Arrangement method for multi-section unloading structure of vertical high draw shaft
By setting up anti-collision devices at the sectional joints of vertically high shafts, the problems of slag stone falling and splashing are solved, the safety and production efficiency of shafts are improved, and the safety risks are reduced.
Patent Information
- Application Number
- CN202510808226.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-06-17
- Publication Date
- 2025-08-15
AI Technical Summary
The existing vertical high-slide structure has problems such as falling, splashing and easy damage to slags at the sectional unloading ports, resulting in high risk of equipment damage and personnel safety, and high risk of replacement of isolation.
Anti-collision devices are installed at the connection port between the segmented joints and vertical high shafts, including concrete suspended walls, ringed inverted wedge hanging piles, series wire ropes and steel structure cross beams. A stable mesh structure is formed through concrete pouring to enhance connection stability and impact resistance.
It effectively avoids the risk of slag and stone pouring into the lower sectional duct, reduces the safety risks of equipment and personnel, improves production safety and unloading efficiency, and reduces the frequency of isolating replacement.
Smart Images

Figure CN120487108A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of mining chute construction, and in particular to a method for arranging a multi-segment unloading structure for a vertical high chute. Background Art
[0002] In mining production, with the continuous maturity of raise-boring technology, vertical high-pass chutes are widely used. Typically, each segmented mine tunnel is connected to the high-pass chutes to form an unloading chamber. Ore (slag) produced from multiple segments is unloaded at different elevations in the same chutes in different time periods, which can accelerate mine construction and improve production and transportation efficiency.
[0003] At present, for the current vertical high chute structure, iron sheets or meshes are mostly used for blocking and isolation at the connection between the unloading port of each segmented ore (slag) channel and the chute to ensure the safety of production operations and normal operation of construction.
[0004] However, this method of using iron sheets or mesh has many problems: when shoveling operations reach the unloading port, some slag in the upper section of the chute will fall through the gap to the section port, which may cause damage to the equipment; when the same chute is used simultaneously up and down, a large amount of slag in the upper section will break through the barrier and flow into the lower section unloading port, affecting the slag chute operation in the lower section; during shoveling operations, large pieces of slag with potential energy will flow into the lower section unloading port through the incision, which may cause splashing and injuring people, endangering the safety of the operators.
[0005] At the same time, mesh isolation materials such as iron sheets cannot completely and effectively block flying rocks, and are easily damaged and cannot be used for a long time. The isolation materials need to be replaced from time to time, and the replacement operation is risky. In addition, since the unloading ports of each section are connected to the main transport tunnel at a short distance, there is a possibility that floating rocks in the chute will splash into the main transport tunnel, affecting the shoveling operation and the passage of personnel, and the safety risk is high. Summary of the Invention
[0006] In order to solve or partially solve the problems existing in the related technology, the present application provides a layout method for a multi-segment unloading structure of a vertical high chute, which can ensure the safety of the chute and effectively ensure the safety of production operations and normal operation of construction.
[0007] The present application provides a method for arranging a multi-segment unloading structure for a vertical high chute, wherein the multi-segment unloading structure comprises: a vertical high chute and a plurality of segmented connecting channels, wherein an anti-collision device is provided at the connection between each segmented connecting channel and the vertical high chute; The anti-collision device comprises: a concrete hanging wall, a ring-mounted inverted wedge hanging pile, a series of steel wire ropes, and a steel structure crossbeam; the ring-mounted inverted wedge hanging pile is embedded in the rock mass at the connection port of the segmented link; the concrete hanging wall is installed at the connection port of the segmented link via the ring-mounted inverted wedge hanging pile; the series of steel wire ropes pass through the rings of the ring-mounted inverted wedge hanging pile to form a mesh structure, serving as the internal steel structure skeleton of the concrete hanging wall; the steel structure crossbeam is installed at the bottom of the concrete hanging wall; The arrangement method comprises the following steps: Step 1: embed and install the ring-shaped inverted wedge hanging pile into the rock mass at the connection port of the segmented joint; Step 2: Pass the series steel wire rope through the rings of each of the ring-wedge hanging piles to form a mesh structure; Step 3: Place the steel structure beam on the two ring-shaped inverted wedge hanging piles on both sides of the rock mass bottom, and weld the steel structure beam to the ring-shaped inverted wedge hanging piles; Step 4: Formwork is provided on both sides of the hanging pile with ring and inverted wedge, and concrete is poured to form the concrete hanging wall after the pouring is completed.
[0008] Optionally, in some embodiments of the present application: Before step 1, the arrangement method further includes: Determine the size of the concrete hanging wall according to the size of the connection port of the segmented joint; The diameter and embedding depth of the ring-mounted inverted wedge hanging pile are determined according to the size of the concrete hanging wall.
[0009] Optionally, in some embodiments of the present application: The installation interval between the ring-wedge hanging piles is 30cm-50cm; The number of the ring-shaped inverted wedge hanging piles to be installed is determined based on the cross-sectional size of the segmented joint and the installation interval.
[0010] Optionally, in some embodiments of the present application: This step 1 specifically includes: Determining a preset position of the concrete hanging wall according to the size of the concrete hanging wall; One inverted wedge hanging pile with a ring is installed in the rock mass on both sides of the bottom of the preset position, and then the remaining inverted wedge hanging piles with rings are installed in the rock mass at equal intervals.
[0011] Optionally, in some embodiments of the present application: The hanging pile with an inverted wedge is vertically embedded and installed in the rock mass.
[0012] Optionally, in some embodiments of the present application: An unloading port is provided at the connection port of the segmented link, and the unloading port is located at the bottom position of the concrete hanging wall.
[0013] Optionally, in some embodiments of the present application: The slope of the unloading port is greater than the natural repose angle of the slag.
[0014] Optionally, in some embodiments of the present application: The vertical high chute is constructed in one go by a raise drilling rig, and the shaft diameter is determined according to demand; The segmented link is designed and constructed according to the size of the unloading equipment.
[0015] The technical solution provided by this application may have the following beneficial effects: This application sets up a multi-segment unloading structure, which can realize the simultaneous operation of multiple sections of the high chute unloading and improve the utilization rate of the chute.
[0016] This application sets an anti-collision device, which can be integrated with the chute wall after construction is completed, effectively reducing the exposed area of the unloading port area. At the same time, the anti-collision device has high strength and impact resistance, and the structure is stable and durable, effectively avoiding the safety risks brought by repeated replacement of isolation materials, and can also avoid the risk of floating stones in the chute splashing to the segmented connecting track. When unloading multiple sections of a high chute at the same time, the anti-collision device can effectively improve the safety of the lower segment unloading operation area, avoid slag and stone from pouring into the lower segmented connecting track, reduce the safety risks of shoveling equipment and personnel, and effectively improve production safety.
[0017] It should be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The above and other objects, features and advantages of the present application will become more apparent through a more detailed description of exemplary embodiments of the present application in conjunction with the accompanying drawings, wherein the same reference numerals generally represent the same components in the exemplary embodiments of the present application.
[0019] Figure 1 This is a schematic cross-sectional view of a multi-segment unloading structure in an embodiment of the present application; Figure 2 is a structural diagram of an anti-collision device in an embodiment of the present application; Figure 3 It is a structural diagram of the arrangement method in the embodiment of the present application.
[0020] Figure numerals: 1-concrete hanging wall; 2-hanging pile with ring and inverted wedge; 3-series steel wire rope; 4-steel structure beam; 5-unloading port; 6-vertical high chute; 7-segmented connecting channel; 8-rock mass. DETAILED DESCRIPTION
[0021] The following describes embodiments of the present application in more detail with reference to the accompanying drawings. Although the accompanying drawings illustrate embodiments of the present application, it should be understood that the present application can be implemented in various forms and should not be limited by the embodiments described herein. Rather, these embodiments are provided to make the present application more thorough and complete, and to fully convey the scope of the present application to those skilled in the art.
[0022] It should be understood that although the terms "first", "second", "third", etc. may be used in this application to describe various information, this information should not be limited to these terms. These terms are only used to distinguish information of the same type from each other. For example, without departing from the scope of this application, the first information may also be referred to as the second information, and similarly, the second information may also be referred to as the first information. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0023] In the description of this application, it should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the accompanying drawings, and are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on this application.
[0024] Unless otherwise expressly specified or limited, terms such as "mounted," "connected," "connect," and "fixed" should be interpreted broadly. For example, they may refer to fixed or detachable connections, or integration; mechanical or electrical connections; direct or indirect connections through an intermediary; and internal communication between two components or interaction between two components. Those skilled in the art will understand the specific meanings of these terms in this application based on the specific circumstances.
[0025] At present, for the current vertical high chute structure, iron sheets or meshes are mostly used for blocking and isolation at the connection between the unloading port of each segmented ore (slag) channel and the chute to ensure the safety of production operations and normal operation of construction.
[0026] However, this method of using iron sheets or mesh has many problems: when shoveling to the unloading port, some slag in the upper section of the chute will fall through the gap to the section port, which may cause damage to the equipment; when the same chute is used simultaneously, there is a possibility that a large amount of slag in the upper section will break through the barrier and flow into the lower section unloading port, affecting the slag shoveling operation in the lower section; during shoveling operations, large pieces of slag with potential energy will flow through the incision into the lower section unloading port, which may cause splashing and injuring people, endangering the safety of the workers. At the same time, mesh isolation materials such as iron sheets cannot completely and effectively block flying rocks, and are easily damaged and cannot be used for a long time. The isolation materials need to be replaced from time to time, which has a high risk of replacement operations. In addition, since the unloading ports of each section are connected to the main transport tunnel at a short distance, there is a possibility that floating rocks in the chute will splash into the main transport tunnel, affecting the shoveling operation and the passage of personnel, and posing a high safety risk.
[0027] In response to the above problems, an embodiment of the present application provides a method for arranging a multi-segment unloading structure for a vertical high chute, which can ensure the safety of the chute and effectively ensure the safety of production operations and normal construction operation.
[0028] The technical solutions of the embodiments of the present application are described in detail below with reference to the accompanying drawings.
[0029] Figure 1 This is a schematic cross-sectional view of a multi-segment unloading structure in an embodiment of the present application; Figure 2 is a structural diagram of an anti-collision device in an embodiment of the present application; Figure 3 It is a structural diagram of the arrangement method in the embodiment of the present application.
[0030] See also Figure 1 A method for arranging a multi-segment unloading structure for a vertical high chute, wherein the multi-segment unloading structure for a vertical high chute includes: a vertical high chute 6 and a plurality of segmented connecting channels 7, and an anti-collision device is provided at the connection port between each segmented connecting channel 7 and the vertical high chute 6.
[0031] Specifically, the vertical high chute 6 is formed in one step by a raise boring machine, and the shaft diameter is determined according to actual construction requirements. The segmented channel 7 is formed according to the design and construction size of the unloading equipment.
[0032] In this embodiment, the diameter and shape of the shaft can be effectively controlled through a one-step construction method, ensuring the shaft's stability and load-bearing capacity, and reducing the need for subsequent maintenance. The size and shape of the segmented duct 7 are determined by the size of the unloading equipment, ensuring the normal operation of subsequent unloading operations.
[0033] The anti-collision device includes: a concrete hanging wall 1, a ring-mounted inverted wedge hanging pile 2, a series of steel wire ropes 3 and a steel structure crossbeam 4; the ring-mounted inverted wedge hanging pile 2 is embedded in the rock mass 8 at the connection port of the segmented link 7; the concrete hanging wall 1 is installed at the connection port of the segmented link 7 through the ring-mounted inverted wedge hanging pile 2; the series of steel wire ropes 3 pass through the rings of the ring-mounted inverted wedge hanging pile 2 and are connected into a mesh structure, serving as the internal steel structure skeleton of the concrete hanging wall 1; the steel structure crossbeam 4 is installed at the bottom of the concrete hanging wall 1.
[0034] In this embodiment, the concrete hanging wall 1 is embedded in the rock mass 8 by using a ring-shaped inverted wedge hanging pile 2, which can effectively fix the wall and the rock mass 8 to ensure the stable installation of the concrete hanging wall 1. By using a series of steel wire ropes 3 inside the wall to pass through the hanging pile rings to form a network, a steel structure skeleton inside the wall can be formed. This connection method ensures the firmness of each connection point and avoids the disconnection problem between the steel bar binding and the hanging pile. At the same time, by using steel structure materials as beams 4 at the bottom of the wall, the wear of the ore body on the lower part of the wall during unloading can be effectively reduced.
[0035] Specifically, an unloading port 5 is provided at the connection port of the segmented connecting channel 7, and the unloading port 5 is located at the bottom of the concrete hanging wall 1. The slope of the unloading port 5 is greater than the natural repose angle of the slag.
[0036] In this embodiment, by setting the unloading port 5, the ore can be unloaded more conveniently. At the same time, by setting the slope of the unloading port 5 to be greater than the natural repose angle of the slag, it can be ensured that the ore can slide smoothly during the unloading process, avoiding the ore being retained at the unloading port 5 due to insufficient slope, thereby ensuring unloading efficiency.
[0037] The arrangement method in this embodiment includes the following steps: S100: Step 1: embed and install the ring-mounted inverted wedge hanging pile 2 into the rock mass 8 at the connection port of the segmented connecting channel 7; Specifically: according to the size of the concrete hanging wall 1, the preset position of the concrete hanging wall 1 is determined; a ring-mounted inverted wedge hanging pile 2 is installed in the rock mass 8 on both sides of the bottom of the preset position, and then the remaining ring-mounted inverted wedge hanging piles 2 are installed in the rock mass 8 at equal intervals.
[0038] In this embodiment, by installing the ring-mounted inverted wedge hanging piles 2 at equal intervals, the force applied to each ring-mounted inverted wedge hanging pile 2 can be effectively dispersed, thereby improving the installation stability and impact resistance.
[0039] Specifically, the installation interval between the ring-mounted inverted wedge hanging piles 2 is 30 cm; the installation quantity of the ring-mounted inverted wedge hanging piles 2 is determined according to the cross-sectional size of the connecting port of the segmented connecting channel 7 and the installation interval.
[0040] In this embodiment, the circumference of the segmented duct 7 connection opening can be determined based on the cross-sectional dimensions of the connection opening and the installation spacing. This circumference is then divided by the installation spacing to determine the number of ring-mounted inverted wedge hanging stakes 2 to be installed. If the circumference is not divisible by an even number, the number of ring-mounted inverted wedge hanging stakes 2 to be installed is rounded up to ensure an even distribution of the hanging stakes 2 along the entire circumference.
[0041] Specifically, the ring-mounted inverted wedge hanging pile 2 is vertically embedded in the rock mass 8 .
[0042] In this embodiment, by vertically installing the ring-mounted inverted wedge hanging pile 2, the installation stability of the entire structure can be improved.
[0043] Specifically: before step 1, the arrangement method further includes: The size of the concrete hanging wall 1 is determined according to the size of the connecting port of the segmented connecting channel 7. This ensures that the concrete hanging wall 1 can effectively cover the connecting port, reduce the exposed area of the unloading port 5 area, and ensure production safety.
[0044] The diameter and embedment depth of the ring-wedge hanging pile 2 are determined based on the size of the concrete suspended wall 1. This ensures the load-bearing capacity and stability of the hanging pile 2, and ensures the stability of the subsequent installation of the concrete suspended wall 1. Specifically, when the length and width of the concrete suspended wall 1 are greater than 3 meters, a ring-wedge hanging pile 2 with a diameter of φ30 mm and an embedment depth of no less than 60 cm is selected.
[0045] S200: Step 2: Pass the series steel wire rope 3 through the rings of each of the ring-wedge hanging piles 2 to connect them into a mesh structure.
[0046] In this embodiment, by using a series of steel wire ropes 3 to pass through the rings of the ring-wedge hanging piles 2, a mesh structure is connected to serve as the internal steel structure skeleton of the concrete hanging wall 1. This can ensure the firmness of each connection point, avoid the disconnection problem between the steel bar binding and the hanging piles 2, and ensure the stability and durability of the subsequent pouring of the concrete hanging wall 1.
[0047] S300: Step 3: Place the steel structure beam 4 on the two ring-mounted inverted wedge hanging piles 2 on both sides of the bottom of the rock mass 8, and weld the steel structure beam 4 to the ring-mounted inverted wedge hanging piles 2 to fix them.
[0048] In this embodiment, the steel structure beam 4 is a channel steel, and the thickness of the channel steel corresponds to the thickness of the concrete suspended wall 1. Through welding, the steel structure beam 4 can be effectively fixed to ensure the normal progress of subsequent concrete pouring work. At the same time, the steel structure beam 4 can effectively reduce the wear of the ore body on the lower part of the wall during unloading, thereby improving the stability and durability of the concrete suspended wall 1.
[0049] S400: Step 4: Formwork is provided on both sides of the ring-shaped inverted wedge hanging pile 2, and concrete is poured. After the pouring is completed, the concrete hanging wall 1 is formed. Thus, the construction and production of the anti-collision device is completed.
[0050] In this embodiment, after the concrete pouring construction is completed, the anti-collision device can be integrated with the chute wall, effectively reducing the exposed area of the unloading port 5 area. At the same time, the anti-collision device has high strength and impact resistance, and the structural stability and durability are strong, which effectively avoids the safety risks brought by repeated replacement of isolation materials. It can also avoid the risk of floating stones in the chute splashing to the segmented link 7. When unloading multiple sections of the high chute at the same time, the anti-collision device can effectively improve the safety of the lower segment unloading operation area, avoid slag and stone from pouring into the lower segmented link 7, reduce the safety risks of shoveling equipment and personnel, and effectively improve production safety.
[0051] The technical solutions in the embodiments of the present application include the following beneficial effects: This application sets up a multi-segment unloading structure, which can realize the simultaneous operation of multiple sections of the high chute unloading and improve the utilization rate of the chute.
[0052] This application sets an anti-collision device, which can be integrated with the chute wall after construction is completed, effectively reducing the exposed area of the unloading port area. At the same time, the anti-collision device has high strength and impact resistance, and the structure is stable and durable, effectively avoiding the safety risks brought by repeated replacement of isolation materials, and can also avoid the risk of floating stones in the chute splashing to the segmented connecting track. When unloading multiple sections of a high chute at the same time, the anti-collision device can effectively improve the safety of the lower segment unloading operation area, avoid slag and stone from pouring into the lower segmented connecting track, reduce the safety risks of shoveling equipment and personnel, and effectively improve production safety.
[0053] Finally, it should be noted that, in this document, relationships such as first and second, etc., are used solely to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations. Moreover, the terms include, comprise, or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that includes a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, article, or apparatus.
[0054] The embodiments of the present application have been described above. The above description is illustrative and not exhaustive, and is not limited to the disclosed embodiments. Many modifications and variations will be apparent to those skilled in the art without departing from the scope and spirit of the described embodiments. The terminology used herein is selected to best explain the principles of the embodiments, their practical applications, or improvements to the technology in the market, or to enable other persons skilled in the art to understand the embodiments disclosed herein.
Claims
1. A method for arranging a multi-segment unloading structure for a vertical high chute, characterized in that: The vertical high chute multi-segment unloading structure includes: a vertical high chute and a plurality of segmented connecting channels, and an anti-collision device is provided at the connection between each segmented connecting channel and the vertical high chute; The anti-collision device comprises: a concrete hanging wall, a ring-mounted inverted wedge hanging pile, a series of steel wire ropes, and a steel structure crossbeam; the ring-mounted inverted wedge hanging pile is embedded in the rock mass at the connection port of the segmented link; the concrete hanging wall is installed at the connection port of the segmented link via the ring-mounted inverted wedge hanging pile; the series of steel wire ropes pass through the rings of the ring-mounted inverted wedge hanging pile to form a mesh structure, which serves as the internal steel structure skeleton of the concrete hanging wall; the steel structure crossbeam is installed at the bottom of the concrete hanging wall; The arrangement method comprises the following steps: Step 1: embedding and installing the ring-mounted inverted wedge hanging pile into the rock mass at the connection port of the segmented joint; Step 2: Pass the series steel wire ropes through the rings of the ring-mounted inverted wedge hanging piles to form a mesh structure; Step 3: Place the steel structure beam on the two ring-shaped inverted wedge hanging piles on both sides of the rock mass bottom, and weld the steel structure beam to the ring-shaped inverted wedge hanging piles; Step 4: Formwork is provided on both sides of the ring-shaped inverted wedge hanging pile, and concrete is poured to form the concrete hanging wall after the pouring is completed.
2. The method for arranging a multi-segment unloading structure for a vertical high chute according to claim 1, characterized in that: Before step 1, the arrangement method further includes: Determine the size of the concrete hanging wall according to the size of the connection port of the segmented joint; The diameter and embedding depth of the ring-mounted inverted wedge hanging pile are determined according to the size of the concrete hanging wall.
3. The method for arranging a multi-segment unloading structure for a vertical high chute according to claim 2, characterized in that: The installation interval between the ring-wedge hanging piles is 30cm-50cm; The number of the ring-mounted inverted wedge hanging piles to be installed is determined according to the cross-sectional dimensions of the segmented joint and the installation spacing.
4. The method for arranging a multi-segment unloading structure for a vertical high chute according to claim 3, characterized in that: The step 1 specifically includes: Determining a preset position of the concrete hanging wall according to the size of the concrete hanging wall; One inverted wedge hanging pile with a ring is installed in the rock mass on both sides of the bottom of the preset position, and then the remaining inverted wedge hanging piles with rings are installed in the rock mass at equal intervals.
5. The method for arranging a multi-segment unloading structure for a vertical high chute according to claim 4, characterized in that: The hanging pile with an inverted wedge is vertically embedded and installed in the rock mass.
6. The method for arranging a multi-segment unloading structure for a vertical high chute according to claim 1, characterized in that: An unloading port is provided at the connection port of the segmented link, and the unloading port is located at the bottom position of the concrete hanging wall.
7. The method for arranging a multi-segment unloading structure for a vertical high chute according to claim 6, characterized in that: The slope of the unloading port is greater than the natural repose angle of the slag.
8. The method for arranging a multi-segment unloading structure for a vertical high chute according to claim 1, characterized in that: The vertical high chute is formed in one step by a raise drilling rig; The segmented link is designed and constructed according to the size of the unloading equipment.