Construction method of caisson prefabricated automatic wire penetrating device

By using tower cranes to lift and relocate the rebar threading system and remotely controlling it, the safety hazards and low efficiency of threading longitudinal diaphragm wall rebars in traditional caisson prefabrication have been solved. This has enabled automated operation and an efficient construction process, ensuring construction safety and quality.

CN120696328BActive Publication Date: 2025-11-04NO 3 ENG COMPANY LTD OF CCCC FIRST HARBOR ENG COMPANY +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202511166508.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-08-20
Publication Date
2025-11-04
Estimated Expiration
2045-08-20

AI Technical Summary

Technical Problem

In the traditional caisson prefabrication process, the process of threading the longitudinal diaphragm wall steel bars poses safety hazards and has low construction efficiency. It cannot meet the safety requirements for high-altitude operations and requires repeated filling and lifting, which reduces construction efficiency.

Method used

The system employs a combination of tower crane lifting and manual traction positioning, utilizing double-strand ropes with graduated markings for limiting movement, and remotely controlled rebar threading devices to achieve automated lateral, flipping, and longitudinal movement of longitudinal rebars. Through a leveling and feeding mechanism, a flipping device, and a longitudinal feeding mechanism, the rebars are ensured to pass smoothly through the side wall rebar mesh, and remote control is achieved through an electrical control box system.

Benefits of technology

It improved the efficiency of rebar installation, reduced the labor intensity of high-altitude operations, ensured construction safety, avoided repeated filling and lifting, met the requirements for safe construction, and improved project quality and construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120696328B_ABST
    Figure CN120696328B_ABST
Patent Text Reader

Abstract

The application relates to a construction method of a caisson prefabricated automatic bar penetrating device, and relates to the technical field of building construction. The method comprises the following steps: adjusting the device structure size, trial hoisting of a hoisting platform, trial operation of the bar penetrating device, longitudinal bar flattening and sequencing, first positioning of the device, first bar penetrating, step-by-step lifting of the device, bar penetrating of the device, and completion of the bar penetrating. The device is lifted and shifted by a tower crane and manually positioned, double-ropes with scale marks are used for lifting and limiting at the front end of the hoisting platform, the lifting height of each step is controlled to be consistent with the vertical spacing of the bar penetrating, the bar penetrating position is quickly aligned, the bar penetrating efficiency is improved, the longitudinal bar is flattened and sequenced in advance by a flattening and discharging mechanism, the position of adjacent steel bars is prevented from being overlapped, the engineering quality is ensured, the single bar penetrating quantity of the caisson is arranged and the bearing requirement is met, the lifting and shifting frequency is reduced, the device is remotely controlled to move horizontally, turn over and move longitudinally, automatic operation is realized, the labor intensity is greatly reduced, and the safety construction is ensured in the whole hoisting process.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of building construction, in particular to a construction method of a caisson prefabrication automatic reinforcement penetrating device. BACKGROUND

[0002] In the process of caisson prefabrication, a reinforcement penetrating large plate is needed for binding longitudinal partition wall reinforcement. The traditional reinforcement penetrating large plate is a simple platform with a fence. The reinforcement penetrating large plate is lifted by a crane, and the reinforcement worker works in the large plate to horizontally penetrate the reinforcement through the side wall and the transverse partition wall, thereby forming the longitudinal partition wall. The crane carries out high-altitude work with people, which has serious safety hazards. Currently, relevant laws and safety technical regulations of the state have clearly stipulated that hoisting machinery is strictly prohibited from hoisting people in any way.

[0003] A caisson prefabrication reinforcement penetrating large plate is disclosed in Chinese Patent No. CN 220005816 U. The plate is provided with a guide frame and a slide. The longitudinal reinforcement is manually filled into the slide. The reinforcement penetrating large plate is lifted to a specified position. The worker on the caisson outer bracket extends the raw material into the side wall. Then, the reinforcement inside the reinforcement mesh is pulled to the specified reinforcement penetrating position by the reinforcement worker. The slide of the present patent is arranged on both sides of the framework. However, the height of the framework is not specified. Through analysis, the height of the framework cantilever should not be too high. The reasons are as follows: first, the framework with a height of 2 m or above belongs to high-altitude work, and manual filling is not convenient; second, the framework is a slender high structure, and its stability is poor when being lifted; and third, the height of the framework is too high to conflict with the position of the lifting cable of the reinforcement large plate. The height of the caisson layered prefabrication is generally 4-6 m. The filling of the slide cannot complete the reinforcement penetrating work of a single longitudinal partition wall. The process of repeated filling-lifting-reinforcement penetrating needs to be repeated, which reduces the construction efficiency. Meanwhile, the worker on the caisson outer bracket needs to extend the raw material into the side wall. The working height of the worker on the caisson outer bracket is limited, and it is necessary to climb upward to the steel bar and pull the steel bar by the reinforcement worker inside the reinforcement mesh, which belongs to "wild" work and is very inconvenient. SUMMARY

[0004] The purpose of the present application is to solve the above-mentioned technical problems of the existing method, and to provide a construction method of a caisson prefabrication automatic reinforcement penetrating device.

[0005] To achieve the above-mentioned purpose, the present application adopts the following technical solutions:

[0006] A construction method of a caisson prefabrication automatic reinforcement penetrating device, which vertically aligns the device with the side wall reinforcement mesh and the first row of reinforcement penetrating positions by tower crane lifting and displacement and manual traction positioning, and stepwise lifts the device to align with the subsequent reinforcement penetrating positions of the longitudinal partition wall by using a double rope with scale marks for limiting. After aligning with the reinforcement penetrating position each time, the longitudinal reinforcement is transversely moved, turned over, and longitudinally moved by remotely controlling the reinforcement penetrating facilities. After penetrating through the side wall reinforcement mesh, the direction of the end of the longitudinal reinforcement is controlled by the reinforcement worker inside the reinforcement mesh until reaching the specified reinforcement penetrating position, and the binding is completed. The construction method specifically includes the following steps:

[0007] S1: Device structure size adjustment. According to the diameter of the longitudinal reinforcement, use the wire drawing or infrared positioning to adjust the length of each turning structure flat section in the turning device by bolts, to ensure that only one reinforcement is placed on it. According to the horizontal spacing of the longitudinal partition wall reinforcement and the size of the side wall and cross wall reinforcement grid, change or adjust the size of the variable diameter guide hole in the longitudinal feeding mechanism to ensure that the reinforcement passes smoothly along the variable diameter guide hole to the side wall and cross wall reinforcement grid. According to the vertical spacing of the longitudinal partition wall reinforcement, set the scale marks on the double rope in the lifting platform, and the scale interval is twice the length of the vertical spacing of the longitudinal partition wall reinforcement.

[0008] S2: Lifting platform test lifting. Use the tower crane to lift the lifting platform 200~500mm from the ground, use the level or level to observe the front and rear inclination of the lifting platform, and adjust the sandbag on the platform to ensure that the total center of gravity of the platform and the reinforcement facilities on the platform is on the same vertical line with the platform centroid.

[0009] S3: Reinforcement facility test run. Connect the electrical control box system to each electrical equipment of the reinforcement facility through the cable and switch plug, then connect the electrical control box system to the distribution box in the prefabrication yard, control the circuit switch through the mobile phone APP or computer terminal, and handle the control failure in time. After each electrical equipment is powered on, observe whether the running direction is correct, and change the motor running direction by replacing the power line switch plug position of the electrical equipment. The mobile phone APP or computer terminal, through the remote communication control module as a bridge, ensures that the mobile phone or computer can successfully connect the equipment to realize real-time remote control; the start-stop, running and fault display function interface of the equipment are set in the mobile phone APP or computer terminal; the mobile phone or computer terminal can send control command information to the remote communication control module, and then the remote communication control module drives the equipment to execute the command, thereby realizing real-time remote control of the equipment.

[0010] S4: Longitudinal reinforcement laying and sorting. The processed longitudinal reinforcement is respectively lifted and placed on the two side laying mechanisms, the motor one of the laying mechanism is started to drive the through shaft to rotate, which drives the horizontal chain gear to rotate, and under the manual cooperation, the longitudinal reinforcement is laid horizontally and moved horizontally, and the arrangement order of the reinforcement is adjusted manually to ensure that the adjacent reinforcement weld positions are staggered, and the motor one is turned off.

[0011] S5: Device first position. The lifting platform is lifted and moved by the tower crane in the prefabrication yard, and the position is adjusted manually by the traction rope and the double rope. When the device is moved to be perpendicular to the side wall reinforcement grid and the variable diameter guide hole in the longitudinal feeding mechanism is aligned with the first row of reinforcement position, the traction rope and the double rope are temporarily fixed with the caisson and the pre-buried anchor on the ground. The double rope with scale marks is temporarily fixed vertically downward on the pre-buried anchor, and one end of any one of the double ropes is adjusted and fixed, so that the scale marks of the other rope coincide with the pre-buried anchor and are temporarily fixed.

[0012] S6: First row of reinforcing bars. The longitudinal reinforcing bars are transversely moved on the laying mechanism on both sides by remote control of the circuit switch through the mobile phone APP or computer terminal, turned over by the turnover device, moved longitudinally along the longitudinal feeding mechanism, and controlled by the reinforcing bar operator inside the reinforcing mesh to the specified reinforcing position after the longitudinal reinforcing bars pass through the reinforcing mesh, and finally completed by binding.

[0013] S7: Device step lifting. Loosen the temporary fixing end of the double rope with scale marks in the hoisting platform, so that the next scale mark coincides with the embedded anchor rod, and then re-fix it. Adjust the tower crane variable frequency device to slowly lift the hoisting platform, loosen the temporary fixing of the other traction ropes and slowly release them, and when the double rope with scale marks is tightened, the tower crane stops lifting, and the traction rope is temporarily fixed with the embedded anchor rod on the ground. The variable diameter guide hole in the longitudinal feeding mechanism is aligned with the next reinforcing position under the limitation of the double rope.

[0014] S8: Device reinforcing. The construction method is the same as step S6.

[0015] S9: Reinforcing is completed. Repeat steps S7 and S8 until all reinforcing work of the longitudinal partition wall of the caisson is completed, and then the tower crane moves the hoisting platform for next use.

[0016] The hoisting platform is a type steel structure, the size of which is determined according to the length and number of reinforcing bars and the arrangement requirements of reinforcing facilities, and it provides support brackets for reinforcing facilities. The lifting holes are symmetrically arranged at the top of the vertical poles on both sides of the hoisting platform and connected with the tower crane cable, and the lifting holes and traction ropes are symmetrically arranged near the bottom of the four corners, among which the front two traction ropes are double ropes with scale marks. The double rope uses the principle that the moving distance of the free end of the movable pulley is equal to twice the moving distance of the object, and the scale interval on it is twice the length of the vertical spacing of the reinforcing bars, which limits the step lifting of the tower crane and ensures that the reinforcing device quickly aligns with the reinforcing position.

[0017] The laying mechanism includes a motor, a vertical chain gear, a horizontal chain gear, and a through shaft. The motor is arranged on a support near the middle of the hoisting platform and connected with the through shaft through the vertical chain gear. The horizontal chain gear is arranged every 2-3 m on the through shaft, and supports are arranged at the corresponding positions. Before the motor is started, the top horizontal chain is in a relaxed state and the longitudinal reinforcing bars placed on it are supported by the supports. When the motor is started, the through shaft is driven to rotate, driving the horizontal chain gear to rotate, and the top horizontal chain is tightened, 5-10 mm above the support surface. Under the cooperation of manual work, the longitudinal reinforcing bars are laid flat and moved horizontally until the frontmost longitudinal reinforcing bar is moved to the flat section of the turnover structure to wait for turnover. The laying mechanism meets the requirement of single reinforcing of the caisson, and the total width is greater than the sum of the diameters after the reinforcing is laid flat.

[0018] The turnover device comprises an electric pump station, a hydraulic rod, a curved connecting rod, a through shaft II and a turnover structure. The electric pump station and the hydraulic rod are arranged on a support near the middle of the hoisting platform. The tail of the hydraulic rod is hinged to the support, and the front end is hinged to the curved connecting rod. The curved connecting rod is fixedly connected to the through shaft II. The turnover structure is arranged every 2-3 m on the through shaft II. The stroke of the hydraulic rod, the position of the tail hinge support point and the eccentricity of the curved connecting rod are set to control the extension direction of the hydraulic rod, so as to realize the forward rotation and reverse rotation of the through shaft and complete the 90° reciprocating movement. The turnover structure is made of two 1 cm steel plates and is divided into an inclined block and an arc-shaped block. The two blocks are connected by bolts, and the whole forms an arc-shaped section, a straight section and an inclined section. The length of the straight section is adjusted by bolts, and the diameter is 2-6 mm larger than that of the reinforcing bar, so that only one longitudinal reinforcing bar is placed on the straight section. The turnover structure rotates 90° reciprocating with the through shaft II. The arc-shaped section prevents the reinforcing bar on the laying and feeding mechanism from moving forward, and the reinforcing bar on the straight section slides to the longitudinal feeding mechanism along the inclined section.

[0019] The longitudinal feeding mechanism comprises a motor II, a vertical chain gear II, a horizontal chain gear II, a roller shaft, a guide cover plate and a variable-diameter guide port. The motor II is arranged on a support near the front end of the hoisting platform and is connected to the frontmost roller shaft through the vertical chain gear II. A roller shaft is arranged every 2-3 m longitudinally and is connected by the horizontal chain gear II. The guide cover plate is made of stainless steel sheet and has a hole at the position of the corresponding roller shaft. The bottom elevation is 10 mm lower than that of the roller shaft. The roller shaft is divided into two longitudinal feeding channels on the plane, which respectively convey the longitudinal reinforcing bars of the horizontal movement and turnover mechanisms on both sides. The motor II drives the roller shaft to rotate, and the longitudinal reinforcing bars are conveyed forward along the guide cover plate by the friction between the reinforcing bars and the roller shaft. A variable-diameter guide port with a length of 50 cm is arranged at the end of the hoisting platform and is connected to the guide cover plate by rivets. The cross-sectional size is adjusted according to the horizontal spacing of the longitudinal partition wall reinforcing bars, and the reinforcing bars can pass through the side wall reinforcing mesh.

[0020] The electric control box system is arranged on a support near the middle of the hoisting platform. It is connected to each electrical equipment of the reinforcing bar installation and the distribution box in the prefabrication field by cables and switch plugs. The cables of each electrical equipment are fixed on the nearby hoisting platform support along the line by cable ties. The length of the cable connected to the prefabrication field distribution box meets the height requirement of the reinforcing bar. The electric control box system supports Ethernet, Wi-Fi or 4G / 5G communication through the integrated remote communication control module. Users can remotely control the switch circuit through a mobile phone APP or a computer terminal.

[0021] The construction method is suitable for different working conditions of reinforcing bar installation in the caisson prefabrication field. For the same working conditions of reinforcing bar installation in the caisson prefabrication field, the subsequent reinforcing bar installation is completed from step S4.

[0022] The application discloses a caisson prefabrication automatic steel bar penetrating device, which comprises a hoisting platform and a steel bar penetrating facility fixed on the hoisting platform, the hoisting platform is lifted and displaced by a tower crane in a prefabrication yard, manually controlled traction ropes are used for limiting and aligning the steel bar penetrating position, and the steel bar penetrating facility is provided with a support bracket, the steel bar penetrating facility comprises a laying and feeding mechanism, a turnover device, a longitudinal feeding mechanism and an electric control box system, the laying and feeding mechanism is arranged on both sides of the hoisting platform and is arranged symmetrically left and right, is used for laying and feeding longitudinal steel bars and can move the longitudinal steel bars to the turnover device in a transverse direction, the turnover device is arranged close to the laying and feeding mechanisms left and right, is arranged symmetrically left and right on the inner sides of the two laying and feeding mechanisms, is used for turning the longitudinal steel bars to the longitudinal feeding mechanism in a transverse direction, the longitudinal feeding mechanism is arranged close to the turnover devices left and right, is arranged in the middle of the two turnover devices, is used for moving the longitudinal steel bars to the designated steel bar penetrating position in a longitudinal direction, and the electric control box system is arranged near the middle of the hoisting platform, is connected with each electrical equipment of the steel bar penetrating facility and a distribution box in the prefabrication yard through cables and switch plugs and realizes remote control of the operation of the steel bar penetrating facility by arranging a remote communication control module.

[0023] By adopting the construction method of the application, the hoisting platform is lifted and displaced by a tower crane and manually controlled traction ropes are used for limiting and aligning the steel bar penetrating position, the lifting height of each step is controlled to be consistent with the vertical spacing of the steel bar penetrating, the steel bar penetrating position can be quickly aligned, and the steel bar penetrating efficiency is improved. The laying and feeding mechanism lays and feeds the longitudinal steel bars in advance, avoids the overlapping of the welding seam positions of adjacent steel bars, ensures the engineering quality, meets the arrangement and bearing requirements of the single steel bar penetrating of the caisson, and reduces the lifting and displacement frequency. The steel bar penetrating facility is transversely moved, turned and longitudinally moved by remote control, automatic operation is realized, and the labor intensity is greatly reduced. In the whole hoisting process, personnel do not need to enter the hoisting platform, and safe construction is ensured. BRIEF DESCRIPTION OF DRAWINGS

[0024] Figure 1 is a construction effect schematic view of the caisson prefabrication automatic steel bar penetrating device.

[0025] Figure 2 is a sectional view of the longitudinal feeding mechanism part of the caisson prefabrication automatic steel bar penetrating device.

[0026] Figure 3 is a sectional view of the laying and feeding mechanism part of the caisson prefabrication automatic steel bar penetrating device.

[0027] Figure 4 is a sectional view of the turnover device and the electric control box system part of the caisson prefabrication automatic steel bar penetrating device.

[0028] Figure 5 is a turnover structure schematic view of the caisson prefabrication automatic steel bar penetrating device.

[0029] Figure 6is a planar schematic view of a variable-diameter guide hole in a caisson prefabrication automated rebar penetrating device of the present application.

[0030] Figure 7 is a flow chart of the construction method of the present application. DETAILED DESCRIPTION

[0031] The present application will be further described in detail below in conjunction with the drawings and specific embodiments.

[0032] Example 1

[0033] The working conditions of this embodiment are different rebar penetrating specifications and spacings in a caisson prefabrication yard, as shown in Figures 1-7 A construction method of a caisson prefabrication automated rebar penetrating device, comprising the following steps:

[0034] S1: Device structure size adjustment. According to the diameter of the longitudinal rebar 6, use a wire pulling device or an infrared positioning device to adjust the length of the flat section of each turnover structure 305 in the turnover device 3 by means of a bolt 305c, so as to ensure that only one rebar is placed on it. According to the horizontal spacing of the longitudinal partition wall rebar and the rebar grid size of the side wall and transverse partition wall, change or adjust the size of the variable-diameter guide hole 406 in the longitudinal feeding mechanism 4, so as to ensure that the rebar passes smoothly along the variable-diameter guide hole 406 to the rebar penetrating position. According to the vertical spacing of the longitudinal partition wall rebar, set the scale marks above the double ropes 102' in the hoisting platform 1, and the scale interval is twice the length of the vertical spacing of the longitudinal partition wall rebar.

[0035] S2: Hoisting platform 1 test hoisting. Use a tower crane to hoist the hoisting platform 1 to a height of 200~500mm from the ground, use a level or a level to observe the inclination of the front and back of the hoisting platform 1, and adjust the platform by adding sandbags at appropriate positions to ensure that the total center of gravity of the platform and the rebar penetrating facilities on the platform is on the same vertical line as the platform centroid.

[0036] S3: Rebar penetrating facility test run. Connect the electric control box system 5 to each electric device of the rebar penetrating facility through a cable and a switch plug, then connect the electric control box system 5 to a distribution box in the prefabrication yard, remotely control the circuit switch through a mobile phone APP or a computer terminal, and timely handle control faults. After each electric device is powered on and started, observe whether the running direction is correct, and change the motor running direction by replacing the power line switch plug position of the electric device. The mobile phone APP or computer terminal, through a remote communication control module as a bridge, ensures that the mobile phone or computer can successfully connect the device to realize real-time remote control; the mobile phone APP or computer terminal is provided with an interface for displaying the start-stop, running and fault of the device; the mobile phone or computer terminal can send control instruction information to the remote communication control module, and then the remote communication control module drives the device to execute the instruction, thereby realizing real-time remote control of the device.

[0037] S4: The longitudinal reinforcement 6 is laid flat. The processed longitudinal reinforcement 6 is respectively hoisted on the two sides of the laying mechanism 2, the motor one 201 is started to drive the through shaft one 204 to rotate, the horizontal chain gear one 203 is driven to rotate, and the longitudinal reinforcement 6 is laid flat and moved horizontally under the cooperation of manual adjustment, the arrangement of the reinforcement is adjusted manually to ensure that the adjacent reinforcement weld positions are staggered, and the motor one 201 is turned off.

[0038] S5: The device is initially positioned. The lifting and moving platform 1 is lifted by the tower crane in the prefabrication yard, the position is adjusted by manually controlling the traction rope 102 and the double rope 102', and when the device is moved to be perpendicular to the side wall reinforcement mesh and the variable diameter guide hole 406 in the longitudinal feeding mechanism 4 is aligned with the first row of reinforcement penetration position, the traction rope 102 and the double rope 102' are temporarily fixed with the caisson and the pre-buried anchor on the ground. The double rope 102' with a scale mark is temporarily fixed vertically downward on the pre-buried anchor, one end of any one of the double ropes 102' is adjusted and fixed, and the scale mark of the other rope is temporarily fixed to coincide with the pre-buried anchor.

[0039] S6: The first row of reinforcement penetration. The longitudinal reinforcement 6 on the two sides of the laying mechanism 2 is moved horizontally by remotely controlling the circuit switch through the mobile phone APP or computer terminal, is turned over by the turnover device 3, is moved longitudinally along the longitudinal feeding mechanism 4, the end direction of the longitudinal reinforcement 6 is controlled by the reinforcement working personnel in the reinforcement mesh until the specified reinforcement penetration position is reached, and binding is completed.

[0040] S7: The device is stepwise lifted. The temporarily fixed end of the double rope 102' with a scale mark in the lifting platform 1 is loosened, the next scale mark is made to coincide with the pre-buried anchor, and is temporarily fixed again. The lifting platform 1 is slowly lifted by the tower crane through the tower crane frequency converter, the temporary fixation of the other traction rope 102 is loosened and slowly released, when the double rope 102' with a scale mark is tightened, the tower crane stops lifting, the traction rope 102 is temporarily fixed with the pre-buried anchor on the ground again. The variable diameter guide hole 406 in the longitudinal feeding mechanism 4 is aligned with the next row of reinforcement penetration position under the limitation of the double rope 102'.

[0041] S8: The device penetrates the reinforcement. The construction method is the same as step S6.

[0042] S9: The reinforcement penetration is completed. Steps S7 and S8 are repeated until all the reinforcement penetration work of the longitudinal partition wall of the caisson is completed, and the lifting platform 1 is transferred by the tower crane for next use.

[0043] Example 2

[0044] The working condition described in this example is that the reinforcement penetration specifications and distances of the caisson prefabrication yard are the same, and therefore the construction method of the automatic reinforcement penetration device for the caisson prefabrication is started from step S4 to complete the subsequent reinforcement penetration work.

[0045] Example 3

[0046] As Figures 1-6 shown, one kind is adopted in the caisson prefabrication automation of example 1 and example 2 and is included in a hoisting platform 1 and the reinforcing bar penetrating facility fixed on hoisting platform 1, hoisting platform 1 is lifted by the displacement of prefabrication yard tower crane, manually controlled traction rope position limiting is aligned with the reinforcing bar penetrating position, and the reinforcing bar penetrating facility is supported by the support bracket, the reinforcing bar penetrating facility includes the flat laying mechanism 2, the turnover device 3, the longitudinal feeding mechanism 4 and the electric control box system 5, the flat laying mechanism 2 is respectively arranged at both sides of hoisting platform 1, symmetrically arranged, for laying longitudinal reinforcement 6 and can move longitudinally to the turnover device 3, the turnover device 3 is respectively adjacent to the left and right flat laying mechanism 2, on the inner side of two flat laying mechanisms 2, symmetrically arranged, for turning the longitudinal reinforcement 6 to the longitudinal feeding mechanism 4, the longitudinal feeding mechanism 4 is adjacent to the left and right turnover device 3, in the middle of two turnover devices 3, for moving longitudinally to the specified reinforcing bar penetrating position, the electric control box system 5 is arranged near the middle of hoisting platform 1, is connected with the power equipment of reinforcing bar penetrating facility and the distribution box in prefabrication yard through cable and switch plug, and the operation of reinforcing bar penetrating facility is realized through the remote communication control module to realize remote control.

[0047] The hoisting platform 1 is a profile steel structure, the size is determined according to the reinforcing bar penetrating length and quantity and the arrangement requirement of reinforcing bar penetrating facility, and the hoisting platform 1 provides support for the reinforcing bar penetrating facility. The lifting eye 101 is symmetrically arranged on the top of the vertical rod at both sides of the hoisting platform 1 and is connected with the tower crane cable, and the lifting eye and traction rope 102 are symmetrically arranged near the bottom of the four corners, wherein the two front end traction ropes adopt double-strand rope 102' with scale marks. The double-strand rope 102' uses the principle that the moving distance of the movable pulley free end is equal to 2 times the object moving distance, and the scale interval on the upper surface is 2 times the length of the reinforcing bar vertical spacing, which limits the tower crane step lifting, and ensures that the reinforcing bar penetrating device is quickly aligned with the reinforcing bar penetrating position.

[0048] The laying mechanism 2 comprises a motor 201, a vertical chain gear 202, a horizontal chain gear 203, and a through shaft 204. The motor 201 is arranged on a support near the middle of the lifting platform 1 and is connected with the through shaft 204 through the vertical chain gear 202. The horizontal chain gear 203 is arranged on the through shaft 204 every 2-3 m, and a support is arranged at the corresponding position. Before the motor 201 is started, the top horizontal chain is in a relaxed state and the longitudinal reinforcement 6 placed thereon is mainly supported by the support. When the motor 201 is started, the through shaft 204 is driven to rotate, the horizontal chain gear 203 is driven to rotate, the top horizontal chain is taut, and the longitudinal reinforcement 6 is moved along with the top horizontal chain under the cooperation of manual work until the turnover structure 305 is blocked, the frontmost longitudinal reinforcement 6 is moved to the flat section of the turnover structure and waits for turnover. The laying mechanism 2 meets the requirement of the number of single reinforcement penetration of the caisson, and the total width is greater than the sum of the diameters after the reinforcement is laid.

[0049] The turnover device 3 comprises an electric pump station 301, a hydraulic rod 302, a curved connecting rod 303, a through shaft 304, and a turnover structure 305. The electric pump station 301 and the hydraulic rod 302 are arranged on a support near the middle of the lifting platform 1, the tail of the hydraulic rod 302 is hinged to the support, the front end is hinged to the curved connecting rod 303, the curved connecting rod 303 is fixedly connected to the through shaft 304, and the turnover structure 305 is arranged on the through shaft 304 every 2-3 m. The stroke of the hydraulic rod 302, the position of the tail hinge point, and the eccentric distance of the curved connecting rod 303 are set to control the extension direction of the hydraulic rod 302, so as to realize the forward rotation and reverse rotation of the through shaft 304 and complete 90° reciprocating motion. The turnover structure 305 is made of two 1 cm steel plates and is divided into an inclined block 305a and an arc-shaped block 305b, which are connected through a bolt 305c and form an arc-shaped section, a flat section, and an inclined section as a whole. The length of the flat section is adjusted through the bolt 305c and is 2-6 mm larger than the diameter of the reinforcement to ensure that only one longitudinal reinforcement 6 is placed on the flat section. The turnover structure 305 rotates 90° reciprocatingly with the through shaft 304, the arc-shaped section prevents the reinforcement on the laying mechanism 2 from moving forward, and the reinforcement on the flat section slides to the longitudinal feeding mechanism 4 along the inclined section.

[0050] The longitudinal feeding mechanism 4 comprises a motor 401, a vertical chain gear 402, a horizontal chain gear 403, a roller shaft 404, a guide cover plate 405, and a variable-diameter guide port 406. The motor 401 is arranged on a support near the front end of the hoisting platform 1 and is connected with the frontmost roller shaft 404 through the vertical chain gear 402. The roller shaft 404 is arranged every 2-3 m longitudinally and is connected through the horizontal chain gear 402. The guide cover plate 405 is made of stainless steel sheet and is provided with holes at the positions of the roller shafts 404. The bottom elevation of the guide cover plate 405 is 10 mm lower than that of the roller shaft 404. The roller shafts 404 are divided into two longitudinal feeding channels on the plane to respectively feed the longitudinal steel bars 6 on the two sides of the mechanism transverse movement and turning. The motor 401 drives the roller shaft 404 to rotate and utilizes the friction between the steel bar and the roller shaft to transmit the longitudinal steel bar 6 to move forward along the guide cover plate 405. The variable-diameter guide port 406 is arranged at the end of the hoisting platform 1 and is connected with the guide cover plate 405 through rivets. The cross-sectional size of the variable-diameter guide port 406 is adjusted according to the horizontal spacing of the longitudinal partition wall steel bars and the steel bar can pass through the side wall steel mesh to move forward.

[0051] The electric control box system 5 is arranged on a support near the middle of the hoisting platform 1 and is connected with each electric device of the steel bar penetrating facility and the distribution box in the prefabrication field through cables and switch plugs. The cables of each electric device are fixed on the support of the hoisting platform 1 near the line through cable ties and the length of the cable connected with the distribution box in the prefabrication field meets the height requirement of the steel bar penetration. The electric control box system 5 supports Ethernet, Wi-Fi or 4G / 5G communication through an integrated remote communication control module and the user can remotely control the switch circuit through a mobile phone APP or a computer terminal.

[0052] The above only describes the preferred embodiments of the present application, but the protection scope of the present application is not limited to this. Any skilled person in the art can make equivalent replacement or change according to the technical solution and the inventive concept of the present application within the technical range disclosed by the present application, which should be covered in the protection scope of the present application.

Claims

1. A construction method for an automated rebar threading device for prefabricated caissons, characterized in that: The device is vertically aligned with the side wall steel mesh and the first row of the steel bar penetrating position by lifting and moving with the tower crane and manually pulling and positioning, and the device is step by step lifted and aligned with the subsequent steel bar penetrating position of the longitudinal partition wall by limiting with the double ropes with scale marks; after aligning with the steel bar penetrating position each time, the longitudinal steel bar is transversely moved, turned over and longitudinally moved by remotely controlling the steel bar penetrating facility, and the direction of the end of the longitudinal steel bar is controlled by the steel bar operating personnel in the steel mesh until reaching the designated steel bar penetrating position to complete the binding; the construction method specifically comprises the following steps: S1: device structure size adjustment; according to the diameter of the longitudinal steel bar, the steel bar is pulled or positioned by infrared rays, the length of the flat section of each turning structure in the turning device is adjusted by a bolt to ensure that only one steel bar is placed on it; according to the horizontal spacing of the longitudinal partition wall steel bar and the size of the steel mesh of the side wall and the transverse partition wall, the size of the variable diameter guide hole in the longitudinal feeding mechanism is changed or adjusted to ensure that the steel bar penetrates through the side wall and the transverse partition wall steel mesh to the steel bar penetrating position along the variable diameter guide hole; according to the vertical spacing of the longitudinal partition wall steel bar, the scale marks above the double ropes in the lifting platform are set, and the scale interval is twice the length of the vertical spacing of the longitudinal partition wall steel bar; S2: lifting platform trial lifting; the lifting platform is lifted by the tower crane to be 200-500 mm away from the ground, the inclination of the lifting platform is observed by using the level or the level meter, the platform is leveled by adding sandbags at appropriate positions on the platform, and the total center of gravity of the platform and the steel bar penetrating facility on the platform is ensured to be on the same vertical line with the platform centroid; S3: steel bar penetrating facility trial operation; the electric control box system is connected with each electrical equipment of the steel bar penetrating facility through the cable and the switch plug, then the electric control box system is connected to the distribution box in the prefabrication yard, the circuit switch is remotely controlled by the mobile phone APP or the computer terminal, and control failures are handled in time; whether the running direction of each electrical equipment is correct is observed after the electrical equipment is powered on and started, and the running direction of the motor is changed by replacing the power line switch plug position of the electrical equipment; S4: longitudinal steel bar laying and sequencing; the processed longitudinal steel bars are respectively hung on the two side laying mechanisms, the motor one of the laying mechanism is started to drive the through shaft to rotate, the horizontal chain gear is driven to rotate, the longitudinal steel bar is laid and moved horizontally under the manual cooperation, the arrangement sequence of the steel bars is adjusted by manual, the adjacent steel bar welding positions are staggered, and the motor one is closed; S5: device first positioning; the lifting platform is lifted and moved by the tower crane in the prefabrication yard, the position of the traction rope and the double ropes is adjusted by manual, when the device is moved to be vertically aligned with the side wall steel mesh and the variable diameter guide hole in the longitudinal feeding mechanism is aligned with the first row of the steel bar penetrating position, the traction rope and the double ropes are temporarily fixed with the caisson and the pre-buried anchor on the ground; the double ropes with scale marks are temporarily fixed on the pre-buried anchor vertically downward from the device, one end of any one of the double ropes is adjusted and fixed, the scale mark of the other rope is overlapped with the pre-buried anchor and is temporarily fixed. S6: first row of reinforcing bars; through the mobile phone APP or computer terminal remote control circuit switch, the two sides of the longitudinal reinforcement on the flat feeding mechanism transverse, through the turnover device turnover, along the longitudinal feeding mechanism, the longitudinal reinforcement through the side wall reinforcement mesh, by the reinforcement mesh inside the reinforcement workers control the longitudinal reinforcement end direction, until to the designated position, complete the binding; S7: device step lifting; loosen the double rope with scale marks temporary fixed end in the lifting platform, so that the next scale mark coincides with the embedded anchor rod, re- temporary fixed; through the tower crane frequency converter to adjust the tower crane slowly lifting platform, loosen the other traction rope temporary fixed and slowly release, when the double rope with scale marks tight, the tower crane stop lifting, traction rope with the ground embedded anchor rod re- temporary fixed; in the double rope limit under the longitudinal feeding mechanism diameter guide hole align the next row of reinforcing position; S8: device reinforcing; construction method steps with S6; S9: reinforcing completion; repeat step S7 and step S8, until the completion of all the box caisson longitudinal wall reinforcing work, the tower crane transfer lifting platform for next use.

2. The construction method of a caisson prefabricated automatic wire penetrating device according to claim 1, characterized in that: The lifting platform is a type steel structure, according to the reinforcing length and quantity and the arrangement requirements of reinforcing facilities to determine the size, and provide support bracket for reinforcing facilities; the lifting platform both sides of the vertical rod top symmetrical setting lifting hole and tower crane cable connection, close to the four corners of the bottom of the symmetrical setting lifting hole and traction rope, wherein the front end of 2 traction rope with scale marks double rope; the double rope uses the principle of movable pulley free end moving distance equal to 2 times the object moving distance, the scale interval on the top is 2 times the length of reinforcing vertical spacing, limiting the tower crane step lifting, ensure the reinforcing device quickly align the reinforcing position.

3. The construction method of a caisson prefabricated automatic wire penetrating device according to claim 1, characterized in that: The flat feeding mechanism, including motor one, vertical chain gear one, horizontal chain gear one, through the shaft one; motor one is arranged on the bracket near the middle of the lifting platform, through the vertical chain gear one and through the shaft one connection; every 2~3m on the through shaft one sets horizontal chain gear, the corresponding position is provided with a bracket; before the motor is started, the top horizontal chain is in a relaxed state, the longitudinal reinforcement on the top horizontal chain is supported by the bracket; start the motor, drive the through shaft rotation, drive the horizontal chain gear one rotation, the top horizontal chain is tight, 5~10mm higher than the bracket surface, under the artificial cooperation, the longitudinal reinforcement along with the flat, horizontal movement, to the turnover device is blocked, the most front end of longitudinal reinforcement moves to the turnover structure flat segment waiting for turnover; the flat feeding mechanism meets the requirement of the single reinforcing quantity of the box, the total width is greater than the sum of the diameter after the reinforcing flat.

4. The construction method of a caisson prefabricated automatic wire penetrating device according to claim 1, characterized in that: The turnover device comprises an electric pump station, a hydraulic rod, a curved connecting rod, a through shaft II and a turnover structure; the electric pump station and the hydraulic rod are arranged on a support near the middle of the hoisting platform, the tail of the hydraulic rod is hinged to the support, the front end is hinged to the curved connecting rod, the curved connecting rod is fixedly connected to the through shaft II, and the turnover structure is arranged on the through shaft II every 2-3 m; the stroke of the hydraulic rod, the position of the tail hinged support and the eccentricity of the curved connecting rod are set to control the extension direction of the hydraulic rod, so that the through shaft is rotated forward and backward, and 90° reciprocating motion is realized; the turnover structure is made of two 1 cm steel plates and is divided into an inclined block and an arc block, the two blocks are connected by bolts, and an arc segment, a straight segment and an inclined segment are formed as a whole, the length of the straight segment is adjusted by bolts, the diameter of the bolt is 2-6 mm larger than that of the reinforcing bar, and only one longitudinal reinforcing bar is placed on the straight segment; the turnover structure rotates 90° reciprocating with the through shaft II, the arc segment prevents the reinforcing bar on the laying and feeding mechanism from moving forward, and the reinforcing bar on the straight segment slides to the longitudinal feeding mechanism along the inclined segment.

5. The construction method of a caisson prefabricated automatic wire penetrating device according to claim 1, characterized in that: The longitudinal feeding mechanism comprises a second motor, a vertical chain gear II, a horizontal chain gear II, a roller shaft, a guide cover plate and a variable-diameter guide port; the second motor is arranged on a support near the front end of the hoisting platform and is connected to the frontmost roller shaft through the vertical chain gear II; a roller shaft is arranged every 2-3 m longitudinally, and the roller shafts are connected through the horizontal chain gear II; the guide cover plate is made of a thin stainless steel plate, has a hole at the position of the corresponding roller shaft, and the bottom elevation is 10 mm lower than that of the roller shaft; the roller shafts are divided into two longitudinal feeding channels on the plane, and the longitudinal reinforcing bars of the two sides of the mechanism are respectively fed; the second motor drives the roller shaft to rotate, and the longitudinal reinforcing bars are conveyed forward along the guide cover plate by the friction between the reinforcing bars and the roller shaft; the variable-diameter guide port is arranged at the end of the hoisting platform, has a length of 50 cm, is connected to the guide cover plate through rivets, and the cross-sectional size is adjusted according to the horizontal spacing of the longitudinal partition wall reinforcing bars, and the reinforcing bars can pass through the side wall reinforcing mesh.

6. The construction method of a caisson prefabricated automatic penetrating device according to claim 1, characterized in that: The electric control box system is arranged on a support near the middle of the hoisting platform, is connected to each electrical equipment of the reinforcing bar installation and the distribution box in the prefabrication field through cables and switch plugs, and the cables of each electrical equipment are fixed on the nearby hoisting platform support along the line by cable ties. The length of the cable connected to the distribution box in the prefabrication field meets the height requirement of the reinforcing bar; the electric control box system supports Ethernet, Wi-Fi or 4G / 5G communication through an integrated remote communication control module, and users can remotely control the switch circuit through a mobile phone APP or a computer terminal.

7. The construction method of a prefabricated automatic bar penetrating device for a caisson according to any one of claims 1 to 6, characterized in that: The construction method is suitable for different working conditions of reinforcing bar installation with different specifications and spacings in the caisson prefabrication field; for working conditions of reinforcing bar installation with the same specifications and spacings in the caisson prefabrication field, subsequent reinforcing bar installation is completed from step S4.

Citation Information

Patent Citations

  • Caisson prefabricated bar penetrating large plate

    CN220005816U

  • Assembly type building rectangular steel pipe making and rib penetrating cutting device

    CN111376055A

  • Tunnel portal assembly type canopy construction method based on BIM technology

    CN117306861A