Production technology of non-prestressed steel cylinder concrete pipe jacking construction pipeline based on laser positioning

Through laser positioning and transmission mechanism-driven pipeline transportation device, the problem of safety risks of artificial lifting of concrete pipelines is solved, and stable feeding and automated construction are achieved.

CN119957727BActive Publication Date: 2025-08-08YUNNAN CHUXIONG HENDERSON PIPELINE IND CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202510129247.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-02-05
Publication Date
2025-08-08
Estimated Expiration
2045-02-05

AI Technical Summary

Technical Problem

The laying of existing concrete pipelines requires manual lifting, which poses safety risks and is inefficient.

Method used

The non-prestressed steel cylinder concrete pipe ejection construction process based on laser positioning is adopted, and the pipeline transportation device and transmission mechanism are used to drive the concrete pipe body into the conveying mechanism through the cylinder, and cooperate with the support frame and limit baffle to ensure stable downward of the pipeline and reduce manual intervention.

Benefits of technology

It is realized that concrete pipes can be stably sent below the tunnel without lifting equipment, reducing safety hazards, improving the degree of automation, and reducing additional equipment investment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119957727B_ABST
    Figure CN119957727B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of pipe jacking equipment, and more specifically, to a production process for jacking non-prestressed steel cylinder concrete pipes based on laser positioning. A pipe jacking machine is used to complete the jacking construction of the concrete pipe body, and a pipe transport device is used to sequentially transport the concrete pipe body above the tunnel into the interior of the working tunnel. This laser-based production process for jacking non-prestressed steel cylinder concrete pipes, by placing a conveying mechanism for vertically transporting the concrete pipe in the working tunnel, allows the concrete pipe to be transported to the bottom of the working tunnel without the need for lifting equipment. Furthermore, a support frame and a limit baffle are used to limit the downward movement of the concrete pipe, thereby ensuring the stability of the concrete pipe during lowering and reducing safety hazards during pipe lowering.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pipe jacking construction equipment, in particular to a production process for a non-prestressed steel cylinder concrete pipe jacking construction pipeline based on laser positioning. Background Art

[0002] Pipe jacking is a trenchless method for laying underground pipelines. Pipe jacking equipment is used in a working pit to push the pipeline into the soil according to the designed slope. It is suitable for crossing complex environments such as roads, railways, and rivers, avoiding large-scale excavation. It has the advantages of high construction efficiency, little impact on ground traffic, and environmental protection and economy. It is widely used in urban water supply and drainage, gas, electricity, communications and other pipeline projects.

[0003] The patent with application number CN201610211700.4 discloses a mud and water pipe jacking machine test device, including a reaction frame and a cylinder support frame. The cylinder support frame is provided with a support guide rail. The pipe jacking machine support and the pressure-bearing device cooperate with the support guide rail. The jacking shoe and the reaction frame are connected. The pipe jacking machine support includes a load-bearing platform. The bottom of the load-bearing platform is provided with a load-bearing roller. The lower part of the sliding support block is arranged in the slide rail at the top of the load-bearing platform, and the upper part of the sliding support block is connected to the support seat; the pressure-bearing device includes a pressure-bearing cylinder fixed on the cylinder support frame, and the pressure-bearing cylinder is provided with a tunnel door water-stop seal.

[0004] However, in current concrete pipe laying operations, when the pipe needs to be delivered to the bottom of the working tunnel, it is usually necessary to rely on manual operation of the lifting structure above the tunnel. Specifically, the workers need to use wire ropes to firmly fix the pipe and then slowly deliver it to the bottom of the tunnel. At the same time, there are also workers below the tunnel responsible for operating the pipe jacking machine. After the pipe is lowered to the predetermined position, the workers below need to manually disconnect the wire rope. This process not only involves a lot of manual intervention, but also poses significant safety risks.

[0005] In view of this, we propose a production process for non-prestressed steel cylinder concrete pipe jacking construction pipeline based on laser positioning. Summary of the Invention

[0006] The purpose of the present invention is to provide a production process for non-prestressed steel cylinder concrete pipe jacking construction pipeline based on laser positioning to solve the problems raised in the above background technology.

[0007] To achieve the above object, the present invention provides the following technical solutions:

[0008] The production process of non-prestressed steel cylinder concrete pipe jacking construction pipeline based on laser positioning includes the following steps:

[0009] S1. First, the operator in the working pit places the concrete pipe on the transport track outside the pipeline transport device and starts the cylinder in the drive mechanism;

[0010] S2. After the cylinder is started, it drives the connecting frame to move toward the fixing mechanism, and pushes the concrete pipe into the interior of the conveying mechanism through the top ring, so that the concrete pipe is placed above a set of load-bearing parts;

[0011] S3. Then, the telescopic rod of the control cylinder is retracted, thereby driving the connecting frame to move away from the fixing mechanism, thereby driving the movable bracket and the fixed tooth plate to move together;

[0012] S4, when the fixed tooth plate moves, it contacts the docking gear in the outer sleeve, driving the outer sleeve ring body to rotate, and the pawls on the inner ring wall come into conflict with the ratchet;

[0013] S4. Subsequently, the ratchet wheel rotates, driving the transmission shaft and the worm to rotate, and further driving the worm wheel and the connecting shaft to rotate;

[0014] S5. When the connecting shaft rotates, it drives the rotating shaft to rotate, and the transmission chain plate drives the transmission chain to move, thereby causing a group of load-bearing parts where the concrete pipe body is placed to move downward along with the transmission chain;

[0015] S6. Repeatedly controlling the extension and retraction of the telescopic rod of the cylinder to sequentially deliver the multiple concrete pipes into the interior of the pipeline transport device until the lowest concrete pipe moves above the fixed guide rail;

[0016] S7. Then, the delivery position of the concrete pipe body is confirmed according to the laser positioning instrument installed on the internal bracket of the pipe jacking machine. After the elevation of the pipe jacking is determined, the pipe jacking machine is started to insert the concrete pipe body into the soil layer of the tunnel;

[0017] S8. Subsequently, repeat the above operation to sequentially insert multiple concrete pipes into the soil layer of the tunnel until the pipe at the end is pushed out from another tunnel;

[0018] The above steps use a pipe jacking machine to complete the jacking construction of the concrete pipe body, and cooperate with the pipeline transportation device to sequentially deliver the concrete pipe body above the tunnel into the interior of the working tunnel;

[0019] The pipeline transportation device includes a fixing mechanism, a conveying mechanism arranged inside the fixing mechanism, a driving mechanism arranged outside the fixing mechanism, and a transmission mechanism for driving the internal structure of the conveying mechanism to move;

[0020] The fixing mechanism includes a fixed base plate, two symmetrically arranged support frames, two parallel limit baffles, and a fixed guide rail arranged between the two support frames;

[0021] The conveying mechanism includes two rotating shafts arranged in parallel up and down, driving chain discs arranged at the ends of the rotating shafts, a driving chain sleeved outside the two driving chain discs, and a number of bearing parts regularly distributed between the two driving chains.

[0022] The bearing part includes two connecting brackets arranged in parallel, a connecting rod arranged between the two connecting brackets, two limiting bumps arranged on the outer side walls of the connecting rod in parallel, a rotating ring sleeved outside the connecting rod, and a limiting block moving together with the rotating ring.

[0023] The driving mechanism includes a connecting frame, a top ring and a fixed toothed plate moving together with the connecting frame.

[0024] The transmission mechanism includes an outer casing, two worm wheels arranged in parallel, a transmission shaft for driving the worm wheels to rotate, a ratchet wheel arranged at the end of the transmission shaft, and an outer sleeve part sleeved outside the ratchet wheel.

[0025] The outer sleeve part includes an outer sleeve ring, a number of pawls regularly distributed on the inner circumferential wall of the outer sleeve ring, and a docking gear sleeved on the outer side wall of the outer sleeve ring.

[0026] In the technical solution of the present invention, the pipe jacking machine is placed on the inner bottom surface of the working pit. A fixed top plate is arranged in parallel above the fixed bottom plate. The upper and lower ends of the support frame are respectively fixedly connected to the fixed top plate and the fixed bottom plate by bolts. The transverse section of the support frame is in a C shape and two parallel frame wall through grooves are provided on the inner side wall. The limiting baffle is welded and fixed on the outer side wall of the support frame.

[0027] In the technical solution of the present invention, the fixed guide rail includes a reinforced bottom plate fixed to the inner side walls of the two support frames by bolts at both ends, a number of outer sleeve brackets fixed to the top surface of the reinforced bottom plate by bolts regularly, and a guide pulley rotatably connected inside the outer sleeve brackets.

[0028] In the technical solution of the present invention, the two ends of the rotating shaft are rotatably connected to the outer side walls on both sides of the support frame. The driving chain disc is fixedly connected to the outer side wall of the rotating shaft by a pin. A protective frame is sleeved outside the driving chain. The protective frame is fixedly connected to the inner side wall of the support frame by bolts.

[0029] In the technical solution of the present invention, the connecting bracket is fixedly connected to the outside of the driving chain by a pin. The two ends of the connecting rod are welded and fixed between the two connecting brackets. The limiting bump is integrally formed with the connecting rod. The rotating ring is rotatably connected to the outside of the connecting rod. The limiting block is welded and fixed to the outer side wall of the rotating ring.

[0030] In the technical solution of the present invention, a cylinder is provided on the outside of the connecting frame, the telescopic rod of the cylinder is fixedly connected to the outer side wall of the connecting frame cross bar by bolts, and a fixing rod is fixedly connected between the top ring and the connecting frame by bolts.

[0031] In the technical solution of the present invention, a movable bracket is fixedly connected to the outer side wall of the top cross bar of the connecting frame by bolts, and the fixed tooth plates are welded and fixed to the outer side walls on both sides of the movable bracket.

[0032] In the technical solution of the present invention, the outer sleeve frame is fixedly connected to the outer wall of the support frame by bolts, and the inner side of the worm gear is fixedly connected with a connecting shaft. One end of the connecting shaft is rotatably connected to the inner wall of the outer sleeve frame, and the other end is fixedly connected to the rotating shaft located above by a pin.

[0033] In the technical solution of the present invention, the upper and lower ends of the transmission shaft are rotatably connected to the outer side walls of the upper and lower sides of the outer casing frame, and a worm engaged with the worm wheel is sleeved on the outer side wall of the transmission shaft, and the ratchet is fixedly connected to the end position of the transmission shaft by a pin.

[0034] In the technical solution of the present invention, the outer collar body is rotatably connected to the top surface of the outer frame body, the pawl is rotatably connected to the groove on the inner ring wall of the outer collar body, and the docking gear is clamped and fixed to the outer wall of the outer collar body.

[0035] Compared with the prior art, the present invention has the following beneficial effects:

[0036] 1. This laser-based positioning-based production process for non-prestressed steel cylinder concrete pipe jacking construction pipelines places a conveying mechanism for vertically transporting concrete pipes in the working tunnel, allowing the concrete pipes to be delivered to the bottom of the working tunnel without the need for lifting equipment. In combination with a support frame and limit baffles to restrict the downward movement of the concrete pipes, this ensures the stability of the concrete pipes during lowering, reducing safety hazards during pipeline lowering.

[0037] 2. This laser-based production process for jacking non-prestressed concrete cylinder pipes for construction is based on a process in which the cylinder in the drive mechanism drives the jacking ring to deliver the concrete pipe into the conveying mechanism. During the contraction of the telescopic rod, the fixed tooth plate cooperates with the transmission mechanism to drive the movement of the entire conveying mechanism, thereby improving the automation of the overall structure while reducing the investment in additional drive equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0039] Figure 2 It is a structural schematic diagram of the pipeline transportation device in the present invention;

[0040] Figure 3 It is a structural schematic diagram of the fixing mechanism in the present invention;

[0041] Figure 4 Schematic diagram of the structure of the fixed guide rail in the present invention;

[0042] Figure 5 It is a structural schematic diagram of the conveying mechanism in the present invention;

[0043] Figure 6 For the present invention Figure 5 A magnified schematic diagram of part A;

[0044] Figure 7 Schematic diagram of the structure of the load-bearing part of the present invention;

[0045] Figure 8 Schematic diagram of the structure of the driving mechanism of the present invention;

[0046] Figure 9 Schematic diagram of the structure of the transmission mechanism of the present invention;

[0047] Figure 10 Schematic diagram of the structure of the outer jacket of the present invention;

[0048] Description of reference numerals:

[0049] 100. Pipe jacking machine;

[0050] 200, pipeline transport device; 210, fixing mechanism; 211, fixed bottom plate; 212, fixed top plate; 213, support frame; 2130, frame wall groove; 214, limit baffle; 215, fixed guide rail; 2150, reinforced bottom plate; 2151, outer cover bracket; 2152, guide pulley; 220, conveying mechanism; 221, rotating shaft; 222, transmission chain plate; 223, transmission chain; 224, protective frame; 225, load-bearing part; 2250, connecting bracket; 2251, connecting rod; 2 252. Limiting protrusion; 2253. Rotating ring body; 2254. Limiting block; 230. Driving mechanism; 231. Connecting frame; 232. Top ring; 233. Fixed rod; 234. Cylinder; 235. Moving bracket; 236. Fixed tooth plate; 240. Transmission mechanism; 241. Outer jacket frame; 242. Worm gear; 243. Connecting shaft; 244. Transmission shaft; 245. Worm; 246. Ratchet; 247. Outer jacket; 2470. Outer jacket ring body; 2472. Ratchet; 2471. Docking gear. DETAILED DESCRIPTION

[0051] The following will provide a clear and complete description of the technical solutions of the present invention in conjunction with the accompanying drawings. Obviously, the embodiments described are only some of the embodiments of the present invention, not all of them. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without making any creative efforts shall fall within the scope of protection of the present invention.

[0052] See also Figures 1-10 As shown, this embodiment provides a technical solution:

[0053] The production process of non-prestressed steel cylinder concrete pipe jacking construction pipeline based on laser positioning includes the following steps:

[0054] S1. First, the operator at the working pit places the concrete pipe body on the transport track outside the pipeline transport device 200 and starts the cylinder 234 in the driving mechanism 230;

[0055] S2. After the cylinder 234 is activated, it drives the connecting frame 231 to move toward the fixing mechanism 210, and pushes the concrete pipe into the interior of the conveying mechanism 220 through the top ring 232, so that the concrete pipe is placed above a set of bearing parts 225;

[0056] S3. Next, the telescopic rod of the control cylinder 234 is retracted, thereby driving the connecting frame 231 to move away from the fixing mechanism 210, thereby driving the movable bracket 235 and the fixed tooth plate 236 to move together;

[0057] S4: When the fixed tooth plate 236 moves, it contacts the docking gear 2471 in the outer sleeve 247, driving the outer ring body 2470 to rotate, and the pawls 2472 on the inner ring wall come into contact with the ratchet 246;

[0058] S4. Subsequently, the ratchet 246 rotates, driving the transmission shaft 244 and the worm 245 to rotate, and further driving the worm wheel 242 and the connecting shaft 243 to rotate;

[0059] S5. As the connecting shaft 243 rotates, it drives the rotating shaft 221 to rotate, and the transmission chain plate 222 drives the transmission chain 223 to move, thereby causing the group of bearing parts 225 on which the concrete pipe body is placed to move downward along with the transmission chain 223;

[0060] S6. Repeatedly control the extension and retraction of the telescopic rod of the air cylinder 234 to sequentially convey the multiple concrete pipes into the interior of the pipeline transport device 200 until the lowest concrete pipe moves above the fixed guide rail 215.

[0061] S7. Next, according to the laser positioning instrument installed on the internal support of the pipe jacking machine 100, confirm the feeding position of the concrete pipe body. After determining the pipe jacking elevation, start the pipe jacking machine 100 to insert the concrete pipe body into the soil layer of the tunnel.

[0062] S8. Subsequently, repeat the above operations to sequentially insert multiple concrete pipe bodies into the soil layer of the tunnel until the pipe at the outermost end is jacked out from another tunnel.

[0063] In this embodiment, as Figure 1-Figure 4 shown, the above steps use the pipe jacking machine 100 to complete the jacking construction operation of the concrete pipe body, and cooperate with the pipe transportation device 200 to sequentially feed the concrete pipe bodies above the tunnel into the interior of the working tunnel.

[0064] Specifically, the pipe transportation device 200 includes a fixing mechanism 210, a set of conveying mechanisms 220 arranged inside the fixing mechanism 210, a driving mechanism 230 arranged outside the fixing mechanism 210, and a transmission mechanism 240 that drives the internal structure of the conveying mechanism 220 to move.

[0065] Furthermore, the fixing mechanism 210 includes a fixing bottom plate 211, two symmetrically arranged support frames 213, two parallel arranged limiting baffles 214, and a fixing guide rail 215 arranged between the two support frames 213.

[0066] Furthermore, the pipe jacking machine 100 is placed on the inner bottom surface of the working pit. A fixing top plate 212 is arranged in parallel above the fixing bottom plate 211. The upper and lower ends of the support frame 213 are respectively fixedly connected to the fixing top plate 212 and the fixing bottom plate 211 by bolts. The transverse section of the support frame 213 is in a U - shape, and two parallel frame wall through - slots 2130 are provided on the inner side wall. The limiting baffle 214 is welded and fixed to the outer side wall of the support frame 213.

[0067]

[0068] Furthermore, the pipe jacking machine 100 is used to deliver multiple concrete pipes into the soil layer of the working pit in sequence. At the same time, a laser positioning instrument is also installed on the internal bracket of the pipe jacking machine 100 to ensure the accuracy of the jacking position of the concrete pipe. The fixed bottom plate 211, the fixed top plate 212 and the support frame 213 are all used to ensure the strength of the fixing mechanism 210. The frame wall groove 2130 is used to limit the moving range of the internal structure of the conveying mechanism 220. The limit baffle 214 is used to limit the downward movement range of the concrete pipe. The reinforced bottom plate 2150 is used to ensure the strength of the fixed guide rail 215. The outer sleeve bracket 2151 is used to increase the rotation range of the guide pulley 2152. The guide pulley 2152 is used to reduce the friction when the concrete pipe moves.

[0069] In this embodiment, Figure 5-Figure 6 As shown, the conveying mechanism 220 includes two rotating shafts 221 arranged parallel to each other, a transmission chain plate 222 arranged at the end of the rotating shaft 221, a transmission chain 223 sleeved on the outside of the two transmission chain plates 222, and a plurality of load-bearing parts 225 regularly distributed between the two transmission chains 223.

[0070] Specifically, the two ends of the rotating shaft 221 are rotatably connected to the outer walls on both sides of the support frame 213, the transmission chain plate 222 is fixedly connected to the outer wall of the rotating shaft 221 by a pin, and the outer side of the transmission chain 223 is provided with a protective frame 224, and the protective frame 224 is fixedly connected to the inner wall of the support frame 213 by bolts.

[0071] Furthermore, after the rotating shaft 221 rotates, it is used to drive the transmission chain plate 222 to rotate, and drive the transmission chain 223 and several load-bearing parts 225 between the two transmission chains 223 to move. The protective frame 224 is used to limit the moving range of the transmission chain 223.

[0072] In this embodiment, Figure 7 As shown, the load-bearing part 225 includes two parallel connecting brackets 2250, a connecting rod 2251 arranged between the two connecting brackets 2250, two limiting protrusions 2252 arranged in parallel on the outer wall of the connecting rod 2251, a rotating ring body 2253 sleeved on the outer side of the connecting rod 2251, and a limiting block 2254 that moves with the rotating ring body 2253.

[0073] Specifically, the connecting bracket 2250 is fixedly connected to the outside of the transmission chain 223 by a pin, the two ends of the connecting rod 2251 are welded and fixed between the two connecting brackets 2250, the limiting protrusion 2252 and the connecting rod 2251 are integrally formed, the rotating ring body 2253 is rotatably connected to the outside of the connecting rod 2251, and the limiting block 2254 is welded and fixed to the outer wall of the rotating ring body 2253.

[0074] Furthermore, the connecting bracket 2250 is used to ensure that the load-bearing part 225 as a whole can move together with the transmission chain 223. The limiting protrusion 2252 on the connecting rod 2251 is used to limit the rotation range of the rotating ring body 2253 and provide support for the concrete pipe when it is placed above the limiting block 2254.

[0075] In this embodiment, Figure 8 As shown, the driving mechanism 230 includes a connecting frame 231 , a top ring 232 and a fixed tooth plate 236 that move along with the connecting frame 231 .

[0076] Specifically, a cylinder 234 is provided on the outside of the connecting frame 231, and the telescopic rod of the cylinder 234 is fixedly connected to the outer wall of the cross bar of the connecting frame 231 by bolts. A fixing rod 233 is fixedly connected between the top ring 232 and the connecting frame 231 by bolts.

[0077] Furthermore, the outer side wall of the top cross bar of the connecting frame 231 is fixedly connected to the movable bracket 235 by bolts, and the fixed tooth plates 236 are welded and fixed to the outer side walls on both sides of the movable bracket 235 .

[0078] Furthermore, after the cylinder 234 is started, it drives the connecting frame 231 to move toward the fixing mechanism 210, and pushes the concrete pipe body into the interior of the conveying mechanism 220 through the top ring 232, so that the concrete pipe body is placed above a set of load-bearing parts 225. The fixing rod 233 is used to fix the cylinder 234 on the outer wall of the connecting frame 231, and the movable bracket 235 together with the fixed tooth plate 236 also moves with the movement of the connecting frame 231.

[0079] In this embodiment, Figure 9-10 As shown, the transmission mechanism 240 includes an outer casing 241, two parallel worm gears 242, a transmission shaft 244 for driving the worm gears 242 to rotate, a ratchet 246 arranged at the end of the transmission shaft 244, and an outer casing 247 sleeved on the outside of the ratchet 246.

[0080] Specifically, the outer sleeve portion 247 includes an outer sleeve ring body 2470 , a plurality of ratchets 2472 regularly distributed on the inner ring wall of the outer sleeve ring body 2470 , and a docking gear 2471 sleeved on the outer ring wall of the outer sleeve ring body 2470 .

[0081] Furthermore, the outer jacket frame 241 is fixedly connected to the outer wall of the support frame 213 by bolts, and the inner side of the worm gear 242 is fixedly connected to the connecting shaft 243, one end of the connecting shaft 243 is rotatably connected to the inner wall of the outer jacket frame 241, and the other end is fixedly connected to the rotating shaft 221 located above by a pin.

[0082] Furthermore, the upper and lower ends of the transmission shaft 244 are rotatably connected to the upper and lower outer walls of the outer casing 241. A worm 245 meshing with the worm wheel 242 is sleeved on the outer wall of the transmission shaft 244, and the ratchet 246 is fixedly connected to the end position of the transmission shaft 244 by a pin.

[0083] Furthermore, the outer collar body 2470 is rotatably connected to the top surface of the outer frame body 241 , the pawl 2472 is rotatably connected to the groove on the inner ring wall of the outer collar body 2470 , and the docking gear 2471 is clamped and fixed to the outer wall of the outer collar body 2470 .

[0084] Furthermore, when the fixed tooth plate 236 moves, it contacts the docking gear 2471 in the outer sleeve 247, driving the outer sleeve ring body 2470 to rotate, and the several pawls 2472 through the inner ring wall come into conflict with the ratchet 246; then, the ratchet 246 rotates, driving the transmission shaft 244 and the worm 245 to rotate, and then driving the worm wheel 242 and the connecting shaft 243 to rotate together, and then driving the rotating shaft 221 to rotate, and allowing the transmission chain plate 222 to drive the transmission chain 223 to move, and then allowing a group of load-bearing parts 225 where the concrete pipe body is placed to move downward along with the transmission chain 223.

[0085] The foregoing descriptions of specific exemplary embodiments of the present invention are for purposes of illustration and description. These descriptions are not intended to limit the invention to the precise forms disclosed, and it is apparent that many variations and modifications are possible in light of the foregoing teachings. The exemplary embodiments have been selected and described for the purpose of explaining the specific principles of the invention and their practical application, thereby enabling those skilled in the art to make and utilize a variety of exemplary embodiments of the invention and various options and modifications. The scope of the invention is intended to be defined by the description and its equivalents.

Claims

1. A production process for non-prestressed concrete cylinder pipe jacking construction pipeline based on laser positioning, characterized by: The following steps are involved: S1. First, an operator located in the working pit places the concrete pipe body on the transport track outside the pipeline transport device (200) and starts the cylinder (234) in the driving mechanism (230); S2. After the cylinder (234) is activated, it drives the connecting frame (231) to move toward the fixing mechanism (210), and pushes the concrete pipe body into the interior of the conveying mechanism (220) through the top ring (232), so that the concrete pipe body is placed above a set of bearing parts (225); S3. Then, the telescopic rod of the control cylinder (234) is contracted, thereby driving the connecting frame (231) to move in a direction away from the fixing mechanism (210), thereby driving the movable bracket (235) and the fixed tooth plate (236) to move together; S4, when the fixed tooth plate (236) moves, it contacts the docking gear (2471) in the outer sleeve (247), driving the outer sleeve ring body (2470) to rotate, and the plurality of ratchet pawls (2472) on the inner ring wall come into contact with the ratchet wheel (246); S4. Subsequently, the ratchet (246) rotates, driving the transmission shaft (244) and the worm (245) to rotate, thereby driving the worm wheel (242) and the connecting shaft (243) to rotate together; S5. When the connecting shaft (243) rotates, the rotating shaft (221) is driven to rotate, and the transmission chain plate (222) drives the transmission chain (223) to move, thereby causing a group of bearing parts (225) on which the concrete pipe body is placed to move downward along with the transmission chain (223); S6, repeatedly controlling the extension and retraction of the telescopic rod of the air cylinder (234), and sequentially sending the plurality of concrete pipes into the interior of the pipeline transport device (200), until the bottom concrete pipe moves to the top of the fixed guide rail (215); S7, then, confirming the delivery position of the concrete pipe body according to the laser positioning instrument installed on the internal bracket of the pipe jacking machine (100), and after determining the elevation of the pipe jacking machine, starting the pipe jacking machine (100) to insert the concrete pipe body into the soil layer of the tunnel; S8. Subsequently, repeat the above operation to sequentially insert multiple concrete pipes into the soil layer of the tunnel until the pipe at the end is pushed out from another tunnel; In the above steps, the pipe jacking machine (100) is used to complete the jacking construction of the concrete pipe body, and the pipe transport device (200) is used to sequentially transport the concrete pipe body above the tunnel into the interior of the working tunnel; The pipeline transport device (200) comprises a fixing mechanism (210), a conveying mechanism (220) disposed inside the fixing mechanism (210), a driving mechanism (230) disposed outside the fixing mechanism (210), and a transmission mechanism (240) for driving the internal structure of the conveying mechanism (220) to move; The fixing mechanism (210) comprises a fixed base plate (211), two symmetrically arranged support frames (213), two parallel limit baffles (214), and a fixed guide rail (215) arranged between the two support frames (213); The conveying mechanism (220) includes two rotating shafts (221) arranged parallel to each other up and down, driving chain discs (222) arranged at the ends of the rotating shafts (221), a driving chain (223) sleeved outside the two driving chain discs (222), and a number of load-bearing parts (225) regularly distributed between the two driving chains (223); The load-bearing part (225) includes two connecting brackets (2250) arranged in parallel, a connecting rod (2251) arranged between the two connecting brackets (2250), two limiting bumps (2252) arranged in parallel on the outer side walls of the connecting rod (2251), a rotating ring body (2253) sleeved outside the connecting rod (2251), and a limiting block (2254) moving together with the rotating ring body (2253); The driving mechanism (230) includes a connecting frame (231), a top ring (232) and a fixed toothed plate (236) moving together with the connecting frame (231). A moving bracket (235) is fixedly connected to the outer side wall of the top cross bar of the connecting frame (231) by bolts, and the fixed toothed plate (236) is welded and fixed to the outer side walls on both sides of the moving bracket (235); The transmission mechanism (240) includes an outer casing (241), two worm wheels (242) arranged in parallel, a transmission shaft (244) for driving the worm wheels (242) to rotate, a ratchet wheel (246) arranged at the end of the transmission shaft (244), and an outer sleeve part (247) sleeved outside the ratchet wheel (246). A worm (245) meshing with the worm wheel (242) is sleeved on the outer side wall of the transmission shaft (244); The outer sleeve part (247) includes an outer sleeve ring body (2470), a number of pawls (2472) regularly distributed on the inner circumferential wall of the outer sleeve ring body (2470), and a butt gear (2471) sleeved on the outer side wall of the outer sleeve ring body (2470).

2. The production process for non-prestressed steel cylinder concrete pipe jacking construction pipeline based on laser positioning according to claim 1 is characterized by: The pipe jacking machine (100) is placed on the inner bottom surface of the working pit. A fixed top plate (212) is arranged in parallel above the fixed bottom plate (211). The upper and lower ends of the support frame (213) are fixedly connected to the fixed top plate (212) and the fixed bottom plate (211) by bolts respectively. The transverse section of the support frame (213) is in a U shape, and two parallel frame wall through grooves (2130) are arranged on the inner side wall. The limiting baffle (214) is welded and fixed to the outer side wall of the support frame (213).

3. The production process for non-prestressed steel cylinder concrete pipe jacking construction pipeline based on laser positioning according to claim 1 is characterized by: The fixed guide rail (215) includes a reinforcing bottom plate (2150) whose two ends are fixedly connected to the inner side walls of the two support frames (213) by bolts, a number of outer sleeve brackets (2151) regularly fixedly connected to the top surface of the reinforcing bottom plate (2150) by bolts, and a guide pulley (2152) rotatably connected inside the outer sleeve brackets (2151).

4. The production process for non-prestressed concrete cylinder pipe jacking construction pipeline based on laser positioning according to claim 1 is characterized by: The two ends of the rotating shaft (221) are rotatably connected to the outer side walls of the support frame (213). The transmission chain disc (222) is fixedly connected to the outer side wall of the rotating shaft (221) via a bayonet. A protective frame (224) is sleeved on the outer side of the transmission chain (223). The protective frame (224) is fixedly connected to the inner side wall of the support frame (213) via bolts.

5. The production process for non-prestressed concrete cylinder pipe jacking construction pipeline based on laser positioning according to claim 1 is characterized in that: The connecting bracket (2250) is fixedly connected to the outer side of the transmission chain (223) via a bayonet pin, the two ends of the connecting rod (2251) are welded and fixed between the two connecting brackets (2250), the limiting protrusion (2252) and the connecting rod (2251) are integrally formed, the rotating ring body (2253) is rotatably connected to the outer side of the connecting rod (2251), and the limiting block (2254) is welded and fixed to the outer side wall of the rotating ring body (2253).

6. The production process for non-prestressed concrete cylinder pipe jacking construction pipeline based on laser positioning according to claim 1 is characterized by: A cylinder (234) is provided on the outside of the connecting frame (231), and a telescopic rod of the cylinder (234) is fixedly connected to the outer side wall of the cross bar of the connecting frame (231) via bolts. A fixing rod (233) is fixedly connected between the top ring (232) and the connecting frame (231) via bolts.

7. The production process for non-prestressed concrete cylinder pipe jacking construction pipeline based on laser positioning according to claim 1 is characterized in that: The outer jacket frame (241) is fixedly connected to the outer side wall of the support frame (213) by bolts, and the inner side of the worm gear (242) is fixedly connected to a connecting shaft (243), one end of the connecting shaft (243) is rotatably connected to the inner side wall of the outer jacket frame (241), and the other end is fixedly connected to the rotating shaft (221) located above by a bayonet pin.

8. The production process for non-prestressed concrete cylinder pipe jacking construction pipeline based on laser positioning according to claim 1 is characterized by: The upper and lower ends of the transmission shaft (244) are rotatably connected to the upper and lower outer side walls of the outer casing frame (241), and the ratchet (246) is fixedly connected to the end positions of the transmission shaft (244) via a bayonet.

9. The production process for non-prestressed concrete cylinder pipe jacking construction pipeline based on laser positioning according to claim 1, characterized in that: The outer sleeve ring body (2470) is rotatably connected to the top surface of the outer sleeve frame body (241), the pawl (2472) is rotatably connected to the groove on the inner ring wall of the outer sleeve ring body (2470), and the docking gear (2471) is clamped and fixed to the outer wall of the outer sleeve ring body (2470).

Citation Information

Patent Citations

  • A test device for a slurry pipe jacking machine

    CN105716895B

  • Long-distance large-diameter pipe jacking construction device

    CN221897253U

  • Propulsion pipe feeder

    JP1999063301A