Construction method of petal-shaped hyperbolic combined modeling wall

By analyzing the unfolded surfaces of the inner and outer surfaces using BIM technology and Rhino software, and combining 3D Max slicing tools and support frame design, the construction challenges of petal-shaped irregular wall surfaces were solved, achieving high-precision and efficient construction results while reducing costs.

CN122013907APending Publication Date: 2026-05-12CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
CHINA CONSTR EIGHT ENG DIV CORP LTD
Filing Date
2025-12-31
Publication Date
2026-05-12

AI Technical Summary

Technical Problem

The curved shape of the petal-shaped wall is difficult to construct and the precision is hard to control, resulting in poor forming quality.

Method used

BIM technology was used to optimize the petal-shaped complex structure. Rhino software was used to analyze the unfolded surfaces of the inner and outer surfaces, generate multiple planar views, and cut them using 3D Max slicing tools to prepare inner and outer templates. The construction was carried out segment by segment, and the templates were fixed. Concrete was poured to form the wall, and the stability was ensured by combining support frames and tie rods.

Benefits of technology

It improved construction precision and progress, reduced steel mold costs, and ensured the consistency of the wall's appearance and the quality of its forming.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122013907A_ABST
    Figure CN122013907A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of special-shaped wall body construction, and discloses a construction method of a petal-shaped hyperbolic combined modeling wall body, which comprises the following steps: S1, fitting a wall body structure into a plurality of broken-line-shaped wall sections; s2, cutting all broken line positions of each wall section by using a 3dmax slicing tool to generate a plurality of planar graphs; s3, preparing a corresponding template according to each expanded surface; and S5, the multiple wall face decoration pieces are installed on the corresponding wall sections. According to the method, modeling optimization of an ellipsoidal petal-shaped complex structure is conducted through the BIM technology, a hyperbolic special-shaped petal wall body is inversely fitted into a multi-section broken-line-shaped petal wall, rhino is used for conducting analysis and mold matching on inner and outer skin expansion faces, the template utilization rate is increased, a planar graph is generated at break point elevation through a 3dmax slicing tool, and site positioning construction control is facilitated; the wall body is optimized in the mode that bending is replaced by bending, so that the problems of high cost and high-altitude reinforcement caused by using a steel mold are avoided, formwork erecting construction is facilitated, and the precision and progress are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of irregular wall construction technology, and specifically relates to a construction method for a petal-shaped hyperbolic composite wall. Background Technology

[0002] With the continuous development and innovation of engineering technology and design concepts, irregular and complex structures have been increasingly widely used in the field of architecture. These structures, with their unique shapes, excellent mechanical properties, and outstanding space utilization, not only meet the modern architectural pursuit of both aesthetics and practicality, but also drive the continuous progress of architectural design and construction technology, leading the future development direction of the construction industry.

[0003] Currently, petal-shaped irregular wall structures are constructed on already completed floors, with the wall surface designed as curved to accommodate the curved decorative layer. However, direct construction of curved walls is difficult, and precision is hard to control, often resulting in regional deformation during construction. This leads to poor overall quality of the petal-shaped wall, failing to meet requirements. Therefore, we propose a construction method for a petal-shaped hyperbolic composite wall structure to solve the above problems. Summary of the Invention

[0004] To address the aforementioned problems, this invention provides a construction method for a petal-shaped hyperbolic composite wall, which solves the difficulty of directly constructing curved walls.

[0005] This invention is achieved through the following scheme: a construction method for a petal-shaped hyperbolic composite wall, comprising the following steps:

[0006] S1. Using modeling software, create models of the wall structure and wall decoration layer according to the design drawings, and fit the wall structure into multiple wall segments in a polygonal shape.

[0007] S2. Use the 3ds Max slicing tool to cut at all polyline positions of each wall segment to generate multiple plan views. Add annotations to the multiple plan views and output them to form construction drawings. The annotations include construction sequence number, installation angle and installation height.

[0008] S3. Use Rhino software to analyze the inner and outer surface development of each wall segment, and prepare corresponding templates according to each development surface to form multiple one-to-one inner and outer templates.

[0009] S4. According to the construction drawings, set up and fix the outer formwork, steel reinforcement cage and inner formwork corresponding to each wall segment at the designated position on the floor according to the construction sequence, installation angle and installation height. Pour concrete between the outer formwork and the inner formwork so that the concrete wraps the steel reinforcement cage and forms the wall after curing.

[0010] S5. Divide the wall decoration layer according to the broken lines of multiple wall segments to generate multiple wall decoration pieces, and install the multiple wall decoration pieces on the corresponding wall segments.

[0011] A further improvement of the construction method for the petal-shaped hyperbolic composite wall of the present invention is that each wall segment includes multiple construction segments, and the multiple construction segments are connected to the multiple planes in step S2. Figure 1 One-to-one correspondence;

[0012] When performing step S4, multiple construction sections are constructed sequentially from bottom to top.

[0013] A further improvement of the construction method for the petal-shaped hyperbolic composite wall of the present invention is that, before constructing the upper construction segment in each of the two adjacent construction segments, the top of the lower construction segment is roughened.

[0014] A further improvement of the construction method of the petal-shaped hyperbolic composite wall of the present invention is that step S4 further includes the following steps: before pouring concrete, holes are made on the outer formwork corresponding to each construction section, and after pouring concrete, a vibrator is inserted into the hole to vibrate the concrete inside, and after the vibration is finished and the vibrator is removed, the hole is sealed.

[0015] A further improvement of the construction method of the petal-shaped hyperbolic composite wall of the present invention is that, in each of the wall segments, the construction segment at the lower end is an outward-sloping segment and the construction segment at the upper end is an inward-sloping segment.

[0016] Before constructing the outward-sloping section, a support frame is erected on the floor, and the support frame is used to fix the outer formwork corresponding to the outward-sloping section during construction.

[0017] Before constructing the inner section, an outer scaffold is erected on the support frame, and during the construction of the inner section, the outer scaffold is used to fix the outer formwork corresponding to the inner section.

[0018] A further improvement of the construction method of the petal-shaped hyperbolic composite wall of the present invention is that, after constructing the outer template, the outer template and the corresponding inner template are connected and fixed by tie rods when constructing the corresponding inner template.

[0019] A further improvement to the construction method of the petal-shaped hyperbolic composite wall of the present invention is that, after the concrete has cured and formed the wall, the method further includes the following step:

[0020] Remove the inner and outer formwork. First, cut off the part of the tie rod that protrudes from the wall, and then continue to cut off the part of the tie rod that is at least 2mm deep into the wall from the wall surface.

[0021] Apply anti-rust paint to the broken end of the tie rod and fill the area between the broken end of the tie rod and the wall with plaster.

[0022] Compared with the prior art, the beneficial effects of the present invention are as follows:

[0023] This invention utilizes BIM technology to optimize the complex ellipsoidal petal-shaped structure, inversely fitting the hyperbolic irregular petal wall into a multi-segment zigzag petal wall. Rhino is used to analyze and match the inner and outer skin surfaces, improving template utilization. 3ds Max slicing tools are used to generate a plan view at the inflection point elevation, facilitating on-site positioning and construction control. By optimizing the wall by replacing curvature with folds, the high cost and high-altitude reinforcement problems associated with using steel formwork are avoided, facilitating formwork erection and construction, and improving accuracy and progress. Attached Figure Description

[0024] Figure 1 A flowchart is shown showing the construction method of the petal-shaped hyperbolic composite wall of the present invention.

[0025] Figure 2 A schematic diagram of the multi-fold wall segment of the present invention is shown.

[0026] Figure 3 A schematic diagram of the unfolded surface of multiple wall segments of the present invention is shown.

[0027] Figure 4 A schematic diagram of the support frame position during construction of the first construction section in the outward tilting section of the present invention is shown.

[0028] Figure 5 A schematic diagram of the support frame position during construction of the second construction section in the outward tilting section of the present invention is shown.

[0029] Figure 6 A schematic diagram of the construction location of the external scaffolding of the present invention is shown.

[0030] Figure 7 A schematic diagram of the present invention showing the removal of the portion of the tie rod protruding from the wall surface is shown.

[0031] Figure 8 A schematic diagram of the bracket mounting position of the present invention is shown.

[0032] Figure 9 A schematic diagram showing the location of the floor decking of the present invention is provided.

[0033] In the diagram: 1. Wall section; 101. Outward-sloping section; 102. Inward-sloping section; 2. Floor; 3. Support frame; 4. External scaffold; 5. Tie rod; 6. Vertical brace; 7. Steel truss; 8. Corbel; 9. Floor deck. Detailed Implementation

[0034] To address the difficulty of directly constructing curved walls, this invention provides a construction method for a petal-shaped hyperbolic composite wall. The following detailed description, in conjunction with accompanying drawings, provides further explanation of this construction method for a petal-shaped hyperbolic composite wall.

[0035] See Figures 1-9 As shown, a construction method for a petal-shaped hyperbolic composite wall includes the following steps:

[0036] S1. Using BIM (Building Information Modeling) software, models of the wall structure and wall decoration layer are created according to the design drawings. The wall structure is fitted into multiple polygonal wall segments 1.

[0037] S2. Using the 3ds Max (3D Studio Max 3D modeling) slicing tool, cut at all polyline positions of each wall segment 1 to generate multiple plan views. After adding annotations to the multiple plan views, output to form construction drawings. The annotations include construction sequence number, installation angle and installation height.

[0038] S3. Use Rhino (Rhinoceros 3D) software to analyze the unfolded surfaces of the inner and outer surfaces of each wall segment 1, and prepare corresponding templates according to each unfolded surface to form multiple one-to-one corresponding inner and outer templates.

[0039] S4. According to the construction drawings, set up and fix the outer formwork, steel reinforcement cage and inner formwork corresponding to each wall segment 1 at the set position on floor 2 according to the construction sequence, installation angle and installation height. Pour concrete between the outer formwork and the inner formwork so that the concrete wraps the steel reinforcement cage. After curing, the wall is formed and the wall has a closing at the top.

[0040] S5. Divide the wall decoration layer according to the broken lines of multiple wall segments 1 to generate multiple wall decoration pieces, and install the multiple wall decoration pieces on the corresponding wall segments 1.

[0041] BIM technology was used to optimize the complex ellipsoidal petal-shaped structure. The hyperbolic irregular petal wall was inversely fitted into a multi-segment zigzag petal wall. Rhino was used to analyze and match the inner and outer skin surfaces to improve the formwork utilization rate. The 3ds Max slicing tool was used to generate a plan view at the inflection point elevation, which facilitates on-site positioning and construction control. By optimizing the wall by replacing curvature with folds, the high cost and high-altitude reinforcement problems caused by using steel formwork were avoided. This facilitated the erection of formwork and improved accuracy and progress. After the wall construction was completed, the wall decoration layer was installed on the wall to ensure that the wall has a petal shape and a consistent appearance.

[0042] Furthermore, in order to better fit the original curved surface, the broken line should be placed in the area where the curve is dense, and the impact of the broken angle on the net height of the stairs should be checked. Fine adjustments should be made while meeting the requirements for net height of stairs and width of platforms.

[0043] Among them, see Figure 3-6 As shown, each wall segment 1 includes multiple construction segments, and these multiple construction segments are connected to multiple planes in step S2. Figure 1 One-to-one correspondence;

[0044] When performing step S4, multiple construction sections are constructed sequentially from bottom to top.

[0045] Segmented construction facilitates the precise setting, adjustment, and fixing of each inner and outer formwork, greatly ensuring the construction accuracy of each segment.

[0046] In this process, before the upper construction section in each of two adjacent construction sections, the top of the lower construction section is roughened.

[0047] By roughening the contact surface area, the connection anchorage between the upper and lower construction sections can be improved.

[0048] Step S4 further includes the following steps: before pouring concrete, make a hole in the outer formwork corresponding to each construction section, with the hole size being 10cm×10cm, and after pouring concrete, use a vibrator to insert into the hole to vibrate the concrete inside, and after the vibration is finished and the vibrator is removed, seal the hole.

[0049] Because the wall is sloping on the facade, it is difficult to insert the vibrator to the bottom of the wall during the concrete pouring process. At the same time, it is difficult for the air bubbles generated during the vibration process to be discharged from the top. Therefore, this application adopts the above design to allow the vibrator to be inserted and the air bubbles generated during the vibration process to be discharged by opening holes in the outer formwork, so as to ensure the forming quality of the wall.

[0050] Among them, see Figure 4-6 As shown, in each wall segment 1, the construction segment at the lower end is the outward-sloping segment 101, and the construction segment at the upper end is the inward-sloping segment 102.

[0051] Before constructing the outward-sloping section 101, a support frame 3 is erected on the floor 2, and the support frame 3 is used to fix the outer formwork corresponding to the outward-sloping section 101 during construction.

[0052] Before constructing the inner section 102, an outer scaffold 4 is erected on the support frame 3, and the outer scaffold 4 is used to fix the outer formwork corresponding to the inner section 102 during the construction of the inner section.

[0053] Furthermore, the height of each erection of the support frame 3 is the height of the fold line position of the fold line wall segment 1. After the support frame 3 is erected, a temporary horizontal template is laid on top to facilitate workers to stand on the horizontal template for point calibration, thereby controlling the tilt angle and corner position of the wall. The support frame 3 can provide stable support for the template. Before each construction section of each wall segment 1 is constructed, a section of support frame 3 is erected to ensure that the height meets the usage requirements. When constructing the inward section 102, an outer frame 4 can be erected on top of the support frame 3 to support the template corresponding to the inward section 102, ensuring its fixation and stability and reducing the probability of deformation.

[0054] Specifically, there is a cavity between the 5.0 elevation cantilever slab and the corresponding construction section, which makes it inconvenient to erect the scaffold 4. In order to facilitate the erection of the scaffold 4, the cavity needs to be temporarily sealed with a cast-in-place reinforced concrete slab, HRB400, 14@200 steel bars are laid, and then a 10cm thick C35 concrete is poured. It can only be chiseled after the scaffold 4 is removed.

[0055] There is a cavity in the middle of the petal wall at the 10.0 elevation, which makes it inconvenient to reinforce the petal wall at the 10.0~13.5 elevation. The cavity needs to be temporarily sealed with cast-in-place reinforced concrete slab, HRB400, 14@200 steel bars are laid, and then 10cm thick C35 concrete is poured. After the formwork is removed, the cavity is chiseled.

[0056] Specifically, both the support frame 3 and the outer frame 4 can be connected and fixed to the outer template by setting multiple diagonal bracing tubes to provide stable support.

[0057] By adopting the above design, the stable support of the formwork for the outward-sloping section 101 and the inward-retracting section 102 can be ensured by using the gradually stacked support frame 3 and the outer frame 4, thereby ensuring construction accuracy.

[0058] In this process, after the outer formwork is constructed, the corresponding inner formwork is constructed by connecting and fixing the outer formwork to the corresponding inner formwork using tie rods 5.

[0059] Furthermore, the inner formwork can be further supported and fixed by using diagonal steel pipes on the inner side of the inner formwork.

[0060] By adopting the above design, the spacing between the inner and outer formwork is ensured by using tie rods 5. The fixed outer formwork can also provide stable support for the inner formwork. In addition, the stability of the inner formwork can be greatly improved by using diagonal bracing steel pipes.

[0061] Among them, see Figure 7 As shown, after the concrete has cured and formed a wall, the following steps are also included:

[0062] Remove the inner and outer formwork. First, cut off the part of the tie rod 5 that protrudes from the wall, and then continue to cut off the part of the tie rod 5 that is at least 2mm deep into the wall from the wall surface.

[0063] Apply anti-rust paint to the break point of tie rod 5, and fill the area between the break point of tie rod 5 and the wall with plaster.

[0064] By adopting the above design, the resulting wall is prevented from being easily corroded and damaged, and the wall surface is ensured to be flat.

[0065] Among them, see Figure 8-9 As shown, before performing step S5, the following steps are also included: a ring of vertical supports 6 are set up on the inner side of the wall and around the wall opening, brackets 8 are fixedly installed on each vertical support 6, steel truss 7 is hoisted to the opening area and fixed on the brackets 8, floor deck 9 template is set up on the steel truss 7, concrete is poured into the mold cavity, and floor deck 9 is formed after curing.

[0066] Specifically, the gaps between the floor deck 9 formwork and the surrounding inward-facing wall section 102 are sealed to prevent grout leakage during the pouring process.

[0067] Furthermore, before constructing the uppermost construction section, the steel truss 7 can be hoisted to the end for installation, and then the construction section can be constructed; this can avoid collisions during the hoisting process or irreversible damage to the wall section.

[0068] By adopting the above design, the stability of the construction of floor deck 9 can be guaranteed.

[0069] It should be noted that, in this document, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, article, or apparatus.

[0070] The present invention has been described in detail above with reference to the accompanying drawings and embodiments. Those skilled in the art can make various modifications to the present invention based on the above description. Therefore, certain details in the embodiments should not be construed as limiting the present invention, and the scope of protection of the present invention shall be defined by the appended claims.

Claims

1. A construction method for a petal-shaped hyperbolic composite wall, characterized in that, Includes the following steps: S1. Using modeling software, create models of the wall structure and wall decoration layer according to the design drawings, and fit the wall structure into multiple wall segments in a polygonal shape. S2. Use the 3ds Max slicing tool to cut at all polyline positions of each wall segment to generate multiple plan views. Add annotations to the multiple plan views and output them to form construction drawings. The annotations include construction sequence number, installation angle and installation height. S3. Use Rhino software to analyze the inner and outer surface development of each wall segment, and prepare corresponding templates according to each development surface to form multiple one-to-one inner and outer templates. S4. According to the construction drawings, set up and fix the outer formwork, steel reinforcement cage and inner formwork corresponding to each wall segment at the designated position on the floor according to the construction sequence, installation angle and installation height. Pour concrete between the outer formwork and the inner formwork so that the concrete wraps the steel reinforcement cage and forms the wall after curing. S5. Divide the wall decoration layer according to the broken lines of multiple wall segments to generate multiple wall decoration pieces, and install the multiple wall decoration pieces on the corresponding wall segments.

2. The construction method of the petal-shaped hyperbolic composite wall as described in claim 1, characterized in that, Each wall segment includes multiple construction sections, and the multiple construction sections correspond one-to-one with the multiple plan views in step S2; When performing step S4, multiple construction sections are constructed sequentially from bottom to top.

3. The construction method of the petal-shaped hyperbolic composite wall as described in claim 2, characterized in that, Before constructing the upper construction section in each of two adjacent construction sections, the top of the lower construction section is roughened.

4. The construction method of the petal-shaped hyperbolic composite wall as described in claim 2, characterized in that, Step S4 further includes the following steps: before pouring concrete, making holes in the outer formwork corresponding to each construction section, and after pouring concrete, using a vibrator to vibrate the concrete inside the holes, and sealing the holes after vibration is completed and the vibrator is removed.

5. The construction method of the petal-shaped hyperbolic composite wall as described in claim 2, characterized in that, In each of the aforementioned wall segments, the construction segments at the lower end are called outward-sloping segments, and the construction segments at the upper end are called inward-sloping segments. Before constructing the outward-sloping section, a support frame is erected on the floor, and the support frame is used to fix the outer formwork corresponding to the outward-sloping section during construction. Before constructing the inner section, an outer scaffold is erected on the support frame, and during the construction of the inner section, the outer scaffold is used to fix the outer formwork corresponding to the inner section.

6. The construction method of the petal-shaped hyperbolic composite wall as described in claim 5, characterized in that, After constructing the outer formwork, the corresponding inner formwork is constructed by connecting and fixing the outer formwork to the corresponding inner formwork using tie rods.

7. The construction method of the petal-shaped hyperbolic composite wall as described in claim 6, characterized in that, After the concrete has cured and formed a wall, the following steps are also included: Remove the inner and outer formwork. First, cut off the part of the tie rod that protrudes from the wall, and then continue to cut off the part of the tie rod that is at least 2mm deep into the wall from the wall surface. Apply anti-rust paint to the broken end of the tie rod and fill the area between the broken end of the tie rod and the wall with plaster.