Narrow river surge soil slope sewage interception pipeline structure and pipeline laying method

By manually setting concrete trunks and steel bar fixtures on both sides of the narrow river surf, the problem of difficulty in access by construction machinery is solved, and the pipeline laying on the soil slope of the narrow river surf is realized, ensuring the economic safety and environmental protection effect of the construction.

CN120486546APending Publication Date: 2025-08-15ARCHITECTURAL DESIGN RES INST OF GUANGDONG PROVINCE
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202510949070.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-07-10
Publication Date
2025-08-15

AI Technical Summary

Technical Problem

In the prior art, there are many houses on both sides of the narrow river surf, and construction machinery and equipment are difficult to enter, resulting in increased difficulty in laying pipeline facilities at half the waist height of the original soil slope.

Method used

Fixed components connected to the soil slope are adopted to set fixing points on both sides of the river and surfing through manual punching and pouring to support sewage intercepting pipelines, including concrete pier and steel bar fixing, and combined with pipeline fixing parts to achieve the fixing and support of the pipeline.

Benefits of technology

Without relying on large-scale mechanical equipment, the pipeline laying on the soil slope of narrow rivers is realized, avoiding the problem of inaccessibility of construction machinery and ensuring the economic safety and environmental protection of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120486546A_ABST
    Figure CN120486546A_ABST
Patent Text Reader

Abstract

The embodiment of the invention provides a narrow river surge soil slope sewage interception pipeline structure and a pipeline laying method, and relates to the technical field of pipeline laying. The technical problem that in the prior art, due to the fact that construction mechanical equipment difficultly enters the two sides of a river for construction, the difficulty of pipeline laying construction at the half-waist height of an original soil slope is increased is solved. The device comprises a sewage intercepting pipeline which is arranged along the river surge trend and is connected with a soil slope through a plurality of fixing assemblies; the fixing assembly comprises a concrete pier used for fixing the sewage intercepting pipeline, and the concrete pier is connected with a soil slope through a concrete pier fixing piece. The concrete pier fixing parts and the concrete piers are driven and poured manually, so that the fixing points for fixing the sewage intercepting pipelines are arranged on the soil slopes on the two sides of the river under the condition that construction mechanical equipment is difficult to enter; and the sewage interception work of the sewage pipelines at the soil slopes on the two sides of the narrow river site is well solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of pipeline laying, and in particular to a narrow river slope sewage interception pipeline structure and a pipeline laying method. Background Art

[0002] With the urgency of sewage treatment, in order to intercept sewage, it is necessary to intercept sewage from the earth slope sewage pipes on both sides of the river.

[0003] In the existing technology, most rivers and streams have narrow cross-sections and are flanked by numerous houses, making it difficult for many construction machines and equipment to enter for construction, increasing the difficulty of laying pipelines at a height of halfway up the original earth slope.

[0004] Therefore, there is an urgent need for a structure and construction method that can achieve pipeline laying on narrow river slopes. Summary of the Invention

[0005] The purpose of the present invention includes providing a sewage interception pipeline structure and a pipeline laying method for narrow river slopes, so as to improve the technical problem in the prior art that construction machinery and equipment find it difficult to enter both sides of the river for construction, thereby increasing the difficulty of laying pipelines at the half-height of the original slope.

[0006] The embodiments of the present invention can be implemented as follows: In a first aspect, the present invention provides a narrow river slope sewage interception pipeline structure, which is laid on the slopes on both sides of the river, comprising: A sewage interception pipe is arranged along the river and connected to the soil slope through a plurality of fixing components; The fixing assembly includes a concrete pier for fixing the sewage interception pipe, and the concrete pier is connected to the soil slope through a concrete pier fixing piece.

[0007] In an optional embodiment, the concrete pier fixing member includes a first fixing member arranged perpendicular to the ground and a second fixing member arranged perpendicular to the soil slope; One end of the first fixing member and the second fixing member are respectively connected to the soil slope, and the other end are respectively connected to the concrete pier.

[0008] In an optional embodiment, the first fixing member and the second fixing member each include multiple sections of steel bars; The multiple sections of steel bars are connected by steel bar connectors; The total length of the connected steel bars is L, and L≥3m.

[0009] In an optional embodiment, the concrete pier is further provided with a pipe fixing member for fixing the sewage interception pipe; The pipeline fixing member includes a third fixing member and a plurality of fourth fixing members. The third fixing member is arranged around the outer wall of the sewage interception pipeline and is fixedly connected to the concrete pier through the plurality of fourth fixing members.

[0010] In an optional embodiment, the third fixing member is a rubber belt or a steel plate, and the fourth fixing member is an anchor bolt.

[0011] In a second aspect, the present invention provides a method for laying a sewage interception pipeline on a narrow river slope, comprising: Determine the layout points of multiple fixed components as pipeline support points; Set up fixing components at corresponding pipeline support points; The sewage interception pipe is set up on a plurality of fixing components, and the sewage interception pipe is connected to the corresponding fixing components through pipe fixing parts.

[0012] In an optional embodiment, the method for determining the arrangement points of the plurality of fixed components is: arranging them along the direction of the river, with the distance between adjacent fixed components being d, d≤3500 mm.

[0013] In an optional embodiment, a method for setting a fixing assembly at a corresponding pipeline support point includes: Install concrete pier fixings at the pipeline support points; Excavate a plane at the pipe support point and pour concrete at the plane to form a concrete pier.

[0014] In an optional embodiment, a method for providing a concrete pier fixing member at a pipeline support point includes: In the vertical direction, multiple steel bars are manually driven in as the first fixing members; In the direction perpendicular to the soil slope, multiple steel bars are manually driven in as the second fixing parts.

[0015] In an optional embodiment, a method of excavating a plane at a pipeline support point and pouring concrete at the plane to form a concrete pier includes: Mark the excavation plane and control the excavation plane area S to be: S≥(D+150)×500 Wherein, D is the outer diameter of the sewage interception pipe; S222, plane manual excavation; S223. Pour the concrete pier and make the height of the concrete pier h, h≥500mm.

[0016] The advantageous effects of the narrow river slope sewage interception pipeline structure and pipeline laying method provided by the embodiments of the present invention include: The present invention provides a narrow river and creek earth slope sewage interception pipeline structure and pipeline laying method, including a sewage interception pipeline arranged along the river and a plurality of fixing components for fixing the sewage interception pipeline and the earth slope; wherein the fixing components include concrete piers artificially cast at the pipeline support points, and the sewage interception pipeline is supported by the plurality of concrete piers to achieve the laying of the sewage interception pipeline; wherein the positioning and pouring process of the concrete piers does not require the use of large-scale construction machinery and equipment, thereby avoiding the problem that the construction machinery and equipment cannot enter the construction site due to terrain reasons, resulting in the inability to lay the pipeline. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying any creative work.

[0018] Figure 1 A schematic structural diagram of the narrow river slope sewage interception pipeline structure provided in this embodiment from a first perspective; Figure 2 for Figure 1 A partial enlarged view of part A in the middle; Figure 3 A schematic diagram of the structure of the narrow river slope sewage interception pipeline structure provided in this embodiment from a second perspective; Figure 4 A schematic flow chart of the method for laying sewage interception pipes on earth slopes in narrow rivers and streams provided in this embodiment.

[0019] Icons: 100-River; 110-Slope; 200-Sewage interception pipeline; 300-fixing assembly; 310-concrete pier; 320-concrete pier fixing piece; 321-first fixing piece; 322-second fixing piece; 323-rebar connector; 400-pipe fixing piece; 410-third fixing piece; 420-fourth fixing piece; 500-House; 600-Sewage pipe. DETAILED DESCRIPTION

[0020] To make the objectives, technical solutions, and advantages of the embodiments of the present invention more clear, the technical solutions of the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings herein can be arranged and designed in various different configurations.

[0021] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention as claimed, but rather merely represents selected embodiments of the present invention. All other embodiments derived by persons of ordinary skill in the art based on the embodiments of the present invention without creative effort are intended to fall within the scope of protection of the present invention.

[0022] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, it does not need to be further defined or explained in subsequent drawings.

[0023] In the description of the present invention, it should be noted that if the terms "upper", "lower", "inside", "outside", etc. appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the accompanying drawings, or is the orientation or position relationship in which the product of the invention is usually placed when in use. It is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it should not be understood as a limitation on the present invention.

[0024] In addition, the terms "first", "second", etc., if used, are merely used to distinguish and describe, and should not be understood as indicating or implying relative importance.

[0025] It should be noted that, in the absence of conflict, the features in the embodiments of the present invention may be combined with each other.

[0026] With the urgency of sewage treatment, more and more sewage interception pipeline projects have been launched. At the same time, many unprecedented and difficult pipeline laying situations have also emerged. One of them is the need to intercept sewage from the earthen slopes on both sides of the river.

[0027] The following describes in detail the overall structure, working principle and technical effects of the narrow river slope sewage interception pipeline structure 110 provided by the present invention through examples and in combination with the accompanying drawings, as well as the detailed steps, implementation principles and technical effects of the corresponding narrow river slope sewage interception pipeline laying method.

[0028] Example 1: The narrow river slope sewage interception pipeline structure provided by the present invention is mainly used for pipeline construction work where there are many obstacles on both sides of the river 100, making it difficult for existing construction machinery and equipment to enter for construction.

[0029] See also Figure 1 and Figure 3 The present invention provides a narrow river slope sewage interception pipeline structure, which can be set on the slope 110 on both sides of the river 100 and used for sewage interception work of houses 500 on both sides of the slope 110.

[0030] Specifically, the houses 500 on both sides of the earth slope 110 are connected to the sewage pipe 600. The end of the sewage pipe 600 away from the house 500 is set toward the river 100. The sewage in the sewage pipe 600 is collected through the sewage interception pipe 200.

[0031] The present invention provides a narrow river earth slope sewage interception pipe structure, comprising a sewage interception pipe 200 arranged on earth slopes 110 on both sides of the river 100, and a fixing assembly 300 for fixing the sewage interception pipe 200 and the earth slope 110.

[0032] The sewage interception pipe 200 is arranged along the river 100 and is used to collect sewage discharged from multiple sewage pipes 600.

[0033] Specifically, the output end of the sewage pipe 600 can be set above the sewage interception pipe 200, and accordingly, an opening for sewage to enter is opened above the sewage interception pipe 200; or an opening is opened at a corresponding position of the sewage interception pipe 200, and the sewage pipe 600 is directly connected to the sewage interception pipe 200 through the opening.

[0034] In this embodiment, the fixing assembly 300 includes a concrete pier 310 for fixing the sewage interception pipe 200. The upper end of the concrete pier 310 is formed with a platform surface for supporting the sewage interception pipe 200, and the lower end of the concrete pier 310 is fixedly connected to the earth slope 110 through a concrete pier fixing member 320.

[0035] See also Figure 1 and Figure 2 In this embodiment, the concrete pier fixing member 320 includes two first fixing members 321 arranged perpendicular to the ground and two second fixing members 322 arranged perpendicular to the earth slope 110 .

[0036] In actual work, the ends of the first fixing member 321 and the second fixing member 322 away from the concrete pier 310 are driven into the earth slope 110 and are respectively connected to the earth slope 110; the other ends are respectively connected to the concrete pier 310. The two first fixing members 321 and the two second fixing members 322 form an oblique steel bar system in the concrete pier 310 to fix the concrete pier 310.

[0037] The arrangement of the first fixing member 321 and the second fixing member 322 can, on the one hand, support the concrete pier 310 and the sewage interception pipe 200 ; on the other hand, can also reinforce the earth slopes 110 on both sides of the river 100 .

[0038] In this embodiment, the first fixing member 321 and the second fixing member 322 are both multiple sections of connected anti-corrosion steel bars.

[0039] Specifically, each section of steel bar is connected by a steel bar connector 323; the length of each section of steel bar is , exemplary, It can be 0.5m, 1m, or 1.5m; the total length of the connected steel bars is L, and L≥3m. For example, L can be 3m, 4m, or 5m.

[0040] In this embodiment, the diameter of the steel bar is φ, φ≥28 mm; illustratively, φ can be 28 mm, 29 mm, or 30 mm.

[0041] Furthermore, both ends of the steel bars need to be pre-threaded using a CNC steel bar thread rolling machine, and the steel bars are fixed in the soil slope 110 by manual driving. For the geology of the relatively loose soil slope 110, a manual hydraulic driving method can be used; in other embodiments, manual hydraulic and other steel bar driving methods can also be used, and the operator can choose the steel bar driving method according to actual work needs.

[0042] Please continue reading Figure 2 In order to further fix the sewage interception pipe 200 and prevent the sewage interception pipe 200 from shifting and falling off, in this embodiment, a pipe fixing member 400 for fixing the sewage interception pipe 200 is provided on the concrete pier 310.

[0043] Furthermore, the pipe fixing member 400 includes a third fixing member 410 and a plurality of fourth fixing members 420 , wherein the third fixing member 410 is arranged around the outer wall of the sewage interception pipe 200 and is fixedly connected to the concrete pier 310 through the plurality of fourth fixing members 420 .

[0044] Specifically, the third fixing member 410 is a rubber belt or a steel plate with an arc-shaped structure, and the fourth fixing member 420 is an anchor bolt.

[0045] During the fixing process, the arc structure fits in contact with the outer wall of the sewage interception pipe 200 , and both ends of the arc structure are fixed to the concrete pier 310 via the fourth fixing member 420 .

[0046] In this embodiment, the sewage interception pipe 200 can be a HDPE pipe, a PVC pipe, a steel pipe or a ductile iron pipe.

[0047] It should be noted that when the sewage interception pipe 200 is an HDPE pipe or a PVC pipe, adjacent sewage interception pipes 200 can be hot-melt connected using portable hot-melt equipment; when the sewage interception pipe 200 is a steel pipe, adjacent sewage interception pipes 200 can be connected by welding; when the sewage interception pipe 200 is a ductile iron pipe, adjacent sewage interception pipes 200 can be connected by load-bearing connection.

[0048] For example, in this embodiment, the construction site on both sides of the river 100 is limited. In order to facilitate manual construction, the sewage interception pipe 200 is a PVC pipe.

[0049] The narrow river slope sewage interception pipeline structure provided in this embodiment can at least achieve the following technical effects: The concrete pier fixings 320 and the concrete pier 310 are both manually driven in and manually poured, so that when construction machinery and equipment are difficult to enter, fixed points for fixing the sewage interception pipe 200 can be set on the earth slope 110 on both sides of the river 100 to support the continuously installed sewage interception pipe 200; at the same time, the lightweight concrete pier 310 will not generate too much additional load on the slope surface of the earth slope 110, thereby avoiding the collapse of the earth slope 110 due to excessive bearing load.

[0050] Example 2: See also Figure 4 Based on the first embodiment, this embodiment provides a method for laying sewage interception pipes on a narrow river slope, including the following steps: S100, determining the arrangement points of multiple fixing components 300 as pipeline support points; In this embodiment, the sewage interception pipe 200 is arranged along the direction of the river 100. Accordingly, the pipe support points should be arranged along the direction of the river 100 or the direction of the earth slopes 110 on both sides of the river 100 to achieve the fixation of the sewage interception pipe 200.

[0051] Specifically, the method for determining the arrangement points of multiple fixing components 300 (i.e., pipeline support points) is: arranging them along the direction of the river 100, with the distance between adjacent fixing components 300 being d, d≤3500mm; the purpose of limiting the spacing between adjacent fixing components 300 is to reasonably control the arrangement density of the fixing components 300, so that the sewage interception pipeline 200 can be reliably fixed while reducing construction costs.

[0052] Furthermore, in order to enable the liquid phase in the sewage interception pipe 200 to be discharged smoothly, the sewage interception pipe 200 should have a certain slope as a whole. For example, the slope of the sewage interception pipe 200 is 0.1%-0.3%; accordingly, the elevation settings of the multiple fixed components 300 should meet the slope requirements of the sewage interception pipe 200.

[0053] For example, assuming that the total length of the sewage interception pipeline 200 is 1000m, the distance between adjacent fixed components 300 is d=3500m, and the slope of the sewage interception pipeline 200 is 3%; the elevation of the starting point (i.e., the first fixed component 300) is H 0, then the elevation of the nth fixed component 300 H n for:

[0054]

[0055] in, is the elevation difference between adjacent fixing assemblies 300 .

[0056] S200, setting a fixing assembly 300 at a corresponding pipeline support point; In this embodiment, after determining the pipeline support point, the method of setting the fixing assembly 300 at the corresponding pipeline support point includes the following steps: S210, installing a concrete pier fixing member 320 at the pipeline support point; Furthermore, the method of setting the concrete pier fixing member 320 at the pipeline support point includes the following steps: S211. Manually driving multiple anti-corrosion steel bars as first fixing members 321 in a direction perpendicular to the ground (i.e., vertical direction); Specifically, the number of the first fixing members 321 is two, and each first fixing member 321 is composed of multiple sections of anti-corrosion steel bars, and the multiple sections of anti-corrosion steel bars are connected by a steel bar connector 323.

[0057] S212, manually driving a plurality of steel bars as second fixing members 322 in a direction perpendicular to the soil slope 110; Specifically, the number of second fixing members 322 is two, and each second fixing member 322 is composed of multiple sections of anti-corrosion steel bars, and the multiple sections of anti-corrosion steel bars are connected by steel bar connectors 323.

[0058] In this embodiment, the first fixing member 321 and the second fixing member 322 are made of anti-corrosion steel bars with a diameter of not less than 28 mm; at the same time, the length of each steel bar is , exemplary, It can be 0.5m, 1m, or 1.5m; the total length of the connected steel bars (ie, the total length of the first fixing member 321 and the second fixing member 322) is L, L≥3m, and for example, L can be 3m, 4m, or 5m.

[0059] S220, excavating a plane at the pipeline support point, and pouring concrete at the plane to form a concrete pier 310; In this embodiment, the method of excavating a plane at a pipeline support point and pouring concrete at the plane to form a concrete pier 310 includes the following steps: S221. Mark the excavation plane and control the excavation plane area S for: S≥(D+150)×500 Wherein, D is the outer diameter of the sewage interception pipe 200.

[0060] S222, plane manual excavation; In this embodiment, the method of plane manual excavation is a conventional earthwork manual excavation operation, which includes using a pickaxe to break up the hard soil layer after on-site investigation, shoveling the soil with a shovel, and transporting the soil to a designated stacking point.

[0061] S223 , pouring the concrete pier 310 , and making the height of the concrete pier 310 h, h≥500 mm.

[0062] In this embodiment, the method of pouring the concrete pier 310 is a conventional manual pouring method, including preliminary pouring construction preparation, template production and installation, base treatment, concrete mixing, concrete pouring, formwork removal and maintenance, etc.; it should be noted that during the pouring process, it is necessary to ensure that the first fixing member 321 and the second fixing member 322 are in the calibrated position in the concrete pier 310.

[0063] Furthermore, lightweight concrete is used for pouring the concrete pier 310 .

[0064] S300 , the sewage interception pipe 200 is set up on the corresponding fixing assembly 300 , and the sewage interception pipe 200 is connected to the corresponding fixing assembly 300 through the pipe fixing member 400 .

[0065] In this embodiment, the method of connecting the sewage interception pipe 200 with the corresponding fixing assembly 300 through the pipe fixing member 400 is: the arc structure of the third fixing member 410 is fitted with the outer wall of the sewage interception pipe 200, and the two ends of the arc structure are fixed to the concrete pier 310 through the fourth fixing member 420.

[0066] In the method for laying sewage interception pipes on earthen slopes in narrow rivers and creeks provided in this embodiment, both the concrete pier fixing parts 320 and the concrete pier 310 are manually driven in and cast, so that when construction machinery and equipment are difficult to enter, fixed points for fixing sewage interception pipes 200 can be provided on the earthen slopes 110 on both sides of the river and creek 100 to support the continuously installed sewage interception pipes 200; this effectively solves the problem of sewage interception of the sewage pipes 600 on the earthen slopes 110 on both sides of the narrow river and creek site, and achieves economical, safe, efficient, environmentally friendly, and green and feasible effects.

[0067] The above description is only a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any changes or substitutions that can be easily conceived by any technician familiar with this technical field within the technical scope disclosed in the present invention should be covered by the scope of protection of the present invention.

Claims

1. A narrow river slope sewage interception pipeline structure, characterized in that: It is arranged on the earth slope (110) on both sides of the river (100), including: A sewage interception pipeline (200), the sewage interception pipeline (200) is arranged along the river (100) and connected to the soil slope (110) via a plurality of fixing components (300); The fixing assembly (300) comprises a concrete pier (310) for fixing the sewage interception pipe (200), and the concrete pier (310) is connected to the earth slope (110) via a concrete pier fixing member (320).

2. The narrow river slope sewage interception pipeline structure according to claim 1 is characterized in that: The concrete pier fixing member (320) includes a first fixing member (321) arranged perpendicular to the ground and a second fixing member (322) arranged perpendicular to the earth slope (110); One end of the first fixing member (321) and the second fixing member (322) are respectively connected to the earth slope (110), and the other end are respectively connected to the concrete pier (310).

3. The narrow river slope sewage interception pipeline structure according to claim 2 is characterized in that: The first fixing member (321) and the second fixing member (322) both include multiple sections of steel bars; The multiple sections of steel bars are connected via steel bar connectors (323); The total length of the connected steel bars is L, and L≥3m.

4. The narrow river slope sewage interception pipeline structure according to claim 1 is characterized in that: The concrete pier (310) is also provided with a pipe fixing member (400) for fixing the sewage interception pipe (200); The pipe fixing member (400) comprises a third fixing member (410) and a plurality of fourth fixing members (420); the third fixing member (410) is arranged around the outer wall of the sewage interception pipe (200) and is fixedly connected to the concrete pier (310) via the plurality of fourth fixing members (420).

5. The narrow river slope sewage interception pipeline structure according to claim 4 is characterized in that: The third fixing member (410) is a rubber belt or a steel plate, and the fourth fixing member (420) is an anchor bolt.

6. A method for laying sewage interception pipes on narrow river slopes, characterized in that: include: Determining the arrangement points of the plurality of fixed components (300) as pipeline support points; Setting a fixing assembly (300) at a corresponding pipe support point; The sewage interception pipe (200) is mounted on a plurality of fixing assemblies (300), and the sewage interception pipe (200) is connected to the corresponding fixing assemblies (300) via pipe fixing members (400).

7. The method for laying sewage interception pipes on narrow river slopes according to claim 6 is characterized in that: The method for determining the arrangement points of the plurality of fixed components (300) is as follows: arranging them along the direction of the stream (100), with the distance between adjacent fixed components (300) being d, d≤3500 mm.

8. The method for laying sewage interception pipes on narrow river slopes according to claim 6 is characterized in that: The method for setting a fixing assembly (300) at a corresponding pipeline support point comprises: Setting a concrete pier fixing member (320) at the pipeline support point; A plane is excavated at the pipe support point, and concrete piers (310) are cast at the plane.

9. The method for laying sewage interception pipes on narrow river slopes according to claim 8, characterized in that: A method for setting a concrete pier fixing member (320) at a pipeline support point comprises: In the vertical direction, manually driving a plurality of steel bars as first fixing members (321); In a direction perpendicular to the soil slope (110), multiple steel bars are manually driven in as second fixing members (322).

10. The method for laying sewage interception pipes on earth slopes in narrow rivers and streams according to claim 8, characterized in that: A method for excavating a plane at a pipe support point and pouring concrete at the plane to form a concrete pier (310) includes: Mark the excavation plane and control the excavation plane area S for: S ≥( D +150)×500 in, D is the outer diameter of the sewage interception pipe (200); S222, plane manual excavation; S223, pouring the concrete pier (310), and making the height of the concrete pier (310) h, h≥500mm.

Citation Information

Patent Citations

  • Reinforcing installation method for anti-buoyancy of rain and sewage pipe concrete encapsulation

    CN119411675A

  • Combination formula buttress structure of river -side house pipeline laying

    CN206512828U

  • Frame pipe type sewage intercepting pipeline

    CN211113990U

  • Pipeline fixing structure for abrupt slope in riverbed

    CN211665853U

  • Sewage collection pipe network arrangement structure for residents along river

    CN214143998U