Structure for arranging portal crane track on side wall of hoist room and construction method
By laying the working arc door track on the side wall of the opening and closing machine room in the flood discharge gate and using the side wall to provide lateral support, the problem of increasing concrete usage in traditional solutions is solved, and the construction period is shortened and investment savings are achieved.
Patent Information
- Application Number
- CN202510755486.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-06-06
- Publication Date
- 2025-08-22
AI Technical Summary
Traditional solutions increase the height of the gate pier in the flood discharge gate to provide lateral support for the working arc door, resulting in an increase in concrete usage, extended construction period and increased investment, which is not economical.
The working arc door track is arranged on the side wall of the opening and closing machine room, and the side wall of the opening and closing machine room provides lateral support, reducing the pouring of the dam top concrete, and connecting the side wall of the opening and closing machine room with a frame structure with the inserts to ensure the stable operation of the arc door.
While ensuring the safety and stability of arc doors, the amount of concrete is reduced, the construction period is shortened and investment is saved, while improving the aesthetics of the project.
Smart Images

Figure CN120520196A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of water conservancy and hydropower engineering, and in particular to a structure and construction method in which a gantry crane track is arranged on the side wall of a hoisting machine room. Background Art
[0002] As a structure that retains and releases water in a sluice project, spillways are crucial to the project's safe operation. With global warming, the hydrological and meteorological conditions of the rivers where the project is located are changing, and the spillways may experience excessive flooding. Therefore, open spillways should be preferred in the project design. When the working arc gate of an open spillway gate is raised to release floodwater, the overflow surface of the water inside the gate is high. The bottom of the working arc gate must be elevated a certain height above the overflow surface, which can easily cause the middle and upper part of the working arc gate to extend beyond the top of the gate pier. Without lateral support, the gate will wobble, affecting its safe operation. To ensure lateral support when the working arc gate is raised to release floodwater, the traditional solution is to partially raise the piers near the gate to ensure that the gate is always within the pier elevation range. However, the lateral force of the working arc gate is very small, and only rigid lateral support is required when the gate is raised to release floodwater. Raising the gate piers increases the amount of concrete and steel required, which in turn increases the construction time and investment, making it uneconomical. Summary of the Invention
[0003] The first aspect of the present application provides a structure in which the gantry crane track is arranged on the side wall of the hoisting machine room. This structure can reduce the pouring of dam top concrete while ensuring the safe and stable operation of the working arc gate, speed up the construction period and save investment.
[0004] The pier arrangement structure of the working arc gate track of the flood discharge gate provided in the first aspect of the present application includes: a hoisting and closing machine room, the hoisting and closing machine room is located on the top of the flood discharge gate pier, and the hoisting and closing machine room has a side wall; An arc gate slot, the arc gate slot comprising a first slot section and a second slot section, the arc length of the first slot section being greater than the arc length of the second slot section, the first slot section being located within the flood discharge gate pier, the second slot section being located within the side wall of the hoisting machine room, the first slot section and the second slot section being connected to each other at the junction of the flood discharge gate pier and the hoisting machine room, and the second slot section extending a preset height on the side wall along the arc extension direction of the first slot section; A working arc door track is arranged in the first slot section and the second slot section.
[0005] In addition, the gate pier arrangement structure provided in this application may also have the following additional technical features: In an optional solution, the top elevation of the second trough section is not higher than the bottom line of the beam of the hoisting machine room, and a notch is reserved in the beam body of the hoisting machine room at the position corresponding to the second trough section, and the depth of the notch is 5 cm.
[0006] In an optional solution, the hoisting machine room adopts a frame structure, the side walls of the hoisting machine room are reinforced concrete walls, and the steel bars of the side walls are anchored in the beams and columns of the hoisting machine room and the piers of the flood discharge gate.
[0007] In an optional solution, the two sides of the working arc door track are respectively pre-embedded in the first groove section and the second groove section through multiple dowel bars, and the multiple dowel bars are arranged at intervals along the extension direction of the first groove section and the second groove section. The dowel bars located in the second groove section are anchored to the steel bars of the side wall.
[0008] A second aspect of the present application provides a construction method for constructing a structure in which a gantry crane track is arranged on a side wall of a hoist room as provided in the first aspect, the construction method comprising the following steps: 1) Fabricate and install the reinforcement of the flood discharge gate piers according to the design requirements and cast the first phase of concrete for the piers in the formwork. The reinforcement on the top surface of the piers must reserve anchorage length for welding with the reinforcement of the side walls of the hoist room. Embed reinforcement in the gate slot on the side of the piers. 2) Install the metal structural embedded parts of the working arc door track and weld them to the pre-embedded dowel bars; 3) Fabricate and install the frame columns, beams and side walls of the gate opening position of the hoisting and closing machine room according to the design requirements. The bottom of the side walls of the hoisting and closing machine room steel bars are welded to the gate pier, the top to the beam, and the upstream and downstream sides to the columns to form a whole. Pre-embed rebars are placed in the gate slots of the side walls. Concrete is poured for the columns, beams and side walls. A 5cm deep notch is reserved in the beam at the working gate track position to prevent the gate from hitting the wall. The height of the side walls must meet the requirements of the gate always being within the gate pier elevation range and the flood discharge requirement of the verification flood. The thickness of the side walls must meet the lateral thrust requirements of the working gate.
[0009] The beneficial effects of this application are: The gate pier arrangement structure in the present application arranges the opening and closing machine room of the working arc gate above the arc gate slot, and the second slot section of the arc gate slot is set on the side wall of the opening and closing machine room. When the working arc gate is started, the side wall of the opening and closing machine room can be used to provide lateral support for the working arc gate, which can reduce the pouring of dam top concrete while ensuring the safe and stable operation of the working arc gate, speed up the construction period, save investment, and the flat dam top is also more beautiful.
[0010] It should be understood that the foregoing general description and the following detailed description are merely illustrative and are not restrictive of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 A schematic structural diagram of a gate pier arrangement structure provided in this application in a specific embodiment; Figure 2 This is a schematic diagram of the arrangement structure of the second trough section on the side wall provided by this application; Figure 3 for Figure 2 A schematic diagram of a partial cross-sectional structure at AA; Figure 4 for Figure 2 Schematic diagram of the partial cross-section structure at BB.
[0012] Figure numerals: hoisting and closing machine room 1, side wall 11, steel bar 12, flood discharge gate pier 2, arc gate slot 3, first slot section 31, second slot section 32, working arc gate track 4, dowel bar 41, beam bottom line 5, flood water surface line for verification 6.
[0013] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application. DETAILED DESCRIPTION
[0014] In order to better understand the technical solution of the present application, the embodiments of the present application are described in detail below with reference to the accompanying drawings.
[0015] It should be clear that the embodiments described are only part of the embodiments of this application, not all of the embodiments. Based on the embodiments in this application, all other technical solutions obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.
[0016] The terms used in the embodiments of the present application are for the purpose of describing specific embodiments only and are not intended to limit the present application. The singular forms "a", "an", "the" and "the" used in the embodiments of the present application and the appended claims are also intended to include plural forms unless the context clearly indicates otherwise.
[0017] It should be understood that the term "and / or" as used herein is merely a description of the relationship between associated objects, indicating that three possible relationships exist. For example, "A and / or B" can represent: A exists alone, A and B exist simultaneously, or B exists alone. Furthermore, the character " / " in this document generally indicates that the associated objects are in an "or" relationship.
[0018] It should be noted that the directional words such as "upper", "lower", "left", and "right" described in the embodiments of the present application are described based on the angles shown in the accompanying drawings and should not be understood as limiting the embodiments of the present application. In addition, in the context, it should be understood that when it is mentioned that an element is connected to another element "on" or "under", it can not only be directly connected to the other element "on" or "under", but also be indirectly connected to the other element "on" or "under" through an intermediate element.
[0019] like Figure 1-4As shown, the first aspect of the embodiment of the present application provides a structure in which a gantry track is arranged on the side wall of the hoisting machine room, and the structure mainly includes a hoisting machine room 1, an arc gate slot 3 and a working arc gate track 4. Among them, the hoisting machine room 1 is located on the top of the flood discharge gate pier 2, and the hoisting machine room 1 has a side wall 11; the arc gate slot 3 includes a first slot section 31 and a second slot section 32, the arc length of the first slot section 31 is greater than the arc length of the second slot section 32, the first slot section 31 is located in the flood discharge gate pier 2, and the second slot section 32 is located in the side wall 11 of the hoisting machine room 1, the first slot section 31 and the second slot section 32 are connected to each other at the junction of the flood discharge gate pier 2 and the hoisting machine room 1, and the second slot section 32 extends a preset height on the side wall 11 along the arc extension direction of the first slot section 31; the working arc gate track 4 is arranged in the first slot section 31 and the second slot section 32. Specifically, the working arc gate track 4 is used to install the working arc gate. Generally speaking, the working arc gate is installed between two oppositely arranged working arc gate tracks 4 and can slide relative to the working arc gate track 4. When the arc gate is opened, the first groove section 31 located in the flood discharge gate pier 2 and the second groove section 32 on the side wall 11 can provide lateral support for the arc gate.
[0020] The pier arrangement structure in this embodiment arranges the operating arc gate's hoisting and closing machine room 1 above the arc gate slot 3, and the second slot section 32 of the arc gate slot 3 is provided on the side wall 11 of the hoisting and closing machine room 1. When the working arc gate is started, the side wall 11 of the hoisting and closing machine room 1 can provide lateral support for the working arc gate, which can reduce the pouring of dam top concrete while ensuring the safe and stable operation of the working arc gate, speed up the construction period, save investment, and the flat dam top is more beautiful.
[0021] like Figure 1-2 As shown, in a specific embodiment, the top elevation of the second slot section 32 is not higher than the bottom line 5 of the beam of the gate room 1, and a slot is reserved in the beam body of the gate room 1 at the position corresponding to the second slot section 32, and the depth of the slot is 5 cm, so as to prevent the working arc door from hitting the wall.
[0022] like Figure 1-4 As shown, in a specific embodiment, the hoisting machine room 1 adopts a frame structure, and the side wall 11 of the hoisting machine room 1 is a reinforced concrete wall 12, and the steel bars 12 of the side wall 11 are anchored in the beams, columns, and flood discharge gate pier 2 of the hoisting machine room 1. This can make the strength of the side wall 11 higher, thereby ensuring the strength and lateral support capacity of the side wall 11 when the arc gate is working; the height of the side wall 11 must meet the requirements of the arc gate always being within the pier elevation range and the flood discharge requirements of the verified flood water surface line 6, and the thickness must meet the lateral thrust requirements of the working arc gate. The specific height and thickness can be calculated according to the flood discharge requirements and thrust requirements, and this article does not make specific restrictions on this. In addition, the top elevation of the flood discharge gate pier 2 is determined by the normal water level + superelevation and the verified flood level + superelevation.
[0023] like Figure 1-4 As shown, in a specific embodiment, the two sides of the working arc door track 4 are pre-embedded in the first slot section 31 and the second slot section 32 through multiple dowel bars 41, and the multiple dowel bars 41 are arranged at intervals along the extension direction of the first slot section 31 and the second slot section 32. The dowel bars 41 located in the second slot section 32 are anchored to the steel bars 12 of the side wall 11.
[0024] A second aspect of the present application provides a construction method for constructing a structure in which a gantry crane track is arranged on a side wall of a hoist room in the embodiment of the first aspect. The construction method mainly comprises the following steps: 1) Fabricate and install the steel bars 12 of the flood discharge gate pier 2 according to the design requirements and cast the first phase of concrete for the pier in the formwork. The steel bars 12 on the top surface of the pier must be allowed to reserve anchorage length for welding to the steel bars 12 on the side wall 11 of the hoist room 1. Pre-embed dowel bars 41 in the gate slot on the side of the pier. 2) Install the metal structural embedded parts of the working arc door track 4 and weld them to the pre-embedded dowel bars 41; 3) Fabricate and install the frame columns and beams of the hoist room 1 and the steel bars 12 of the side wall 11 at the arc gate position according to the design requirements. Weld the steel bars 12 of the side wall 11 of the hoist room 1 to the gate pier at the bottom, to the beam at the top, and to the columns on the upstream and downstream sides to form a whole. Embed dowel bars 41 in the arc gate slot 3 of the side wall 11. Pour concrete on the columns, beams and side walls 11. Reserve a 5cm deep notch in the beam at the working arc gate track 4 to prevent the arc gate from hitting the wall. The height of the side wall 11 must meet the requirements of ensuring that the arc gate is always within the elevation range of the gate pier and verifying the flood discharge. The thickness of the side wall 11 must meet the lateral thrust requirements of the working arc gate.
[0025] This method of use is used to construct the pier arrangement structure of the working arc gate track of the flood discharge gate in the first embodiment. The entire construction method is simple and efficient, the construction period is short and investment can be saved.
[0026] The above are merely preferred embodiments of the present application and are not intended to limit the present application. Those skilled in the art will readily appreciate that various modifications and variations are possible. Any modifications, equivalent substitutions, or improvements made within the spirit and principles of the present application shall be included within the scope of protection of the present application.
Claims
1. A structure in which the door crane track is arranged on the side wall of the hoist room, characterized in that: include: A hoisting and shutting machine room, the hoisting and shutting machine room being located on top of the flood discharge gate pier and having side walls; An arc gate slot, the arc gate slot comprising a first slot section and a second slot section, the arc length of the first slot section being greater than the arc length of the second slot section, the first slot section being located within the flood discharge gate pier, the second slot section being located within the side wall of the hoisting machine room, the first slot section and the second slot section being connected to each other at the junction of the flood discharge gate pier and the hoisting machine room, and the second slot section extending a preset height on the side wall along the arc extension direction of the first slot section; A working arc door track is arranged in the first slot section and the second slot section.
2. The structure of the door crane track arranged on the side wall of the hoist room according to claim 1 is characterized in that: The top elevation of the second trough section is not higher than the bottom line of the beam of the hoisting machine room. The beam of the hoisting machine room is provided with a notch at the position corresponding to the second trough section, and the depth of the notch is 5 cm.
3. The structure of the door crane track arranged on the side wall of the hoist room according to claim 1 or 2, characterized in that: The hoisting machine room adopts a frame structure, the side walls of the hoisting machine room are reinforced concrete walls, and the steel bars of the side walls are anchored in the beams and columns of the hoisting machine room and the piers of the flood discharge gate.
4. The structure of the door crane track arranged on the side wall of the hoist room according to claim 3 is characterized in that: Both sides of the working arc door track are pre-embedded in the first groove section and the second groove section through multiple dowel bars, and the multiple dowel bars are arranged at intervals along the extension direction of the first groove section and the second groove section. The dowel bars located in the second groove section are anchored to the steel bars of the side wall.
5. A construction method, characterized in that: The method for constructing a structure in which the gantry crane track is arranged on the side wall of the hoist room according to any one of claims 1 to 4 comprises the following steps: 1) Fabricate and install the reinforcement of the flood discharge gate piers according to the design requirements and cast the first phase of concrete for the piers in the formwork. The reinforcement on the top surface of the piers must reserve anchorage length for welding with the reinforcement of the side walls of the hoist room. Embed reinforcement in the gate slot on the side of the piers. 2) Install the metal structural embedded parts of the working arc door track and weld them to the pre-embedded dowel bars; 3) Fabricate and install the frame columns, beams and side walls of the gate opening position of the hoisting and closing machine room according to the design requirements. The bottom of the side walls of the hoisting and closing machine room steel bars are welded to the gate pier, the top to the beam, and the upstream and downstream sides to the columns to form a whole. Pre-embed rebars are placed in the gate slots of the side walls. Concrete is poured for the columns, beams and side walls. A 5cm deep notch is reserved in the beam at the working gate track position to prevent the gate from hitting the wall. The height of the side walls must meet the requirements of the gate always being within the gate pier elevation range and the flood discharge requirement of the verification flood. The thickness of the side walls must meet the lateral thrust requirements of the working gate.