Lift for construction

By designing a construction hoist for standard tower sections, cages, and adjustment plates, the problems of limited applicability and low safety in existing technologies for inclined surface construction have been solved, achieving a construction effect that is widely applicable and highly safe.

CN120864342APending Publication Date: 2025-10-31GUANGXI HAOTONG CONSTR MASCH MFG CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202511254194.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-09-03
Publication Date
2025-10-31

AI Technical Summary

Technical Problem

Existing construction hoists have limited applicability when working on inclined surfaces, are costly, and pose a risk of tipping over due to imbalance.

Method used

Design a construction hoist, including a standard tower section, a cage, an adjusting plate, and multiple guide wheels. The cage has a connected left and right compartment. The adjusting plate is parallel to the building. The angle of the cage can be adjusted through the guide wheels and the adjusting plate to ensure that the cage is always vertical and avoids tipping.

Benefits of technology

It enables construction on buildings with different tilt angles, has a wide range of applications, improves safety and stability, and reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120864342A_ABST
    Figure CN120864342A_ABST
Patent Text Reader

Abstract

The invention discloses an elevator for construction, and relates to the technical field of equipment for building construction, all guide wheels are installed on a suspension cage, all the guide wheels are located between the suspension cage and a guide rail pipe of a tower body standard knot, the guide wheels are located on the periphery of the guide rail pipe, the guide wheels are used for clamping the guide rail pipe, and a left compartment and a right compartment which are communicated with each other are arranged in the suspension cage; the left compartment and the right compartment are located on the left side and the right side of the tower body standard knot correspondingly and are symmetrically arranged, the adjusting plate is installed on the side, away from a building, of the tower body standard knot and is parallel to the construction surface of the building, and the upper end of the adjusting plate is hinged to an upper top frame at the upper end of the lifting cage. The lower end of the adjusting plate is detachably connected to a lower bottom frame at the lower end of the cage and can be adjusted and fixed at different front and back positions, so that the cage can be adjusted at different angles relative to a tower body standard knot. Construction of building inclined planes with different inclination angles can be achieved, the application range is wide, and the use safety is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of construction machinery technology, and in particular to a construction hoist. Background Technology

[0002] In the process of equipment installation and building construction, it is often necessary to construct inclined surfaces. That is, when the cross-sectional area of ​​a building is larger at the bottom and smaller at the top, an inclined surface will be formed on the side wall of the building, such as chimneys, bridge piers, tower buildings, and inclined buildings.

[0003] Current construction hoists are typically only suitable for vertical surface construction. However, when constructing on inclined surfaces, it is crucial to ensure that the top and bottom surfaces of the hoist remain level at all times to guarantee the balance of personnel and materials during transportation. Furthermore, the distance between the hoist and the building must remain essentially constant regardless of changes in the building's height. Therefore, in existing technologies, to achieve the above effects for inclined surface construction, a custom-designed inclined surface construction hoist is created based on the slope of the building being constructed—one hoist per inclined surface. This results in a limited range of applicability and increased costs associated with traditional inclined surface construction hoists.

[0004] Furthermore, during the lifting and dismantling process, existing inclined construction hoists are prone to overall imbalance when the lifting heights of the left and right cages are inconsistent, which can lead to tipping accidents and affect the safety of use. Summary of the Invention

[0005] The purpose of this invention is to provide a construction hoist to solve the problems existing in the prior art, realize construction on the inclined surfaces of buildings with different inclination angles, and have a wide range of applications and high safety.

[0006] To achieve the above objectives, the present invention provides the following solution:

[0007] This invention provides a construction hoist, comprising a standard tower section, a cage, an adjusting plate, and multiple guide wheels. Each guide wheel is mounted on the cage and located between the cage and the guide rail tube of the standard tower section. The guide wheels are located on the outer periphery of the guide rail tube and are used to clamp the guide rail tube. The cage has interconnected left and right compartments, which are located on the left and right sides of the standard tower section, respectively, and are symmetrically arranged. The adjusting plate is mounted on the side of the standard tower section away from the building and parallel to the construction surface of the building. The upper end of the adjusting plate is hinged to the upper top frame of the upper end of the cage, and the lower end of the adjusting plate is detachably connected to the lower bottom frame of the lower end of the cage. It can be adjusted and fixed at different positions to achieve different angle adjustments of the cage relative to the standard tower section.

[0008] Preferably, the cage is concave, and the cage also has an operating room inside. The operating room is located between the left compartment and the right compartment, and the operating room can connect the left compartment and the right compartment. The standard tower section is located in the concave part of the cage.

[0009] Preferably, the upper end of the cage is provided with an upper top frame, the upper end of the adjusting plate is hinged to the upper top frame, the lower end of the cage is provided with a lower bottom frame, the lower end of the adjusting plate and the lower bottom frame are detachable and can be adjusted and fixed in different positions in the front and back, the two outer sides of the cage are respectively provided with an outer side panel, the two outer side panels are the left outer side panel and the right outer side panel, the cage is provided with an outer front panel on the construction wall away from the building, and the cage is provided with an inner side panel on the two opposite side walls for contacting the standard section of the tower body, the two inner side panels are the left inner side panel and the right inner side panel.

[0010] Preferably, the lower frame is provided with multiple connecting holes. By connecting the lower end of the adjusting plate to different connecting holes, the angle of the cage relative to the standard section of the tower can be adjusted, and the cage can be kept vertical when the building and the standard section of the tower are tilted.

[0011] Preferably, there are eight sets of guide wheels, four of which are detachably mounted on the upper top frame and the other four are detachably mounted on the lower bottom frame. The mounting position of each guide wheel is adjustable. Each guide wheel includes three pressure rollers, namely a first pressure roller, a second pressure roller, and a third pressure roller. The first pressure roller is connected to the inner side panel, and the second and third pressure rollers are connected to the lower bottom frame. The axis of the first pressure roller mounted on the inner side panel is always parallel to the cross-section of the standard tower section. The axes of the second and third pressure rollers are both perpendicular to the inner side panel. The second and third pressure rollers are symmetrically arranged on the front and rear sides of the guide rail tube. The first pressure roller is located on the left or right side of the guide rail tube away from the standard tower section. The first, second, and third pressure rollers can jointly clamp the guide rail tube.

[0012] Preferably, the control room is further provided with a control panel for controlling the lifting and lowering of the cage. Preferably, the left compartment is provided with a door frame on the side facing the construction wall of the building, the right compartment is provided with a door frame on the side facing the construction wall of the building, and the right compartment is provided with a door frame on the side facing the construction wall of the building. The door frame is divided into a front door frame and a rear door frame.

[0013] Preferably, the adjustment plate is equipped with a fall arrestor, a frequency converter control cabinet, an operating panel, an over-height limit switch, an under-height limit switch, and an extreme switch. The fall arrestor is used to prevent the cage from falling.

[0014] Preferably, a drive mechanism and a transmission mechanism are installed on the standard section of the tower body. The drive mechanism is used to drive the transmission mechanism to move, and the transmission mechanism is used to drive the cage to rise and fall.

[0015] Preferably, the standard tower section is connected to the construction wall of the building via a wall-mounted frame.

[0016] The present invention achieves the following technical effects compared to the prior art:

[0017] The construction hoist provided by this invention includes a standard tower section, a cage, an adjusting plate, and multiple guide wheels. Each guide wheel is installed on the cage and located between the cage and the guide rail tube of the standard tower section. The guide wheels are located on the outer periphery of the guide rail tube and are used to clamp the guide rail tube, thereby guiding the cage during the lifting process and improving lifting stability. The cage has interconnected left and right compartments, located on the left and right sides of the standard tower section respectively, and the left and right compartments are symmetrically arranged. The cage is designed as an integrated structure. Compared with the traditional design where the left and right cages are set up separately and lifted separately, this design ensures that the left and right compartments lift simultaneously during lifting, thereby achieving relative balance of the cage relative to the front, rear, left, and right sides of the standard tower section when the cage is empty, avoiding problems during installation and disassembly. To prevent tipping accidents during construction and improve safety, an adjustment plate is installed on the side of the tower standard section away from the building and parallel to the construction surface of the building. The upper end of the adjustment plate is hinged to the upper top frame of the cage, and the lower end is detachably connected to the lower bottom frame of the cage. It can be adjusted and fixed in different positions, allowing for different angle adjustments of the cage relative to the tower standard section. This ensures that when constructing on inclined surfaces of buildings with different inclination angles, the tower standard section remains parallel to the inclined surface of the building. By adjusting the angle of the cage through the adjustment plate, the cage can be kept vertical regardless of the angle of the tower standard section. That is, the upper and lower surfaces of the cage are parallel to the horizontal plane, and it is not limited by the angle of the inclined surface of the building. This has a wide range of applications and improves stability during construction. Attached Figure Description

[0018] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0019] Figure 1 This is a schematic diagram of the construction hoist used in this invention when constructing on the vertical surface of a building;

[0020] Figure 2 for Figure 1 Enlarged diagram of point A in the diagram;

[0021] Figure 3 This is a schematic diagram of the construction hoist used in this invention when constructing on the inclined surface of a building;

[0022] Figure 4 for Figure 3 Enlarged diagram of point B in the image;

[0023] Figure 5 for Figure 3 The left view;

[0024] Figure 6 This is a top view of the construction hoist in this invention;

[0025] Figure 7 for Figure 6 Enlarged diagram of point C in the diagram;

[0026] Figure 8 This is a schematic diagram showing the installation location of the fall arrestor in this invention;

[0027] Figure 9 for Figure 8 Enlarged diagram of point D in the diagram;

[0028] In the diagram: 1-Building, 2-Cage, 3-Drive mechanism, 4-Transmission mechanism, 5-Hinge point, 6-Adjusting plate, 7-Guide wheel, 8-Standard tower section, 9-Wall-mounted frame, 10-Fall arrestor, 11-Variable frequency control cabinet, 12-Electrical control box, 13-Operating console, 14-Door frame, 15-Left compartment, 16-Right compartment, 17-Top frame, 18-Bottom frame, 19-Outer panel, 20-Outer front panel, 21-First pressure roller, 22-Second pressure roller, 23-Third pressure roller, 24-Guide rail tube, 25-Inner panel, 26-Rack surface, 27-Gear, 28-Rack. Detailed Implementation

[0029] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0030] The purpose of this invention is to provide a construction hoist that solves the problems existing in the prior art, enables construction on the inclined surfaces of buildings with different inclination angles, has a wide range of applications, and is highly safe to use.

[0031] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0032] like Figures 1-9 As shown, this embodiment provides a construction hoist, including a standard tower section 8, a cage 2, an adjusting plate 6, and multiple guide wheels 7. Each guide wheel 7 is installed on the cage 2 and is located between the cage 2 and the guide rail tube 24 of the standard tower section 8. The guide wheels 7 are located on the outer periphery of the guide rail tube 24 and are used to clamp the guide rail tube 24, thereby guiding the cage 2 during the lifting process and improving lifting stability. The cage 2 has a left compartment 15 and a right compartment 16 that are interconnected. The left compartment 15 and the right compartment 16 are located on the left and right sides of the standard tower section 8, respectively, and are symmetrically arranged. The cage 2 is designed as an integral structure. Compared with the traditional design where the left and right cages are set up separately and lifted separately, the left compartment 15 and the right compartment 16 can be lifted and lowered simultaneously during lifting. This ensures that the cage 2 is relatively balanced relative to the front, back, left, and right sides of the standard tower section 8 when the cage is empty, preventing the equipment from tipping over during installation and disassembly. To prevent accidents and improve safety, the adjustment plate 6 is installed on the side of the standard tower section 8 away from the building 1, i.e., the other side where the wall-mounted bracket 9 is installed, and parallel to the construction surface of the building 1. The upper end of the adjustment plate 6 is hinged to the upper top frame 17 of the upper end of the cage 2, and the lower end of the adjustment plate 6 is detachably connected to the lower bottom frame 18 of the lower end of the cage 2. It can be adjusted and fixed in different positions, realizing different angle adjustments of the cage 2 relative to the standard tower section 8. Thus, when constructing on the inclined surface of the building 1 with different inclination angles, the standard tower section 8 is made parallel to the inclined surface of the building 1, and the angle of the cage 2 is adjusted by the adjustment plate 6. Therefore, regardless of the angle of the standard tower section 8, the cage 2 can be kept vertical, that is, the upper top surface and lower bottom surface of the cage 2 are parallel to the horizontal plane, and it is not limited by the angle of the inclined surface of the building 1. It has a wide range of applications, solves the problem of excessive cost caused by one special machine for each inclination angle, and improves the stability during construction.

[0033] Specifically, the cage 2 is concave, which facilitates connection to the tower standard section 8. The cage 2 also contains an operator's cabin located between the left and right side chambers 15 and 16, and is connected to both chambers. The tower standard section 8 is located in the concave part of the cage 2, allowing the cage 2 to be stably positioned on the tower standard section 8 through the cooperation between the tower standard section 8 and the concave part of the cage 2. The cage 2 is designed with a symmetrical structure, ensuring its center of gravity is on the left-right centerline of the cage 2 and within the cross-section of the tower standard section 8. This ensures that the cage 2 remains balanced relative to the tower standard section 8 in the empty state, without any tilting moment.

[0034] The upper end of the hoisting cage 2 is provided with an upper top frame 17, and the upper end of the adjusting plate 6 is hinged to the upper top frame 17, forming a hinge point 5. The hoisting cage 2 can rotate relative to the adjusting plate 6 around the hinge point 5. The lower end of the hoisting cage 2 is provided with a lower bottom frame 18, and the lower end of the adjusting plate 6 can be detachably connected to the lower bottom frame 18 and can be adjusted and fixed in different positions. The two outer sides of the hoisting cage 2 are each provided with an outer panel 19, namely the left outer panel and the right outer panel. The hoisting cage 2 has an outer front panel 20 on the side away from the construction wall of the building 1. The hoisting cage 2 has an inner panel 25 on each of the two opposite side walls that are used to contact the tower standard section 8, namely the left inner panel and the right inner panel, thus forming a closed hoisting cage 2, improving structural stability and safety of use, and preventing tools or personnel from falling during lifting. In addition, the adjusting plate 6 can be adaptively adjusted according to the tilt angle of the tower standard section 8, ensuring that the adjusting plate 6 remains parallel to the transmission surface of the tower standard section 8 in any state.

[0035] The bottom frame 18 is provided with multiple connection holes, which can be arranged in multiple rows. By connecting the lower end of the adjustment plate 6 to different connection holes, the angle of the cage 2 relative to the standard section 8 of the tower body can be adjusted and fixed, and the cage 2 can always be in a vertical state when the building 1 and the standard section 8 of the tower body are tilted, ensuring the stability of the personnel and tools inside the cage 2, and making the rack surface 26 of the standard section 8 of the tower body parallel to the tilted surface (i.e. the construction surface) of the building 1.

[0036] As a preferred embodiment, in order to ensure the stability of the fit between the cage 2 and the standard tower section 8, and to enable the cage 2 to move stably up and down along the standard tower section 8, the guide wheels 7 are designed in eight sets. Four of the guide wheels 7 are detachably installed on the upper top frame 17, and the other four guide wheels 7 are detachably installed on the lower bottom frame 18. That is, the eight guide wheels 7 are respectively set at the center intersection of the left and right longitudinal beams of the upper top frame 17 and the center intersection of the guide rail tube 24 of the standard tower section 8, and at the center intersection of the left and right longitudinal beams of the lower bottom frame 18 and the guide rail tube 24 of the standard tower section 8. All eight guide wheels 7 are set in the recess of the cage 2, and the installation position of each guide wheel 7 can be adjusted. Thus, when constructing the inclined surface of the building 1 with different inclination angles, the installation position of each guide wheel 7 is adjusted as the angle of the standard tower section 8 is adjusted, so as to ensure that the guide wheels 7 can effectively press the guide tube of the standard tower section 8.

[0037] The guide wheel 7 includes three pressure rollers: a first pressure roller 21, a second pressure roller 22, and a third pressure roller 23. The first pressure roller 21 is connected to the inner panel 25, while the second and third pressure rollers 22 and 23 are connected to the lower frame 18. The axis of the first pressure roller mounted on the inner panel 25 is always parallel to the cross-section of the standard tower section 8. The axes of the second and third pressure rollers 22 and 23 are both perpendicular to the inner panel 25. The second and third pressure rollers 22 and 23 are symmetrically arranged on the front and rear sides of the guide rail tube 24. The first pressure roller 21 is located on the left or right side of the guide rail tube 24, away from the standard tower section 8. 3 are located at the three sides of a rectangle, wherein the second pressure roller 22 and the third pressure roller 23 are arranged opposite to each other, and the first pressure roller 21 and the second pressure roller 22, as well as the first pressure roller 21 and the third pressure roller 23 are arranged adjacent to each other. The first pressure roller 21, the second pressure roller 22 and the third pressure roller 23 can jointly clamp the guide rail tube 24 and cooperate with the tower body standard section 8 to limit the circumference of the guide rail tube 24, thereby restricting the forward, backward, left and right movement of the cage 2 in the horizontal direction of the tower body standard section 8, ensuring that the cage 2 can only move up and down along the tower body standard section 8. In this embodiment, by setting the pressure rollers, the pressure rollers can fit with the outer wall of the guide rail tube 24 to achieve a better clamping and limiting effect.

[0038] As a preferred embodiment, the pressure rollers of the four sets of guide wheels 7 at the top frame 17 can be adjusted according to the tilt angle of the standard tower section 8 via the eccentric shaft of the pressure rollers to ensure that all upper pressure rollers are correctly pressed against the guide rail tube 24. The pressure rollers of the four sets of guide wheels 7 at the bottom frame 18 can be adjusted forward and backward according to the tilt angle of the standard tower section 8 via pre-drilled holes or sliders to ensure that the four sets of guide wheels 7 at the bottom maintain correct pressing against the guide rail tube 24 when the angle of the standard tower section 8 is adjusted. An operating platform 13 is also provided in the operating room. The operating platform 13 is used to control the lifting and lowering of the cage 2 to achieve construction at different heights on the inclined surface of the building 1. The left compartment 15 is equipped with a door frame 14 on the side of the construction wall close to the building 1, the left compartment 15 is equipped with a door frame 14 on the side of the construction wall away from the building 1, the right compartment 16 is equipped with a door frame 14 on the side of the construction wall close to the building 1, and the right compartment 16 is equipped with a door frame 14 on the side of the construction wall away from the building 1. The door frame 14 is divided into a front door frame and a rear door frame, which are used for staff to enter and exit and operate, and to protect staff during the lifting process.

[0039] A fall arrestor 10 is installed on the side of the regulating plate 6 away from the standard tower section 8. The fall arrestor 10 is used to prevent the cage 2 from falling and to ensure that the gear 27 of the fall arrestor 10 meshes correctly with the rack 28 of the standard tower section 8. The regulating plate 6 is also equipped with traditional hoist components such as the operating panel 13, frequency converter control cabinet 11, electrical control box 12, intelligent operating system, over-high limit switch, under-low limit switch, and limit switch.

[0040] The standard section 8 of the tower body is equipped with a drive mechanism 3 and a transmission mechanism 4. The drive mechanism 3 is used to drive the transmission mechanism 4 to move, and the transmission mechanism 4 is used to drive the cage 2 to rise and fall. The specific drive and transmission principles are the same as those of traditional elevators.

[0041] The standard tower section 8 is connected to the construction wall of building 1 via the wall-mounted frame 9, so as to achieve stable installation of the standard tower section 8 and ensure the stable lifting and lowering of the subsequent cage 2 for construction of the construction wall of building 1.

[0042] This embodiment achieves the effect of multiple uses with one machine through the above design. It can realize both ordinary vertical construction and construction on any inclined plane, which greatly improves the utilization rate of equipment and reduces construction costs. At the same time, it also completely solves the problem of overturning accidents caused by the asynchronous up and down movement of the left and right cages during the lifting and lowering of cage 2.

[0043] Specific examples have been used to illustrate the principles and implementation methods of this invention. The descriptions of the above embodiments are only for the purpose of helping to understand the method and core ideas of this invention. Furthermore, those skilled in the art will recognize that, based on the ideas of this invention, there will be changes in the specific implementation methods and application scope. Therefore, the content of this specification should not be construed as a limitation of this invention.

Claims

1. A construction hoist, characterized in that: The system includes a standard tower section, a cage, an adjusting plate, and multiple guide wheels. Each guide wheel is mounted on the cage and located between the cage and the guide rail of the standard tower section. The guide wheels are located on the outer periphery of the guide rail and are used to clamp the guide rail. The cage has interconnected left and right compartments located on the left and right sides of the standard tower section, respectively, and are symmetrically arranged. The adjusting plate is mounted on the side of the standard tower section away from the building and parallel to the construction surface of the building. The upper end of the adjusting plate is hinged to the upper top frame of the cage, and the lower end is detachably connected to the lower bottom frame of the cage. The adjusting plate can be adjusted and fixed at different positions to achieve different angle adjustments of the cage relative to the standard tower section.

2. The construction hoist according to claim 1, characterized in that: The cage is concave, and the cage also has an operating room inside. The operating room is located between the left compartment and the right compartment, and the operating room can connect the left compartment and the right compartment. The standard tower section is located in the concave part of the cage.

3. The construction hoist according to claim 2, characterized in that: The upper end of the cage is provided with an upper top frame, and the upper end of the adjusting plate is hinged to the upper top frame. The lower end of the cage is provided with a lower bottom frame. The lower end of the adjusting plate and the lower bottom frame are detachable and can be adjusted and fixed in different positions at the front and rear. The two outer sides of the cage are respectively provided with an outer side panel, namely the left outer side panel and the right outer side panel. The cage is provided with an outer front panel on the construction wall away from the building. The cage is provided with an inner side panel on the two opposite side walls used to contact the standard section of the tower body, namely the left inner side panel and the right inner side panel.

4. The construction hoist according to claim 3, characterized in that: The lower frame is provided with multiple connecting holes. By connecting the lower end of the adjusting plate to different connecting holes, the angle of the cage relative to the standard section of the tower can be adjusted, and the cage can be kept vertical when the building and the standard section of the tower are tilted.

5. The construction hoist according to claim 3, characterized in that: The guide wheels consist of eight sets, four of which are detachably mounted on the upper top frame and the other four on the lower bottom frame. The mounting position of each guide wheel is adjustable. Each guide wheel includes three pressure rollers: a first pressure roller, a second pressure roller, and a third pressure roller. The first pressure roller is connected to the inner side panel, and the second and third pressure rollers are connected to the lower bottom frame. The axis of the first pressure roller mounted on the inner side panel is always parallel to the cross-section of the standard tower section. The axes of the second and third pressure rollers are perpendicular to the inner side panel. The second and third pressure rollers are symmetrically arranged on the front and rear sides of the guide rail tube. The first pressure roller is located on the left or right side of the guide rail tube away from the standard tower section. The first, second, and third pressure rollers can jointly clamp the guide rail tube.

6. The construction hoist according to claim 2, characterized in that: The control room is also equipped with a control panel, which is used to control the lifting and lowering of the cage.

7. The construction hoist according to claim 1, characterized in that: The left compartment is equipped with a door frame on the side of the construction wall close to the building, the left compartment is equipped with a door frame on the side of the construction wall away from the building, the right compartment is equipped with a door frame on the side of the construction wall close to the building, and the right compartment is equipped with a door frame on the side of the construction wall away from the building. The door frame is divided into a front door frame and a rear door frame.

8. The construction hoist according to claim 1, characterized in that: The adjustment plate is equipped with a fall arrestor, a frequency converter control cabinet, an operating panel, an over-height limit switch, an under-height limit switch, and an extreme switch. The fall arrestor is used to prevent the cage from falling.

9. The construction hoist according to claim 1, characterized in that: The standard section of the tower body is equipped with a drive mechanism and a transmission mechanism. The drive mechanism is used to drive the transmission mechanism to move, and the transmission mechanism is used to drive the cage to rise and fall.

10. The construction hoist according to claim 1, characterized in that: The standard tower sections are connected to the construction wall of the building via wall-mounted frames.

Citation Information

Cited By

  • Construction lifting equipment

    CN122233247A

  • A construction hoist

    CN122233247B