Building engineering construction pouring formwork

By designing a construction casting formwork that includes multiple baffles and specific connecting structures, the problems of inaccurate position and poor practicality of existing formwork during use are solved, and higher casting quality and construction efficiency are achieved.

CN119981422APending Publication Date: 2025-05-13SHANDONG SHENGHENG CONSTR ENG CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202510409597.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-04-02
Publication Date
2025-05-13

AI Technical Summary

Technical Problem

During the use of existing construction project casting formwork, the spring connection is uncontrollable, resulting in inaccurate position of the extension plate, which is prone to problems such as natural mold expansion, which reduces the casting quality; at the same time, the formwork is limited in volume and poor in practicality, and cannot be used with other forms.

Method used

A construction casting formwork including a baffle, a first groove, a second groove, a plug block, a through hole, a sleeve, a pull-off screw, a limit seat, a fixing nut, a fixed steel pipe and a connecting base are designed. Through the combination and connection of multiple baffles, the versatility and flexibility of the template are improved, and the stability and connection force of the structure are enhanced through the use of pulling screws and fixed steel pipes.

Benefits of technology

The formwork is convenient for transportation and installation, has a stable structure and high applicability, which improves casting quality and construction efficiency, while reducing storage space requirements and purchasing costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119981422A_ABST
    Figure CN119981422A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building engineering construction, and discloses a building engineering construction pouring formwork which comprises a baffle, a first groove is formed in the top face of the baffle, a second groove is formed in the left side face of the baffle, a first inserting block is arranged on the bottom face of the baffle, a second inserting block is arranged on the right side face of the baffle, and a through hole is formed in the front side face of the baffle. A sleeve is installed in the through hole, a split screw is installed in the sleeve, a limiting seat and a fixing nut are installed on the outer side face of the split screw, a fixing steel pipe is installed in the limiting seat, a connecting base is installed on the front side face of the baffle, and a fixing bolt is installed on the front side face of the connecting base. The multiple baffles can be connected together by inserting the first inserting blocks into the first grooves and inserting the second inserting blocks into the second grooves, the stability and integrity of the device are enhanced, meanwhile, the workload of one-by-one installation is reduced, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building engineering construction, in particular to a casting template for building engineering construction. Background Art

[0002] Construction engineering construction refers to the process of turning various lines on design drawings into physical objects, including foundation engineering construction, main structure construction, roof engineering construction, decoration engineering construction, etc. During the construction process, the support of the casting formwork can maintain the shape and position of the building structure, ensure the stability and safety of the building, and at the same time, the casting formwork, as a temporary structure for concrete pouring, can bear the weight of concrete and construction load, and provide necessary support for construction. In order to enable concrete to be poured into corresponding shapes and sizes according to design requirements and ensure that the appearance and size of the concrete meet the architectural design requirements, the present invention proposes a casting formwork for construction engineering construction.

[0003] According to the search, the Chinese patent document, announcement number: CN220807885U, discloses a construction engineering casting template, which is set by setting a No. 1 U-shaped baffle, a No. 2 U-shaped baffle, a U-shaped lifting frame, a lifting block and a threaded knob to cooperate with each other, push the No. 2 U-shaped baffle, so that the push plate moves to the required position, and then rotate the threaded knob, at this time the U-shaped lifting frame will continue to rise, when the U-shaped lifting frame rises to a certain height, the extension plate will lose the squeezing force of the U-shaped embedded groove, and the spring will pull the stop block forward, so that the extension plate is flush with the inner side of the No. 1 U-shaped baffle, so that a higher finished product can be cast. However, in actual use of the device, since the extension plate and the U-shaped lifting frame are connected and fixed by a spring, and the elastic force of the spring is uncontrollable, the position of the extension plate cannot be accurately fixed during casting, and it is easy to cause natural mold expansion, etc., which reduces the overall casting quality; in addition, the template has a limited volume, and the modules that can be cast are also very limited, and it cannot be used in conjunction with other templates, which reduces the overall practicality. Summary of the invention

[0004] 1. Technical issues to be resolved

[0005] In view of the deficiencies in the prior art, the present invention provides a casting template for construction engineering, which has the advantages of convenient transportation and installation, stable structure, high applicability, and improved casting quality, thereby solving the above-mentioned technical problems.

[0006] (II) Technical solution

[0007] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: A casting formwork for construction engineering, comprising a baffle, a first groove is provided on the top surface of the baffle, a second groove is provided on the left side surface of the baffle, a first plug-in block is provided on the bottom surface of the baffle, a second plug-in block is provided on the right side surface of the baffle, a through hole is provided on the front side surface of the baffle, a sleeve is installed inside the through hole, a tension screw is installed inside the sleeve, a limit seat and a fixing nut are installed on the outer side surface of the tension screw, a fixing steel pipe is installed inside the limit seat, a connecting base is installed on the front side surface of the baffle, and a fixing bolt is installed on the front side surface of the connecting base.

[0008] Preferably, there are multiple baffles, and the multiple baffles can be connected to each other.

[0009] Through the above technical solution, multiple baffles can be combined according to different construction requirements, which improves the versatility and flexibility of the formwork, and multiple baffles can be decomposed into smaller parts for easy transportation and storage, reducing the demand for storage space. At the same time, the baffles can also be reused, reducing the purchase and replacement costs of the device.

[0010] Preferably, the first groove, the second groove, the first plug-in block and the second plug-in block are all provided in plural numbers, and the first plug-in block is correspondingly installed inside the first groove, and the second plug-in block is correspondingly installed inside the second groove.

[0011] Through the above technical solution, the first plug-in block is correspondingly inserted into the interior of the first groove, and the second plug-in block is correspondingly inserted into the interior of the second groove to initially connect multiple baffles together, which not only enhances the stability and integrity of the device, but also reduces the workload of installation one by one, thereby improving construction efficiency.

[0012] Preferably, the through hole, the sleeve and the tension screw are all provided in plural numbers.

[0013] Through the above technical solution, multiple through holes can prevent the position of the casing from shifting during the concrete pouring process, saving time for later installation. At the same time, multiple tension screws can provide strong connecting force to ensure the stability of the overall structure. The tension screws can withstand the lateral pressure and other loads of the concrete, preventing the baffle from deformation or cracking during the concrete pouring process, effectively improving the overall stability and construction efficiency.

[0014] Preferably, the number of the limiting seat, the fixing nut and the fixing steel pipe is multiple, and the fixing nut is threadedly connected to the outer surface of the tension screw.

[0015] Through the above technical solution, the limit seat and multiple fixed steel pipes can be installed on the outer side of the baffle by installing multiple fixing nuts. The fixed steel pipes can not only help maintain the overall shape and position of the device and prevent the baffle from deformation or displacement during concrete pouring, but also facilitate installation and disassembly, thereby improving construction efficiency and recycling rate and reducing material waste.

[0016] Preferably, the connection base and the fixing bolts are both provided in plural numbers, and the fixing bolts are threadedly connected to the inside of the baffle.

[0017] Through the above technical solution, the connecting base can be installed on the outer side of the baffle by installing multiple fixing bolts, and the connecting base can increase the connection strength between multiple baffles, making the entire device system more stable, and it can also be easily disassembled after pouring is completed, which is convenient for subsequent cleaning and maintenance.

[0018] Compared with the prior art, the present invention provides a construction engineering casting template having the following

[0019] Beneficial effects:

[0020] 1. The present invention can preliminarily connect multiple baffles together by correspondingly plugging the first plug-in block into the inside of the first groove and the second plug-in block into the inside of the second groove. The multiple baffles can be combined according to different construction requirements, which improves the versatility and flexibility of the template. The multiple baffles can be decomposed into smaller parts for easy transportation and storage, reducing the demand for storage space. The baffles can also be reused, reducing the purchase and replacement costs of the device. At the same time, the multiple through holes can prevent the position of the sleeve from shifting during the concrete pouring process, saving time for later installation. The multiple tension screws can provide a strong connection force to ensure the stability of the overall structure. The tension screws can withstand the lateral pressure and other loads of the concrete, preventing the baffles from deformation or rupture during the concrete pouring process, effectively improving the overall stability and construction efficiency.

[0021] 2. The present invention can install a limit seat and a plurality of fixed steel pipes on the outer side of the baffle by installing a plurality of fixing nuts. The fixed steel pipes can not only help maintain the overall shape and position of the device and prevent the baffle from deformation or displacement during concrete pouring, but also facilitate installation and disassembly, thereby improving construction efficiency and recycling rate and reducing material waste. The connecting base can be installed on the outer side of the baffle by installing a plurality of fixing bolts, and the connecting base can increase the connection strength between the plurality of baffles, thereby making the entire device system more stable, and can be easily disassembled after pouring is completed, thereby facilitating subsequent cleaning and maintenance work. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a three-dimensional schematic diagram of the structure of the present invention;

[0023] Figure 2 It is a three-dimensional schematic diagram of the structural baffle and other parts of the present invention;

[0024] Figure 3 It is a front view schematic diagram of the structural baffle and other parts of the present invention.

[0025] Among them: 1. baffle; 2. first groove; 3. second groove; 4. first plug-in block; 5. second plug-in block; 6. through hole; 7. sleeve; 8. tension screw; 9. limit seat; 10. fixing nut; 11. fixing steel pipe; 12. connecting base; 13. fixing bolt. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0027] See also Figure 1-3 A casting template for construction engineering comprises a baffle 1, a first groove 2 is provided on the top surface of the baffle 1, a second groove 3 is provided on the left side surface of the baffle 1, a first plug-in block 4 is provided on the bottom surface of the baffle 1, a second plug-in block 5 is provided on the right side surface of the baffle 1, a through hole 6 is provided on the front side surface of the baffle 1, a sleeve 7 is installed inside the through hole 6, a tension screw 8 is installed inside the sleeve 7, a limit seat 9 and a fixing nut 10 are installed on the outer side surface of the tension screw 8, a fixing steel pipe 11 is installed inside the limit seat 9, a connecting base 12 is installed on the front side surface of the baffle 1, and a fixing bolt 13 is installed on the front side surface of the connecting base 12.

[0028] Specifically, the number of baffles 1 is multiple, and the multiple baffles 1 can be connected to each other. The advantage is that through this structure, the multiple baffles 1 can be combined according to different construction requirements, which improves the versatility and flexibility of the template, and the multiple baffles 1 can be decomposed into smaller parts, which is convenient for transportation and storage, reducing the demand for storage space, and the baffles 1 can be reused, reducing the purchase and replacement costs of the device.

[0029] Specifically, the number of the first groove 2, the second groove 3, the first plug-in block 4 and the second plug-in block 5 are all multiple, and the first plug-in block 4 is correspondingly installed in the first groove 2, and the second plug-in block 5 is correspondingly installed in the second groove 3. The advantage is that through this structure, the first plug-in block 4 is correspondingly plugged into the inside of the first groove 2, and the second plug-in block 5 is correspondingly plugged into the inside of the second groove 3, so that multiple baffles 1 can be preliminarily connected together, which not only enhances the stability and integrity of the device, but also reduces the workload of installing one by one, and improves the construction efficiency.

[0030] Specifically, the number of through holes 6, sleeves 7 and tension screws 8 are all set in multiple numbers. The advantage is that the multiple through holes 6 in this structure can prevent the position of the sleeve 7 from being offset during the concrete pouring process, saving time for later installation, and the multiple tension screws 8 can provide a strong connection force to ensure the stability of the overall structure, and the tension screws 8 can withstand the lateral pressure and other loads of the concrete, preventing the baffle 1 from being deformed or broken during the concrete pouring process, effectively improving the overall stability and construction efficiency.

[0031] Specifically, the number of the limiting seat 9, the fixing nut 10 and the fixing steel pipe 11 is multiple, and the fixing nut 10 is threadedly connected to the outer surface of the tension screw 8. The advantage is that the limiting seat 9 and the multiple fixing steel pipes 11 can be installed on the outer surface of the baffle 1 by installing multiple fixing nuts 10, and the fixing steel pipe 11 can not only help maintain the overall shape and position of the device, and prevent the baffle 1 from deformation or displacement during the concrete pouring process, but also the fixing steel pipe 11 is easy to install and disassemble, improve construction efficiency and recycling rate, and reduce material waste.

[0032] Specifically, the number of the connection base 12 and the fixing bolt 13 are both provided in plurality, and the fixing bolt 13 is threadedly connected to the inside of the baffle 1. The advantage is that the connection base 12 can be installed on the outer surface of the baffle 1 by installing a plurality of fixing bolts 13, and the connection base 12 can increase the connection strength between the plurality of baffles 1, making the entire device system more stable, and it can also be easily disassembled after the pouring is completed, which is convenient for subsequent cleaning and maintenance work.

[0033] When in use, multiple baffles 1 can be preliminarily connected together by correspondingly plugging the first plug-in block 4 into the inside of the first groove 2 and the second plug-in block 5 into the inside of the second groove 3. Multiple baffles 1 can be combined according to different construction requirements, which improves the versatility and flexibility of the formwork, and multiple baffles 1 can be decomposed into smaller parts for easy transportation and storage, reducing the demand for storage space, and the baffles 1 can also be reused, reducing the cost of purchasing and replacing the device; at the same time, multiple through holes 6 can prevent the position of the sleeve 7 from shifting during the concrete pouring process, saving time for later installation, and multiple tension screws 8 can provide strong connecting force to ensure the stability of the overall structure, and the tension screws 8 can withstand the lateral pressure and other loads of the concrete to prevent the baffles from 1 is deformed or cracked during the concrete pouring process, which effectively improves the overall stability and construction efficiency; by installing a plurality of fixing nuts 10, the limit seat 9 and a plurality of fixed steel pipes 11 can be installed on the outer side of the baffle 1, and the fixed steel pipe 11 can not only help maintain the overall shape and position of the device, and prevent the baffle 1 from being deformed or displaced during the concrete pouring process, but also facilitate installation and disassembly, improve construction efficiency and recycling rate, and reduce material waste; by installing a plurality of fixing bolts 13, the connecting base 12 can be installed on the outer side of the baffle 1, and the connecting base 12 can increase the connection strength between the plurality of baffles 1, making the entire device system more stable, and it can also be easily disassembled after the pouring is completed, which is convenient for subsequent cleaning and maintenance.

[0034] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A casting template for construction engineering, comprising a baffle (1), characterized in that: The top surface of the baffle (1) is provided with a first groove (2), the left side surface of the baffle (1) is provided with a second groove (3), the bottom surface of the baffle (1) is provided with a first plug-in block (4), the right side surface of the baffle (1) is provided with a second plug-in block (5), the front side surface of the baffle (1) is provided with a through hole (6), a sleeve (7) is installed inside the through hole (6), a tension screw (8) is installed inside the sleeve (7), a limit seat (9) and a fixing nut (10) are installed on the outer side surface of the tension screw (8), a fixing steel pipe (11) is installed inside the limit seat (9), a connecting base (12) is installed on the front side surface of the baffle (1), and a fixing bolt (13) is installed on the front side surface of the connecting base (12).

2. A construction pouring formwork according to claim 1, characterized in that: The baffles (1) are provided in a plurality, and the plurality of baffles (1) can be connected to each other.

3. A construction pouring formwork according to claim 1, characterized in that: The first groove (2), the second groove (3), the first plug-in block (4) and the second plug-in block (5) are all provided in plural numbers, and the first plug-in block (4) is correspondingly installed inside the first groove (2), and the second plug-in block (5) is correspondingly installed inside the second groove (3).

4. A construction pouring formwork according to claim 1, characterized in that: The through hole (6), the sleeve (7) and the tension screw rod (8) are all provided in plural numbers.

5. A construction pouring formwork according to claim 1, characterized in that: The number of the limiting seat (9), the fixing nut (10) and the fixing steel pipe (11) is multiple, and the fixing nut (10) is threadedly connected to the outer surface of the tension screw rod (8).

6. A construction pouring formwork according to claim 1, characterized in that: The connection base (12) and the fixing bolts (13) are both provided in plural numbers, and the fixing bolts (13) are threadedly connected to the inside of the baffle (1).

Citation Information