Construction waste treatment method
By modifying the bucket and connecting it to the excavator, efficient sorting and separation of construction waste was achieved, solving the problem of low efficiency in manual screening and improving the secondary utilization rate of concrete and steel bars.
Patent Information
- Application Number
- CN202410660554.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-27
- Publication Date
- 2025-11-28
AI Technical Summary
The current method of manual screening in construction waste disposal is inefficient and makes it difficult to effectively separate concrete blocks and metal products such as steel bars, resulting in a large workload and long processing time.
The modified bucket is a digging bucket, using digging teeth and a vertical bucket structure, connected to the excavator. Its flexibility is tested through a hydraulic transmission system. It is used to sort construction waste, separating large pieces of concrete and steel bars. The steel bars are then manually removed, and the concrete blocks are sent to a crushing plant for pulverization. Smaller pieces of waste are then landfilled.
It improves the efficiency of construction waste screening, achieves efficient separation of concrete and steel bars, reduces manual operation, and increases the secondary utilization rate.
Smart Images

Figure CN121024140A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of construction waste treatment, in particular to a construction waste treatment method. BACKGROUND
[0002] Construction waste refers to the construction, construction unit or individual of various buildings, structures, pipe network, etc. during the construction, laying or demolition, repair process of the slag, abandoned soil, waste, silt and other waste.
[0003] The existing construction waste is mostly sorted by manual, and the recyclable metals are selected and loaded into the slag truck by the loader for transfer, landfill or crushing. The manual screening first needs a large amount of labor and workload, and in the screening process, the large concrete blocks cannot be manually turned over to check whether there are steel bars and other metal products under them. In addition, the construction waste is often scattered after the construction is completed, and the manual screening is time-consuming and low in screening efficiency. Therefore, a construction waste treatment method is proposed to solve the above problems. SUMMARY
[0004] (I) Technical problems solved
[0005] In view of the deficiencies of the prior art, the present application provides a construction waste treatment method, which has the advantages of high screening efficiency, and solves the problems that the existing construction waste is mostly sorted by manual, and the recyclable metals are selected and loaded into the slag truck by the loader for transfer, landfill or crushing. The manual screening first needs a large amount of labor and workload, and in the screening process, the large concrete blocks cannot be manually turned over to check whether there are steel bars and other metal products under them. In addition, the construction waste is often scattered after the construction is completed, and the manual screening is time-consuming and low in screening efficiency.
[0006] (II) Technical solutions
[0007] The technical solutions of the present application to solve the above technical problems are as follows: a construction waste treatment method, comprising a bucket and the following steps:
[0008] S1: modifying the bucket, modifying the ordinary bucket into a bucket, the bucket is composed of digging teeth, reinforcing plates and a vertical bucket, the number of digging teeth is multiple and all are fixedly connected with the front surface of the vertical bucket, reinforcing plates are fixedly connected between adjacent two digging teeth, adjacent two digging teeth are arranged in a hollow manner, the front surface of the vertical bucket is arranged in a bucket shape, and the vertical bucket is drivingly connected with the excavator;
[0009] S2: installing the bucket, drivingly connecting the bucket with the excavator, and testing the flexibility of the bucket through the hydraulic transmission system of the excavator, and operating after meeting the overturning limit requirements of the bucket;
[0010] S3: selecting an area, driving the excavator, selecting a scattered construction waste pile or an area with a bagging rate lower than 20% for waste sorting;
[0011] S4: screening the waste, using a bucket to shake and sort the waste by the excavator, separating large concrete and steel bars from small construction waste such as sand and gravel;
[0012] S5: separating the waste, piling up the large concrete and steel bars, manually removing the steel bars, loading the removed large concrete into a dump truck for transportation to a crushing station for crushing, and loading the small construction waste such as sand and gravel into a dump truck for transportation to a landfill for landfill.
[0013] The beneficial effects of the present application are:
[0014] The construction waste treatment method has the advantages of high screening efficiency.
[0015] Based on the above technical solution, the present application can also be improved as follows.
[0016] Further, the bucket is made of pure steel welding, the number of digging teeth is not less than 5, and the spacing between adjacent two digging teeth is not less than 30CM, and the vertical bucket accounts for 30% of the total volume of the bucket.
[0017] The beneficial effects of the above further scheme are that the spacing between adjacent two digging teeth is not less than 30CM, which is convenient for leaking out smaller construction waste, and separating large and solid concrete and gravel, sand and gravel.
[0018] Further, the overturning limit angle of the bucket is 180 degrees, and the excavator is a DX130 medium-sized excavator.
[0019] The beneficial effects of the above further scheme are that a 130 excavator is used, which has a larger horsepower, and is convenient for pushing larger concrete construction waste.
[0020] Further, when sorting the waste, small construction waste such as sand and gravel leaks out through the gap between the digging teeth to the ground, and larger concrete and part of the steel bars are transferred to the surrounding by the bucket for construction waste separation.
[0021] Further, the large concrete is treated into standard coarse gravel, fine gravel, coarse sand, fine sand, and other recycled materials such as silt by the crushing station, for secondary utilization, and the steel bars and other metal products can also be recycled after manual recovery.
[0022] The beneficial effects of the above further scheme are that the crushing and secondary utilization of large and solid concrete construction waste can reduce material loss and improve the environmental protection effect of construction waste treatment. BRIEF DESCRIPTION OF DRAWINGS
[0023] Fig. 1 The flow chart of the present application is shown in the figure.
[0024] Fig. 2 The bucket structure of the present application is shown in the figure.
[0025] In the figure: 1, bucket; 101, digging tooth; 102, reinforcing plate; 103, vertical bucket. DETAILED DESCRIPTION
[0026] The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of protection of the present application.
[0027] In the embodiments, a building waste treatment method is given, and the present application comprises a bucket 1 and the following steps: Figs. 1-2
[0028] S1: modifying the bucket, modifying the ordinary bucket into the bucket 1, the bucket 1 is composed of digging teeth 101, reinforcing plates 102 and vertical buckets 103, the number of the digging teeth 101 is multiple, and each is fixedly connected with the front face of the vertical bucket 103, the reinforcing plate 102 is fixedly connected between each two adjacent digging teeth 101, each two adjacent digging teeth 101 are arranged in a hollow manner, the front face of the vertical bucket 103 is arranged in a bucket shape, and the vertical bucket 103 is drivably connected with the excavator;
[0029] S2: installing the bucket, driving the bucket 1 to be drivably connected with the excavator, and testing the flexibility of the bucket 1 through the hydraulic transmission system of the excavator, and then performing the operation after the turning limit requirement of the bucket 1 is met;
[0030] S3: selecting the area, driving the excavator, and selecting the area with scattered building waste piles or the area with a bagging rate lower than 20% to sort the waste;
[0031] S4: screening the waste, using the bucket 1 of the excavator to shake and sort the waste, and separating the large concrete and steel bars from the small building waste such as sandstone;
[0032] S5: separating the waste, piling up the large concrete and steel bars, manually removing the steel bars, piling up the large concrete removed into the loader and transporting it to the crushing station for crushing, and using the loader to load the small building waste such as sandstone into the loader and transporting it to the landfill site for landfill.
[0033] The digging bucket 1 is made of pure steel welding, the number of digging teeth 101 is not less than 5, and the spacing between adjacent two digging teeth 101 is not less than 30CM, and the vertical bucket 103 accounts for 30% of the total volume of the digging bucket 103.
[0034] The spacing between adjacent two digging teeth 101 is not less than 30CM, which is convenient for leaking out small construction waste, and separating large and solid concrete and gravel, sand and the like.
[0035] The turning limit angle of the digging bucket 1 is 180 degrees, and the excavator is a DX130 medium-sized excavator.
[0036] The 130 excavator is used, which has larger horsepower, and is convenient for pushing larger concrete construction waste.
[0037] When sorting the garbage, small construction waste such as sand and gravel leaks out through the gap between the digging teeth 101 to the ground, and larger concrete and part of the reinforcing steel is transported by the digging bucket to the surrounding area for construction waste classification.
[0038] The large and solid concrete construction waste is processed into standard coarse gravel, fine gravel, coarse sand, fine sand, and other recycled materials such as silt, and is used for secondary utilization. The steel bars and other metal products can also be recycled after manual recovery.
[0039] The crushing and secondary utilization of large and solid concrete construction waste can reduce material loss and improve the environmental protection effect of construction waste treatment.
[0040] Working principle:
[0041] The modified digging bucket 1 is assembled with the 130 excavator, and the digging bucket 1 is used through the 130 excavator to collect small piles of construction waste to form a larger construction waste cluster. In the process of collection, large and solid concrete construction waste can be intercepted in the digging bucket 1 by the vertical bucket 103, and small construction waste such as sand and gravel can be dropped through the gap between adjacent two digging teeth 101, so as to separate large construction waste from small construction waste such as sand and gravel. At the same time, small piles of construction waste are concentrated and collected, which is convenient for manual screening and reduces the use of manpower. In the screening process, longer reinforcing steel can be directly intercepted by the digging teeth 101, which is convenient for manual separation of longer reinforcing steel and construction waste, reduces the time of manual searching and screening in each construction waste pile, and thus improves the screening efficiency.
[0042] It is to be understood that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting; it is not intended to exclude myriad other embodiments of the present application that other inventors can develop based on the same general inventive concepts embodied by the described embodiments. That is, although the present application is described in terms of particular embodiments and implementations, it is to be understood that the terminology used is for the purpose of descriptive clarity and that it should be taken in its broadest possible sense. For example, the terms "a", "an", and "the" include both singular and plural referents unless the context clearly dictates otherwise. The terms "comprises", "comprising", "includes", "including" and the like can be used in conjunction with the term "consisting of to include the elements or steps listed after such conjunctive language, but not to the exclusion of other elements or steps. The singular forms "a", "an" and "the" include plural referents unless the context clearly dictates otherwise. The term "plurality" means two or more. The term "consisting essentially of to provide that the composition or process include additional steps, elements, compounds, compositions of matter, or materials not specifically recited. The use of the terms "first", "second", and the like does not imply any particular ordering, but rather are used to denote distinct and separate steps. Where the context requires, the singular forms "a", "an" and "the" include their corresponding plural referents unless the context clearly dictates otherwise. Terms such as "above" and "below" refer to positions relative to the orientation of the figures and are used for purposes of illustration and description only. Terms such as "first" and "second" are used to identify various elements, but the elements should not be limited by these terms. The use of the terms "first" and "second" are not necessarily intended to connote chronological order, but rather serve as labels to distinguish one element from another. The use of the terms "a", "an", and "the" and / or the use of articles in the singular and plural sense are intended to cover a
[0043] While the embodiments of the application have been shown and described herein, it is to be understood that the application is not limited to these embodiments. Rather, many modifications, changes, alternatives and variations will be apparent to those skilled in the art once the general inventive concepts have been made known. Accordingly, the scope of the claims should not be limited to the described embodiments.
Claims
1. A construction waste processing method, characterized by, Including excavator (1) and the following steps: S1: modify the bucket, the ordinary bucket is modified into excavator (1), the excavator (1) is composed of digging tooth (101), reinforcing plate (102) and vertical bucket (103), the number of digging tooth (101) is multiple and is fixedly connected with the front of vertical bucket (103), reinforcing plate (102) is fixedly connected between adjacent two digging tooth (101), adjacent two digging tooth (101) are arranged in a hollow manner, the front of vertical bucket (103) is arranged in a bucket shape, and the vertical bucket (103) can be connected with the transmission of the excavator; S2: install the excavator, the excavator (1) is connected with the transmission of the excavator, and the flexibility of the excavator (1) is tested through the hydraulic transmission system of the excavator, and the operation is carried out after meeting the overturning limit requirements of the excavator (1); S3: select the area, drive the excavator, select the scattered construction waste pile or the area with a bagging rate lower than 20% for waste sorting; S4: screening waste, the excavator uses the excavator (1) to shake the material and sort the waste, and the large concrete and steel bars are separated from the small construction waste such as sandstone; S5: separate the waste, the large concrete and steel bars are piled up, the steel bars are removed manually, the large concrete removed is loaded into the dump truck and transported to the crushing station for crushing, and the small construction waste such as sandstone is loaded into the dump truck and transported to the landfill for landfill.
2. A method of construction waste processing according to claim 1, wherein: The excavator (1) is made of pure steel welding, the number of digging tooth (101) is not less than 5, and the spacing between adjacent two digging tooth (101) is not less than 30CM, and the vertical bucket (103) accounts for 30% of the total volume of the excavator (103).
3. A method of construction waste processing according to claim 1, wherein: The overturning limit angle of the excavator (1) is 180 degrees, and the excavator is DX130 medium-sized excavator.
4. The method of claim 1, wherein: When sorting the waste, the small construction waste such as sandstone leaks out to the ground through the gap of the digging tooth (101), and the larger concrete and part of the steel bars are transported to the surrounding by the excavator for construction waste separation.
5. The method of claim 1, wherein: The large concrete is treated into standard coarse gravel, fine gravel, coarse sand, fine sand and other recycled materials in the crushing station, and is used for secondary utilization, and the steel bars and other metal products can also be used for secondary utilization after manual recovery.