Pouring type asphalt concrete steel bridge deck pavement construction method
By introducing adjustment, interlocking reinforcement, and stress-sharing mechanisms into the construction of cast-in-place asphalt concrete steel bridge deck paving, the problem of inconvenient paving layer thickness adjustment was solved, achieving flexible adaptation of bridge alignment and high strength and crack resistance of the paving layer.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-02-09
- Publication Date
- 2026-04-03
AI Technical Summary
The existing construction method for cast-in-place asphalt concrete steel bridge deck pavement cannot be flexibly selected and adjusted in real time according to the actual alignment requirements of the bridge. This makes it inconvenient to adjust the pavement layer thickness during construction, making it difficult to adapt to the differentiated requirements of different loads and alignments, and affecting the integrity of the pavement layer and the interlayer bonding.
The system employs an adjustment mechanism, an interlocking reinforcement mechanism, and a stress-sharing mechanism. Through the cooperation of multi-stage adjustment grooves, sliding columns, and springs on the vertical plate, it achieves multi-stage stable adjustment of the pavement layer thickness. A resin coating and polymer fiber mesh are laid on top of the steel plate to enhance the interlocking force of the pavement layer. Phase change microcapsules and flexible microtube mesh are incorporated to adjust temperature stress and load stress.
It enables flexible adjustment of the pavement layer thickness, enhances the overall bonding strength and fatigue resistance of the pavement layer, effectively buffers temperature stress and load stress, and improves the crack resistance and deformation resistance of the bridge deck pavement.
Smart Images

Figure CN121781530A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of road and bridge engineering technology, and in particular to a method for constructing cast-in-place asphalt concrete steel bridge deck paving. Background Technology
[0002] Steel bridge deck paving is a key technical aspect of bridge engineering, and its quality directly affects the bridge's load-bearing capacity, driving comfort, and service life. Cast-in-place asphalt concrete has become a key solution for long-span steel bridge deck paving due to its excellent water tightness, ability to follow the deformation of the steel bridge deck, and construction characteristics that do not require compaction.
[0003] Traditional cast-in-place asphalt concrete steel bridge deck paving construction methods involve spraying an adhesive layer onto a pre-treated steel bridge deck, followed by spreading high-temperature mixed cast-in-place asphalt mixture on top. The mixture's self-leveling properties form a dense paving layer, which is then cooled and cured. The drawback of this method is the fixed paving layer thickness, which cannot adapt to the varying thickness requirements of different loads and bridge alignments. Current cast-in-place asphalt concrete steel bridge deck paving construction methods largely follow traditional processes, using pavers or manual labor, but lack integrated thickness adjustment functionality. This highlights the current lack of a convenient and reliable paving thickness adjustment device. The absence of such a device prevents flexible selection and real-time adjustments based on the bridge's actual alignment, local stiffness compensation, future maintenance and overlay requirements, and other needs. However, in practice, such devices are inconvenient to adjust, difficult to effectively coordinate with the paving process, and can damage the integrity of the paving layer and interlayer adhesion. Summary of the Invention
[0004] The purpose of this invention is to provide a method for constructing cast-in-place asphalt concrete steel bridge deck paving, which solves the problem of not being able to flexibly select and adjust in real time according to the actual alignment requirements of the bridge.
[0005] To achieve the above objectives, the present invention provides the following technical solution: a method for constructing cast-in-place asphalt concrete steel bridge deck pavement, comprising a steel plate, a pavement layer fixedly connected to the top of the steel plate, an adjustment mechanism provided on the outer side of the steel plate, the adjustment mechanism being an auxiliary mechanism for adjusting the construction thickness of the pavement layer, an interlocking reinforcement mechanism provided on the inner side of the pavement layer, the interlocking reinforcement mechanism being used to enhance the interlocking force within the pavement layer and between it and the steel plate, and a stress averaging mechanism provided on the top of the pavement layer, the stress averaging mechanism being used to disperse and offset the stress generated within the pavement layer;
[0006] The adjustment mechanism includes a vertical plate with multiple adjustment grooves on its outer side. A sliding column is slidably connected to the outer side of the steel plate. A limit plate is fixedly connected to the bottom end of the sliding column, and a spring is fixedly connected to the outer side of the sliding column.
[0007] Multiple adjustment grooves are machined on the outside of the upright plate. The outside of the steel plate is connected to a sliding column in a sliding manner. A limiting plate is fixed at the bottom of the sliding column, and a spring is also fixed on the outside of the sliding column.
[0008] Preferably, the adjustment mechanism further includes an extension plate, which is fixedly connected to the top of the slide column, and a rail plate is fixedly connected to the top of the extension plate. An inner plate is slidably connected to the inner side of the extension plate.
[0009] Resin was laid on top of the steel plate, a polymer fiber mesh was laid on top of the first resin coating, ceramsite was laid on top of the mesh, and finally an asphalt layer was laid on top of the ceramsite.
[0010] Preferably, the interlocking reinforcement mechanism includes a first resin coating, which is laid on top of the steel plate. A polymer fiber mesh is laid on top of the first resin coating, ceramsite is laid on top of the polymer fiber mesh, and an asphalt layer is laid on top of the ceramsite.
[0011] Resin was laid on top of the steel plate, a polymer fiber mesh was laid on top of the first resin coating, ceramsite was laid on top of the mesh, and finally an asphalt layer was laid on top of the ceramsite.
[0012] Preferably, the stress-sharing mechanism includes phase change microcapsules, which are laid on top of the layer. A flexible microtube mesh is laid on top of the phase change microcapsules, and a second resin coating is laid on top of the flexible microtube mesh.
[0013] Microcapsules were laid on top of the substrate, and a flexible microtube mesh was laid on top of the microcapsules. The mesh was then covered with a second resin coating.
[0014] Preferably, the top of the steel plate is fixedly connected to a plurality of support anchors, and the outer side of the support anchors is slidably connected to a frame.
[0015] Multiple support anchors are fixed to the top of the steel plate, and the outer side of the support anchors is slidably connected to a frame.
[0016] Preferably, a coating plate is fixedly connected to the bottom of the frame, and casters are fixedly connected to the bottom of the frame.
[0017] A coating plate is fixed to the bottom of the frame, and casters are installed at the bottom of the frame to facilitate the movement of the equipment.
[0018] Preferably, a motor is fixedly connected to the outside of the frame, and a transmission assembly is rotatably connected to the outside of the motor.
[0019] The motor is fixed to the outside of the frame, and the outside of the motor is rotatably connected to a transmission assembly.
[0020] Preferably, the top of the frame is connected to a hopper, and the output end of the motor is fixedly connected to a screw shaft.
[0021] The top of the frame is connected to the hopper, and the output end of the motor is fixed with a screw shaft.
[0022] Preferably, the motors are symmetrically distributed along the central axis of the frame, and the motors and transmission components are electrically connected.
[0023] The motors are arranged symmetrically along the central axis of the frame, and the motors and transmission components are connected by circuitry.
[0024] A method for constructing cast-in-place asphalt concrete steel bridge deck pavement, using the method described in any one of claims 1-9, includes the following steps:
[0025] S1. Pre-treatment of steel plate panels for steel bridges: Sandblasting process is used to thoroughly remove rust and clean the surface of the steel plates to obtain a clean, dry construction interface with a specified roughness.
[0026] S2. Pre-adjust the laying thickness on the pre-treated steel plate. By pressing the inner plate, adjust the inner plate and the three adjustment grooves. After the adjustment is completed, move the shifting wheel of the laying device to the rail plate and move it onto the steel plate until it is completely moved onto the steel plate.
[0027] S3. The first resin coating is evenly applied to the steel plate to form a buffer layer with both strong adhesion and flexibility. Then, the resin-modified asphalt concrete main load-bearing layer is poured on it. During the pouring process, a three-dimensional randomly distributed polymer fiber mesh is pre-embedded. Finally, before the main load-bearing layer is completely cured, a special equipment is used to embed the ceramsite crushed stone into its surface with a certain pressure to form an interlocking structure of the coating layer.
[0028] S4. When mixing the main load-bearing layer casting material, high-strength closed-cell hollow glass microspheres and temperature-induced phase change microcapsules are added according to the design ratio. Flexible microtube grids are laid on the buffer layer in the main stress direction. Then, a second resin coating is covered and poured to form a built-in stress and heat regulation microchannel system.
[0029] S5. Pavement layer maintenance and post-treatment: After the paving construction is completed, maintenance shall be carried out in accordance with the specified conditions until the material reaches the design strength. When necessary, the built-in microchannel network can be used for diagnosis or injection of repair materials.
[0030] In summary, the present invention has at least one of the following beneficial technical effects:
[0031] 1. This invention provides multiple selectable fixing points for the vertical height position of the extension plate through multi-level adjustment grooves opened on the upright plate. Under the pre-tightening force and buffering effect provided by the spring, the sliding column can slide smoothly relative to the steel plate. After the height is adjusted to the correct position, the inner plate locks the extension plate in the selected adjustment groove. This mechanism realizes multi-level, stable and adjustable laying reference height, enabling construction to flexibly match different design thicknesses and alignment requirements.
[0032] 2. This invention lays a highly permeable resin coating on the top of a steel plate, which can tightly wet the steel plate and cure into a flexible adhesive buffer layer. Then, a polymer fiber mesh is laid on top of it, which enhances the tensile and shear strength of the overall structure and inhibits crack development. Next, ceramsite of a specific particle size is embedded into the incompletely cured lower layer under a certain pressure to form a mechanically interlocked rough surface layer. Finally, asphalt concrete is poured to form the main structural layer, which improves the overall bonding strength, fatigue resistance and deformation resistance of the pavement system.
[0033] 3. The present invention incorporates phase change microcapsules into the pavement layer, which can undergo reversible phase change when the ambient temperature changes, actively absorbing or releasing latent heat, thereby effectively buffering and dissipating the internal thermal stress generated by temperature cycling. When external loads or temperature stresses are applied to the pavement layer, the flexible microtubes disperse the concentrated stress and convert it into small deformation energy, thereby improving the pavement layer's ability to resist temperature cracking and load fatigue. Attached Figure Description
[0034] Figure 1 This is a perspective view of the present invention;
[0035] Figure 2 This is a schematic diagram of the frame structure of the present invention;
[0036] Figure 3 This is a side view of the frame of the present invention;
[0037] Figure 4 This is a top view of the frame of the present invention;
[0038] Figure 5 This is a front view of the frame of the present invention;
[0039] Figure 6 for Figure 5 Enlarged view of point A;
[0040] Figure 7 This is a cross-sectional view of the layup layer of the present invention;
[0041] Figure 8 This is a cross-sectional view of the stress-sharing mechanism of the present invention.
[0042] The components include: 1. Steel plate; 2. Laying layer; 3. Adjustment mechanism; 301. Limiting plate; 302. Sliding column; 303. Spring; 304. Extension plate; 305. Rail plate; 306. Inset plate; 307. Adjustment groove; 308. Vertical plate; 4. Engagement reinforcement mechanism; 401. First resin coating; 402. Polymer fiber mesh; 403. Ceramsite; 404. Asphalt layer; 5. Stress sharing mechanism; 501. Phase change microcapsule; 502. Flexible microtube mesh; 503. Second resin coating; 6. Support anchor; 7. Frame; 8. Coating plate; 9. Transfer wheel; 10. Laying hopper; 11. Spiral shaft; 12. Motor; 13. Transmission assembly. Detailed Implementation
[0043] The following is in conjunction with the appendix Figure 1 -Appendix Figure 8 The present invention will be further described in detail below.
[0044] Please see the appendix Figure 1 -Appendix Figure 6 This invention provides a construction method for cast-in-place asphalt concrete steel bridge deck pavement, including a steel plate 1, which is the basic load-bearing and support structure of the entire pavement structure. A paving layer 2 is fixedly connected to the top of the steel plate 1, and the paving layer 2 is laid on the steel plate 1 to realize the composite pavement structure of road surface function. An adjustment mechanism 3 is provided on the outer side of the steel plate 1. The adjustment mechanism 3 is a working device for adjusting the construction benchmark or thickness of the paving layer. An interlocking reinforcement mechanism 4 is provided on the inner side of the paving layer 2. The interlocking reinforcement mechanism 4 is used to enhance the interlocking force inside the paving layer and between it and the steel plate. A stress averaging mechanism 5 is provided on the top of the paving layer 2. The stress averaging mechanism 5 is used to disperse, transmit or offset the internal stress of the paving layer.
[0045] The adjustment mechanism 3 includes a vertical plate 308, which is an upright plate that serves as a support or connector. Multiple adjustment slots 307 are provided on the outer side of the vertical plate 308. These slots are used to fix the extension plate 304 at different heights. A sliding column 302 is slidably connected to the outer side of the steel plate 1. A limit plate 301 is fixedly connected to the bottom end of the sliding column 302. A spring 303 is fixedly connected to the outer side of the sliding column 302. The spring 303 provides elastic force and performs buffering, reset, and pre-tightening functions. The adjustment mechanism 3 also includes an extension plate 304, which is fixedly connected to the top of the sliding column 302. A rail plate 305 is fixedly connected to the top of the extension plate 304. The rail plate 305 provides a sliding track for the moving parts of the laying device. An inner plate 306 is slidably connected to the inner side of the extension plate 304. The inner plate 306 is used to fix the extension plate 304 in a suitable adjustment slot 307.
[0046] Specifically, the upright plate 308 is an upright plate that provides support and connection. Multiple adjustment slots 307 are provided on the outer side of the upright plate 308. The adjustment slots 307 are used to fix the extension plate 304 at different working heights. The outer side of the steel plate 1 is slidably connected to the sliding column 302. The bottom end of the sliding column 302 is fixed with a limit plate 301. A spring 303 is fixed on the outer side of the sliding column 302. The spring 303 is a component that provides elastic force and realizes buffer reset and pre-tightening functions. The extension plate 304 is fixed to the top of the sliding column 302. The top of the extension plate 304 is fixed to the rail plate 305. The rail plate 305 provides a sliding track for the moving parts on the laying device. The inner side of the extension plate 304 is slidably connected to the inner plate 306. The function of the inner plate 306 is to lock the extension plate 304 in the selected appropriate adjustment slot 307.
[0047] Please see the appendix Figure 7 The interlocking reinforcement mechanism 4 includes a first resin coating 401, which is a layer of resin material laid first for bonding and cushioning. The first resin coating 401 is laid on top of the steel plate 1. A polymer fiber mesh 402 is laid on top of the first resin coating 401. The polymer fiber mesh 402 is a mesh-like pad made of polymer fibers for reinforcement and toughening. Ceramsite 403 is laid on top of the polymer fiber mesh 402. Ceramsite 403 is used for the paving surface layer and provides lightweight aggregate with anti-slip and wear-resistant functions. An asphalt layer 404 is laid on top of the ceramsite 403. The asphalt layer 404 is the main paving structure layer with asphalt as the main binder.
[0048] Specifically, the first resin coating 401 is the first layer of resin material laid for bonding and cushioning. The first resin coating 401 is laid on top of the steel plate 1. On top of the first resin coating 401, a polymer fiber mesh 402 is laid. The first resin coating 401 is made of polymer fibers and has a mesh structure to enhance and toughen it. On top of the polymer fiber mesh 402, expanded clay aggregate 403 is laid. Expanded clay aggregate 403 is a lightweight aggregate used for paving the surface layer. Expanded clay aggregate 403 provides the surface with anti-slip and wear-resistant functions. Finally, an asphalt layer 404 is laid on top of the expanded clay aggregate 403. The asphalt layer 404 is a paving structure composed of asphalt as a binder.
[0049] Please see the appendix Figure 8The stress-equalizing mechanism 5 includes a phase change microcapsule 501, which is a microcapsule containing a phase change material for temperature stress regulation. The phase change microcapsule 501 is laid on top of the layer 2. A flexible microtube mesh 502 is laid on top of the phase change microcapsule 501. The flexible microtube mesh 502 is a mesh composed of flexible microtubes, which is used to form stress dissipation channels. A second resin coating 503 is laid on top of the flexible microtube mesh 502. The resin film subsequently covered by the second resin coating 503 is used to seal or bond the surface.
[0050] Specifically, the phase change microcapsule 501 encapsulates microcapsules of phase change material to regulate stress caused by temperature changes. The phase change microcapsule 501 is laid on top of the layer 2. On top of the phase change microcapsule 501, a flexible microtube mesh 502 is laid. The flexible microtube mesh 502 is composed of flexible microtubes, and its function is to form internal channels that can dissipate stress. The top of the flexible microtube mesh 502 is covered with a second resin film 503, which is a resin film that is subsequently applied and its function is to seal the surface or provide adhesion.
[0051] Please see the appendix Figure 1 -Appendix Figure 5 The top of the steel plate 1 is fixedly connected to multiple support anchors 6, which are components that provide support or anchoring. The outer side of the support anchors 6 is slidably connected to a frame 7, which is the main support frame of the coating device. The bottom of the frame 7 is fixedly connected to a coating plate 8, which is a plate-shaped tool used for scraping or spreading adhesive materials. The bottom of the frame 7 is fixedly connected to a transfer wheel 9, which is a wheel that facilitates the movement of the equipment. The outer side of the frame 7 is fixedly connected to a motor 12, and the outer side of the motor 12 is rotatably connected to a transmission assembly 13, which is a mechanical component that transmits the power of the motor 12 to the working parts. The top of the frame 7 is connected to a hopper 10, which is a hopper for holding and pouring paving materials. The output end of the motor 12 is fixedly connected to a spiral shaft 11, which is a spiral shaft that conveys or stirs materials by rotation. The motors 12 are symmetrically distributed along the central axis of the frame 7. The motors 12 are electric motors that provide power to the paving device. The motors 12 and the transmission assembly 13 are electrically connected.
[0052] Specifically, the anchor 6 is a component that provides support and anchoring. The outer side of the anchor 6 is slidably connected to the frame 7. The frame 7 is the main support frame of the coating device. The bottom of the frame 7 is fixed with a coating plate 8, which is a plate-shaped tool used for scraping or spreading adhesive materials. The bottom of the frame 7 is also fixed with a transfer wheel 9, which is a wheel that facilitates the movement of the equipment. On the outer side of the frame 7, a motor 12 is fixedly installed. The outer side of the motor 12 is rotatably connected to a transmission assembly 13. The transmission assembly 13 is a mechanical component that transmits the power of the motor 12 to the working parts. The top of the frame 7 is connected to a hopper 10, which is a hopper for holding and pouring paving materials. The output end of the motor 12 is connected to a spiral shaft 11, which is a spiral shaft that conveys or stirs materials by rotation. The motors 12 are symmetrically distributed along the central axis of the frame 7. The motors 12 are electric motors that provide power to the entire paving device.
[0053] like Figure 7 and Figure 8 As shown, the construction method for cast-in-place asphalt concrete steel bridge deck pavement may include the following steps:
[0054] S1. Pre-treatment of the steel plate 1 panel of the steel bridge: Sandblasting process is used to thoroughly remove rust and clean the surface of the steel plate 1 to obtain a clean, dry construction interface with a specified roughness.
[0055] S2. The laying thickness is pre-adjusted on the pre-treated steel plate 1. By pressing the inner plate 306, the inner plate 306 and the three adjustment grooves 307 are adjusted. After the adjustment is completed, the laying device's transfer wheel 9 is aligned with the rail plate 305 and moved onto the steel plate 1 until it is completely moved onto the steel plate 1.
[0056] S3. A first resin coating 401 is uniformly coated on the steel plate 1 to form a buffer layer with both strong adhesion and flexibility. Then, a resin-modified asphalt concrete main load-bearing layer is poured on it. During the pouring process, a three-dimensional randomly distributed polymer fiber mesh 402 is pre-embedded. Finally, before the main load-bearing layer is completely cured, a special equipment is used to embed ceramsite 403 into its surface with a certain pressure to form an interlocking structure surface layer.
[0057] S4. When mixing the main load-bearing layer casting material, high-strength closed-cell hollow glass microspheres and temperature-induced phase change microcapsules 501 are added according to the design ratio. Flexible microtube grids 502 are laid on the buffer layer in the main stress direction. Then, a second resin film 503 is covered and poured to form a built-in stress and heat regulation microchannel structure.
[0058] S5. Pavement layer maintenance and post-treatment: After the paving construction is completed, maintenance shall be carried out in accordance with the specified conditions until the material reaches the design strength. When necessary, the built-in microchannel network can be used for diagnosis or injection of repair materials.
[0059] Working principle: The multi-level adjustment grooves 307 on the vertical plate 308 provide multiple selectable fixing points for the vertical height position of the extension plate 304. Under the pre-tightening force and buffering effect provided by the spring 303, the sliding column 302 can slide smoothly relative to the steel plate 1. After the height is adjusted to the correct position, the inner plate 306 locks the extension plate 304 in the selected adjustment groove 307. This mechanism realizes multi-level stable adjustment of the paving reference height, which allows the construction process to flexibly match different design thicknesses and alignment requirements, thereby ensuring accurate control of the paving layer thickness and surface flatness.
[0060] A highly permeable first resin film 401 is laid on top of the steel plate 1. This film can tightly wet the surface of the steel plate and cure into a flexible adhesive buffer layer. Then, a polymer fiber mesh 402 is laid on top of it. This mesh enhances the tensile and shear strength of the overall structure and effectively inhibits the initiation and development of cracks. Next, ceramsite 403 of a specific particle size is embedded into the incompletely cured lower layer under a certain pressure to form a mechanically interlocked rough surface layer. Finally, an asphalt layer 404 is poured to form the main structural layer. This composite structure improves the overall bonding strength, fatigue resistance and deformation resistance of the pavement system.
[0061] By incorporating phase change microcapsules 501 into the pavement layer, a reversible phase change occurs when the ambient temperature changes, actively absorbing or releasing latent heat, thereby effectively buffering and dissipating the internal thermal stress generated by temperature cycling. When external loads or temperature stresses are applied to the pavement layer, the flexible microtube mesh 502 can disperse the concentrated stress and convert it into tiny deformation energy. The second resin coating 503 covering it ensures the integrity of the internal structure. This mechanism improves the pavement layer's resistance to temperature cracking from the structural design level.
[0062] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A method for constructing cast-in-place asphalt concrete steel bridge deck pavement, comprising steel plates (1), characterized in that, The top of the steel plate (1) is fixedly connected to the paving layer (2). An adjustment mechanism (3) is provided on the outside of the steel plate (1). The adjustment mechanism (3) is an auxiliary mechanism for adjusting the construction thickness of the paving layer. An interlocking reinforcement mechanism (4) is provided on the inside of the paving layer (2). The interlocking reinforcement mechanism (4) is used to enhance the interlocking force inside the paving layer and between it and the steel plate. A stress averaging mechanism (5) is provided on the top of the paving layer (2). The stress averaging mechanism (5) is used to disperse and offset the stress generated inside the paving layer. The adjustment mechanism (3) includes a vertical plate (308), and multiple adjustment slots (307) are provided on the outer side of the vertical plate (308). A sliding column (302) is slidably connected to the outer side of the steel plate (1). A limit plate (301) is fixedly connected to the bottom end of the sliding column (302), and a spring (303) is fixedly connected to the outer side of the sliding column (302).
2. The construction method for cast-in-place asphalt concrete steel bridge deck pavement according to claim 1, characterized in that, The adjustment mechanism (3) further includes an extension plate (304), which is fixedly connected to the top of the slide column (302). The top of the extension plate (304) is fixedly connected to a rail plate (305), and an inner plate (306) is slidably connected to the inner side of the extension plate (304).
3. The construction method for cast-in-place asphalt concrete steel bridge deck pavement according to claim 1, characterized in that, The interlocking enhancement mechanism (4) includes a first resin coating (401), which is laid on the top of the steel plate (1). A polymer fiber mesh (402) is laid on top of the first resin coating (401), and a ceramic aggregate (403) is laid on top of the polymer fiber mesh (402). An asphalt layer (404) is laid on top of the ceramic aggregate (403).
4. The construction method for cast-in-place asphalt concrete steel bridge deck pavement according to claim 1, characterized in that, The stress averaging mechanism (5) includes a phase change microcapsule (501), which is laid on top of the layer (2). A flexible microtube mesh (502) is laid on top of the phase change microcapsule (501), and a second resin coating (503) is laid on top of the flexible microtube mesh (502).
5. The construction method for cast-in-place asphalt concrete steel bridge deck pavement according to claim 1, characterized in that, The top of the steel plate (1) is fixedly connected to a plurality of support anchors (6), and the outer side of the support anchors (6) is slidably connected to a frame (7).
6. The construction method for cast-in-place asphalt concrete steel bridge deck pavement according to claim 1, characterized in that, The bottom of the frame (7) is fixedly connected to a coating plate (8), and the bottom of the frame (7) is fixedly connected to a caster wheel (9).
7. The construction method for cast-in-place asphalt concrete steel bridge deck pavement according to claim 1, characterized in that, A motor (12) is fixedly connected to the outside of the frame (7), and a transmission assembly (13) is rotatably connected to the outside of the motor (12).
8. A method for constructing cast-in-place asphalt concrete steel bridge deck pavement, characterized in that, The top of the frame (7) is connected to the hopper (10), and the output end of the motor (12) is fixedly connected to the screw shaft (11).
9. A method for constructing cast-in-place asphalt concrete steel bridge deck pavement, characterized in that, The motor (12) is symmetrically distributed along the central axis of the frame (7), and the motor (12) and the transmission assembly (13) are electrically connected.
10. A method for constructing cast-in-place asphalt concrete steel bridge deck pavement, using the method for constructing cast-in-place asphalt concrete steel bridge deck pavement as described in any one of claims 1-9, comprising the following steps: S1. Pretreatment of the steel plate (1) panel of the steel bridge: The surface of the steel plate (1) is thoroughly rusted and cleaned by sandblasting process to obtain a clean, dry construction interface with a specified roughness. S2. The laying thickness is pre-adjusted on the pre-treated steel plate (1). By pressing the inner plate (306), the inner plate (306) and the three adjustment grooves (307) are adjusted. After the adjustment is completed, the laying device's transfer wheel (9) is aligned with the rail plate (305) and moved onto the steel plate (1) until it is completely moved onto the steel plate (1). S3. The first resin coating (401) is uniformly coated on the steel plate (1) to form a buffer layer with strong adhesion and flexibility. Then, the resin-modified asphalt concrete main load-bearing layer is poured on it. During the pouring process, a three-dimensional randomly distributed polymer fiber mesh (402) is pre-embedded. Finally, before the main load-bearing layer is completely cured, a special equipment is used to embed the ceramsite (403) into its surface with a certain pressure to form an interlocking structure coating layer. S4. When mixing the main load-bearing layer casting material, high-strength closed-cell hollow glass microspheres and temperature-induced phase change microcapsules (501) are added according to the design ratio. Flexible microtube grids (502) are laid on the buffer layer in the main stress direction. Then, the second resin coating layer (503) is covered and poured to form a built-in stress and heat regulation microchannel structure. S5. Pavement layer maintenance and post-treatment: After the paving construction is completed, maintenance shall be carried out in accordance with the specified conditions until the material reaches the design strength. When necessary, the built-in microchannel network can be used for diagnosis or injection of repair materials.