A mechanical and electrical equipment progress control method based on BIM technology
By incorporating additional structural parameters of the pipeline into the BIM model, quantifying collision risks, and adjusting progress working hours, the problem of ignoring the actual outer wall contour differences in BIM design was solved, and scientific and reasonable management and control of the progress of mechanical and electrical equipment was achieved, reducing construction deviations and stagnation.
Patent Information
- Application Number
- CN202511047379.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-07-29
- Publication Date
- 2025-10-10
- Estimated Expiration
- 2045-07-29
AI Technical Summary
Existing BIM software only calculates according to the outer contour of the electromechanical equipment pipe model during design, ignoring the difference between the actual outer wall contour and the model contour. As a result, pipes are prone to being too close or colliding during actual construction, causing the installation process to stagnate and require rework, affecting construction efficiency.
By incorporating additional structural parameters such as the insulation layer, connectors, and instruments of the electromechanical equipment pipelines into the BIM model, the collision risk is quantified using the hierarchical analysis method and weighted comprehensive evaluation method, and the progress working hours are adjusted according to the risk level to generate the final parametric progress management model.
Identify possible pipeline collision risks during construction in advance, reduce installation process stagnation and rework, ensure the scientificity and accuracy of working time adjustments, narrow the deviation between the actual installation progress and the BIM control progress, and improve progress control efficiency.
Smart Images

Figure CN120542891B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electromechanical equipment progress management, and in particular to a method for electromechanical equipment progress management based on BIM technology. Background Art
[0002] In the construction of mechanical and electrical engineering, the installation process of equipment and pipelines is complex and cross-operation is frequent. The traditional progress control method relies on two-dimensional drawings and experience judgment, which makes it difficult to track the progress of each link in real time. Problems such as poor process connection and unreasonable resource allocation are prone to occur, leading to construction delays. BIM technology can integrate equipment parameters, progress plans and other information by constructing three-dimensional models to achieve visual control, making it easier to detect progress deviations in advance and make timely adjustments. Therefore, it has become an important means to improve the efficiency of mechanical and electrical equipment progress control.
[0003] In the process of mechanical and electrical equipment progress control, the installation progress of mechanical and electrical equipment pipelines has a key impact. As the core carrier of equipment connection, the pipeline laying path and installation sequence are closely related to the equipment placement. Delays or deviations in pipeline installation will directly lead to the subsequent equipment being unable to connect as planned, thereby slowing down the overall progress.
[0004] During the design process, BIM software only calculates according to the model outer contour of the electromechanical equipment pipe body. The actual outer wall contour is affected by additional structures such as the insulation layer, connector protrusions, and instrument installation, resulting in the actual outer wall contour being inconsistent with the model contour. This makes some pipe bodies not show collision risks during design. However, in actual construction, due to the superposition of the real contours, it is very easy for pipes to be too close or even collide, which in turn causes the installation process to stagnate and rework, resulting in a deviation between the actual installation progress of the electromechanical equipment and the BIM management progress, affecting the overall construction efficiency. Summary of the Invention
[0005] In response to the shortcomings of the existing technology, the present invention provides a method for controlling the progress of electromechanical equipment based on BIM technology, which solves the problem that the existing BIM software only calculates according to the outer contour of the electromechanical equipment pipe body model during design, while the actual outer wall contour of the pipe body is different from the model contour due to additional structures such as the insulation layer, connector protrusions, and instrument installation. As a result, some pipe bodies have no collision risk when designed, but are prone to pipes being too close or colliding during actual construction, which in turn causes the installation process to stagnate and rework, resulting in a deviation between the actual installation progress of the electromechanical equipment and the BIM control progress.
[0006] To achieve the above objectives, the present invention is implemented through the following technical solutions: A method for controlling the progress of electromechanical equipment based on BIM technology, comprising the following steps:
[0007] S1. Use 3D modeling software and BIM integration software to substitute multiple electromechanical equipment parameters to establish a basic electromechanical equipment BIM model.
[0008] The multiple electromechanical equipment parameters include: electromechanical equipment parameters and electromechanical equipment pipeline parameters; the electromechanical equipment parameters include: electromechanical equipment model and electromechanical equipment size; the electromechanical equipment pipeline parameters include: electromechanical equipment pipeline diameter, electromechanical equipment pipeline length, electromechanical equipment pipeline material, electromechanical equipment pipeline insulation layer, electromechanical equipment pipeline connectors and electromechanical equipment pipeline instruments;
[0009] S2. Allocate the progress work hours for electromechanical equipment and the progress work hours for electromechanical equipment pipelines based on the basic electromechanical equipment BIM model established in step S1;
[0010] S3. Based on the electromechanical equipment pipeline parameters collected in step S1, dynamic collision risk is quantified using the weight calculation formula of the analytic hierarchy process and the weighted comprehensive evaluation method to obtain a comprehensive calculated collision probability;
[0011] S4. Adjust the electromechanical equipment progress working hours and electromechanical equipment pipeline progress working hours set in step S2 according to the comprehensive calculated collision probability obtained in step S3;
[0012] S5. Re-enter the mechanical and electrical equipment progress working hours and mechanical and electrical equipment pipeline progress working hours adjusted in step S4 into the basic mechanical and electrical equipment BIM model in step S2, and generate the final parameterized mechanical and electrical equipment progress management BIM model to realize mechanical and electrical equipment progress control.
[0013] Preferably, in step S1, a basic electromechanical equipment BIM model is established by using 3D modeling software and BIM integration software to substitute multiple electromechanical equipment parameters, including:
[0014] First, use 3D modeling software to create an electromechanical equipment family according to the electromechanical equipment model, set the model as the type parameter, and then enter the length, width, and height dimensions of the electromechanical equipment. Then, the 3D modeling software will generate a model based on the model and the length, width, and height dimensions of the electromechanical equipment.
[0015] Then add the electromechanical equipment piping family, set the diameter and material as type parameters, and explicitly set the pipe length parameters. Insert the insulation thickness, and then insert the number and size of connectors and instruments.
[0016] Finally, use BIM integration software to first import the model produced by the 3D modeling software, then associate the equipment and pipelines to form a complete basic model and check the accuracy of the connection.
[0017] Preferably, in step S1, the electromechanical equipment parameters include: electromechanical equipment model and electromechanical equipment size; the electromechanical equipment pipeline parameters include: electromechanical equipment pipeline diameter, electromechanical equipment pipeline length, electromechanical equipment pipeline material, electromechanical equipment pipeline insulation layer, electromechanical equipment pipeline connectors and electromechanical equipment pipeline instruments.
[0018] Preferably, in step S2, the allocation of the electromechanical equipment progress working hours and the electromechanical equipment pipeline progress working hours includes:
[0019] In the BIM integration software, process hours are associated with model attributes according to the electromechanical equipment model. For example, if the water pump model is ISG50-160, the corresponding installation process hours are 8 hours. Large equipment models require an additional 24 hours of transportation and hoisting hours, while small equipment models do not require additional hours.
[0020] The working hours for electromechanical equipment pipelines are set according to the diameter and length, including: DN300×100m pipeline, the corresponding installation process working hours are 50 hours.
[0021] Preferably, in step S3, the electromechanical equipment pipeline parameters include: electromechanical equipment pipeline material, electromechanical equipment pipeline insulation layer, electromechanical equipment pipeline connectors and electromechanical equipment pipeline instruments.
[0022] Preferably, in step S3, the weight calculation formula of the analytic hierarchy process is specifically:
[0023] According to the probability and severity of occurrence, the weight calculation formula of the hierarchical analysis method is used to allocate the weights of the electromechanical equipment pipeline material, electromechanical equipment pipeline insulation layer, electromechanical equipment pipeline connectors and electromechanical equipment pipeline instruments;
[0024]
[0025] in:
[0026] Representative Initial weights of item parameter interference; Representative The probability of occurrence of parameter interference is divided into three levels: high 0.7, medium 0.5, and low 0.3; Representative The severity of the interference of each parameter is divided into three levels: high 0.8, medium 0.5, and low 0.2; Represents the total number of parameter interferences, where =4, corresponding to the material of electromechanical equipment pipeline, the insulation layer of electromechanical equipment pipeline, the connectors of electromechanical equipment pipeline and the instrument of electromechanical equipment pipeline respectively.
[0027] Preferably, in step S3, the weighted comprehensive evaluation method calculation formula is specifically:
[0028] Substitute the mechanical and electrical equipment pipeline parameters into the weighted comprehensive evaluation method calculation formula to comprehensively calculate the collision probability:
[0029]
[0030] in:
[0031] represents the comprehensive collision probability;
[0032] Represents the weight of the material of the electromechanical equipment pipeline;
[0033] Represents the contour deviation caused by the pipe material, that is, the dimensional change due to thermal expansion and contraction, which can be obtained through material measurement;
[0034] Represents the weight of the insulation layer of the mechanical and electrical equipment pipeline;
[0035] Represents the thickness of the insulation layer, directly taking the insulation layer parameter value recorded in S1;
[0036] Represents the weight of the mechanical and electrical equipment pipeline connector;
[0037] Represents the raised height of the connector, which is obtained by actual measurement of the model, including the raised height of the flange connector. The actual measurement of the model is specifically: measured using a measuring ruler based on the size of the connector of different models;
[0038] Represents the weight of electromechanical equipment, piping and instrumentation;
[0039] Represents the protruding size of the instrument, obtained through actual measurement of the model, including pressure gauges and flow meters;
[0040] The safety distance threshold between pipe bodies is 100-300mm according to the specification;
[0041] At the same time, considering that the interference of multiple parameters in different situations is different, dynamic adjustment is performed based on the weight distribution in the calculation formula of the weighted comprehensive evaluation method. The different situations include high temperature and high humidity environments and areas with a large number of precision detection instruments.
[0042] Preferably, in step S4, the progress working hours of electromechanical equipment and the progress working hours of electromechanical equipment pipelines are adjusted, specifically:
[0043] Depending on the value of the comprehensive calculated collision probability, the installation schedule and working hours adjustment plan for electromechanical equipment and pipelines will also be different, including:
[0044] When the comprehensive collision probability is ≤0.2, the collision probability is judged to be low risk, and the original mechanical and electrical equipment progress working hours remain unchanged; when 0.2<comprehensive collision probability ≤0.5, the collision probability is judged to be medium risk, and the original mechanical and electrical equipment progress working hours are appropriately increased; when the comprehensive collision probability is greater than 0.5, the collision probability is judged to be high risk, and the working hours are significantly increased based on the original mechanical and electrical equipment progress working hours;
[0045] The final mechanical and electrical equipment progress hours are then calculated using the risk-weighted adjustment formula, including:
[0046]
[0047] in:
[0048] Represents the adjusted progress working hours of electromechanical equipment;
[0049] Represents the initial progress hours allocated in step S2;
[0050] is the risk impact coefficient,
[0051] If the risk is judged to be low, the original mechanical and electrical equipment progress hours remain unchanged. At this time: =0,
[0052] If it is judged to be a medium risk, the working hours of the original mechanical and electrical equipment will be appropriately increased. At this time: =0.3,
[0053] If it is judged to be high risk, the working hours will be significantly increased based on the original progress working hours of electromechanical equipment. At this time: =0.8;
[0054] is the comprehensive collision probability obtained in step S3.
[0055] The present invention provides a method for controlling the progress of electromechanical equipment based on BIM technology. It has the following beneficial effects:
[0056] 1. This invention incorporates additional structural parameters such as the insulation layer, connectors, and instruments of electromechanical equipment pipelines when establishing the BIM model, and uses the hierarchical analysis method and weighted comprehensive evaluation method to quantify the collision risks caused by these parameters. This solves the problem of traditional BIM design that only calculates based on the outer contour of the pipe model while ignoring the differences in the actual outer wall contour. It can identify the pipeline collision risks that may occur in actual construction in advance, reducing the occurrence of installation process stagnation and rework.
[0057] 2. This invention makes targeted adjustments to the progress hours of electromechanical equipment and pipelines based on the dynamic collision risk quantification results. By linking the comprehensive collision probability with the risk level, the direction of work hour adjustments at different risk levels is clearly defined, ensuring that work hour adjustments are based on evidence and avoiding the blind increase or decrease of work hours.
[0058] 3. The present invention combines the risk-weighted adjustment method formula to calculate the final progress working hours, organically combining the initial working hours, risk impact coefficient and comprehensive collision probability, so that the adjusted working hours can not only reflect the impact of collision risk on construction, but also maintain the scientificity and accuracy of the calculation, effectively reducing the deviation between the actual installation progress of electromechanical equipment and the BIM control progress, and improving the rationality of progress control. BRIEF DESCRIPTION OF THE DRAWINGS
[0059] Figure 1 Flow chart of the method of the present invention. DETAILED DESCRIPTION
[0060] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the drawings in the present specification. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.
[0061] Please see the attached Figure 1 , an embodiment of the present invention provides a method for controlling the progress of electromechanical equipment based on BIM technology, comprising the following steps:
[0062] S1. Using 3D modeling software and BIM integration software to substitute multiple electromechanical equipment parameters to establish a basic electromechanical equipment BIM model, wherein the multiple electromechanical equipment parameters include electromechanical equipment parameters and electromechanical equipment piping parameters;
[0063] Specifically:
[0064] First, use 3D modeling software to create an electromechanical equipment family according to the electromechanical equipment model, set the model as the type parameter, and then enter the length, width, and height dimensions of the electromechanical equipment. Then, the 3D modeling software will generate a model based on the model and the length, width, and height dimensions of the electromechanical equipment.
[0065] Then add the electromechanical equipment piping family, set the diameter and material as type parameters, and explicitly set the pipe length parameters. Insert the insulation thickness, and then insert the number and size of connectors and instruments.
[0066] Finally, use BIM integration software to import the model created by the 3D modeling software, then associate the equipment and pipelines to form a complete basic model and check the connection accuracy;
[0067] The three-dimensional modeling software includes but is not limited to: Revit;
[0068] The BIM integration software includes but is not limited to: Navisworks;
[0069] The electromechanical equipment parameters include: electromechanical equipment model and electromechanical equipment size;
[0070] The electromechanical equipment pipeline parameters include: electromechanical equipment pipeline diameter, electromechanical equipment pipeline length, electromechanical equipment pipeline material, electromechanical equipment pipeline insulation layer, electromechanical equipment pipeline connectors and electromechanical equipment pipeline instruments;
[0071] S2. Allocate the progress and working hours of the electromechanical equipment and electromechanical equipment pipelines based on the basic electromechanical equipment BIM model established in step S1, specifically:
[0072] In the BIM integration software, process hours are associated with model attributes according to the electromechanical equipment model. For example, if the water pump model is ISG50-160, the corresponding installation process hours are 8 hours. Large equipment models require an additional 24 hours of transportation and hoisting hours, while small equipment models do not require additional hours.
[0073] The working hours for electromechanical equipment pipelines are set based on diameter and length, including: DN300×100m pipeline, the corresponding installation process working hours are given as 50 hours;
[0074] S3. Based on the electromechanical equipment pipeline parameters collected in step S1, the dynamic collision risk is quantified using the weight calculation formula of the hierarchical analysis method and the weighted comprehensive evaluation method to obtain a comprehensive calculation collision probability, specifically:
[0075] The electromechanical equipment pipeline parameters include: electromechanical equipment pipeline material, electromechanical equipment pipeline insulation layer, electromechanical equipment pipeline connectors and electromechanical equipment pipeline instruments;
[0076] First, the weights of the electromechanical equipment pipeline material, electromechanical equipment pipeline insulation layer, electromechanical equipment pipeline connectors and electromechanical equipment pipeline instruments are allocated using the analytic hierarchy process weight calculation formula according to the probability and severity of occurrence;
[0077]
[0078] in:
[0079] Representative Initial weights of item parameter interference; Representative The probability of occurrence of parameter interference is divided into three levels: high 0.7, medium 0.5, and low 0.3; Representative The severity of the interference of each parameter is divided into three levels: high 0.8, medium 0.5, and low 0.2; Represents the total number of parameter interferences, where =4, corresponding to the material of electromechanical equipment pipeline, the insulation layer of electromechanical equipment pipeline, the connector of electromechanical equipment pipeline and the instrument of electromechanical equipment pipeline respectively;
[0080] Then, the parameters of the electromechanical equipment pipeline are substituted into the weighted comprehensive evaluation method calculation formula to comprehensively calculate the collision probability:
[0081]
[0082] in:
[0083] represents the comprehensive collision probability;
[0084] Represents the weight of the material of the electromechanical equipment pipeline;
[0085] Represents the contour deviation caused by the pipe material, that is, the dimensional change due to thermal expansion and contraction, which can be obtained through material measurement;
[0086] Represents the weight of the insulation layer of the mechanical and electrical equipment pipeline;
[0087] Represents the thickness of the insulation layer, directly taking the insulation layer parameter value recorded in S1;
[0088] Represents the weight of the mechanical and electrical equipment pipeline connector;
[0089] Represents the raised height of the connector, which is obtained by actual measurement of the model, including the raised height of the flange connector. The actual measurement of the model is specifically: measured using a measuring ruler based on the size of the connector of different models;
[0090] Represents the weight of electromechanical equipment, piping and instrumentation;
[0091] Represents the protruding size of the instrument, obtained through actual measurement of the model, including pressure gauges and flow meters;
[0092] The safety distance threshold between pipe bodies is 100-300mm according to the specification;
[0093] Finally, the weight distribution is dynamically adjusted to take into account the different interferences of multiple parameters in different situations. Specifically:
[0094] The different conditions include high temperature and high humidity environments and areas with a large number of precision testing instruments;
[0095] In high temperature and high humidity environments:
[0096] Pipe material: Thermal expansion and contraction have a significant impact, so the initial weight is increased by 0.1;
[0097] Insulation layer: Moisture-proof requirements are increased, and the initial weight is increased by 0.05;
[0098] Connectors: Less affected by the environment, reduced by 0.03;
[0099] Instruments: In high temperature and high humidity environments, most instruments have protective measures, and the impact of their protruding size on collisions is relatively weakened, reducing 0.12
[0100] Areas with a large number of precision testing instruments:
[0101] Pipeline material: The impact of pipeline material on the collision risk in the instrument area is relatively stable, with no significant changes and remains unchanged;
[0102] Insulation layer: The collision correlation between the insulation layer and the precision instrument is low, and its impact on the overall collision risk is relatively reduced, reducing by 0.05
[0103] Connectors: The probability of collision between connectors and precision instruments is low, reduced by 0.05;
[0104] Instruments: When there are a large number of precision instruments, the collision risk caused by their protruding size increases significantly, and the damage after the collision is greater, increasing by 0.1;
[0105] S4. Adjust the mechanical and electrical equipment progress working hours and mechanical and electrical equipment pipeline progress working hours set in step S2 according to the comprehensive calculated collision probability obtained in step S3, specifically:
[0106] Depending on the value of the comprehensive calculated collision probability, the installation schedule and working hours adjustment plan for electromechanical equipment and pipelines will also be different, including:
[0107] When the comprehensive collision probability is ≤0.2, the collision probability is judged to be low risk, and the original mechanical and electrical equipment progress working hours remain unchanged;
[0108] When 0.2<comprehensive collision probability≤0.5, the collision probability is judged to be medium risk, and the original mechanical and electrical equipment progress working hours are appropriately increased;
[0109] When the comprehensive collision probability is greater than 0.5, it is judged that the collision probability is high risk, and the working hours of the original electromechanical equipment are greatly increased;
[0110] The final electromechanical equipment progress working hours are calculated by using the risk weighting adjustment method formula, including:
[0111]
[0112] Among them:
[0113] represents the adjusted electromechanical equipment progress working hours;
[0114] represents the initial progress working hours allocated in step S2;
[0115] is a risk influence coefficient,
[0116] When it is judged as low risk, the original electromechanical equipment progress working hours remain unchanged, at this time: =0,
[0117] When it is judged as medium risk, the original electromechanical equipment progress working hours are appropriately increased, at this time: =0.3,
[0118] When it is judged as high risk, the original electromechanical equipment progress working hours are greatly increased, at this time: =0.8;
[0119] is the comprehensive collision probability obtained in step S3;
[0120] S5, the electromechanical equipment progress working hours and the electromechanical equipment pipeline progress working hours adjusted in step S4 are re-entered into the basic electromechanical equipment BIM model in step S2, and a final parameterized electromechanical equipment progress management BIM model is generated, realizing electromechanical equipment progress management and control.
[0121] Although the embodiments of the present application have been shown and described, it can be understood by those skilled in the art that various changes, modifications, replacements and variations can be made to the embodiments without departing from the principles and spirits of the present application, and the scope of the present application is defined by the appended claims and their equivalents.
Claims
1. A method for controlling the progress of electromechanical equipment based on BIM technology, characterized in that: The following steps are involved: S1. Using 3D modeling software and BIM integration software to substitute multiple electromechanical equipment parameters to establish a basic electromechanical equipment BIM model, wherein the multiple electromechanical equipment parameters include electromechanical equipment parameters and electromechanical equipment piping parameters; In step S1, a basic electromechanical equipment BIM model is established by using 3D modeling software and BIM integration software to input multiple electromechanical equipment parameters, including: First, use 3D modeling software to create an electromechanical equipment family according to the electromechanical equipment model, set the model as the type parameter, and then enter the length, width, and height dimensions of the electromechanical equipment. Then, the 3D modeling software will generate a model based on the model and the length, width, and height dimensions of the electromechanical equipment. Then add the electromechanical equipment piping family, set the diameter and material as type parameters, and explicitly set the pipe length parameters. Insert the insulation thickness, and then insert the number and size of connectors and instruments. Finally, use BIM integration software to import the model created by the 3D modeling software, then associate the equipment and pipelines to form a complete basic model and check the connection accuracy; In step S1, the electromechanical equipment parameters include: electromechanical equipment model and electromechanical equipment size; the electromechanical equipment pipeline parameters include: electromechanical equipment pipeline diameter, electromechanical equipment pipeline length, electromechanical equipment pipeline material, electromechanical equipment pipeline insulation layer, electromechanical equipment pipeline connectors and electromechanical equipment pipeline instruments; S2. Allocate the progress work hours for the electromechanical equipment and the progress work hours for the electromechanical equipment pipelines based on the basic electromechanical equipment BIM model established in step S1; S3. Based on the electromechanical equipment pipeline parameters collected in step S1, dynamic collision risk is quantified using the weight calculation formula of the analytic hierarchy process and the weighted comprehensive evaluation method to obtain a comprehensive calculated collision probability; In step S3, the electromechanical equipment pipeline parameters include: electromechanical equipment pipeline material, electromechanical equipment pipeline insulation layer, electromechanical equipment pipeline connectors and electromechanical equipment pipeline instruments; S4. Adjust the electromechanical equipment progress working hours and electromechanical equipment pipeline progress working hours set in step S2 according to the comprehensive calculated collision probability obtained in step S3; S5. Re-enter the mechanical and electrical equipment progress working hours and mechanical and electrical equipment pipeline progress working hours adjusted in step S4 into the basic mechanical and electrical equipment BIM model in step S2, and generate the final parameterized mechanical and electrical equipment progress management BIM model to realize mechanical and electrical equipment progress control.
2. The method for controlling the progress of electromechanical equipment based on BIM technology according to claim 1, characterized in that: In step S2, the allocation of the electromechanical equipment progress working hours and the electromechanical equipment pipeline progress working hours includes: In the BIM integration software, process hours are associated with model attributes according to the electromechanical equipment model. For example, if the water pump model is ISG50-160, the corresponding installation process hours are 8 hours. Large equipment models require an additional 24 hours of transportation and hoisting hours, while small equipment models do not require additional hours. The working hours for electromechanical equipment pipelines are set according to the diameter and length, including: DN300×100m pipeline, the corresponding installation process working hours are 50 hours.
3. The method for controlling the progress of electromechanical equipment based on BIM technology according to claim 1, characterized in that: In step S3, the weight calculation formula of the analytic hierarchy process is specifically: According to the probability and severity of occurrence, the weight calculation formula of the hierarchical analysis method is used to allocate the weights of the electromechanical equipment pipeline material, electromechanical equipment pipeline insulation layer, electromechanical equipment pipeline connectors and electromechanical equipment pipeline instruments; in: Representative Initial weights of item parameter interference; Representative The probability of occurrence of parameter interference is divided into three levels: high 0.7, medium 0.5, and low 0.3; Representative The severity of the interference of each parameter is divided into three levels: high 0.8, medium 0.5, and low 0.2; Represents the total number of parameter interferences, where =4, corresponding to the material of electromechanical equipment pipeline, the insulation layer of electromechanical equipment pipeline, the connectors of electromechanical equipment pipeline and the instrument of electromechanical equipment pipeline respectively.
4. The method for controlling the progress of electromechanical equipment based on BIM technology according to claim 1, characterized in that: In step S3, the weighted comprehensive evaluation method calculation formula is specifically: Substitute the mechanical and electrical equipment pipeline parameters into the weighted comprehensive evaluation method calculation formula to comprehensively calculate the collision probability: in: represents the comprehensive collision probability; Represents the weight of the material of the electromechanical equipment pipeline; Represents the amount of profile deviation caused by the pipe material; Represents the weight of the insulation layer of the mechanical and electrical equipment pipeline; Represents the thickness of the insulation layer, directly taking the insulation layer parameter value recorded in S1; Represents the weight of the mechanical and electrical equipment pipeline connector; Represents the raised height of the connector, which is obtained by actual measurement of the model, including the raised height of the flange connector. The actual measurement of the model is specifically: measured using a measuring ruler based on the size of the connector of different models; Represents the weight of electromechanical equipment, piping and instrumentation; Represents the protruding size of the instrument, obtained through actual measurement of the model, including pressure gauges and flow meters; The safety distance threshold between pipe bodies is 100-300mm according to the specification; At the same time, considering that the interference of multiple parameters in different situations is different, dynamic adjustment is performed based on the weight distribution in the calculation formula of the weighted comprehensive evaluation method. The different situations include high temperature and high humidity environments and areas with a large number of precision detection instruments.
5. The method for controlling the progress of electromechanical equipment based on BIM technology according to claim 1, characterized in that: In step S4, the progress working hours of electromechanical equipment and the progress working hours of electromechanical equipment pipelines are adjusted, specifically: Depending on the value of the comprehensive calculated collision probability, the installation schedule and working hours adjustment plan for electromechanical equipment and pipelines will also be different, including: When the comprehensive collision probability is ≤0.2, the collision probability is judged to be low risk, and the original mechanical and electrical equipment progress working hours remain unchanged; when 0.2<comprehensive collision probability ≤0.5, the collision probability is judged to be medium risk, and the original mechanical and electrical equipment progress working hours are appropriately increased; when the comprehensive collision probability is greater than 0.5, the collision probability is judged to be high risk, and the working hours are significantly increased based on the original mechanical and electrical equipment progress working hours; The final mechanical and electrical equipment progress hours are then calculated using the risk-weighted adjustment formula, including: in: Represents the adjusted progress working hours of electromechanical equipment; Represents the initial progress hours allocated in step S2; is the risk impact coefficient, If the risk is judged to be low, the original mechanical and electrical equipment progress hours remain unchanged. At this time: =0, If it is judged to be a medium risk, the working hours of the original mechanical and electrical equipment will be appropriately increased. At this time: =0.3, If it is judged to be high risk, the working hours will be significantly increased based on the original progress working hours of electromechanical equipment. At this time: =0.8; is the comprehensive collision probability obtained in step S3.
Citation Information
Patent Citations
Modularized prefabricated heat exchange machine room construction method based on BIM technology
CN117371101A
Municipal pipeline construction system based on BIM technology
CN119885513A