Method and system for replacing electricity meter based on handheld device

By using handheld machine and meter management system in the meter replacement process, a balance transfer token is generated, efficient replacement of the meter is achieved, and the existing replacement process is complicated and resource waste is solved.

CN120126252APending Publication Date: 2025-06-10HEXING ELECTRICAL CO LTD +6
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202510136794.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-02-07
Publication Date
2025-06-10

AI Technical Summary

Technical Problem

The existing meter replacement process is cumbersome, and staff need to travel back and forth between the power business hall and the user site many times, resulting in waste of resources and inefficiency.

Method used

The handheld machine-based replacement method is used to obtain the original table information and new table information through the handheld machine, and upload it to the power meter management system to generate a balance transfer token, and the new table receives the token to complete the replacement of the table.

Benefits of technology

The process of replacing the electricity meter has been simplified. Staff only need to go to the user's site to complete the meter replacement, optimize resource utilization and reduce human resource consumption.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120126252A_ABST
    Figure CN120126252A_ABST
Patent Text Reader

Abstract

The invention provides an electricity meter replacement method and system based on a handheld device, and belongs to the technical field of electricity meter replacement. The electricity meter replacement method based on the handheld device comprises the following steps that S1, the handheld device obtains original meter information and new meter information and uploads the original meter information and the new meter information to an electricity meter management system; s2, the electric meter management system generates a balance transfer token corresponding to the new meter information based on the original meter information; and S3, the new table receives the input balance transfer token to complete table change. A worker uploads original meter information and new meter information to an electric meter management system through a handheld device, the electric meter management system generates a balance transfer token corresponding to the new meter information based on the original meter information, the new meter receives the input balance transfer token to complete meter replacement, the balance transfer token is generated to transfer the balance of the original meter to the new meter, and the balance of the new meter is transferred to the original meter. A worker only needs to go to a user site for one time to complete meter replacement, the meter replacement process is optimized, and manpower resource consumption is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electricity meter replacement, and in particular, to a method and system for replacing an electricity meter based on a handheld computer. Background Art

[0002] When the user's meter is damaged, or when the customer needs to expand the capacity due to line renovation, an application for replacing the meter needs to be submitted to the power business hall or the designated electricity sales point. The power business hall or the electricity sales point dispatches staff to inspect on-site whether the meter meets the requirements for meter replacement. If the requirements are met, the staff returns to the power business hall or the electricity sales point, enters the system information in the system, generates a meter replacement token, and finally the staff carries the new meter back to the user's site for meter replacement. The meter replacement cycle is long, which easily causes waste of resources of the power bureau. Summary of the Invention

[0003] To solve the above problems, the embodiments of the present application provide a method and system for replacing an electricity meter based on a handheld computer.

[0004] In a first aspect, the embodiments of the present application provide a method for replacing an electricity meter based on a handheld computer, including the following steps: S1: The handheld computer obtains the original meter information and the new meter information, and uploads the original meter information and the new meter information to the electricity meter management system respectively; S2: The electricity meter management system generates a balance transfer token corresponding to the new meter information based on the original meter information; S3: The new meter receives the input balance transfer token to complete the meter replacement.

[0005] Preferably, the handheld computer is connected to the electricity meter management system through a webservice interface.

[0006] Preferably, the original meter information includes the original meter power consumption information, and the new meter information includes the new meter number. Step S2 includes: the electricity meter management system generates a balance transfer token corresponding to the new meter number based on the original meter power consumption information.

[0007] Preferably, the original meter information further includes the original meter number. Between step S1 and step S2, it further includes: the electricity meter management system obtains the original meter file information corresponding to the original meter based on the original meter number; the electricity meter management system obtains the meter replacement bill data receipt based on the original meter file information; the electricity meter management system sends the meter replacement bill data receipt to the handheld computer; the handheld computer sends a charging completion instruction to the electricity meter management system.

[0008] Preferably, the electricity meter management system obtaining the meter replacement bill data based on the original meter file information specifically includes: The electricity meter management system calculates and obtains the meter replacement cost information and the tax information based on the original meter file information; The electricity meter management system generates a replacement electricity meter bill data receipt based on the replacement meter cost information and tax information.

[0009] In a second aspect, an embodiment of the present application provides a replacement electricity meter system based on a handheld device, including a handheld device, an electricity meter management system, and a new electricity meter; The handheld device obtains the original meter information and the new meter information, and uploads the original meter information and the new meter information to the electricity meter management system respectively; The electricity meter management system generates a balance transfer token corresponding to the new meter information based on the original meter information; The new electricity meter receives the input balance transfer token to complete the replacement of the electricity meter.

[0010] Preferably, the handheld device is connected to the electricity meter management system through a webservice interface.

[0011] Preferably, the original meter information includes the original meter power consumption information, the new meter information includes the new meter number, and the electricity meter management system generates a balance transfer token corresponding to the new meter number based on the original meter power consumption information.

[0012] Preferably, the original meter information includes the original meter number, the electricity meter management system obtains the original meter file information corresponding to the original meter based on the original meter number; the electricity meter management system obtains the replacement electricity meter bill data receipt based on the original meter file information; the electricity meter management system sends the replacement electricity meter bill data receipt to the handheld device; the handheld device sends a charging completion instruction to the electricity meter management system.

[0013] Preferably, the electricity meter management system obtaining the replacement electricity meter bill data based on the original meter file information specifically includes: The electricity meter management system calculates and obtains the replacement meter cost information and tax information based on the original meter file information; The electricity meter management system generates a replacement electricity meter bill data receipt based on the replacement meter cost information and tax information.

[0014] The beneficial effects of the present invention are as follows: The staff upload the original meter information and the new meter information to the electricity meter management system through the handheld device respectively. The electricity meter management system generates a balance transfer token corresponding to the new meter information based on the original meter information. The new electricity meter receives the input balance transfer token to complete the replacement of the electricity meter, and the balance of the original meter is transferred to the new meter by generating the balance transfer token. The staff only need to go to the user site once to complete the replacement of the electricity meter, optimizing the replacement meter process and reducing the consumption of human resources. Description of the Drawings

[0015] To more clearly illustrate the technical solutions in the embodiments of the present application, the accompanying drawings required for the embodiments will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some embodiments of the present application. For those of ordinary skill in the art, without creative efforts, other accompanying drawings can be obtained based on these drawings.

[0016] Figure 1 It is a schematic flowchart of a method for replacing an electric meter based on a handheld device provided by an embodiment of the present application; Figure 2 It is a schematic structural diagram of a system for replacing an electric meter based on a handheld device provided by an embodiment of the present application; Figure 3 It is a schematic flowchart of the electric meter replacement process provided by an embodiment of the present application. Detailed implementation manners

[0017] Next, the technical solutions in the embodiments of the present application will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present application.

[0018] In the following description, the terms "first" and "second" are only for the purpose of description and cannot be construed as indicating or implying relative importance. The following description provides multiple embodiments of the present application. Different embodiments can be replaced or combined. Therefore, the present application can also be considered to include all possible combinations of the same and / or different embodiments described. Thus, if one embodiment includes features A, B, and C, and another embodiment includes features B and D, then the present application should also be considered to include embodiments containing all other possible combinations of A, B, C, and D, although such embodiments may not be explicitly described in the following content.

[0019] The following description provides examples and does not limit the scope, applicability, or examples set forth in the claims. Changes can be made to the functions and arrangements of the described elements without departing from the scope of the content of the present application. Various processes or components can be appropriately omitted, substituted, or added to each example. For example, the described method can be executed in a different order from the described order, and various steps can be added, omitted, or combined. In addition, the features described in some examples can be combined into other examples.

[0020] Please refer to Figure 1 , 3 . Figure 1 It is a schematic flowchart of a method for replacing an electric meter based on a handheld device provided by an embodiment of the present application, Figure 3 It is a schematic flowchart of the electric meter replacement process provided by an embodiment of the present application. In the embodiments of the present application, the method includes the following steps: S1: The handheld device obtains the original meter information and the new meter information, and uploads the original meter information and the new meter information to the electricity meter management system respectively; S2: The electricity meter management system generates a balance transfer token corresponding to the new meter information based on the original meter information; S3: The new meter receives the input balance transfer token to complete the meter replacement.

[0021] In the embodiment of the present application, the present application is mainly used when the user's meter is damaged. After the power bureau staff conduct a preliminary exploration of the damaged meter on site, they use a handheld device to call the electricity meter management system to replace the meter, improving the efficiency of meter replacement business processing.

[0022] In the embodiment of the present application, the present application encrypts the balance transfer token through a standard transmission specification. The standard transmission specification (STS) is a set of secure messaging protocols. When selling electricity, a string of encrypted tokens (20 BCD codes) is generated according to the STS protocol. The TID is an important data component in the STS protocol, which can represent the moment of purchasing the token and is non-repeating. The protocol requires the meter to reserve 50 record spaces to store the TID. The meter judges the validity of the token based on this record. If the TID in the token has been stored in the record, the meter will prompt USED and reject acceptance. If it is earlier than 50 records, the meter will prompt OLD and reject acceptance; STS also provides key encryption technology to protect each token.

[0023] In the embodiment of the present application: 1. The user submits an application, and the user provides a meter replacement application and the meter information of the original meter; 2. The power bureau staff go to the site for inspection. The staff judge whether the original meter meets the meter replacement conditions; 3. The handheld device enters information. If the original meter meets the meter replacement conditions, the staff record the electricity quantity information of the original meter on site through the handheld device, and the handheld device enters it into the electricity meter management system through the webservice interface method; the electricity meter management system generates a balance transfer token according to the entered electricity quantity information of the original meter; 4. Install the new meter. The relevant balance transfer token is input into the new meter. The staff remove the original meter and install the new meter. Enter the balance transfer token in the new meter, and the user can use the new meter normally.

[0024] In the embodiment of the present application, the new meter receives the input balance transfer token to complete the meter replacement specifically includes: Some new meters have a keyboard, and the balance transfer token can be directly input through the keyboard. Some new meters do not have a keyboard. Connect the relevant input device to the new meter, and input the balance transfer token to the new meter through the relevant input device.

[0025] In the embodiment of the present application, the new meter cannot be powered on without a power value, similar to a mobile phone card. Without phone credit, it cannot be used, and without power, the switch will be tripped. After the balance transfer token is input into the new meter, the new meter will close the switch when it has power, and the core meter can be used normally. This balance transfer token is equivalent to the activation code corresponding to the new meter number. After input, the new meter can be used. The on-site staff will record the remaining power of the original meter and upload it to the system through the handheld device. The system generates a balance transfer token for the new meter based on the uploaded remaining power, and the power value carried by the token is the same as the remaining power of the old meter.

[0026] In an implementable manner, the handheld device is connected to the electricity meter management system through a webservice interface.

[0027] In an implementable manner, the original meter information includes the original meter power information, and the new meter information includes the new meter number. Step S2 includes: the electricity meter management system generates a balance transfer token corresponding to the new meter number based on the original meter power information.

[0028] In the embodiment of the present application, the staff of the power bureau enters the original meter power information into the handheld device. The handheld device uploads the original meter power information to the electricity meter management system through the interface, and the electricity meter management system generates a balance transfer token. The staff enters the new meter number into the handheld device, and the handheld device uploads the new meter number to the electricity meter management system.

[0029] In an implementable manner, the original meter information further includes the original meter number. Between steps S1 and S2, it further includes: the electricity meter management system obtains the original meter file information corresponding to the original meter based on the original meter number; the electricity meter management system obtains the meter replacement bill data receipt based on the original meter file information; the electricity meter management system sends the meter replacement bill data receipt to the handheld device; the handheld device sends a charge completion instruction to the electricity meter management system.

[0030] In an implementable manner, the electricity meter management system obtaining the meter replacement bill data based on the original meter file information specifically includes: The electricity meter management system calculates and obtains the meter replacement cost information and tax information based on the original meter file information; The electricity meter management system generates a meter replacement bill data receipt based on the meter replacement cost information and tax information.

[0031] In an embodiment of the present application, after the staff enters the original meter number in the handheld device, the handheld device uploads the original meter number to the electricity meter management system. There is a storage module in the electricity meter management system for storing information related to the meter. The electricity meter management system obtains the original meter file information corresponding to the original meter number from the storage module according to the original meter number. The electricity meter management system calculates and obtains the meter replacement cost information and tax information for this meter replacement based on the original meter file information. The electricity meter management system generates a meter replacement bill data receipt based on the meter replacement cost information and tax information, and the electricity meter management system sends the meter replacement bill data receipt to the handheld device.

[0032] In an embodiment of the present application, the on-site staff and the user confirm the meter replacement bill data on the meter replacement bill data receipt in the handheld device. After that, the on-site staff collects the relevant fees, and then the charging process is completed. The on-site staff sends a charging completion instruction to the electricity meter management system through the handheld device. The electricity meter management system considers the charging to be successful, and the electricity meter management system generates a balance transfer token.

[0033] In an embodiment of the present application, after the user initiates an order, the staff goes to the site for inspection, completes the information entry and collection of the meter replacement handling fee according to the meter replacement reason. The system simultaneously calculates the user's taxes for recovery, helping the power bureau recover the taxes and avoiding economic losses to the power bureau. At the same time, the system generates a balance transfer token based on the entered electricity quantity information, which is input by the staff into the meter to complete the transfer of the remaining electricity in the customer's old meter to the new meter, ensuring the rights and interests of the electricity-using customers. At this time, the meter replacement is completed, which shortens the meter replacement process cycle to a certain extent, reduces the waste of human resources of the power bureau, and at the same time helps the power bureau recover other fees such as taxes.

[0034] In an embodiment of the present application, 1. The present application optimizes the meter replacement process of the power bureau and reduces the consumption of human resources; 2. The present application generates a balance transfer token, thereby transferring the balance of the original meter to the new meter; 3. Recover the fees generated by the user's meter replacement and the taxes for the current month, and save the records.

[0035] Next, a meter replacement system based on a handheld device provided in an embodiment of the present application will be introduced in detail. It should be noted that the Figure 2 shown meter replacement system based on a handheld device is used to execute the method of the embodiment of the present application. For the sake of convenience of description, only the parts related to the embodiment of the present application are shown. For the specific technical details not disclosed, please refer to the Figure 2 shown embodiment of the present application. Figure 1 The method shown in the embodiment of the present application. For the sake of convenience of explanation, only the parts related to the embodiment of the present application are shown. For the specific technical details not disclosed, please refer to the Figure 1 shown embodiment of the present application.

[0036] Please refer to Figure 2 、 3 , Figure 2It is a schematic structural diagram of a replacement electricity meter system based on a handheld device provided by an embodiment of the present application. Figure 3 It is a schematic diagram of the electricity meter replacement process provided by an embodiment of the present application. As Figure 2-3 shown, the system includes a handheld device 201, an electricity meter management system 202, and a new electricity meter 203; The handheld device 201 obtains the information of the original electricity meter and the new electricity meter 203, and uploads the information of the original electricity meter and the new electricity meter 203 to the electricity meter management system 202 respectively; The electricity meter management system 202 generates a balance transfer token corresponding to the information of the new electricity meter 203 based on the information of the original electricity meter; The new electricity meter 203 receives the input balance transfer token to complete the replacement of the electricity meter.

[0037] In an implementable manner, the handheld device 201 is connected to the electricity meter management system 202 through a webservice interface.

[0038] In an implementable manner, the information of the original electricity meter includes the electricity quantity information of the original electricity meter, the information of the new electricity meter 203 includes the meter number of the new electricity meter 203, and the electricity meter management system 202 generates a balance transfer token corresponding to the meter number of the new electricity meter 203 based on the electricity quantity information of the original electricity meter.

[0039] In an implementable manner, the information of the original electricity meter includes the meter number of the original electricity meter, the electricity meter management system 202 obtains the original electricity meter file information corresponding to the original electricity meter based on the meter number of the original electricity meter; the electricity meter management system 202 obtains the replacement electricity meter bill data receipt based on the original electricity meter file information; the electricity meter management system 202 sends the replacement electricity meter bill data receipt to the handheld device 201; the handheld device 201 sends a charging completion instruction to the electricity meter management system 202.

[0040] In an implementable manner, the electricity meter management system 202 obtaining the replacement electricity meter bill data based on the original electricity meter file information specifically includes: The electricity meter management system 202 calculates and obtains the replacement electricity meter cost information and tax information based on the original electricity meter file information; The electricity meter management system 202 generates a replacement electricity meter bill data receipt based on the replacement electricity meter cost information and tax information.

[0041] Those skilled in the art can clearly understand that the technical solutions of the embodiments of the present application can be implemented by means of software and / or hardware. The "unit", "module", and "section" in this specification refer to software and / or hardware that can independently complete or cooperate with other components to complete specific functions, where the hardware can be, for example, a Field-Programmable Gate Array (FPGA), an Integrated Circuit (IC), etc.

[0042] It should be noted that, for the foregoing method embodiments, for the sake of simple description, they are all expressed as a series of action combinations. However, those skilled in the art should know that this application is not limited by the described action sequence, because according to this application, certain steps can be performed in other sequences or simultaneously. Secondly, those skilled in the art should also know that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily essential to this application.

[0043] In the above embodiments, the descriptions of the respective embodiments have their own emphases. For the parts not detailed in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0044] In the several embodiments provided by this application, it should be understood that the disclosed device can be implemented in other ways. For example, the device embodiments described above are merely illustrative. For example, the division of the units is only a logical function division. In actual implementation, there can be other division methods. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the displayed or discussed coupling or direct coupling or communication connection to each other can be through some service interfaces. The indirect coupling or communication connection of the device or unit can be in an electrical or other form.

[0045] The units described as separate components may or may not be physically separated. The components displayed as units may or may not be physical units, that is, they can be located in one place, or can be distributed to multiple network units. Some or all of the units can be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0046] In addition, in each embodiment of this application, the various functional units can be integrated in a processing unit, or each unit can exist physically alone, or two or more units can be integrated in one unit. The above integrated units can be implemented in the form of hardware or in the form of software functional units.

[0047] When the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable memory. Based on this understanding, the technical solution of this application, in essence, or the part that contributes to the prior art, or all or part of this technical solution, can be embodied in the form of a software product. This computer software product is stored in a memory and includes several instructions for causing a computer device (which can be a personal computer, a server, or a network device, etc.) to execute all or part of the steps of the methods described in the various embodiments of this application. The aforementioned memory includes: USB flash drives, read-only memory (ROM), random access memory (RAM), external hard drives, magnetic disks, or optical discs, etc., all kinds of media that can store program codes.

[0048] Those of ordinary skill in the art can understand that all or part of the steps in the various methods of the above embodiments can be completed by instructing relevant hardware through a program. This program can be stored in a computer-readable memory, and the memory can include: flash drives, read-only memory (ROM), random access memory (RAM), magnetic disks, or optical discs, etc.

[0049] The above are only exemplary embodiments of the present disclosure and should not be used to limit the scope of the present disclosure. That is, any equivalent changes and modifications made in accordance with the teachings of the present disclosure still fall within the scope covered by the present disclosure. After considering the specification and practicing the present disclosure, those skilled in the art will easily think of other embodiments of the present disclosure. This application aims to cover any variations, uses, or adaptive changes of the present disclosure. These variations, uses, or adaptive changes follow the general principles of the present disclosure and include common general knowledge or conventional technical means in the technical field not described in the present disclosure. The specification and embodiments are only regarded as exemplary, and the scope and spirit of the present disclosure are defined by the claims.

Claims

1. A method for replacing an electric meter based on a handheld device, characterized in that: The steps include: S1: The handheld device obtains the original meter information and the new meter information, and uploads the original meter information and the new meter information to the meter management system respectively; S2: The electricity meter management system generates a balance transfer token corresponding to the new meter information based on the original meter information; S3: The new table receives the input balance transfer token to complete the table swap.

2. A method for replacing an electric meter based on a handheld device as claimed in claim 1, characterized in that: The handheld device is connected to the electric meter management system through a webservice interface.

3. A method for replacing an electric meter based on a handheld device as claimed in claim 1 or 2, characterized in that: The original meter information includes original meter power information, and the new meter information includes a new meter number. Step S2 includes: the meter management system generates a balance transfer token corresponding to the new meter number based on the original meter power information.

4. The method for replacing an electric meter based on a handheld device as claimed in claim 3, characterized in that: The original meter information also includes the original meter number, and between steps S1 and S2, it also includes: the meter management system obtains the original meter file information corresponding to the original meter based on the original meter number; the meter management system obtains the meter replacement bill data receipt based on the original meter file information; the meter management system sends the meter replacement bill data receipt to the handheld device; the handheld device sends a charging completion instruction to the meter management system.

5. The method for replacing an electric meter based on a handheld device as claimed in claim 4, characterized in that: The electric meter management system obtains the meter replacement bill data based on the original meter file information, specifically including: The electric meter management system calculates and obtains meter replacement fee information and tax information based on the original meter file information; The electric meter management system generates a meter replacement bill data receipt based on the meter replacement fee information and tax information.

6. A handheld device-based electric meter replacement system, characterized in that: Including handheld devices, meter management systems, and new meters; The handheld device obtains the original meter information and the new meter information, and uploads the original meter information and the new meter information to the meter management system respectively; The electric meter management system generates a balance transfer token corresponding to the new meter information based on the original meter information; The new table receives the input balance transfer token to complete the table switch.

7. The handheld device-based electric meter replacement system as claimed in claim 6, characterized in that: The handheld device is connected to the electric meter management system through a webservice interface.

8. A handheld device-based electric meter replacement system as claimed in claim 6 or 7, characterized in that: The original meter information includes original meter power information, the new meter information includes a new meter number, and the meter management system generates a balance transfer token corresponding to the new meter number based on the original meter power information.

9. The handheld device-based electric meter replacement system as claimed in claim 8, characterized in that: The original meter information includes the original meter number, and the electric meter management system obtains the original meter file information corresponding to the original meter based on the original meter number; The electric meter management system obtains the meter replacement bill data receipt based on the original meter file information; The electric meter management system sends the meter replacement bill data receipt to the handheld device; The handheld device sends a charging completion instruction to the electricity meter management system.

10. The handheld device-based electric meter replacement system as claimed in claim 9, characterized in that: The electric meter management system obtains the meter replacement bill data based on the original meter file information, specifically including: The electric meter management system calculates and obtains meter replacement fee information and tax information based on the original meter file information; The electric meter management system generates a meter replacement bill data receipt based on the meter replacement fee information and tax information.

Citation Information

Patent Citations

  • Method for managing intelligent prepayment measuring and controlling terminal and intelligent prepayment measuring and controlling terminal

    CN106257546A

  • Information maintaining method and device for use in replacement of electric energy meter

    CN110058067A

  • Method and system for quickly replacing common metering instrument with Internet of Things metering instrument

    CN110232425A