmitted by the natural disaster information collection system and the construction progress collection system and in combination with the structural design model; The safety assessment module uses finite element software to perform safety analysis on the structural model of the construction phase.

2. The construction phase structural safety assessment method according to claim 1, characterized in that: The construction status acquisition system identifies the image and video data of the on-site construction site and exports the on-site construction status information to the construction progress acquisition system, including: The construction status acquisition system is based on CNN or RNN machine learning technology to identify the image and video data of the on-site construction site and export the on-site construction status information to the construction progress acquisition system.

3. The construction phase structural safety assessment method according to claim 1, characterized in that: Before the construction status acquisition system recognizes the image and video data of the on-site construction site, it also includes: Visual monitoring equipment using high-definition cameras, drones and laser scanners are installed at the construction site to capture images and video data of the construction site in real time.

4. The construction phase structural safety assessment method according to claim 1, characterized in that: The on-site construction status information includes: the number of plane components installed on each floor and the connection status of the components.

5. The construction phase structural safety assessment method according to claim 1, characterized in that: The site conditions include: the current status of construction personnel, machinery and equipment, and materials.

6. The method for evaluating structural safety during construction as claimed in claim 1, characterized in that: The emergencies include: design changes, material supply delays, bad weather and safety and quality accidents.

7. The construction phase structural safety assessment method according to claim 1, characterized in that: The safety assessment module uses finite element software to perform safety analysis on the structural model of the construction phase, including: The safety assessment module uses finite element software to perform safety analysis on the structural model of the construction phase.

8. The construction phase structural safety assessment method according to claim 1, characterized in that: The safety assessment module uses finite element software to perform safety analysis on the structural model of the construction phase, including: When the natural disasters are typhoons and rainstorms, the safety assessment module conducts wind resistance analysis on the structural model during the construction phase; When the natural disaster is an earthquake, the safety assessment module performs seismic analysis on the structural model during the construction phase; When the natural disasters occur in the form of extremely high temperatures or severe cold, the safety assessment module conducts temperature response analysis on the structural model during the construction phase.

9. A computer-readable storage medium having computer-executable instructions stored thereon, wherein: When the computer executable instructions are executed by a processor, the processor is caused to: adopt the method according to any one of claims 1 to 8.

10. A computer device, wherein: include: processor; as well as A memory arranged to store computer executable instructions which, when executed, cause the processor to: employ a method as claimed in any one of claims 1 to 8.

Citation Information

Patent Citations

  • Bridge construction and maintenance whole-process intelligent monitoring, assessment, alarming and decision-making system and method

    CN108460231A

  • Device for controlling, monitoring and visualizing construction sites

    CN111183440A

  • BIM-based power transmission and transformation project refined construction management method

    CN114565312A

  • Bridge construction process safety monitoring system based on unmanned aerial vehicle image

    CN115659673A

  • Construction method and system for foundation pit support based on BIM and storage medium

    CN118278090A