Horizontal flow shallow layer grouting plugging treatment method and device under flowing water condition
By constructing vertical and filling curtains in the coal mining area to form an aquiclude, the problems of water level drop and resource shortage caused by coal mining were solved, and a balance was achieved between ecological environment protection and safe production.
Patent Information
- Application Number
- CN202510991214.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-07-18
- Publication Date
- 2025-10-17
AI Technical Summary
The drop in water levels and loss of water resources in the Quaternary aquifer caused by traditional coal mining affect the ecological environment and production safety, and may cause water inrush accidents and resource shortages.
Vertical curtains and filling curtains are constructed in the treatment area. Through short-distance and long-distance drilling and grouting, stable water layers and aquicludes are formed to cut off external laminar recharge and prevent water loss.
Protect and conserve the Quaternary ecological aquifer, prevent water shortages, balance resource development and ecological protection, and form a virtuous cycle of ecology and production.
Smart Images

Figure CN120798237A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of stratum treatment, and in particular to a horizontal flow to shallow layer grouting plugging treatment method under dynamic water conditions. BACKGROUND
[0002] Traditional coal mining technology will disturb the quaternary aquifer and cause a series of environmental and production problems. In terms of ecology, the water in the aquifer infiltrates through the water-conducting fissure zone, causing the shallow groundwater level to drop, damaging the regional water cycle system, weakening the water conservation capacity of the aquifer, and possibly causing degradation of surface vegetation, shrinkage of wetlands, and even affecting the water for daily use and agricultural irrigation of surrounding residents. In terms of mining safety, a large amount of water flowing into the underground mine will increase the water inflow of the mine, increase the drainage cost, and also possibly induce water inrush accidents, threatening the safety of miners; at the same time, the interaction between water and coal rock may soften the surrounding rock, reduce the stability of the coal seam roof, and exacerbate the deformation of the roadway, affecting the mining efficiency and resource recovery rate. In addition, long-term drainage may cause the aquifer to dry out, further exacerbating the shortage of regional water resources, forming a vicious cycle of ecology-production. Therefore, the present application proposes a horizontal flow to shallow layer grouting plugging treatment method under dynamic water conditions, which is constructed by interval distribution of short-distance directional horizontal holes and long-distance directional horizontal holes to build a closed curtain, and performs horizontal flow to shallow layer plugging treatment under dynamic water conditions, in order to protect the quaternary ecological aquifer and balance resource development and ecological protection. SUMMARY
[0003] Therefore, the present application proposes a horizontal flow to shallow layer grouting plugging treatment method and device under dynamic water conditions.
[0004] To achieve the above purpose, the present application provides a horizontal flow to shallow layer grouting plugging treatment method under dynamic water conditions, which comprises: constructing a vertical curtain in a preset treatment area to form a stable water layer in the treatment area; and constructing a filling curtain in the treatment area to connect the filling curtain with the vertical curtain to form an aquiclude.
[0005] In some embodiments, the vertical curtain is constructed in the preset treatment area, specifically comprising: calculating a first drilling position according to the treatment area; opening a first drilling hole according to the first drilling position; and performing grouting into the first drilling hole to obtain the vertical curtain.
[0006] In some embodiments, the filling curtain comprises a curtain skeleton and a reinforcing curtain. The filling curtain is constructed in the treatment area to connect the filling curtain with the vertical curtain to form an aquiclude, specifically comprising: constructing a curtain skeleton in the treatment area. The curtain skeleton is arranged vertically with the vertical curtain. A reinforcing curtain is constructed in the gap between at least two curtain skeletons. The reinforcing curtain is arranged parallel to the curtain skeleton.
[0007] In some embodiments, the curtain skeleton is constructed in the treatment area, specifically comprising: calculating a second drilling position according to the position of the vertical curtain. A second drilling hole is opened according to the second drilling position. The second drilling hole is a long distance drilling hole. The second drilling hole is grouted by using a forward grouting method to obtain the curtain skeleton. The grouting distance of the forward grouting method is 25-100m.
[0008] In some embodiments, the reinforced curtain is constructed in the gap between at least two curtain skeletons, specifically comprising: calculating a third drilling position according to the position of the curtain skeleton. A third drilling hole is opened according to the third drilling position. The third drilling hole is a short distance drilling hole. The third drilling hole is grouted to obtain the reinforced curtain.
[0009] The application also provides a horizontal flow shallow layer grouting plugging treatment device under dynamic water conditions, comprising: a vertical curtain construction module for constructing a vertical curtain in a preset treatment area to form a stable water layer in the treatment area; and a filling curtain construction module for constructing a filling curtain in the treatment area to connect the filling curtain with the vertical curtain to form a water-resisting layer.
[0010] In some embodiments, the vertical curtain construction module specifically comprises: a first calculation module for calculating a first drilling position according to the treatment area; a first drilling module for opening a first drilling hole according to the first drilling position; and a first grouting module for grouting into the first drilling hole to obtain the vertical curtain.
[0011] In some embodiments, the filling curtain comprises a curtain skeleton and a reinforced curtain. The filling curtain construction module specifically comprises: a curtain skeleton construction module for constructing a curtain skeleton in the treatment area. The curtain skeleton is vertically arranged with the vertical curtain. A reinforced curtain construction module is used to construct a reinforced curtain in the gap between at least two curtain skeletons. The reinforced curtain is arranged in parallel with the curtain skeleton.
[0012] In some embodiments, the curtain skeleton is constructed in the treatment area, specifically comprising: a second calculation module for calculating a second drilling position according to the position of the vertical curtain; a second drilling module for opening a second drilling hole according to the second drilling position. The second drilling hole is a long distance drilling hole. A second grouting module is used to grout the second drilling hole by using a forward grouting method to obtain the curtain skeleton. The grouting distance of the forward grouting method is 25-100m.
[0013] In some embodiments, the reinforced curtain is constructed in the gap between at least two curtain skeletons, specifically comprising: a third calculation module for calculating a third drilling position according to the position of the curtain skeleton; a third drilling module for opening a third drilling hole according to the third drilling position. The third drilling hole is a short distance drilling hole. A third grouting module is used to grout the third drilling hole to obtain the reinforced curtain.
[0014] From the above, it can be seen that the horizontal flow under the condition of water to the shallow layer grouting plugging management method provided by the application, by constructing a vertical curtain in the management area, to form a stable water layer in the management area, facilitate subsequent construction, and then by constructing a filling curtain in the management area, and connecting the filling curtain with the vertical curtain to form a waterproof layer, thereby protecting the fourth ecological aquifer, preventing regional water resource shortage, balancing resource development and ecological protection, and forming an ecological-production virtuous cycle. BRIEF DESCRIPTION OF DRAWINGS
[0015] In order to more clearly illustrate the technical solutions in the application or related art, the following will briefly introduce the drawings needed to be used in the embodiments or related art description. Obviously, the drawings in the following description are only embodiments of the application, and other drawings can be obtained by those skilled in the art without creative labor.
[0016] Figure 1 The flowchart of the horizontal flow under the condition of water to the shallow layer grouting plugging management method provided by the embodiment of the application is shown in the figure.
[0017] Figure 2 The stratigraphic section schematic diagram of constructing a vertical curtain according to the method provided by the embodiment of the application is shown in the figure.
[0018] Figure 3 The stratigraphic section schematic diagram of constructing a curtain curtain skeleton according to the method provided by the embodiment of the application is shown in the figure.
[0019] Figure 4 The stratigraphic section schematic diagram of constructing a reinforced curtain according to the method provided by the embodiment of the application is shown in the figure.
[0020] Figure 5 The drilling point position schematic diagram provided by the embodiment of the application is shown in the figure.
[0021] Figure 6 The structure schematic diagram of the horizontal flow under the condition of water to the shallow layer grouting plugging management device provided by the embodiment of the application is shown in the figure. DETAILED DESCRIPTION
[0022] In order to make the purpose, technical solutions and advantages of the application more clear and obvious, the following will further illustrate the application in combination with specific embodiments and with reference to the drawings.
[0023] It should be noted that the technical terms or scientific terms used in the embodiments of the present application should be understood as the general meaning understood by those skilled in the art to which the embodiments of the present application belong, unless otherwise defined. The terms "first", "second", and similar terms used in the embodiments of the present application do not represent any order, quantity or importance, but are only used to distinguish different components. The terms "include" or "contain" and similar terms mean that the elements or objects before the terms cover the elements or objects listed after the terms and their equivalents, and do not exclude other elements or objects. The terms "connect" or "connected" and similar terms are not limited to physical or mechanical connections, but can include electrical connections, whether direct or indirect. "Up", "down", "left", "right" and the like are only used to represent relative positional relationships, and when the absolute position of the described object changes, the relative positional relationship may also change accordingly.
[0024] As Figure 1 shown, the present application provides a horizontal flow to shallow grouting plugging treatment method under dynamic water conditions, comprising:
[0025] Step S1, constructing a vertical curtain in a predetermined treatment area to form a stable water layer in the treatment area.
[0026] In this embodiment, by constructing a vertical curtain, external layer flow supply can be cut off, and dynamic water environment can be isolated by dam body bottoming, so that a stable water layer is formed in the treatment area, avoiding the displacement of grout to outside the treatment area under dynamic water conditions, and facilitating subsequent construction operation.
[0027] Among them, the treatment area is selected according to the interlayer relationship between the strata and the quaternary water-rich condition, by finding the section which is easily affected by the coal mine roadway excavation and needs to be treated, a curtain is constructed in the treatment area to form a water-resisting layer, so as to prevent water resources loss of the quaternary ecological water-bearing layer.
[0028] Step S2, constructing a filling curtain in the treatment area to connect the filling curtain with the vertical curtain to form a water-resisting layer.
[0029] Among them, by constructing a filling curtain in the treatment area and connecting the filling curtain with the vertical curtain to form a water-resisting layer, water resources loss of the upper water-bearing layer caused by the water-conducting fractured zone generated in the process of coal mining is prevented, adverse effects on the ecological environment are avoided, the quaternary ecological water-bearing layer is protected, and the role of protecting the ecological environment and the domestic water of nearby residents is played.
[0030] In some embodiments, step S1 specifically comprises:
[0031] Step S11, calculating a first drilling position according to the treatment area.
[0032] In this embodiment, asFigure 5 As shown, the first drilling position is the first sequence hole shown in the figure, which is set at the outermost side of the treatment area. The spacing and number of the first drilling positions can be reasonably adjusted according to the actual geological conditions.
[0033] Step S12: opening a first borehole according to the first borehole position.
[0034] Step S13: grouting is performed into the first borehole to obtain a vertical curtain.
[0035] Among them, such as Figure 2 As shown, by opening a first borehole at the first borehole location and grouting the first borehole, external laminar recharge is cut off, forming a stable water layer within the treatment area. During the construction of the first borehole, short-distance branch holes can be constructed by overlapping the casing of the long-distance horizontal hole, with the drilling trajectory parallel to the long branch directional horizontal hole.
[0036] In some embodiments, the filling curtain includes a curtain frame and a reinforcing curtain.
[0037] Step S2 specifically includes:
[0038] Step S21: constructing a curtain frame in the treatment area, wherein the curtain frame is arranged perpendicular to the vertical curtain.
[0039] Step S22: constructing a reinforced curtain in the gap between at least two curtain frames, wherein the reinforced curtain is arranged parallel to the curtain frames.
[0040] In this embodiment, the curtain frame is used to fill the treatment area to form a water-proof layer, and the reinforcing curtain is used to strengthen the gaps between the curtain frames and reinforce the water-proof layer.
[0041] In some embodiments, step S21 specifically includes:
[0042] Step S211 : calculating a second drilling position according to the position of the vertical curtain.
[0043] In this embodiment, if Figure 5 As shown, the second drilling position is the second-order hole shown in the figure, which is set in the middle of the treatment area. The spacing and number of the second drilling positions can be reasonably adjusted according to the actual geological conditions.
[0044] Step S212: Drill a second hole according to the second hole location, wherein the second hole is drilled using a long distance.
[0045] Step S213: Grouting the second borehole using a forward grouting method to obtain a curtain frame, wherein the grouting distance of the forward grouting method is 25 to 100 meters.
[0046] Among them, such as Figure 3 As shown, a long-distance horizontal curtain is formed in the long-distance borehole by opening a long-distance borehole at a second borehole position and grouting the second borehole.
[0047] Preferably, in order to improve the strength of the curtain frame, the grouting distance of the forward grouting method is preferably 50m.
[0048] In some embodiments, step S22 specifically includes:
[0049] Step S221 : calculating the third drilling position according to the position of the curtain frame.
[0050] In this embodiment, if Figure 5 As shown, the third drilling position is the three-sequence hole shown in the figure, which is set between the curtain frame and the vertical curtain. The spacing and number of the third drilling positions can be reasonably adjusted according to actual geological conditions.
[0051] Step S222: Drill a third borehole according to the third borehole position, wherein the third borehole is drilled in a short distance.
[0052] Step S223: Grouting is performed on the third borehole to obtain a reinforced curtain.
[0053] Among them, such as Figure 4 As shown, the waterproof layer is reinforced by opening a long-distance borehole at the third borehole position and grouting the third borehole.
[0054] Preferably, the third borehole treatment layer is mainly the top of the weathered bedrock, and short-distance directional horizontal hole grouting is carried out between the second boreholes, arranged parallel to the second boreholes, to fill the horizontal waterproof curtain and strengthen the curtain filling in the curtain skeleton established by the long-distance horizontal grouting holes, and short-distance directional horizontal hole grouting is added at the connection of the long-distance horizontal grouting holes to further strengthen the curtain filling, so that the overall waterproof effect of the waterproof curtain is stronger.
[0055] As an optional implementation method, the construction of grouting holes follows the principle of "sparse first, dense later, and construction in sequence": first construct the grouting holes on all sides, overlap with the bottom of the Quaternary system and isolate the dynamic water environment; then construct the long horizontal holes to build the curtain skeleton; finally, construct the remaining short horizontal holes and fill the horizontal water-blocking curtain.
[0056] As an optional implementation, the method provided by the application can also form a vertical grouting curtain by first using long-distance horizontal holes to drain and grout at the edge of the selected treatment area, cut off the external laminar flow supply, connect to the bottom of the dam body, and isolate the dynamic water environment, so as to form a stable water layer in the treatment area; form a horizontal curtain by using long-distance horizontal holes to drain and grout in the water conducting fractured zone supply area in the treatment area, and build a curtain skeleton; arrange short-distance directional horizontal holes between the long-distance directional horizontal hole skeletons, so that the short-distance directional horizontal holes are distributed at intervals with the long-distance directional horizontal holes, and increase short-distance horizontal holes at the connection between the long-distance holes, so as to achieve the effect of strengthening the curtain filling.
[0057] As an optional implementation, the method provided by the application builds a closed vertical curtain when the upper aquifer is in a horizontal dynamic water condition, cuts off the external laminar flow supply, and prevents the slurry from being washed out of the treatment area under dynamic water conditions. Further, shallow plugging treatment is performed by long-distance horizontal hole grouting and short-distance horizontal hole grouting to prevent the water resources of the upper aquifer from being lost due to the water conducting fractured zone caused by coal mining, thereby causing adverse effects on the ecological environment, and further playing a role in protecting the fourth ecological aquifer and the ecological environment and the domestic water of nearby residents. The long-distance directional horizontal hole is filled to form a horizontal curtain, thereby forming a stable aquifuge.
[0058] As an optional implementation, as shown in Figure 5 The first borehole (first sequence hole) includes short-distance boreholes for grouting on both sides and long-distance boreholes for grouting on one side, the long-distance boreholes are used to fill the treatment area, and the short-distance boreholes are used to reinforce the vertical curtain, so as to build a vertical curtain with high strength.
[0059] As an optional implementation, as shown in Figure 5 The second borehole (second sequence hole) includes short-distance boreholes for grouting on both sides and long-distance boreholes for grouting on one side, the long-distance boreholes are used to fill the treatment area, and the short-distance boreholes are used to reinforce the vertical curtain, so as to build a vertical curtain with high strength.
[0060] As an optional implementation, as shown in Figure 5 The third borehole (third sequence hole) only includes short-distance boreholes for grouting on both sides, the third borehole is used to further reinforce the treatment area, so as to make the aquifuge have a more stable structure and prevent the fourth ecological aquifer from losing water resources.
[0061] As an optional implementation, under the horizontal water environment, the grouting slurry in the first sequence hole has a relatively short diffusion distance, but has a higher requirement for the setting speed, and needs to quickly isolate the water environment, so the grouting material is single liquid cement slurry. However, the single liquid cement slurry has a relatively high cost and a relatively short diffusion distance, and is not suitable for wide use in the second sequence and the third sequence. Therefore, clay cement slurry is used in the second sequence and the third sequence, more than 90% of which is natural clay in volume ratio. The diffusion distance is relatively far, and the cost is relatively low. The grouting density of the clay cement slurry in the second sequence and the third sequence is strengthened. Through different grouting materials and different processes, the dual protection of engineering quality and economy is realized.
[0062] As can be seen from the above embodiments of the application, the vertical curtain is constructed in the treatment area to form a stable water layer in the treatment area, facilitating subsequent construction. The filling curtain is constructed in the treatment area, and the filling curtain is connected with the vertical curtain to form a water-resisting layer, thereby protecting the fourth system ecological water-bearing layer, preventing regional water resource shortage, balancing resource development and ecological protection, and forming an ecological-production virtuous cycle.
[0063] It should be noted that the method of the embodiments of the application can be executed by a single device, such as a computer or a server. The method of the embodiments can also be applied to a distributed scenario and completed by multiple devices cooperating with each other. In this distributed scenario, one of the multiple devices can only execute one or more steps in the method of the embodiments of the application, and the multiple devices can interact with each other to complete the method.
[0064] It should be noted that some embodiments of the application have been described above. Other embodiments are within the scope of the appended claims. In some cases, the actions or steps recited in the claims can be performed in a different order than the order described above and still achieve desirable results. In addition, the processes depicted in the figures do not necessarily require the particular order shown or sequential order to achieve the desired results. In certain implementations, multitasking and parallel processing can be advantageous.
[0065] Based on the same inventive concept, corresponding to any of the above-mentioned embodiment methods, the application further provides a horizontal flow to shallow layer grouting plugging treatment device under dynamic water conditions.
[0066] Reference Figure 6 The horizontal flow to shallow layer grouting plugging treatment device under dynamic water conditions comprises:
[0067] The vertical curtain construction module 100 is configured to construct a vertical curtain in a preset treatment area to form a stable water layer in the treatment area.
[0068] The filling curtain construction module 200 is configured to construct a filling curtain in the treatment area, so as to connect the filling curtain with the vertical curtain to form a water-resisting layer.
[0069] In some embodiments, the vertical curtain construction module 100 specifically comprises:
[0070] The first calculation module is configured to calculate a first drilling position according to the treatment area.
[0071] The first drilling module is configured to drill a first drilling hole according to the first drilling position.
[0072] The first grouting module is configured to grout into the first drilling hole to obtain the vertical curtain.
[0073] In some embodiments, the filling curtain comprises a curtain skeleton and a reinforcing curtain.
[0074] The filling curtain construction module 200 specifically comprises:
[0075] The curtain skeleton construction module is configured to construct a curtain skeleton in the treatment area. The curtain skeleton is arranged perpendicularly to the vertical curtain.
[0076] The reinforcing curtain construction module is configured to construct a reinforcing curtain in the gap between at least two curtain skeletons. The reinforcing curtain is arranged in parallel to the curtain skeleton.
[0077] In some embodiments, the construction of the curtain skeleton in the treatment area specifically comprises:
[0078] The second calculation module is configured to calculate a second drilling position according to the position of the vertical curtain.
[0079] The second drilling module is configured to drill a second drilling hole according to the second drilling position. The second drilling hole is a long-distance drilling hole.
[0080] The second grouting module is configured to grout into the second drilling hole by using a forward grouting method to obtain the curtain skeleton. The grouting distance of the forward grouting method is 25-100 m.
[0081] In some embodiments, the construction of the reinforcing curtain in the gap between at least two curtain skeletons specifically comprises:
[0082] The third calculation module is configured to calculate a third drilling position according to the position of the curtain skeleton.
[0083] The third drilling module is configured to drill a third drilling hole according to the third drilling position. The third drilling hole is a short-distance drilling hole.
[0084] The third grouting module is configured to grout into the third drilling hole to obtain the reinforcing curtain.
[0085] For the convenience of description, the above apparatus is described in various modules in terms of functions. Of course, the functions of the modules can be implemented in one or more software and / or hardware in the implementation of the present application.
[0086] The apparatus of the above embodiments is used to implement the horizontal flow to shallow grouting plugging treatment method under the corresponding hydrodynamic condition in any of the preceding embodiments, and has the beneficial effects of the corresponding method embodiments, which are not described here again.
[0087] It should be noted that the embodiments of the present application can also be further described in the following ways:
[0088] A horizontal flow to shallow grouting plugging treatment method under hydrodynamic condition, comprising:
[0089] A vertical curtain is constructed in a preset treatment area, so as to form a stable water layer in the treatment area.
[0090] A filling curtain is constructed in the treatment area, so as to connect the filling curtain with the vertical curtain to form a water-resisting layer.
[0091] Optionally, the vertical curtain is constructed in the preset treatment area, specifically comprising:
[0092] The first drilling position is calculated according to the treatment area.
[0093] The first drilling hole is opened according to the first drilling position.
[0094] Grouting is performed into the first drilling hole to obtain the vertical curtain.
[0095] Optionally, the filling curtain comprises a curtain skeleton and a reinforcing curtain.
[0096] The filling curtain is constructed in the treatment area, so as to connect the filling curtain with the vertical curtain to form a water-resisting layer, specifically comprising:
[0097] The curtain skeleton is constructed in the treatment area. The curtain skeleton is arranged perpendicularly to the vertical curtain.
[0098] The reinforcing curtain is constructed in the gap between at least two curtain skeletons. The reinforcing curtain is arranged in parallel to the curtain skeleton.
[0099] Optionally, the curtain skeleton is constructed in the treatment area, specifically comprising:
[0100] The second drilling position is calculated according to the position of the vertical curtain.
[0101] The second drilling hole is opened according to the second drilling position. The second drilling hole is a long-distance drilling hole.
[0102] The forward grouting method is used to grout the second drill hole to obtain the curtain skeleton. The grouting distance of the forward grouting method is 25-100 m.
[0103] Optionally, the reinforced curtain is constructed in the gap between at least two curtain skeletons, and specifically includes:
[0104] The third drill hole position is calculated according to the position of the curtain skeleton.
[0105] The third drill hole is drilled according to the third drill hole position. The third drill hole is a short distance drill hole.
[0106] The third drill hole is grouted to obtain the reinforced curtain.
[0107] A device for treating and plugging a shallow layer under the condition of flowing water, comprising:
[0108] A vertical curtain construction module is configured to construct a vertical curtain in a preset treatment area to form a stable water layer in the treatment area.
[0109] A filling curtain construction module is configured to construct a filling curtain in the treatment area to connect the filling curtain with the vertical curtain to form a water-resisting layer.
[0110] Optionally, the vertical curtain construction module specifically includes:
[0111] A first calculation module is configured to calculate a first drill hole position according to the treatment area.
[0112] A first drill hole module is configured to drill a first drill hole according to the first drill hole position.
[0113] A first grouting module is configured to grout the first drill hole to obtain the vertical curtain.
[0114] Optionally, the filling curtain includes a curtain skeleton and a reinforced curtain.
[0115] The filling curtain construction module specifically includes:
[0116] A curtain skeleton construction module is configured to construct a curtain skeleton in the treatment area. The curtain skeleton is arranged perpendicularly to the vertical curtain.
[0117] A reinforced curtain construction module is configured to construct a reinforced curtain in the gap between at least two curtain skeletons. The reinforced curtain is arranged in parallel to the curtain skeleton.
[0118] Optionally, the curtain skeleton is constructed in the treatment area, and specifically includes:
[0119] A second calculation module is configured to calculate a second drill hole position according to the position of the vertical curtain.
[0120] The second drilling module is used to open a second borehole according to the second borehole position, wherein the second borehole adopts long-distance drilling.
[0121] The second grouting module is used to grout the second borehole using a forward grouting method to obtain a curtain frame. The forward grouting method has a grouting distance of 25 to 100 meters.
[0122] Optionally, a reinforced curtain is constructed in the gap between at least two curtain frames, specifically comprising:
[0123] The third calculation module is used to calculate the third drilling position according to the position of the curtain frame.
[0124] The third drilling module is used to open a third borehole according to a third borehole position, wherein the third borehole adopts short-distance drilling.
[0125] The third grouting module is used to grout the third borehole to obtain a reinforced curtain.
[0126] Those skilled in the art should understand that the discussion of any of the above embodiments is merely illustrative and is not intended to imply that the scope of the present application (including the claims) is limited to these examples. Within the scope of the present application, the technical features in the above embodiments or different embodiments may be combined, the steps may be implemented in any order, and there are many other variations of the different aspects of the embodiments of the present application as described above, which are not provided in detail for the sake of simplicity.
[0127] In addition, for simplicity of description and discussion, and in order not to make the embodiment of the application difficult to understand, the known power supply / ground connection with integrated circuit (IC) chip and other components may or may not be shown in the accompanying drawings provided. In addition, the device can be shown in the form of a block diagram to avoid making the embodiment of the application difficult to understand, and this also takes into account the following fact, that is, the details of the embodiment of these block diagram devices are highly dependent on the platform to be implemented in the embodiment of the application (that is, these details should be fully within the scope of understanding of those skilled in the art). When specific details (for example, circuit) are set forth to describe exemplary embodiments of the application, it will be apparent to those skilled in the art that the embodiment of the application can be implemented without these specific details or when these specific details are changed. Therefore, these descriptions should be considered to be illustrative rather than restrictive.
[0128] While the present application has been described in conjunction with specific embodiments thereof, many alternatives, modifications and variations of these embodiments will be apparent to those skilled in the art in light of the foregoing description.
[0129] Embodiments of the present application are intended to embrace all such alterations, modifications, and variations that fall within the broad scope of the appended claims. Accordingly, any one or more features of a given embodiment are intended to be illustrative only and not limiting of the scope of the application.
Claims
1. A method for grouting and plugging shallow layers in horizontal flow under dynamic water conditions, comprising: Constructing a vertical curtain in a preset treatment area to form a stable water layer in the treatment area; A filling curtain is constructed in the treatment area so that the filling curtain is connected to the vertical curtain to form a water-proof layer.
2. The shallow grouting and plugging treatment method for horizontal flow under dynamic water conditions according to claim 1, wherein: The construction of a vertical curtain in a preset treatment area specifically includes: calculating a first drilling position according to the treatment area; opening a first borehole according to the first borehole position; Grouting is performed into the first borehole to obtain the vertical curtain.
3. The shallow grouting and plugging treatment method for horizontal flow under dynamic water conditions according to claim 1, wherein: The filling curtain includes a curtain frame and a reinforcement curtain; The step of constructing a filling curtain in the treatment area so as to connect the filling curtain with the vertical curtain to form a water-proof layer specifically includes: Constructing the curtain frame in the treatment area; wherein the curtain frame is arranged perpendicular to the vertical curtain; The reinforced curtain is constructed in the gap between at least two curtain frames; wherein the reinforced curtain is arranged parallel to the curtain frames.
4. The shallow grouting and plugging treatment method for horizontal flow under dynamic water conditions according to claim 3, wherein: The curtain frame is constructed in the treatment area, specifically comprising: calculating a second drilling position according to the position of the vertical curtain; Opening a second borehole according to the second borehole position; wherein the second borehole is drilled over a long distance; The second borehole is grouted by a forward grouting method to obtain the curtain skeleton; wherein the grouting distance of the forward grouting method is 25 to 100 meters.
5. The shallow grouting and plugging treatment method for horizontal flow under dynamic water conditions according to claim 3, wherein: The step of constructing the reinforced curtain in the gap between at least two curtain frames specifically includes: Calculating a third drilling position according to the position of the curtain frame; Opening a third borehole according to the third borehole position; wherein the third borehole adopts short-distance drilling; Grouting is performed on the third borehole to obtain the reinforced curtain.
6. A shallow grouting and plugging treatment device for horizontal flow under dynamic water conditions, comprising: A vertical curtain construction module is used to construct a vertical curtain in a preset treatment area to form a stable water layer in the treatment area; The filling curtain construction module is used to construct a filling curtain in the treatment area so that the filling curtain is connected to the vertical curtain to form a water-proof layer.
7. The device according to claim 6, wherein The vertical curtain construction module specifically includes: a first calculation module, configured to calculate a first drilling position according to the treatment area; a first drilling module, configured to open a first drilling hole according to the first drilling position; The first grouting module is used to inject grout into the first borehole to obtain the vertical curtain.
8. The device according to claim 6, wherein The filling curtain includes a curtain frame and a reinforcement curtain; The filling curtain building module specifically includes: A curtain frame construction module, used to construct the curtain frame in the treatment area; wherein the curtain frame is arranged perpendicular to the vertical curtain; The reinforced curtain construction module is used to construct the reinforced curtain in the gap between at least two of the curtain frames; wherein the reinforced curtain is arranged parallel to the curtain frames.
9. The device according to claim 8, wherein The curtain frame is constructed in the treatment area, specifically comprising: a second calculation module, configured to calculate a second drilling position according to the position of the vertical curtain; A second drilling module is configured to open a second borehole according to the second borehole position; wherein the second borehole is long-distance drilling; The second grouting module is used to grout the second borehole using a forward grouting method to obtain the curtain frame; wherein the grouting distance of the forward grouting method is 25 to 100 meters.
10. The device according to claim 8, wherein The step of constructing the reinforced curtain in the gap between at least two curtain frames specifically includes: a third calculation module, configured to calculate a third drilling position according to the position of the curtain frame; A third drilling module is used to open a third borehole according to the third borehole position; wherein the third borehole adopts short-distance drilling; The third grouting module is used to perform grouting on the third borehole to obtain the reinforced curtain.
Citation Information
Cited By
Underground coal gasification method based on carbon circulation and carbon sequestration
CN121047553A